Documente Academic
Documente Profesional
Documente Cultură
A. Concrete Works
Item Description Quantity Unit
Portland Cement 501 bags (40kg)
Sand 29 m3
Crushed Gravel 57 m3
B. Masonry Works
Item Description Quantity Unit
CHB (6" thk.) 2517 pcs.
CHB (4" thk.) 1474 pcs.
Portland Cement 289 bags (40kg)
Sand 23 m3
Fine Sand 12 m3
C. Steel Works
Item Description Quantity Unit
10 mm ø RSB (6 meters) 793 pcs.
12 mm ø RSB (6 meters) 403 pcs.
16 mm ø RSB (6 meters) 207 pcs.
#16 G.I. Tie Wire (30 cm) 138 kg.
Concrete Works
Slab
Ground Floor
Mark Width (m) Length (m) Depth (m) No. of Sets Volume (m3)
F1 1.10 1.10 0.30 8 2.904
F2 0.80 0.80 0.30 5 0.96
Total 3.864
Wall Footing
Mark Width (m) Depth (m) Estimated Perimeter (m) Volume (m3)
WF1 0.50 0.25 15.365 1.921
Column
Ground Floor
Mark Width (m) Depth (m) Length (m) No. of Sets Volume (m3)
1.750 2 0.1750
3.800 1 0.1900
3.100 1 0.1550
3.650 1 0.1825
3.150 1 0.1575
GB1 0.20 0.25 3.700 3 0.5550
3.475 2 0.3475
3.575 1 0.17875
3.525 2 0.3525
3.375 1 0.16875
3.750 2 0.3750
3.600 1 0.1800
Total 18 3.0175
Ground Floor
Mark Width (m) Depth (m) Length (m) No. of Sets Volume (m3)
1.750 2 0.2100
3.800 1 0.2280
3.100 1 0.1860
3.650 1 0.2190
3.150 1 0.1890
RCB1 0.20 0.30 3.700 3 0.6660
3.475 2 0.4170
3.575 1 0.2145
3.525 2 0.4230
3.375 1 0.2025
3.750 1 0.2250
3.600 1 0.2160
3.750 1 0.1875
RCB2 0.20 0.25 3.800 1 0.1900
4.500 1 0.2250
Total 20 3.9985
Mark Width (m) Depth (m) Length (m) No. of Sets Volume (m3)
RCB2 0.20 0.25 3.700 2 0.3700
3.475 1 0.1738
3.375 2 0.3375
3.525 1 0.1763
3.575 1 0.1788
RCB3 0.15 0.25 1.825 2 0.1369
1.875 1 0.0703
3.775 2 0.2831
Total 12 1.7266
Stairs
Span = 1.1 m
CHB Wall
*CHB laying started 0.55 m below natural ground line
First Floor
C-D 0 0
1-2 6.90 25.185
A-B 0 0
B-C 2.40 7.45 17.880
CHB (15x20x40)
Quantity of Cement and Sand for CHB Mortar
Referring from Table 2-2 of SCE by Max Fajardo
Using 15x20x40 under class C mixture;
Steel Works
No. 16 G.I. Tie Wire for CHB Reinforcement per Square Meter
Referring from Table 3-6 of SCE by Max Fajardo
Along 60 cm. vertical spacing and 3 layers horizontal spacing of reinforcement at 30 cm. long tie wire;
Mark: F1
Dimensions: 1.10 m x 1.10 m x 0.30 m
Footing Reinforcement: 8 – 16 mm ø RSB both ways
No. of sets: 8
Hook/bend: not specified on the plan
Required no. of steel bars = 128/6 = 21.33 say 22 pieces of 16 mm ø steel bars at 6 meters long
Mark: F2
Dimensions: 0.80 m x 0.80 m x 0.30 m
Footing Reinforcement: 8 – 16 mm ø RSB both ways
No. of sets: 5
Hook/bend: not specified on the plan
Required no. of steel bars = 80/9 = 8.88 say 9 pieces of 16 mm ø steel bars at 6 meters long
Mark: WF1
Dimensions: 0.25 m x 0.50 m
Footing Reinforcement: 3 – 10 mm ø temperature bars, 12 mm ø main bars spaced at 140 mm
Estimated Perimeter = 15.365 meters
Hook/bend: not specified on the plan
Total no. of bars for 6 sets = 9 x 6 = 54 pieces of 16 mm ø steel bars at 6 meters long
Lateral ties
For L1 = 4.45 m
For L2 = 2.15 m
Total no. of steel bars (ties) = 294 pcs. x 1.0 m = 294 m / 6 = 49 pieces of 10 mm ø steel bars at 6
meters long
Tie Wire
Using 30 cm long ties
6 pcs. x 49 pcs. = 294 pcs
294 pcs x 0.30 m = 88.2 meters
Total length of tie wires for 6 sets = 88.2 x 6 = 529.2 meters
Total no. of bars for 2 sets = 6 x 2 = 12 pieces of 16 mm ø steel bars at 6 meters long
Lateral ties
For L1 = 4.45 m
Total no. of steel bars (ties) = 60 pcs. x 1.0 m = 60 m / 6 = 10 pieces of 10 mm ø steel bars at 6 meters
long
Tie Wire
Using 30 cm long ties
6 pcs. x 30 pcs. = 180 pcs
180 pcs x 0.30 m = 54 meters
Total length of tie wires for 2 sets = 54 x 2 = 108 meters
Total no. of bars for 4 sets = 6 x 4 = 24 pieces of 16 mm ø steel bars at 6 meters long
Lateral ties
For L1 = 4.45 m
Total no. of steel bars (ties) = 120 pcs. x 0.80 m = 96 m / 6 = 16 pieces of 10 mm ø steel bars at 6
meters long
Tie Wire
Using 30 cm long ties
6 pcs. x 30 pcs. = 180 pcs
180 pcs x 0.30 m = 54 meters
Total length of tie wires for 4 sets = 54 x 4 = 216 meters
Total no. of bars for 1 set = 6 x 1 = 6 pieces of 16 mm ø steel bars at 6 meters long
Lateral ties
For L1 = 4.45 m
Total no. of steel bars (ties) = 30 pcs. x 1.0 m = 30 m / 6 = 5 pieces of 10 mm ø steel bars at 6 meters
long
Tie Wire
Using 30 cm long ties
6 pcs. x 30 pcs. = 180 pcs
180 pcs x 0.30 m = 54 meters
Total length of tie wires for 1 set = 54 x 1 = 54 meters
Total no. of bars for 1 sets = 9 x 1 = 9 pieces of 16 mm ø steel bars at 6 meters long
Lateral ties
For L1 = 4.45 m
For L2 = 2.15 m
Total no. of steel bars (ties) = 49 pcs. x 0.80 m = 39.2 m / 6 = 6.53 say 7 pieces of 10 mm ø steel bars at
6 meters long
Tie Wire
Using 30 cm long ties
6 pcs. x 49 pcs. = 294 pcs
294 pcs x 0.30 m = 88.2 meters
Total length of tie wires for 1 set = 88.2 x 1 = 88.2 meters
Total no. of bars for 2 sets = 4 x 2 = 8 pieces of 16 mm ø steel bars at 6 meters long
Lateral ties
For L2 = 2.15 m
Total no. of steel bars (ties) = 38 pcs. x 0.80 m = 30.40 m / 6 = 5.07 say 6 pieces of 10 mm ø steel bars
at 6 meters long
Tie Wire
Using 30 cm long ties
6 pcs. x 19 pcs. = 114 pcs
114 pcs x 0.30 m = 34.2 meters
Total length of tie wires for 2 sets = 34.2 x 2 = 68.4 meters
Slab
First Floor
Second Floor
Beam
Mark: RCB1
Dimensions: 0.20 m x 0.30 m
Average length: 4 meters
Left & Right Support bars: 3 – 16 mm ø top bars, 2 – 16 mm ø bottom bars
Midspan: 2 – 16 mm ø top bars, 3 – 16 mm ø bottom bars
Stirrups: 10 mm ø RSB spaced at 3 – 50 mm, 3 – 100 mm, 3 – 150 mm, rest – 200 mm
No. of sets: 15
Total length required for 15 sets with 5 main bars on each set
L = 5 x 5 x 15= 375 meters
No. of steel bars = 375/6 = 62.5 say 63 pieces of 16 mm ø steel bars at 6 meters long
Stirrups
9 pcs. stirrups for 0.85 meters length
L=4m
4 – 2(0.85) = 2.30 m
(2.30/0.20) – 1 = 10.5 say 10 pieces
Total no. stirrups = 18 + 10 = 28 pieces
Total no. of stirrups for 15 sets = 28 x 15 = 420 pieces
Tie Wire
Using 30 cm long ties
5 pcs. x 28 pcs. = 140 pcs
140 pcs x 0.30 m = 42 meters
Total length of tie wires for 15 sets = 42 x 15 = 630 meters
Mark: RCB2
Dimensions: 0.20 m x 0.25 m
Average length: 4 meters
Left & Right Support bars: 2 – 12 mm ø top bars, 4 – 12 mm ø bottom bars
Midspan: 4 – 12 mm ø top bars, 2 – 12 mm ø bottom bars
Stirrups: 10 mm ø RSB spaced at 3 – 50 mm, 3 – 100 mm, 3 – 150 mm, rest – 200 mm
No. of sets: 10
Total length required for 10 sets with 6 main bars on each set
L = 5 x 6 x 10= 300 meters
Stirrups
9 pcs. stirrups for 0.85 meters length
L=4m
4 – 2(0.85) = 2.30 m
(2.30/0.20) – 1 = 10.5 say 10 pieces
Total no. stirrups = 18 + 10 = 28 pieces
Total no. of stirrups for 10 sets = 28 x 10 = 280 pieces
Total no. of steel bars (stirrups) = 280 pcs. x 0.70 m = 196 m / 6 = 32.67 say 33 pieces of 10 mm ø steel
bars at 6 meters long
Tie Wire
Using 30 cm long ties
6 pcs. x 28 pcs. = 168 pcs
168 pcs x 0.30 m = 50.4 meters
Total length of tie wires for 10 sets = 50.4 x 10 = 504 meters
Using # 16 G.I. tie wire
Weight of tie wire = 504 / 53 = 9.51 kilograms of # 16 G.I. wire
Mark: RCB3
Dimensions: 0.15 m x 0.25 m
Average length: 2.875 meters
Left & Right Support bars: 2 – 12 mm ø top bars, 4 – 12 mm ø bottom bars
Midspan: 4 – 12 mm ø top bars, 2 – 12 mm ø bottom bars
Stirrups: 10 mm ø RSB spaced at 3 – 50 mm, 3 – 100 mm, 3 – 150 mm, rest – 200 mm
No. of sets: 5
Stirrups
9 pcs. stirrups for 0.85 meters length
L = 2.875 m
Total no. of steel bars (stirrups) = 110 pcs. x 0.60 m = 66 m / 6 = 11 pieces of 10 mm ø steel bars at 6
meters long
Tie Wire
Using 30 cm long ties
6 pcs. x 22 pcs. = 132 pcs
132 pcs x 0.30 m = 39.6 meters
Total length of tie wires for 5 sets = 39.6 x 5 = 198 meters
Mark: GB1
Dimensions: 0.20 m x 0.25 m
Average length: 4 meters
Left & Right Support bars: 2 – 12 mm ø top bars, 4 – 12 mm ø bottom bars
Midspan: 4 – 12 mm ø top bars, 2 – 12 mm ø bottom bars
Stirrups: 10 mm ø RSB spaced at 3 – 50 mm, 3 – 100 mm, 3 – 150 mm, rest – 200 mm
No. of sets: 17
Stirrups
9 pcs. stirrups for 0.85 meters length
L=4m
4 – 2(0.85) = 2.30 m
(2.30/0.20) – 1 = 10.5 say 10 pieces
Total no. stirrups = 18 + 10 = 28 pieces
Total no. of stirrups for 17 sets = 28 x 17 = 476 pieces
Total no. of steel bars (stirrups) = 476 pcs. x 0.70 m = 333.2 m / 6 = 55.53 say 56 pieces of 10 mm ø
steel bars at 6 meters long
Tie Wire
Using 30 cm long ties
6 pcs. x 28 pcs. = 168 pcs
168 pcs x 0.30 m = 50.4 meters
Total length of tie wires for 17 sets = 50.4 x 17 = 856.8 meters