Sunteți pe pagina 1din 23

Summary/Bill of Materials

Project Title: PROPOSED ONE-STOREY RESIDENTIAL HOUSE WITH MEZZANINE


Project Location: BLK. 10, STA. ROSA HOMES SUBD., BRGY. DITA, STA. ROSA LAGUNA
Subject: STRUCTURAL MATERIALS ESTIMATE
Prepared by: Carlo Michael Villafuerte BSCE-4B
Student no: 18-21852

A. Concrete Works
Item Description Quantity Unit
Portland Cement 501 bags (40kg)
Sand 29 m3
Crushed Gravel 57 m3

B. Masonry Works
Item Description Quantity Unit
CHB (6" thk.) 2517 pcs.
CHB (4" thk.) 1474 pcs.
Portland Cement 289 bags (40kg)
Sand 23 m3
Fine Sand 12 m3

C. Steel Works
Item Description Quantity Unit
10 mm ø RSB (6 meters) 793 pcs.
12 mm ø RSB (6 meters) 403 pcs.
16 mm ø RSB (6 meters) 207 pcs.
#16 G.I. Tie Wire (30 cm) 138 kg.
Concrete Works

Slab

For shorter computation I used AREA command in AutoCAD.

Ground Floor

Room Floor Area


Living room 28.963 m2
Dining room 15.207 m2
Kitchen 12.230 m2
Toilet 4.908 m2
Storage 5.776 m2
T&B 4.925 m2
Bedroom 01 14.724 m2
Total 86.733 m2

Ground Floor Slab Thickness = 0.20 m


Volume = (86.733 m2)(0.20 m) = 17.3466 m3

Second Floor (Mezzanine)

Room Floor Area


Staircase entrance 13.524 m2
Bedroom 02 10.638 m2
Bedroom 03 9.984 m2
Terrace 1 6.469 m2
Terrace 2 10.818 m2
Toilet 2.568 m2
Total 54.001 m2

Second Floor Slab Thickness = 0.15 m


Volume = (54.001 m2)(0.15 m) = 8.1002 m3

Total Slab Volume = 17.3466 m3 + 8.1002 m3


Total Slab Volume = 25.4468 m3

Referring from Table 1-2 of SCE by Max Fajardo


Using 40 kg. cement (in bag) class A mixture;

Cement: 25.4468 x 9.0 = 229.0212 bags


Sand: 25.4468 x .50 = 12.7234 m3
Gravel: 25.4468 x 1.0 = 25.4468 m3
Footing

Mark Width (m) Length (m) Depth (m) No. of Sets Volume (m3)
F1 1.10 1.10 0.30 8 2.904
F2 0.80 0.80 0.30 5 0.96
Total 3.864

Wall Footing

Mark Width (m) Depth (m) Estimated Perimeter (m) Volume (m3)
WF1 0.50 0.25 15.365 1.921

Total Footing Volume = 3.864 m3 + 1.921 m3


Total Footing Volume = 5.785 m3

Referring from Table 1-2 of SCE by Max Fajardo


Using 40 kg. cement (in bag) class B mixture;

Cement: 5.785 x 7.5 = 43.3875 bags


Sand: 5.785 x .50 = 2.8925 m3
Gravel: 5.785 x 1.0 = 5.785 m3

Column

Ground Floor

Mark Size (m) Length (m) No. of Sets Volume (m3)


C1 0.25 x 0.35 4.45 8 3.115
C2 0.25 x 0.25 4.45 4 1.1125
C3 0.30 x 0.30 4.45 1 0.4005
FC4 0.15 x 0.35 4.45 1 0.233625
Total 4.861

Second Floor (Mezzanine)

Mark Size (m) Length (m) No. of Sets Volume (m3)


C1 0.25 x 0.35 2.8 6 1.47
FC4 0.15 x 0.35 2.8 3 0.441
Total 1.911

Total Column Volume = 4.861 m3 + 1.911 m3


Total Column Volume = 6.772 m3

Referring from Table 1-2 of SCE by Max Fajardo


Using 40 kg. cement (in bag) class A mixture;

Cement: 6.772 x 9.0 = 60.948 bags


Sand: 6.772 x .50 = 3.386 m3
Gravel: 6.772 x 1.0 = 6.772 m3
Beam

Foundation (tie beams)

Mark Width (m) Depth (m) Length (m) No. of Sets Volume (m3)
1.750 2 0.1750
3.800 1 0.1900
3.100 1 0.1550
3.650 1 0.1825
3.150 1 0.1575
GB1 0.20 0.25 3.700 3 0.5550
3.475 2 0.3475
3.575 1 0.17875
3.525 2 0.3525
3.375 1 0.16875
3.750 2 0.3750
3.600 1 0.1800
Total 18 3.0175

Ground Floor

Mark Width (m) Depth (m) Length (m) No. of Sets Volume (m3)
1.750 2 0.2100
3.800 1 0.2280
3.100 1 0.1860
3.650 1 0.2190
3.150 1 0.1890
RCB1 0.20 0.30 3.700 3 0.6660
3.475 2 0.4170
3.575 1 0.2145
3.525 2 0.4230
3.375 1 0.2025
3.750 1 0.2250
3.600 1 0.2160
3.750 1 0.1875
RCB2 0.20 0.25 3.800 1 0.1900
4.500 1 0.2250
Total 20 3.9985

Second Floor (Mezzanine)

Mark Width (m) Depth (m) Length (m) No. of Sets Volume (m3)
RCB2 0.20 0.25 3.700 2 0.3700
3.475 1 0.1738
3.375 2 0.3375
3.525 1 0.1763
3.575 1 0.1788
RCB3 0.15 0.25 1.825 2 0.1369
1.875 1 0.0703
3.775 2 0.2831
Total 12 1.7266

Total Beam Volume = 3.0175 m3 + 3.9985 m3 + 1.7266 m3


Total Beam Volume = 8.7426 m3

Referring from Table 1-2 of SCE by Max Fajardo


Using 40 kg. cement (in bag) class A mixture;
Cement: 8.7426 x 9.0 = 78.6834 bags
Sand: 8.7426 x .50 = 4.3713 m3
Gravel: 8.7426 x 1.0 = 8.7426 m3

Stairs

Total cross-sectional area = 8.03 m2 + 0.86 m2


Total cross-sectional area = 8.89 m2

Span = 1.1 m

Volume = (1.1 m)(8.89 m2) = 9.779 m3

Referring from Table 1-2 of SCE by Max Fajardo


Using 40 kg. cement (in bag) class A mixture;

Cement: 9.779 x 9.0 = 88.011 bags


Sand: 9.779 x .50 = 4.8895 m3
Gravel: 9.779 x 1.0 = 9.779 m3
Masonry Works

CHB Wall
*CHB laying started 0.55 m below natural ground line

First Floor

Exterior Walls (15x20x40)

Section Height (m) Perimeter (m) Area (m2)

A-B 14.12 51.538


B-C 3.65 13.04 47.596

C-D 7.00 25.550


1-2 5.05 18.433

2-3 7.35 26.838


3-4 0 0

Total 46.56 169.955

Interior Walls (10x20x40)

Section Height (m) Perimeter Area (m2)


A-B 5.80 21.170
B-C 3.65 3.70 13.505

C-D 0 0
1-2 6.90 25.185

2-3 3.55 12.958


3-4 3.10 11.315

Total 23.05 84.133

Second Floor (Mezzanine)

Exterior Walls (15x20x40)

Section Height (m) Perimeter (m) Area (m2)

A-B 0 0
B-C 2.40 7.45 17.880

C-D 7.10 17.040


1-2 6.85 16.440

2-3 3.64 8.736


3-4 0 0

Total 25.04 60.096


Interior Walls (10x20x40)

Section Height (m) Perimeter Area (m2)

A-B 3.48 8.532


B-C 2.40 5.84 14.016

C-D 2.33 5.592


1-2 4.83 11.592

2-3 1.875 4.500


3-4 0 0

Total 18.36 44.232

Windows & Doors (Exterior Walls)


Total Area = 3W1+W2+W3+W5+2D1+D7+2D8
Total Area = 3[(1.20)(0.90)]+(1.20)(0.60)+(2.10)(2.40)+(2.10)(3.60)+2[(1.20)(2.40)]+3[(2.15)(1.00)]
Total Area = 28.77 m2

Windows & Doors (Interior Walls)


Total Area = 2W4+D2+D3+D4+D5+D6
Total Area = 2[(0.6)(0.6)]+(2.15)(1.00)+(2.10)(1.20)+(1.85)(0.70)+(2.10)(0.90)+(2.10)(0.90)
Total Area = 10.465 m2

Total Exterior Wall Area (15x20x40)


Area = [(169.955) + (60.096)] - 28.77 = 201.281 m 2

Total Interior Wall Area (10x20x40)


Area = [(84.133) + (44.232)] - 10.465 = 117.9 m 2

CHB (15x20x40)
Quantity of Cement and Sand for CHB Mortar
Referring from Table 2-2 of SCE by Max Fajardo
Using 15x20x40 under class C mixture;

CHB = 201.281 x 12.5 = 2516.0125 pcs.


Cement = 201.281 x 0.763 = 153.577 bags
Sand = 201.281 x 0.0844 = 16.988 m3

Area of top surface of the fence = 0.15 x (46.56 + 25.04) = 10.74 m 2


Area to be plastered = 201.281(2) + 10.74 = 413.302 m 2

Quantity of Cement and Sand for Plaster


Referring from Table 2-4 of SCE by Max Fajardo
Using 40 kg. cement class D, 20 mm thick plaster

Cement = 413.302 x 0.150 = 61.995 bags


Sand = 413.302 x 0.020 = 8.266 m3 (fine sand)
CHB (10x20x40)
Quantity of Cement and Sand for CHB Mortar
Referring from Table 2-2 of SCE by Max Fajardo
Using 10x20x40 under class C mixture;

CHB = 117.9 x 12.5 = 1473.75 pcs.


Cement = 117.9 x 0.394 = 46.453 bags
Sand = 117.9 x 0.0435 = 5.129 m3

Area of top surface of the fence = 0.15 x (23.05 + 18.36) = 6.21 m 2


Area to be plastered = 117.9(2) + 6.21 = 242.010 m 2

Quantity of Cement and Sand for Plaster


Referring from Table 2-4 of SCE by Max Fajardo
Using 40 kg. cement class C, 12 mm thick plaster

Cement = 242.010 x 0.108 = 26.137 bags


Sand = 242.010 x 0.012 = 2.904 m3 (fine sand)

Steel Works

Reinforcement of Concrete Hollow Blocks

Total Area of Fence (Exterior & Interior Walls)


Area = 201.281 + 117.9 = 319.181 m2

Length of Reinforcing Bars for CHB in Meters


Referring from Table 3-5 of SCE by Max Fajardo

Vertical reinforcement: spaced at 60 centimeters (600 mm)


Vertical reinforcement = 319.181 x 2.13 = 679.86 m. long

Horizontal reinforcement: placed at every 3 layers


Horizontal reinforcement = 319.181 x 2.15 = 686.24 m long

Total length = 679.86 + 686.24 = 1366.1 m


No. of steel bar = 1366.1/6.0 = 227.7 pieces 10 mm ø x 6.00 m

Tie Wire for CHB Reinforcement

Total Area of Fence (Exterior & Interior Walls)


Area = 201.281 + 117.9 = 319.181 m2

No. 16 G.I. Tie Wire for CHB Reinforcement per Square Meter
Referring from Table 3-6 of SCE by Max Fajardo

Along 60 cm. vertical spacing and 3 layers horizontal spacing of reinforcement at 30 cm. long tie wire;

Weight of tie wire = 319.181 x 0.032 = 10.21 kg. # 16 G.I. wire


Independent Footing Reinforcement

Mark: F1
Dimensions: 1.10 m x 1.10 m x 0.30 m
Footing Reinforcement: 8 – 16 mm ø RSB both ways
No. of sets: 8
Hook/bend: not specified on the plan

Net Length = 1.10 – 2(0.075)


Net Length = 0.95 m

No. of cut bars = 8 x 2 = 16 pieces of 16 mm at 0.95 m. long


Total cut bars = 16 x 8 = 128 pieces

Using 6.00 m long commercial steel bar


6.00/0.95 = 6.32 pieces

Without considering the fractional value;

Required no. of steel bars = 128/6 = 21.33 say 22 pieces of 16 mm ø steel bars at 6 meters long

Footing Tie Wire (F1)

No. of intersections in one footing = 8 x 8 = 64 intersections


Total ties = 64 x 8 = 512 ties

Using 30 cm long ties


Length = 512 x 0.30 = 153.6 meters G.I. wire

1 kg. of #16 tie wire ≈ 53 meters

Weight of tie wire = 153.6/53 = 2.89 say 3 kilograms # 16 G.I. wire

Mark: F2
Dimensions: 0.80 m x 0.80 m x 0.30 m
Footing Reinforcement: 8 – 16 mm ø RSB both ways
No. of sets: 5
Hook/bend: not specified on the plan

Net Length = 0.80 – 2(0.075)


Net Length = 0.65 m

No. of cut bars = 8 x 2 = 16 pieces of 16 mm at 0.65 m. long


Total cut bars = 16 x 5 = 80 pieces

Using 6.00 m long commercial steel bar


6.00/0.65 = 9.23 pieces

Without considering the fractional value;

Required no. of steel bars = 80/9 = 8.88 say 9 pieces of 16 mm ø steel bars at 6 meters long

Footing Tie Wire (F2)

No. of intersections in one footing = 8 x 8 = 64 intersections


Total ties = 64 x 5 = 320 ties

Using 30 cm long ties


Length = 320 x 0.30 = 96 meters G.I. wire

1 kg. of #16 tie wire ≈ 53 meters

Weight of tie wire = 96/53 = 1.81 say 2 kilograms # 16 G.I. wire

Mark: WF1
Dimensions: 0.25 m x 0.50 m
Footing Reinforcement: 3 – 10 mm ø temperature bars, 12 mm ø main bars spaced at 140 mm
Estimated Perimeter = 15.365 meters
Hook/bend: not specified on the plan

Length of main bar


L = 0.50 – 2(0.075) + 4(0.012) = 0.398 ≈ 0.40 meters
No. of main bars given 15.365 meters of footing length
# = 15.365/0.14 = 109.75 say 109 pieces
Total length of main bars = 109 x 0.40 = 43.9 meters
No. of steel bars (main bars) required = 43.9/6 = 7.32 say 8 pieces 12 mm ø steel bars at 6 meters long

Total length of temp. bars given 15.365 meters of footing length


Total length of temp. bars = 15.365 x 3 = 46.095 meters
No. of steel bars (temp. bars) required = 46.095/6 = 7.68 say 8 pieces 10 mm ø steel bars at 6 meters
long

No. of intersections for wall footing = 3 x 109 = 327 intersections

Using 30 cm long ties


Length = 327 x 0.30 = 98.1 meters G.I. wire

Weight of tie wire = 98.1/53 = 1.85 say 2 kilograms # 16 G.I. wire


Post and Column Reinforcement

Mark: C1 (from ground floor to second floor)


Dimensions: 0.25 m x 0.35 m
Main Bars: 6 – 16 mm ø RSB
Lateral Ties: 10 mm ø RSB
No. of Sets: 6
Length of Main Steel Bar
L = 0.40 + 0.25 + 2.15 + 0.30 + 2.7 + 0.25 + 1.5 + 0.30 = 7.85 m
L1 = 4.45 m
L2 = 2.15 m
Ties: spaced as follows; 3 – 50 mm, 3 – 100 mm, 3 – 150 mm, rest – 200 mm

For 6 meters length RSB additional splicing = 20(0.016) + 0.16 = 0.48 m


L = 7.85 + 0.48 = 8.33 m ≈ 9 meters
Total length of steel bars required = 9 m x 6 main bars = 54 linear meters
No. of bars required = 54/6 = 9 pieces 16 mm ø steel bars at 6 meters long

Total no. of bars for 6 sets = 9 x 6 = 54 pieces of 16 mm ø steel bars at 6 meters long

Lateral ties

9 pcs. Ties for 0.85 meters length

For L1 = 4.45 m

4.45 – 2(0.85) = 2.75 m


(2.75/0.20) – 1 = 12.75 say 12 pieces
Total ties for L1 = 18 + 12 = 30 pcs.

For L2 = 2.15 m

2.15 – 2(0.85) = 0.45 m


(0.45/0.20) – 1 = 1.25 say 1 piece
Total ties for L2 = 18 + 1 = 19 pcs.
Total ties = 30 + 19 = 49 pcs
Total ties for 6 sets = 49 x 6 = 294 pieces

Length of Ties (assuming 40 cm steel cover)


LTIES = 2(0.27+0.17) = 0.88 m
Overlapping (assuming 0.10 m)
Total length of ties = 0.88 + 0.10 = 0.98 m ≈ 1.0 m

Total no. of steel bars (ties) = 294 pcs. x 1.0 m = 294 m / 6 = 49 pieces of 10 mm ø steel bars at 6
meters long

Tie Wire
Using 30 cm long ties
6 pcs. x 49 pcs. = 294 pcs
294 pcs x 0.30 m = 88.2 meters
Total length of tie wires for 6 sets = 88.2 x 6 = 529.2 meters

Using # 16 G.I. tie wire


Weight of tie wire = 529.2 / 53 = 9.98 kilograms of # 16 G.I. wire

Mark: C1 (only ground floor)


Dimensions: 0.25 m x 0.35 m
Main Bars: 6 – 16 mm ø RSB
Lateral Ties: 10 mm ø RSB
No. of Sets: 2
Length of Main Steel Bar
L = 0.30 + 2.7 + 0.25 + 1.5 + 0.30 = 5.05 m
L1 = 4.45 m
Ties: spaced as follows; 3 – 50 mm, 3 – 100 mm, 3 – 150 mm, rest – 200 mm

For 6 meters length RSB additional splicing = 20(0.016) + 0.16 = 0.48 m


L = 5.05 + 0.48 = 5.53 m ≈ 6 meters
Total length of steel bars required = 6 m x 6 main bars = 36 linear meters
No. of bars required = 36/6 = 6 pieces 16 mm ø steel bars at 6 meters long

Total no. of bars for 2 sets = 6 x 2 = 12 pieces of 16 mm ø steel bars at 6 meters long

Lateral ties

9 pcs. Ties for 0.85 meters length

For L1 = 4.45 m

4.45 – 2(0.85) = 2.75 m


(2.75/0.20) – 1 = 12.75 say 12 pieces
Total ties for L1 = 18 + 12 = 30 pcs.
Total ties for 2 sets = 30 x 2 = 60 pieces

Length of Ties (assuming 40 cm steel cover)


LTIES = 2(0.27+0.17) = 0.88 m
Overlapping (assuming 0.10 m)
Total length of ties = 0.88 + 0.10 = 0.98 m ≈ 1.0 m

Total no. of steel bars (ties) = 60 pcs. x 1.0 m = 60 m / 6 = 10 pieces of 10 mm ø steel bars at 6 meters
long
Tie Wire
Using 30 cm long ties
6 pcs. x 30 pcs. = 180 pcs
180 pcs x 0.30 m = 54 meters
Total length of tie wires for 2 sets = 54 x 2 = 108 meters

Using # 16 G.I. tie wire


Weight of tie wire = 108 / 53 = 2.04 kilograms of # 16 G.I. wire

Mark: C2 (only ground floor)


Dimensions: 0.25 m x 0.25 m
Main Bars: 6 – 16 mm ø RSB
Lateral Ties: 10 mm ø RSB
No. of Sets: 4
Length of Main Steel Bar
L = 0.30 + 2.7 + 0.25 + 1.5 + 0.30 = 5.05 m
L1 = 4.45 m
Ties: spaced as follows; 3 – 50 mm, 3 – 100 mm, 3 – 150 mm, rest – 200 mm

For 6 meters length RSB additional splicing = 20(0.016) + 0.16 = 0.48 m


L = 5.05 + 0.48 = 5.53 m ≈ 6 meters
Total length of steel bars required = 6 m x 6 main bars = 36 linear meters
No. of bars required = 36/6 = 6 pieces 16 mm ø steel bars at 6 meters long

Total no. of bars for 4 sets = 6 x 4 = 24 pieces of 16 mm ø steel bars at 6 meters long

Lateral ties

9 pcs. Ties for 0.85 meters length

For L1 = 4.45 m

4.45 – 2(0.85) = 2.75 m


(2.75/0.20) – 1 = 12.75 say 12 pieces
Total ties for L1 = 18 + 12 = 30 pcs.
Total ties for 4 sets = 30 x 4 = 120 pieces

Length of Ties (assuming 40 cm steel cover)


LTIES = 2(0.17+0.17) = 0.68 m
Overlapping (assuming 0.10 m)
Total length of ties = 0.68 + 0.10 = 0.78 m ≈ 0.80 m

Total no. of steel bars (ties) = 120 pcs. x 0.80 m = 96 m / 6 = 16 pieces of 10 mm ø steel bars at 6
meters long
Tie Wire
Using 30 cm long ties
6 pcs. x 30 pcs. = 180 pcs
180 pcs x 0.30 m = 54 meters
Total length of tie wires for 4 sets = 54 x 4 = 216 meters

Using # 16 G.I. tie wire


Weight of tie wire = 216 / 53 = 4.08 kilograms of # 16 G.I. wire

Mark: C3 (only ground floor)


Dimensions: 0.30 m x 0.30 m
Main Bars: 6 – 16 mm ø RSB
Lateral Ties: 10 mm ø RSB
No. of Sets: 1
Length of Main Steel Bar
L = 0.30 + 2.7 + 0.25 + 1.5 + 0.30 = 5.05 m
L1 = 4.45 m
Ties: spaced as follows; 3 – 50 mm, 3 – 100 mm, 3 – 150 mm, rest – 200 mm

For 6 meters length RSB additional splicing = 20(0.016) + 0.16 = 0.48 m


L = 5.05 + 0.48 = 5.53 m ≈ 6 meters
Total length of steel bars required = 6 m x 6 main bars = 36 linear meters
No. of bars required = 36/6 = 6 pieces 16 mm ø steel bars at 6 meters long

Total no. of bars for 1 set = 6 x 1 = 6 pieces of 16 mm ø steel bars at 6 meters long

Lateral ties

9 pcs. Ties for 0.85 meters length

For L1 = 4.45 m

4.45 – 2(0.85) = 2.75 m


(2.75/0.20) – 1 = 12.75 say 12 pieces
Total ties for L1 = 18 + 12 = 30 pcs.
Total ties for 1 set = 30 x 1 = 30 pieces

Length of Ties (assuming 40 cm steel cover)


LTIES = 2(0.22+0.22) = 0.88 m
Overlapping (assuming 0.10 m)
Total length of ties = 0.88 + 0.10 = 0.98 m ≈ 1.0 m

Total no. of steel bars (ties) = 30 pcs. x 1.0 m = 30 m / 6 = 5 pieces of 10 mm ø steel bars at 6 meters
long
Tie Wire
Using 30 cm long ties
6 pcs. x 30 pcs. = 180 pcs
180 pcs x 0.30 m = 54 meters
Total length of tie wires for 1 set = 54 x 1 = 54 meters

Using # 16 G.I. tie wire


Weight of tie wire = 54 / 53 = 1.02 kilograms of # 16 G.I. wire

Mark: FC4 (from ground floor to second floor)


Dimensions: 0.15 m x 0.35 m
Main Bars: 6 – 16 mm ø RSB
Lateral Ties: 10 mm ø RSB
No. of Sets: 1
Length of Main Steel Bar
L = 0.40 + 0.25 + 2.15 + 0.30 + 2.7 + 0.25 + 1.5 + 0.30 = 7.85 m
L1 = 4.45 m
L2 = 2.15 m
Ties: spaced as follows; 3 – 50 mm, 3 – 100 mm, 3 – 150 mm, rest – 200 mm

For 6 meters length RSB additional splicing = 20(0.016) + 0.16 = 0.48 m


L = 7.85 + 0.48 = 8.33 m ≈ 9 meters
Total length of steel bars required = 9 m x 6 main bars = 54 linear meters
No. of bars required = 54/6 = 9 pieces 16 mm ø steel bars at 6 meters long

Total no. of bars for 1 sets = 9 x 1 = 9 pieces of 16 mm ø steel bars at 6 meters long

Lateral ties

9 pcs. Ties for 0.85 meters length

For L1 = 4.45 m

4.45 – 2(0.85) = 2.75 m


(2.75/0.20) – 1 = 12.75 say 12 pieces
Total ties for L1 = 18 + 12 = 30 pcs.

For L2 = 2.15 m

2.15 – 2(0.85) = 0.45 m


(0.45/0.20) – 1 = 1.25 say 1 piece
Total ties for L2 = 18 + 1 = 19 pcs.
Total ties = 30 + 19 = 49 pcs
Total ties for 1 set = 49 x 1 = 49 pieces
Length of Ties (assuming 40 cm steel cover)
LTIES = 2(0.07+0.27) = 0.68 m
Overlapping (assuming 0.10 m)
Total length of ties = 0.68 + 0.10 = 0.78 m ≈ 0.80 m

Total no. of steel bars (ties) = 49 pcs. x 0.80 m = 39.2 m / 6 = 6.53 say 7 pieces of 10 mm ø steel bars at
6 meters long

Tie Wire
Using 30 cm long ties
6 pcs. x 49 pcs. = 294 pcs
294 pcs x 0.30 m = 88.2 meters
Total length of tie wires for 1 set = 88.2 x 1 = 88.2 meters

Using # 16 G.I. tie wire


Weight of tie wire = 88.2 / 53 = 1.66 kilograms of # 16 G.I. wire

Mark: FC4 (only second floor)


Dimensions: 0.15 m x 0.35 m
Main Bars: 6 – 16 mm ø RSB
Lateral Ties: 10 mm ø RSB
No. of Sets: 2
Length of Main Steel Bar
L = 0.40 + 0.25 + 2.15 = 2.80 m
L2 = 2.15 m
Ties: spaced as follows; 3 – 50 mm, 3 – 100 mm, 3 – 150 mm, rest – 200 mm

For 6 meters length RSB additional splicing = 20(0.016) + 0.16 = 0.48 m


L = 2.80 + 0.48 = 3.28 m ≈ 4 meters
Total length of steel bars required = 4 m x 6 main bars = 24 linear meters
No. of bars required = 24/6 = 4 pieces 16 mm ø steel bars at 6 meters long

Total no. of bars for 2 sets = 4 x 2 = 8 pieces of 16 mm ø steel bars at 6 meters long

Lateral ties

9 pcs. Ties for 0.85 meters length

For L2 = 2.15 m

2.15 – 2(0.85) = 0.45 m


(0.45/0.20) – 1 = 1.25 say 1 piece
Total ties for L2 = 18 + 1 = 19 pcs.
Total ties for 2 sets = 19 x 2 = 38 pieces

Length of Ties (assuming 40 cm steel cover)


LTIES = 2(0.07+0.27) = 0.68 m
Overlapping (assuming 0.10 m)
Total length of ties = 0.68 + 0.10 = 0.78 m ≈ 0.80 m

Total no. of steel bars (ties) = 38 pcs. x 0.80 m = 30.40 m / 6 = 5.07 say 6 pieces of 10 mm ø steel bars
at 6 meters long
Tie Wire
Using 30 cm long ties
6 pcs. x 19 pcs. = 114 pcs
114 pcs x 0.30 m = 34.2 meters
Total length of tie wires for 2 sets = 34.2 x 2 = 68.4 meters

Using # 16 G.I. tie wire


Weight of tie wire = 68.4 / 53 = 1.29 kilograms of # 16 G.I. wire

Slab

First Floor

Referring from Table 3-12 of SCE by Max Fajardo


Quantity of Steel Bars in a Two Way Reinforced Concrete Slab per Square Meter
Using a 6.00 m. steel bars at 15 cm. spacing of main reinforcement, use 3.221 as multiplier;

Referring from Table 3-13 of SCE by Max Fajardo


Tie Wire in a Two Way Reinforced Concrete Slab in Kilograms per Square Meter
Along 15 cm. bar spacing and 30 cm. long tie wire, use 0.350 as multiplier;

Section A-B, 1-2


Area = (2.0 m)(1.875 m) + ½ (1.90 m)(2.0 m) = 5.65 m 2
No. of steel bars = 5.65 x 3.221 = 18.20 pieces of 10 mm ø steel bars at 6 meters long
Weight of tie wire = 5.65 x 0.350 = 1.98 kilograms of # 16 G.I. wire

Section A-B, 2-3


Area = (2.0 m)(4.0 m) = 8 m2
No. of steel bars = 8 x 3.221 = 25.77 pieces of 10 mm ø steel bars at 6 meters long
Weight of tie wire = 8 x 0.350 = 2.8 kilograms of # 16 G.I. wire

Section A-B, 3-4


Area = (2.0 m)(0.55 m) + ½ (2.85 m)(2.0 m) = 3.95 m 2
No. of steel bars = 3.95 x 3.221 = 12.72 pieces of 10 mm ø steel bars at 6 meters long
Weight of tie wire = 3.95 x 0.350 = 1.38 kilograms of # 16 G.I. wire

Section B-C, 1-2


Area = (4.0 m)(3.775 m) = 15.1 m2
No. of steel bars = 15.1 x 3.221 = 48.64 pieces of 10 mm ø steel bars at 6 meters long
Weight of tie wire = 15.1 x 0.350 = 5.29 kilograms of # 16 G.I. wire

Section B-C, 2-3


Area = (4.0 m)(4.0 m) = 16 m2
No. of steel bars = 16 x 3.221 = 51.54 pieces of 10 mm ø steel bars at 6 meters long
Weight of tie wire = 16 x 0.350 = 5.6 kilograms of # 16 G.I. wire

Section B-C, 3-4


Area = (3.40 m)(2.575 m) + (1.475 m)(1.225 m) + (2.175 m)(1.475 m)= 13.77 m 2
No. of steel bars = 13.77 x 3.221 = 44.35 pieces of 10 mm ø steel bars at 6 meters long
Weight of tie wire = 13.77 x 0.350 = 4.82 kilograms of # 16 G.I. wire

Section B-C, 4-5


Area = 3.19 m2
No. of steel bars = 3.19 x 3.221 = 10.27 pieces of 10 mm ø steel bars at 6 meters long
Weight of tie wire = 3.19 x 0.350 = 1.11 kilograms of # 16 G.I. wire

Section C-D, 1-2


Area = (3.825 m)(3.775 m) = 14.44 m2
No. of steel bars = 14.44 x 3.221 = 46.51 pieces of 10 mm ø steel bars at 6 meters long
Weight of tie wire = 14.44 x 0.350 = 5.05 kilograms of # 16 G.I. wire

Section C-D, 2-3


Area = (4.0 m)(3.825 m) = 15.3 m2
No. of steel bars = 15.3 x 3.221 = 49.28 pieces of 10 mm ø steel bars at 6 meters long
Weight of tie wire = 15.3 x 0.350 = 5.36 kilograms of # 16 G.I. wire

Second Floor

Referring from Table 3-12 of SCE by Max Fajardo


Quantity of Steel Bars in a Two Way Reinforced Concrete Slab per Square Meter
Using a 6.00 m. steel bars at 15 cm. spacing of main reinforcement, use 3.221 as multiplier;

Referring from Table 3-13 of SCE by Max Fajardo


Tie Wire in a Two Way Reinforced Concrete Slab in Kilograms per Square Meter
Along 15 cm. bar spacing and 30 cm. long tie wire, use 0.350 as multiplier;

Section A-B, 1-2


Area = (2.0 m)(1.875 m) + ½ (1.90 m)(2.0 m) = 5.65 m 2
No. of steel bars = 5.65 x 3.221 = 18.20 pieces of 12 mm ø steel bars at 6 meters long
Weight of tie wire = 5.65 x 0.350 = 1.98 kilograms of # 16 G.I. wire

Section A-B, 2-3


Area = (2.0 m)(4.0 m) = 8 m2
No. of steel bars = 8 x 3.221 = 25.77 pieces of 12 mm ø steel bars at 6 meters long
Weight of tie wire = 8 x 0.350 = 2.8 kilograms of # 16 G.I. wire

Section B-C, 1-2


Area = (4.0 m)(3.775 m) = 15.1 m2
No. of steel bars = 15.1 x 3.221 = 48.64 pieces of 12 mm ø steel bars at 6 meters long
Weight of tie wire = 15.1 x 0.350 = 5.29 kilograms of # 16 G.I. wire

Section B-C, 2-3


Area = (4.0 m)(4.0 m) = 16 m2
No. of steel bars = 16 x 3.221 = 51.54 pieces of 12 mm ø steel bars at 6 meters long
Weight of tie wire = 16 x 0.350 = 5.6 kilograms of # 16 G.I. wire

Section C-D, 1-2


Area = (1.425 m)(3.775 m) = 5.40 m2
No. of steel bars = 5.40 x 3.221 = 46.51 pieces of 12 mm ø steel bars at 6 meters long
Weight of tie wire = 5.40 x 0.350 = 5.05 kilograms of # 16 G.I. wire
Section C-D, 2-3
Area = (4.0 m)(3.825 m) = 15.3 m2
No. of steel bars = 15.3 x 3.221 = 49.28 pieces of 12 mm ø steel bars at 6 meters long
Weight of tie wire = 15.3 x 0.350 = 5.36 kilograms of # 16 G.I. wire

Beam

Mark: RCB1
Dimensions: 0.20 m x 0.30 m
Average length: 4 meters
Left & Right Support bars: 3 – 16 mm ø top bars, 2 – 16 mm ø bottom bars
Midspan: 2 – 16 mm ø top bars, 3 – 16 mm ø bottom bars
Stirrups: 10 mm ø RSB spaced at 3 – 50 mm, 3 – 100 mm, 3 – 150 mm, rest – 200 mm
No. of sets: 15

For 6 meters length RSB additional splicing = 25(0.016) + 0.15 = 0.55 m


Net Length of Main Steel Bar
LNET = 4 + 2[12(0.016)] + 0.55 = 4.934 ≈ 5 meters

Total length required for 15 sets with 5 main bars on each set
L = 5 x 5 x 15= 375 meters

No. of steel bars = 375/6 = 62.5 say 63 pieces of 16 mm ø steel bars at 6 meters long

Stirrups
9 pcs. stirrups for 0.85 meters length

L=4m

4 – 2(0.85) = 2.30 m
(2.30/0.20) – 1 = 10.5 say 10 pieces
Total no. stirrups = 18 + 10 = 28 pieces
Total no. of stirrups for 15 sets = 28 x 15 = 420 pieces

Length of stirrups (assuming 40 cm steel cover)


LTIES = 2(0.12+0.22) = 0.68 m
Overlapping (assuming 0.10 m)
Total length of ties = 0.68 + 0.10 = 0.78 m ≈ 0.80 m
Total no. of steel bars (stirrups) = 420 pcs. x 0.80 m = 336 m / 6 = 56 pieces of 10 mm ø steel bars at 6
meters long

Tie Wire
Using 30 cm long ties
5 pcs. x 28 pcs. = 140 pcs
140 pcs x 0.30 m = 42 meters
Total length of tie wires for 15 sets = 42 x 15 = 630 meters

Using # 16 G.I. tie wire


Weight of tie wire = 630 / 53 = 11.89 kilograms of # 16 G.I. wire

Mark: RCB2
Dimensions: 0.20 m x 0.25 m
Average length: 4 meters
Left & Right Support bars: 2 – 12 mm ø top bars, 4 – 12 mm ø bottom bars
Midspan: 4 – 12 mm ø top bars, 2 – 12 mm ø bottom bars
Stirrups: 10 mm ø RSB spaced at 3 – 50 mm, 3 – 100 mm, 3 – 150 mm, rest – 200 mm
No. of sets: 10

For 6 meters length RSB additional splicing = 25(0.012) + 0.15 = 0.45 m


Net Length of Main Steel Bar
LNET = 4 + 2[12(0.012)] + 0.45 = 4.738 ≈ 5 meters

Total length required for 10 sets with 6 main bars on each set
L = 5 x 6 x 10= 300 meters

No. of steel bars = 300/6 = 50 pieces of 12 mm ø steel bars at 6 meters long

Stirrups
9 pcs. stirrups for 0.85 meters length

L=4m

4 – 2(0.85) = 2.30 m
(2.30/0.20) – 1 = 10.5 say 10 pieces
Total no. stirrups = 18 + 10 = 28 pieces
Total no. of stirrups for 10 sets = 28 x 10 = 280 pieces

Length of stirrups (assuming 40 cm steel cover)


LTIES = 2(0.12+0.17) = 0.58 m
Overlapping (assuming 0.10 m)
Total length of ties = 0.58 + 0.10 = 0.68 m ≈ 0.70 m

Total no. of steel bars (stirrups) = 280 pcs. x 0.70 m = 196 m / 6 = 32.67 say 33 pieces of 10 mm ø steel
bars at 6 meters long
Tie Wire
Using 30 cm long ties
6 pcs. x 28 pcs. = 168 pcs
168 pcs x 0.30 m = 50.4 meters
Total length of tie wires for 10 sets = 50.4 x 10 = 504 meters
Using # 16 G.I. tie wire
Weight of tie wire = 504 / 53 = 9.51 kilograms of # 16 G.I. wire

Mark: RCB3
Dimensions: 0.15 m x 0.25 m
Average length: 2.875 meters
Left & Right Support bars: 2 – 12 mm ø top bars, 4 – 12 mm ø bottom bars
Midspan: 4 – 12 mm ø top bars, 2 – 12 mm ø bottom bars
Stirrups: 10 mm ø RSB spaced at 3 – 50 mm, 3 – 100 mm, 3 – 150 mm, rest – 200 mm
No. of sets: 5

For 6 meters length RSB additional splicing = 25(0.012) + 0.15 = 0.45 m


Net Length of Main Steel Bar
LNET = 2.875 + 2[12(0.012)] + 0.45 = 3.613 ≈ 4 meters

Total length required for 5 sets with 6 main bars on each


L = 4 x 6 x 5= 120 meters

No. of steel bars = 120/6 = 20 pieces of 12 mm ø steel bars at 6 meters long

Stirrups
9 pcs. stirrups for 0.85 meters length

L = 2.875 m

2.875 – 2(0.85) = 1.175 m


(1.175/0.20) – 1 = 4.875 say 4 pieces
Total no. stirrups = 18 + 4 = 22 pieces
Total no. of stirrups for 5 sets = 22 x 5 = 110 pieces

Length of stirrups (assuming 40 cm steel cover)


LTIES = 2(0.07+0.17) = 0.48 m
Overlapping (assuming 0.10 m)
Total length of ties = 0.48 + 0.10 = 0.58 m ≈ 0.60 m

Total no. of steel bars (stirrups) = 110 pcs. x 0.60 m = 66 m / 6 = 11 pieces of 10 mm ø steel bars at 6
meters long
Tie Wire
Using 30 cm long ties
6 pcs. x 22 pcs. = 132 pcs
132 pcs x 0.30 m = 39.6 meters
Total length of tie wires for 5 sets = 39.6 x 5 = 198 meters

Using # 16 G.I. tie wire


Weight of tie wire = 198 / 53 = 3.74 kilograms of # 16 G.I. wire

Mark: GB1
Dimensions: 0.20 m x 0.25 m
Average length: 4 meters
Left & Right Support bars: 2 – 12 mm ø top bars, 4 – 12 mm ø bottom bars
Midspan: 4 – 12 mm ø top bars, 2 – 12 mm ø bottom bars
Stirrups: 10 mm ø RSB spaced at 3 – 50 mm, 3 – 100 mm, 3 – 150 mm, rest – 200 mm
No. of sets: 17

For 6 meters length RSB additional splicing = 25(0.012) + 0.15 = 0.45 m


Net Length of Main Steel Bar
LNET = 4 + 2[12(0.012)] + 0.45 = 4.738 ≈ 5 meters

Total length required for 17 sets with 6 main bars on each


L = 5 x 6 x 17= 510 meters

No. of steel bars = 510/6 = 85 pieces of 12 mm ø steel bars at 6 meters long

Stirrups
9 pcs. stirrups for 0.85 meters length

L=4m

4 – 2(0.85) = 2.30 m
(2.30/0.20) – 1 = 10.5 say 10 pieces
Total no. stirrups = 18 + 10 = 28 pieces
Total no. of stirrups for 17 sets = 28 x 17 = 476 pieces

Length of stirrups (assuming 40 cm steel cover)


LTIES = 2(0.12+0.17) = 0.58 m
Overlapping (assuming 0.10 m)
Total length of ties = 0.58 + 0.10 = 0.68 m ≈ 0.70 m

Total no. of steel bars (stirrups) = 476 pcs. x 0.70 m = 333.2 m / 6 = 55.53 say 56 pieces of 10 mm ø
steel bars at 6 meters long
Tie Wire
Using 30 cm long ties
6 pcs. x 28 pcs. = 168 pcs
168 pcs x 0.30 m = 50.4 meters
Total length of tie wires for 17 sets = 50.4 x 17 = 856.8 meters

Using # 16 G.I. tie wire


Weight of tie wire = 856.8 / 53 = 16.17 kilograms of # 16 G.I. wire