Question
Which of the following aspects are essential to ensure quality of purchased items?
Correct Answer
Defining right quality for the job , Vendor performance evaluation , Making sure
that suppliers understand the requirements
Your Answer
Defining right quality for the job , Vendor performance evaluation , Making sure
that suppliers understand the requirements
True/False
Question
After goods have been manufactured, route sheets and operation layouts should
not be collected back.
Correct Answer
False
Your Answer
False
True/False
Question
In case of centralised inspection, inspection rooms generally become bottleneck
and cause delay in taking action regarding rejection or rework.
Correct Answer
True
Your Answer
True
True/False
Question
During set up of X bar-R control chart, control limts should be practically revised
from time to time as additional data is accumulated.
Correct Answer
True
Your Answer
False
True/False
Question
Floor inspection delays the identification of faults which can not be rectified
immediately before large lots are spoiled.
Correct Answer
False
Your Answer
False
True/False
Question
Cent percent inspection is required on WIP prior to the key, critical or costly
operation.
Correct Answer
True
Your Answer
True
True/False
Question
An activity can share the same tail event and same head event with any other
activity.
Correct Answer
False
Your Answer
True
True/False
Question
Independent float either affects the float of preceding activities or that of
succeeding activities.
Correct Answer
False
Your Answer
False
True/False
Question
F W Taylor devised a system for classifying motions into basic divisions called
Therbligs
Correct Answer
False
Your Answer
False
True/False
Question
In case of two handed process chart, the simultaneous activities of both hands are
recorded opposite to each other on the chart.
Correct Answer
True
Your Answer
True
True/False
Question
An activity should represent an operation or set of operations which can be
performed using a particular kind of equipment or a special skill.
Correct Answer
True
Your Answer
True
True/False
Question
In case of X bar, if the process is not under control indicated by some points
falling outside the control limits, such points outside the control limits are
eliminated and new trial control limits for the remaining points are computed.
Correct Answer
True
Your Answer
True
True/False
Question
After goods have been manufactured, route sheets and operation layouts should
not be collected back.
Correct Answer
False
Your Answer
False
True/False
Question
Planned lubrication is said to be the nervous system of the equipment.
Correct Answer
True
Your Answer
True
True/False
Question
An activity can share the same tail event and same head event with any other
activity.
Correct Answer
False
Your Answer
True
True/False
Question
Only skilled worker can use the fixed limit gauge.
Correct Answer
False
Your Answer
False
True/False
Question
Breakdown of machines, absenteeism of worker does not dislocate the
manufacturing activity in process layout
Correct Answer
True
Your Answer
True
True/False
Question
Dust gets mixed with lubricants, forms an abrasive substance and causes pre-
mature failure of machinery.
Correct Answer
True
Your Answer
True
True/False
Question
Operation process charts though indicates the sequence of events but do not
show movements.
Correct Answer
True
Your Answer
True
http://scdlpapers.blogspot.com
True/False
Question
The problems of congestion, bottlenecks and backtracking can not be visualized
by using templates and models.
Correct Answer
False
Your Answer
False
True/False
Question
Skill of labour force in a product type layout is usually higher than in the process
type of layout
Correct Answer
False
Your Answer
True
True/False
Question
Recording of movement is not necessary in case of method study in any form.
Correct Answer
False
Your Answer
True
True/False
Question
Inspection should be conducted on all incoming materials, semifinished items,
bought out components, subcontract items prior to any operation, assembly.
Correct Answer
True
Your Answer
True
True/False
Question
A load chart specifies the work to be carried out by each person of company
during shift hours.
Correct Answer
False
Your Answer
False
True/False
Question
Breakdown is inversly proportional to the investment in W.I.P.
Correct Answer
False
Your Answer
True
True/False
Question
short cycle job should be studied for macroscopic motions.
Correct Answer
False
Your Answer
True
True/False
Question
Inspection Order can be a verbal order
Correct Answer
True
Your Answer
False
True/False
Question
In case of backward pass computation, the latest event time of the end event
equals to the earliest event time minus duration of that activity.
Correct Answer
False
Your Answer
True
True/False
Question
In Gantt Chart, the horizontal lines devide vertical lines into sections which
represents either operations or work centres.
Correct Answer
True
Your Answer
True
Multiple Choice Multiple Answer
Question Why graphical method of recording is preferred over the descriptive
method during method study?
Correct Answer It segregates effective part form ineffective parts , It reduces
effort involved in writing , Critical examinations easier and more effective
Your Answer Critical examinations easier and more effective , It segregates
effective part form ineffective parts , It reduces effort involved in writing
True/False
Question Expediting action is necessary if the delays and interruptions are
abnormal and hence any subsequent delay is bound to extend the promised
delivery date.
Correct Answer True
Your Answer True
True/False
Question Breakdown of machines, absenteeism of worker does not dislocate the
manufacturing activity in process layout
Correct Answer True
Your Answer True
True/False
Question Dust gets mixed with lubricants, forms an abrasive substance and
causes pre-mature failure of machinery.
Correct Answer True
Your Answer True
Multiple Choice Multiple Answer
Question Which of the following can be subtypes of corrective maintenance?
Correct Answer Shutdown Maintenance , Design-out Maintenance , Design-in
Maintenance
Your Answer Shutdown Maintenance , Design-out Maintenance , Design-in
Maintenance
True/False
Question All activities must not be tied up into the network
Correct Answer False
Your Answer False
True/False
Question Operation Process Chart provides information on time and distances
Correct Answer False
Your Answer False
True/False
Question Inspection order is must even for simple jobs which can be inspected by
shop inspector with the tooling available on shop.
Correct Answer False
Your Answer True
True/False
Question Feasibility of time schedule requires that an activity be scheduled before
any of it's predecessors are scheduled.
Correct Answer False
Your Answer True
True/False
Question Planned lubrication is said to be the nervous system of the equipment.
Correct Answer True
Your Answer True
True/False
Question A network should be progression of activities always moving forward.
Correct Answer True
Your Answer True
True/False
Question For p-chart, the central line of fraction defectives is determined by
average percentage defectives.
Correct Answer True
Your Answer True
POM assgn
Multiple Choice Single Answer
Question
MRP is based on the concept of inventory demand which is of following type
Correct Answer
Dependent and independent
Your Answer
Dependent and independent
True/False
Question
As a general rule, the number of tail event of an activity is more than that of it's
head event.
Correct Answer
False
Your Answer
False
Select The Blank
Question
The ________ is the probability that a good lot will be rejected by the sampling
plan.
Correct Answer
Producer's risk
Your Answer
Producer's risk
True/False
Question
All activities must not be tied up into the network
Correct Answer
False
Your Answer
False
True/False
Question
In case of X bar, if the process is not under control indicated by some points
falling outside the control limits, such points outside the control limits are
eliminated and new trial control limits for the remaining points are computed.
Correct Answer
True
Your Answer
True
True/False
Question
Inspection order is must even for simple jobs which can be inspected by shop
inspector with the tooling available on shop.
Correct Answer
False
Your Answer
False
True/False
Question
Cent percent inspection is often more practical and economical than sampling
inspection.
Correct Answer
False
Your Answer
False
True/False
Question
A load chart specifies the work to be carried out by each person of company
during shift hours.
Correct Answer
False
Your Answer
True
True/False
Question
Cellular layout is based on the concept of Group Technology
Correct Answer
True
Your Answer
True
True/False
Question
In case of forward pass computation, the earliest event time of the first event is
zero.
Correct Answer
True
Your Answer
True
True/False
Question
As a general rule, a site five times the actual plant size is considered minimum for
parking, access facilities and future expansion.
Correct Answer
True
Your Answer
True
True/False
Question
Independent float either affects the float of preceding activities or that of
succeeding activities.
Correct Answer
False
Your Answer
False
True/False
Question
As a general rule, the number of tail event of an activity is more than that of it's
head event.
Correct Answer
False
Your Answer
False
True/False
Question
All activities must not be tied up into the network
Correct Answer
False
Your Answer
False
True/False
Question
In case of X bar, if the process is not under control indicated by some points
falling outside the control limits, such points outside the control limits are
eliminated and new trial control limits for the remaining points are computed.
Correct Answer
True
Your Answer
True
True/False
Question
Inspection order is must even for simple jobs which can be inspected by shop
inspector with the tooling available on shop.
Correct Answer
False
Your Answer
False
True/False
Question
Cent percent inspection is often more practical and economical than sampling
inspection.
Correct Answer
False
Your Answer
False
True/False
Question
A load chart specifies the work to be carried out by each person of company
during shift hours.
Correct Answer
False
Your Answer
True
True/False
Question
In case of forward pass computation, the earliest event time of the first event is
zero.
Correct Answer
True
Your Answer
True
True/False
Question
As a general rule, a site five times the actual plant size is considered minimum for
parking, access facilities and future expansion.
Correct Answer
True
Your Answer
True
True/False
Question
Independent float either affects the float of preceding activities or that of
succeeding activities.
Correct Answer
False
Your Answer
False