cylinder 4 K5452
Jan 19, Bahia Blanca, Argentina
Dow.com
Event description
Date: January 7th.
Description: LDPE was proactively SD due to a abnormal noise detected on Hyper Compressor coming
from cyl#4, preliminary finding shows that one spring of the poppet valve was found broken,
therefore the plant should be ready to SU after valve replacement.
Unfortunately, LDPE train will remain down due to lack of steam supply from BB1. Steam leaks were
detected a month ago and have been increasing until current situation that header should be repair in
order to minimize potential risk. According to site utilities team this repair will take 7 days working
around the clock and 9 days of total downtime. BB1 is the only one supplier of high pressure steam
for LDPE.
AU Losses: TBD.
Eatool: TBD.
DOW RESTRICTED 2
Findings Cylinder # 4 2nd stage
Coupling
DOW RESTRICTED 3
Findings discharge valve (Cylinder # 4 2nd stage)
Parts Finding Days Pictures
running
G7 – Spring. • Discharge valve springs 182
broken. The cone was
found down without
spring pre load.
DOW RESTRICTED 4
Findings gas packing (Cylinder # 4 2nd stage)
DOW RESTRICTED 5
Findings high pressure packing (Cylinder # 4 2nd stage)
Parts Finding Days Pictures
running
E47 – • Radial ring opened on 183
Metallic packing cup # 3 and 2.
packing incl.
E12a + E70.
• Tangential ring broken
on packing cup # 4.
DOW RESTRICTED 6
Findings high pressure packing (Cylinder # 4 2nd stage)
Parts Finding Days Pictures
running
E47 – • Marks on cup # 3. This 183
Metallic is the face is in contact
packing incl. with cup #4. It was
E12a + E70. necessary to lapidate
and then machine this
cup 0.1 mm to mitigate
these marks. After that
it was discarded due to
out of tolerance.
• Tangential ring
different as per
Burckhardt design. The
KRANZ ring design has
more pieces and those
match with cup #3
marks.
DOW RESTRICTED 7
Findings plunger (Cylinder # 4 2nd stage)
Parts Finding Days Pictures
running
E53 – • Diameter out of tolerance 2,570
Plunger. minimum φ read 82,72 mm. (No
data, at
According the maintenance least
procedure the minimum tolerance since Diameter out of tolerance.
is φ 82,87 mm. (0.10 mm bellow 2012)
nominal dimension)
DOW RESTRICTED 8
Findings coupling of plunger (Cylinder # 4 2nd stage)
E34 Parts Finding Days Pictures
E35 running
E34 – Piston • Surface 730
coupling nut. marks.
• Fretting
fatigue.
E44
E35 – • Fretting 730
The coupling was last inspected Pressing fatigue and
during the pit stop due to packing piece. high
replacement and re tightening in wearing
rate on the
Jul-18. outside.
• Surface
corroded. DOW RESTRICTED 9
Action taken – Cylinder #4 (2nd stage)
• Upgrade the maintenance procedure # 2678 (packing and valve replacement procedure) adding
the coupling inspection to detect the damage fond at this opportunity. On going.
• Replace the plunger according maintenance procedure # 2678 (packing and valve replacement
procedure). Done.
• Inspect the cylinder #5 coupling regarding the failure fund at cylinder #4. Done.
DOW RESTRICTED 10
Cylinder # 5 2nd stage
During the Plant SD it was decided to inspect and repair the gas packing according the process
variable we were monitoring.
At this moment we also evaluated the cylinder 3, but it was not prioritized because the cylinder 5
suddenly increased oil leak, vibration levels and the plant team toke the decision to increase the oil
rate until the corrective action could be done.
11
Findings Cylinder # 5 2nd stage
12
Findings gas packing (Cylinder # 5 2nd stage)
The inspection and findings will be pending until it can be repaired.
DOW RESTRICTED 13
Findings plunger (Cylinder # 5 2nd stage)
Parts Finding Days Pictures
running
E53 – • Diameter out of tolerance 1,228
Plunger. minimum φ read 82,81 mm.
DOW RESTRICTED 14
Findings coupling of plunger (Cylinder # 5 2nd stage)
E34 Parts Finding Days Pictures
E35 running
E34 – Piston • No 730
coupling nut. findings.
E44
E35 – • No major 730
The coupling has been running Pressing findings.
since Nov-16. piece.
DOW RESTRICTED 15
Action taken – Cylinder #5 (2nd stage)
• Replace pieces of the coupling in a preventive way. It was installed a new coupling. Done.
• Replace the plunger according maintenance procedure # 2678 (packing and valve replacement
procedure). Done.
DOW RESTRICTED 16
Compressor plungers days running
2 1
4 3
6 5
18