TECHNICAL PROPOSAL
BSRTA4-MS01
REV NO DATE PREPARED BY: REVIEWED BY: APPROVED BY: REMARKS/ STATUS
01
02
03
Table of Contents
1. Purpose 3
2. Scope 3
3. Location 3
4. Competent Person 3
5. Material, Machineries, Equipment 3
6. Work Procedure 3
6.1. Pre Shutdown Work 3
6.2. Shutdown Work 5
6.3. Removal of Actuator and orifice plate from Slide Valve 5
6.4. Cutting the SV-1503 / SV-1504 valve body 6
6.5. Flue gas line internal scaffold and preparation of new SV-1503 / SV-1504 valve
body 8
6.6. Install new SV-1503 (SV-1504) valve body and reinstate actuators 9
7. Final acceptance for the work 10
7.1. Final inspection 10
7.2. Completion: 10
8. Emergency And Rescue Operation 10
1. Purpose
This method statement explains the safe work method of supporting the slide valve (SV),
supporting the top and bottom flue gas line section of the valve body, as well as securing the valve
body before cutting and removing it and replacing it with a new valve body.
2. Scope
The scope of this method statement is applicable to SV-1503 and SV-1504 valve body replacement
and SV-1501, SV-1502 internal parts replace.
.
3. Location
Binh Son Refinery, Vietnam.
4. Competent Person
A person who has such practical and theoretical knowledge and actual experience of the
respective operation he is assigned to. If applicable he shall have obtained the approval from the
government bodies or certification as a certified and approved person.
6. Work Procedure
6.1. Pre Shutdown Work
Design and fabricate 2 sets of SV actuator support skids for SV-1503A & B (and SV-1504A &
B), load tested to hold 1 ton load. Design and fabricate SV valve body lifting jigs, load tested
to carry 2 tons of load as per sketches below.
REV NUMBER:BSRTA4-MS04- Technical Proposal
01 BSRTA4-MS01 RFCC Slide Valve Works Proposal (SV-1501,1502,1503 and
BSR 4TH PACKAGE 1 1504)
TECHNICAL PROPOSAL Page 3/ 10
F A L K O R E N G I N E E R I N G S E R V I C E S P T E L T D
T A N A H T E M A S I K S D N B H D
G U S T E A M C O R P S D N B H D
D M C M I D D L E C O . , L T D
Fig 1:
Actuator
Support skids
x 2 sets
Heavy duty
castor wheels
with lock, 4 nos
Knock-down
structure to be
assembled on
SV platform
Height of
bracing at
middle of Fig 2: SV
SV valve body lifting
body from Jigs
platform
Heavy duty
castor wheels
Removable with lock, 4 nos
pieces
Erect scaffold platforms at external under the Slide Valve platform for bracing installation.
Weld surface preparation of new SV-1503 and SV-1504 valve body.
Install temporary steel structure bracing to platform supports above SV-1503 / SV-1504.
Install SV actuator support skids and assemble SV body lifting jigs at SV-1501, SV-1502, SV-
1503, SV-1504 platform. Lock all castor wheels.
Mobilize construction tools, equipment and set-up the 90 T Mobile Crane as layout plan
below.
Crane area
Work Area
Apply the Work Permit & get the Approval from BSR Operation.
Blinding as per approved blind list. Inspect Blinding status by related department
(Hold Point).
Remove small bore obstruction air purging piping and instruments.
Disconnect instruments from SV-1501, SV-1502, SV-1503, and SV-1504 to facilitate
the removal works requirement.
Record and mark the all spring supports in hot condition as per list of support.
Lock the all spring supports after cool down the pipe and record.
Unlock the castor wheels and move the SV actuator support skids to aside and lock
the wheels
SV-1503A
SV-1504A
SV
SV-1503B
actuator
SV-1504B
support
(seated on
platform)
Removable
pieces
SV valve body
lifting jigs on castor
wheels with locks
Sample picture of
cutting through
concrete with rebar
Sample picture of
cutting through
dissimilar material
and note the surface
flatness after the cut
6.5. Flue gas line internal scaffold and preparation of new SV-1503 / SV-1504 valve body
Open-up the manholes below the SV valve body that was cut.
Set-up the ventilation as per approved ventilation plan.
6.6. Install new SV-1503 (SV-1504) valve body and reinstate actuators
The new SV-1503 (SV-1504) valve body will be lifted by the 90 ton crane onto the
platform.
Use chain block and lifting slings to rig up the new SV valve body from the platform by
the same lifting jig.
Push the lifting jig to the flue gas line area and align the new SV valve body onto the
top and bottom section of the flue gas line.
Fit up the valve body to the flue gas line and tag weld as per WPS.
Valve material SA516, Gr 70 Thickness 30 mm and edge preparation shall be visually
inspected before welding.
Follow up with necessary NDT as per ITP.
When SV-1503, SV-1504 body valve replaced and re-installed internal part, properly
completed in full compliance with all applicable procedures, Site Supervisor shall arrange for
final inspection with present of all related BSR disciplines and third parties (where
applicable).
7.2. Completion: