WORK METHOD STATEMENT

WMS Rev.No 6

ACTIVITY: ROAD WORKS COMPANY NAME DATE 7TH Feb 2019

PAVEMENT WORK CONCRETE POURING,REBAR WORK,FORM PROJECT SITE/ LOCATION


DESCRIPTION OF BNPP-HEAVY EQUIPMENT ROAD
WORK,PVC PIPE WORK, WATER PROOFING WORK &
WORK SCAFFOLDING WORKS IN GREEN ZONE AND REDZONE
CONTACT NO. 050-1366523

JHA REF. NO. BNPP-HSE-JHA-2014-210


PERSON COMPLETING THIS STATEMENT: KARTHIK BABU
JHA REV. NO. 6

Task Step
Tool and Equipment Required Description of Work (In detail)
(Activity)

Road marking. 1.Air compressor 1. Applied paint for new traffic lines and repaints existing traffic 1.
2.Boiller machine lines.
3.Sparying machine 2. Clean out paint with air compressor.
3. Lays out new markings according to drawings.
4. Records information associated with the specific tasks carried
out.
5. Operates line marking equipment’s and manual work in all
weather and traffic conditions.
6. The road surface shall be dry and air blasted prior to application
of road marking material.

Page 1 of 8
1. Start-up checks 1. Surveying Equipment’s 7. Ground conditions to be assessed by the soil investigation reports 2. Refer to the procedures BNPP-HSE-
prior to work 8. Clearance from the relevant authorities to be taken P28.
9. Preliminary Survey to be carried out to plot the existing ground profile 3. Before start the activity conduct TBM
10. Necessary Road signages & safety signages & barricading to be done 4. Barricading the area and visible
signed.
5. First Aider to be available.
6. Methods to be available and followed.

2. Excavation 1.Backhoe loader 1. The area to be excavated shall be properly mark and clear before
2.JCB starting the work
3.Excavator 2. The depth of excavated shall be periodically checked by a surveyor to
avoid over excavation. The bank of excavated area shall be slope 30
degrees and shall be maintained to avoid collapse of bank into the
excavated area.
3. All excavated materials shall be kept minimum of 1.0 meter from the
edge of excavation or shall be shock piled to the area designated by the
engineer
4. For all excavation activities, adequate safety barriers, sign boards,
advance warning signs would be used.
3. Existing surface – 1. Grader 1. PPE (Safety helmet, Coverall, High visibility vest, Safety glass, Safety 1. The workers shall be physically &
preparation or back 2. Back hoe/ Loader shoes, Hand gloves) psychologically fit.
filling 2. Necessary Road signages & safety signages & barricading to be done 2. Closely monitored the supervisor by
3. Dump Trucks
3. Operators shall be third party certified qualified experienced and trained.
4. Competent workers to be assigned for the job.
5. Necessary road signages & safety signages and barricading to be done

Page 2 of 8
4.Laying of kerbstone, 1. Grader 1. PPE (Safety helmet, Coverall, High visibility vest, Safety glass, Safety 1. Competent supervision to be place on
tiles & interlocking 2. Back hoe/Loader shoes, Hand gloves) site at all the times.
block will be done in 2. Necessary Road signages & safety signages & barricading to be done 2. The supervisor conduct HSE plan
3. Dump Truckers
the following give awareness or guide to the
4. Transit mixer 3. The surface to be cleaned properly prior to precast of kerbstones, tiles &
sequence workers
interlocking blocks.
5. HI-AB
4. proper barricading to be done to avoid any vehicle movement on 3. Methods to be available and followed
6. Kerbstone cutter
prepared surface.
7. Concrete Grinder
5. placing of concrete bed backing for supporting concrete kerb stone
6. precast kerbstone & tiles shall be unloaded from the trucks to the paver
machine & shall be levelled properly according to the required levels and
shall be properly compacted using the compactors.
7.Application of kerbstone paint on wheel stoppers
8.Cutting and grinding od kerbstone & tiles

5.Aggregate base 1. Dump Trucks 1. PPE (Safety helmet, Coverall, Safety glass, Safety shoes, Hand gloves) 1. Refer to the procedures PMPP-HSE-
course & base course 2. Back hoe/ Loader 2. ABC material to be unloaded and levelled & graded property to the P39 and BNPP-HSE-P25
filling required layer thickness & levels 2. The supervisor conduct HSE plan
3.Compacting Rollers
3. Third party certified operators & riggers shall facilitate the works give awareness or guide to the
workers
4. The ABC layers to be compacted to the specification requirements
3. The HSE supervisor support and
guidance.
4. The first aider in the vicinity of area

6.Prime Coat & Tack 1. Bitumen Spreader machine 1. PPE (Safety helmet, Coverall, Safety glass, Safety boots, Hand gloves) 4. Competent supervision to be place on
Coat 2. Prime Coating & Tack Coating to be done as per the Specification site at all the times.
requirements. The minimum letters per unit area value to be maintained. 5. The supervisor conduct HSE plan
3.Necessary Road signages & safety signages to be done give awareness or guide to the
workers
4. Proper barricading to be done to avoid any vehicle movement on coated
surface. 6. Methods to be available and followed

Page 3 of 8
7.Asphalt Base 1. Pneumatic pressure guns 1. PPE (Safety helmet, Coverall, Safety glass, Safety boots, Hand gloves) 1. Competent supervision to be place on
Course & Asphalt 2. Asphalt Trucks 2. Necessary Road signages & safety signages & barricading to be done site at all the times.
Wearing Course 2. The supervisor conduct HSE plan
3. Asphalt Paver 3. The surface to be cleaned properly prior to asphalt paving
give awareness or guide to the
4. Asphalt Compactors 3. Proper barricading to be done to avoid any vehicle movement on
workers
prepared surface.
3. Methods to be available and followed
4. Asphalt material shall be unloaded from the trucks to the paver machine
& shall be levelled properly according to the required levels and shall be
properly compacted using the compactors
5. Area shall not be exposed to traffic until properly hardened.
8.Blasting Works 1. Portable (dust free ) 1. PPE (Safety helmet, Coverall, High visibility vest, Safety Goggles, Face Shield,

blasting machine Safety shoes, Hand gloves, apron) 1. Follow KEPCO Procedure P42 for
2. All equipment’s shall be inspected & colour coded. Machine & Hand Tools.
3. Only competent & trained personals to use the Machines.
4. Pre-job meeting to be conducted prior to commencement.
9.Piping installation in the
excavation  Conduit glue, coupling Proper material arrangement and shifting maerials to the excavation. Lay out of pipe
 pipe and join with Pipeglue. Maintain manual handling training procedure[BNPP-HSE-
 Roller P39]

9.Installation Rebar
1. The surface of the reinforcing steel bar to be placed shall be free
from loss mortar, dirt, mud, oil, ice, snow or other nonmetallic
1.spreader beam coatings that adversely affect bonding capacity
2.moblie crane
2. Reinforcing steel bars shall be securely tied with No.16 or heavier
3.tower crane
gauge tie wires and shall be held in position by approved supports
3. All size of reinforcing steel bars shall be in accordance to
Drawing.

Page 4 of 8
10. FORMWORK – 1. mobile crane/crawler 1. Form design shall include considerations of the following
fabrication, installation &
de shuttering crane/tower crane/Hiab Truck
i. Rate and method of placing concrete
etc.
ii. Density of concrete
iii. Construction loads including vertical, horizontal and
impact loads
2. Forms shall be readily removable, without the injury of concrete.
Forms shall be wood, metal, structural hardboard or other suitable
material that will produce the required surface finish

11.Assemble, laying 1. Mobile Crane 1. All personnel not to exceed 15kg for manual lifting capacity.
and installation of 2. Hand Tools 2. Supervisor to ensure safe work rest period when personnel are
Waterproofing repetitive manual lifting.
Membrane System
3. Use mechanical means whenever possible
4. PPE (Safety helmet, Coverall, Safety glass, Safety shoes, Hand
gloves)

Page 5 of 8
12. PLACING OF 1. Concrete Pump Car 1. Placing equipment shall be of adequate size and capacity to handle the concrete
CONCRETE & Grout
a. Lean concrete, 2. Conveyors mixes furnished. Conveying and placing shall be in accordance with the ACI
Screed concrete, 3. Chutes regulations.
Mud mat,
2. Before depositing concrete, all placing equipment shall be cleaned. All compacted
soil, rock or concrete surfaces to receive concrete shall be thoroughly moistened
before placement
3. The free fall of concrete shall be limited to approximately 6ft. (1892mm). The
horizontal flow within the mass from the point of deposition shall be limited to
approximately 5ft.(1524mm)
4. The concrete placing shall be completed within 1 ½ hours after introduction of
the mixing water to the cement and aggregates
5. Concrete shall be deposited in layers not deeper than 24 in. (610mm), the step
method of placement as described in Section 5.6 in ACI 304R shall be followed
for mass concreting in order to minimize the occurrence of cold joints
6. Concrete shall be deposited at or near its final placement position and shall not
be caused to flow such that the lateral movement will permit or cause segregation
of the coarse aggregate, mortar or water from the concrete mass.
7. Concrete and the exposed surface of fresh concrete shall be protected from rain
and snow during and after placement

Page 6 of 8
13.Repair of concrete 1) Imperfections in formed concrete shall be repaired as soon as practicable after removal
surface 1. Grinders
of forms, imperfections in sound concrete shall be removed by chipping with
2. Pneumatic Chisel heads
perpendicular chip edges.
3. Power Tools
2) No feather edges shall be permitted
4. Drilling & Grinding
3) Application of the adhesive shall conform to the manufacturer’s written instruction.
Machine
After repair, all filling shall be bonded tightly to the surface of the holes.
5. Leak injection machine 4) Repair, except for tie rod holes shall be cured in accordance to curing section
mentioned above

Page 7 of 8
10.Erection &
Dismantling Of  Mobile Crane 1. Mobilization of materials shall be done with due safety and care 3. Refer to the procedures BNPP-HSE-
2. Remind all workers through TBM to use only the right tools for the P21 and BNPP-HSE-P25, P39.
Scaffolding  Boom Truck
job. 4. The workers shall be physically &
 Hand Tools
3. Examine each tools for any signs of damage and removed psychologically fit.
 Spirit level. immediately from service if found defective. 5. Closely monitored the supervisor by
4. Keep tools in good condition and store it properly at designated qualified experienced and trained.
storage room or tool box after usage
5. Timber shall be placed at the base to support the scaffold
6. The standards, and the entire cup lock system shall be set up as
per approved drawings and by authorized personnel.
7. Bracing tubes, universal clamps other such support mechanisms
shall be placed at designated areas for proper supports
8. To provide protection to the workers guard rails shall be provided
at appropriate heights and also toe board shall be installed to
prevent the falling of objects from scaffolding heights
9. Lifting area to be covered and appropriate signages to be
posted.Tag line to be placed at corners of loads,
10. Ensure load is balance, stable and secure during lifting.
11. All working platforms to be erected by competent personnel as
close as possible to reinforcement bar locations to prevent steel
fixers over reaching
12. Remove all obstruction in pathways.
13. Tools and materials to be secured with tool tie or place din
secured storage container.
14. Competent supervision and tool box meeting
15. PPE (Safety helmet, Coverall, Safety glass, Safety shoes, Hand
gloves)

Prepared by: Approved by: KEPCO


Check by: HSJV Discipline Dept.
Discipline Dept.

Page 8 of 8