Task Name:
All personnel will follow EDC SMS procedures; Crane Drivers will only be given instructions by a
dedicated banksman.
Do not stand below loads; keep hands clear of rigging as slack is taken up.
Do not climb onto containers or stacked pallets; never stand between loads and obstructions (i.e.
bulkheads or handrails).
The load should be initially lifted a nominal distance, this trial lift will verify that the load is balanced and
in a safe condition.
Never travel the load over other work groups, running machinery, well test areas, diving spreads,
pressurized pipework or accommodation.
Use tag line when appropriate.
Precautions Yes No N/A Comment
Basic Non Routine Lift.
1. The lift involves the use of basic hoisting equipment.
2. The lift is carried out using a crane’s main hoist.
The lift is from a dedicated structure (pad eyes, runway
3.
beams).
4. The lift is not in a restricted, difficult or sensitive area.
The load to be lifted must have certified lifting points or be
5.
easy to sling.
The lift needs to be planned or have a documented method or
6.
procedure.
7. The lift is supervised by the Crane Operator..
A Safe Job Analysis must be carried out by a competent
8.
person.
A pre-job safety meeting will be held by the Crane Operator or
9.
section supervisor.
Supervisor Name:
Title:
Signature: