Documente Academic
Documente Profesional
Documente Cultură
Table of Contents
i|Page
Construction of widening to 2-Lane with paved shoulder including Public Works Department (NH)
geometric improvement ch 318.650 km to 339.940 km (Length 21.949 km) Govt. of Tripura
on Churiabari to Agartala section of NH44 (new NH8) in Tripura under
EPC mode. PAVEMENT DESIGN REPORT
Homogeneous Sections
A homogeneous section for new construction has been adopted based on the type of founding
strata for embankment, subgrade, height of embankment and traffic.
CBR of Subgrade / Modulus of Resilience of Road bed soil
Based on the results of tests from borrow area soils, the 4 day soaked CBR value of soil in
subgrade has been adopted for design of pavement. Resilient subgrade modulus will be taken
from the correlation MR (psi) = 1500 x CBR as given in page I-14 of AASHTO Guide (Heukelom
and Klomp) for Pavement Structures and correlation of Group Index Values of soil properties
(on HRB classification) with Fig.6, Appendix FF-II, Vol-2 AASHTO Guide, whichever is lower.
As per test Average CBR (Design) is 6.5%
1-2 | P a g e
Construction of widening to 2-Lane with paved shoulder including Public Works Department (NH)
geometric improvement ch 318.650 km to 339.940 km (Length 21.949 km) Govt. of Tripura
on Churiabari to Agartala section of NH44 (new NH8) in Tripura under
EPC mode. PAVEMENT DESIGN REPORT
Design life
As per TOR, the design life for flexible pavement is 15 years Design life will be considered
accordingly.
Design Traffic
Based on the projection of future traffic on the Project Road and also the results of axle load
survey, design traffic in terms of equivalent million standard axles (msa) will be computed for
the design life of 15 years.
Thickness of Pavement Layers
The flexible pavement will be designed following AASHTO Guidelines for Design of Pavement
Structures, 1993 and IRC:37-2012.
Rigid pavement will be designed following IRC Guidelines for the Design of Plain Jointed Rigid
Pavement for Highways (2nd Revision), IRC:58:2002.
Comparing these two methods, the thickness of pavement and component layers will be
determined.
Road side drains will be designed as per guidelines in IRC-SP:50-1999.
1.2 INTRODUCTION
The existing carriageway will be widened to double lane. There will be concentric widening and eccentric
widening mostly in stretches with reference to the existing carriageway. Pavement design will,
therefore, comprise:-
i. New construction :
Widening configuration
- eccentric widening : 2 lane carriageway with each lane of 3.5m width, paved shoulder 1.5m width
at 2.5% slope & unpaved shoulder 1.0m width at 3.5% slope,
- Concentric widening : Approximately 4.00m (depends on the existing carriageway width) wide
carriageway with paved shoulder 1.5m wide at 2.5% slope and unpaved shoulder 1.0m wide at 3.5%
slope on each side
ii. Strengthening of the existing pavement will be done on maximum location with average condition of
the road.
iii. THICKNESS OF E XISTING PAVEMENT LAYERS
A summary of pavement thicknesses averagely as obtained from trial pits performed during field
investigations are as follows:
Table – 1.1 : Existing Pavement Composition
WBM & Old Bituminous Layer
Sl Chainage Brick Bats
BT (mm) Thickness (mm)
No (mm)
From (Km) To (Km) DBM BC
1 0.000 21.940 200-350 70-140 0.00 30-50
1-3 | P a g e
Construction of widening to 2-Lane with paved shoulder including Public Works Department (NH)
geometric improvement ch 318.650 km to 339.940 km (Length 21.949 km) Govt. of Tripura
on Churiabari to Agartala section of NH44 (new NH8) in Tripura under
EPC mode. PAVEMENT DESIGN REPORT
Homogenous Section Ex. Carriageway Width (m) Design CBR (%) Design Traffic (MSA)
0.00 – 21.940 Km 5.5 to 7.0 m 6.5% 52
1-4 | P a g e
Construction of widening to 2-Lane with paved shoulder including Public Works Department (NH)
geometric improvement ch 318.650 km to 339.940 km (Length 21.949 km) Govt. of Tripura
on Churiabari to Agartala section of NH44 (new NH8) in Tripura under
EPC mode. PAVEMENT DESIGN REPORT
Pavement design as per IRC: 37-2012 is based on mechanistic pavement design principle which has
evolved from theoretical, laboratory and pavement performance studies on Indian pavement materials
and pavements constructed in India. In IRC: 37-2012, for analysis, DBM layer with 60/70 bitumen and
an annual average pavement temperature (AAPT) of 35C have been used. The vertical strain between
the dual wheels and the horizontal tensile strain at the bottom of the DBM layer below one of the wheels
(vide Annexure-1 IRC: 37-2012), are assumed to be the design criteria for fatigue and rutting failure of
the pavement. Apart from the axle load, the design thickness depends on tyre pressure and the wheel
configuration. The standards taken for single wheel load, tyre pressure and wheel configuration are at
variance with different codes of practices. IRC:37-2012 adopts 20.5 KN as single wheel load, 310 mm as
centre to centre distance between dual wheels and 560 Kpa as tyre pressure whereas shell Pavement
Design Manual, London adopts these parameters as 20.0 KN, 315 mm & 600 Kpa and Austroads adopts
these parameters as 20.5 KN, 330mm & 550-700 Kpa respectively, as basis of mechanistic pavement
design approach.
1-5 | P a g e
Construction of widening to 2-Lane with paved shoulder including Public Works Department (NH)
geometric improvement ch 318.650 km to 339.940 km (Length 21.949 km) Govt. of Tripura
on Churiabari to Agartala section of NH44 (new NH8) in Tripura under
EPC mode. PAVEMENT DESIGN REPORT
The bituminous pavement design charts in India are calibrated as per constant AAPT of 35C throughout
the design period. However, pavement design which takes into account temperatures prevalent in
various seasons as well as various regions, would definitely give more reliable results compared to the
pavement design that assumes single value of AAPT throughout the whole design period. This provision
is incorporated in the Asphalt Institute, Manual series No.1 (MS-1), 9 th edition.
Thickness of bituminous pavement layers by the Austroads and the AASHTO methods are by and large,
in agreement with the suggested design. But the thicknesses of base course & bituminous course by
other methods are found to be larger compared to that found by the Indian method. This may be
because of the fact that the acceptable level of serviceability is much higher in other countries than
what is expected in India. In the current IRC design method the fatigue and rutting criteria are based
on 20% surface cracking and 20mm as the limiting rut depth, whereas these values are lower in
developed countries.
As regards to the gradings for different pavement layers, it is proposed to use Grading-II for DBM and
BC. For construction purposes, the compaction details for different bituminous layers are as follows:
The width and other details of each layer shall be as per Typical Cross section enclosed in
Drawing Volume. The applicability of different typical cross sections chainage-wise is also provided in a
table form in the same Drawing Volume.
1-6 | P a g e
Construction of widening to 2-Lane with paved shoulder including Public Works Department (NH)
geometric improvement ch 318.650 km to 339.940 km (Length 21.949 km) Govt. of Tripura
on Churiabari to Agartala section of NH44 (new NH8) in Tripura under
EPC mode. PAVEMENT DESIGN REPORT
Note:
1. Manufacturer Specification of Geo-Composite as Drainage Layers as per MoRTH specification 704
had been attached at Annexure-III with the Report.
2. Manufacturer Specification of SAMI Layers as per MoRTH specification had been attached at
Annexure-III with the Report.
3. Typical Cross Section will be provided with Drawing Volume with Pavement Compositions.
4. For Widen Stretches, at Existing Road only BC-50mm & DBM-50mm along with SAMI Layers to be
provided after scarifying the existing Bitumen top.
1-7 | P a g e
Construction of widening to 2-Lane with paved shoulder including Public Works Department (NH)
geometric improvement ch 318.650 km to 339.940 km (Length 21.949 km) Govt. of Tripura
on Churiabari to Agartala section of NH44 (new NH8) in Tripura under
EPC mode. PAVEMENT DESIGN REPORT
Annexure-I
Pavement Design Report
Input Data:
Design MSA: 52
Design CBR at Sub-grade: 6.5%
MRSubgrade 1.76xCBR0.64 = 55 MPa
MR Bituminous 5000 MPa
E Cemented Base 600 MPA
Now,
1-8 | P a g e
Construction of widening to 2-Lane with paved shoulder including Public Works Department (NH)
geometric improvement ch 318.650 km to 339.940 km (Length 21.949 km) Govt. of Tripura
on Churiabari to Agartala section of NH44 (new NH8) in Tripura under
EPC mode. PAVEMENT DESIGN REPORT
1-9 | P a g e
Construction of widening to 2-Lane with paved shoulder including Public Works Department (NH)
geometric improvement ch 318.650 km to 339.940 km (Length 21.949 km) Govt. of Tripura
on Churiabari to Agartala section of NH44 (new NH8) in Tripura under
EPC mode. PAVEMENT DESIGN REPORT
So the Pavement Composition as per the Design we provide as per below table:
Existing/
Widen/
Layer Overlay
Layers with specifications Reconstruction Remarks
No. Portion
Portion (mm)
(mm)
1 Bituminous Concrete (BC) 50.0 50.0
Dense Bituminous Macadam
2 50.0 50.0
(DBM)
Paving Fabric- Stress Absorbing As per IRC-37: 2012,
3 Membrane Interlayer (SAMI - Annexure-X, clause X7 &
layer) Manufacturer's specifications
Stabilized Base Course with 6.5% As per IRC-37: 2012, clause
4 170.0 Existing
Cement Treated 7.2.2, page-19
Pavement
after As per MoRTH Spec 704 &
5 Geo-Composite (Drainage Layers) -
scarifying Manufacturer's specifications
Stabilized Sub-Base Course with top As per IRC-37: 2012, clause
6 160.0
3.5% Cement Treated Bituminous 7.2.2, page-19
layers
7 Sub-grade with 5-6.5% CBR 500.0
Total Pavement Thickness
8 430.0 100.0
(Excluding Sub-grade):
Note: Details will be shown at Typical Cross Section (TCS) at Drawing Volume
1-10 | P a g e
Construction of widening to 2-Lane with paved shoulder including Public Works Department (NH)
geometric improvement ch 318.650 km to 339.940 km (Length 21.949 km) Govt. of Tripura
on Churiabari to Agartala section of NH44 (new NH8) in Tripura under
EPC mode. PAVEMENT DESIGN REPORT
Annexure-II
Composition of Pavement Materials
1. As per IRC-37, Clause7.2.2, it is required that the stabilized soil layer should retain the permeability, when
water is likely to enter into pavement form shoulder, median or through the cracks. It is therefore
recommended that Geo-Composite possessing the necessary parameter be provided over the entire
sub base layer which would facilitate as drainage layer. Ensure that the Geo- Composite material which
is laid as drainage layer is running up to the end of toe for sub Base layer including shoulder. The Geo-
Composite should conform to MORTH Specification, Section, 704.
2. Cemented layer may develop transverse and longitudinal cracks due to shrinkage during service life.
Hence, it is recommended to provide the Paving fabric as per IRC: 37-2012, Annex – X, clause no. X-7as
crack preventive layer (SAMI) over the prepared Base layer. It is therefore recommended that Paving
fabric as per MORTH clause 708.2.1is provided over the Base Layer as Crack preventive layer. Ensure that
VG-10 bitumen to a temperature between 143 to 1630 C and application is maintained at 1kg per sq.m as
a tack coat and if Emulsion (RS-1) being used, maintain the temperature of application between 55 to 71 oC
, and increase the amount of rate of application of the tack cote considering the amount of water present
in emulsion.
3. Provide Dense Bituminous with VG30 as bituminous base course and Bituminous Concrete as wearing
course as per MORTH Clause No.507, with VG-30 as Bitumen grades per IS-73, in single layer over
previously laid paving fabric (SAMI layer) as per above mentioned specifications.
4. Cementitious material in cementitious base layer as per IRC: 37, clause No.507, with VG-30 as Bituminous
Concrete as Wearing course as per BIS: 4331 (Part-IV)-1968 to determine the loss of weight of the
stabilized material after 12 cycles of wetting and drying, accordingly the results for loss of weight found
to be 10 % after 12 cycles of wetting and drying and the results meet acceptance criteria of weight not
exceeding 14%.
1-11 | P a g e
Construction of widening to 2-Lane with paved shoulder including Public Works Department (NH)
geometric improvement ch 318.650 km to 339.940 km (Length 21.949 km) Govt. of Tripura
on Churiabari to Agartala section of NH44 (new NH8) in Tripura under
EPC mode. PAVEMENT DESIGN REPORT
Annexure-III
(Manufacturer Specifications of Geo-Composite as Drainage Layers & SAMI
Layers.
1-12 | P a g e