Documente Academic
Documente Profesional
Documente Cultură
B1
T1
1- Steel fy not less than 460 N/mm2.
B2 2- Concrete fcu should not be less
T2 than 30N/mm2 for 28days strength.
B1
T1
X X
3-Max-Aggregate size 20mm for
Refer to Footing R.C Details Refer to Footing R.C Details beams & col.s and 30mm for found.s.
FOUNDATION PLAN (F1,F2,&F3) FOUNDATION PLAN (F4) 4- Concrete cover for reinforcement
should not be less than
25mm for beams & columns and
50mm for foundations.
5- Over laps of steel should not be less
B2 than 45 times larger bar size &should
T2 always be located within concrete
being under compression.
Refer to Footing R.C Details Refer to Footing R.C Details
Refer to Footing R.C Details
6- Construction joints shall be located
Refer to Footing R.C Details at onefifth of span of slabs.
RAFT FOOTING PLAN 7- All Dimensions are in mm.
8- Bearing Capacity= 180 KN/m2.
Refer to Footing R.C Details
LOCATION
Khartoum - Algeref west
OWNER
Mr. OTHMAN IBRAHIM ALBOUR
Str. Design
Eng. Sharif Abdallah Agban
Str. Drafting