Sunteți pe pagina 1din 8

SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - JUNE 2008) REV 3 30-Jun-08

SATR NUMBER DATE APPROVED QR NUMBER


SAUDI ARAMCO TEST REPORT
SATR-X-3205
Internal Tank Bottom Testing CP-
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.

LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.

SCHEDULED TEST DATE & TIME ACTUAL TEST DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?

SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL

ITEM
TEST PROCEDURE ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.

A. Appropriate safety precautions must be followed when making electrical measurements:

Use properly insulated test lead clips and terminals to avoid contact with
unexpected hazardous voltages.
- Test clips should be attached one at a time each time a connection is
SAEP-332
A1 made.
Sec. 3 a
- A single hand should be used to make the connection, in a well
balanced body position, while the other hand should be free from resting
on any surface.

Use caution when long test leads (100 meters or longer) are extended
near overhead high voltage AC power lines, since hazardous voltages
SAEP-332
A2 can be induced into the test leads. Use rubber mats, rubber gloves, or
Sec. 3 b
both, when making measurements if induced AC potentials over 15 volts
are measured on pipelines near high voltage AC power lines.

Use caution when making tests at electrical isolation devices.


Appropriate voltage detection instruments or voltmeters with insulated SAEP-332
A3
test leads should be used to determine if hazardous voltages exist before Sec. 3 c
proceeding with tests.

Personnel must be knowledgeable and qualified in electrical safety


SAEP-332
A4 precautions prior to installing, adjusting, repairing or removing impressed
Sec. 3 e
current protection equipment.

Testing should be avoided when thunderstorms are in the area. Remote


SAEP-332
A5 lightning strikes can create hazardous voltage surges that travel along
Sec. 3 f
the pipe under test.

B. CP Test Equipment and Maintenance- Voltmeters, ammeters and Reference Electrodes

Use proper voltmeters and ammeters and suitable reference electrodes


for CP testing. These meters are operated by batteries. Check meter SAEP-332
B1
batteries periodically to ensure they still function properly. Generally, they Sec. 4.3.1
should be replaced every year.

SAEP-332
B2 Calibrate all meters annually.
Sec. 4.3.2

Use high input impedance meters for structure-to-electrolyte potential


measurements, especially in areas of high soil resistivity. Input
SAEP-332
B3 impedance should be 20 megohms or greater. Multimeter with various
Sec. 4.3.3
setting levels of input impedance are preferred, for example, Miller model
LC-4©.

Page 1 of 8
Use a clamp-on-ammeter for the direct measurements of DC currents.
Meters having current measuring capacity up to 200 amps and a variety
of clamp sizes are preferred. When changing clamp sizes for the same SAEP-332
B4
meter, refer to the manufacturer's instructions for adjusting the readings. Sec. 4.3.4
Currently, the clamp-on ammeters made by William H. Swain company
are widely used in Saudi Aramco facilities.

Page 2 of 8
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - JUNE 2008) REV 3 30-Jun-08
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
SATR-X-3205
Internal Tank Bottom Testing CP-
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.

Properly maintain copper-copper sulfate and silver-silver chloride


reference electrodes, as follows:
1-Clean the tips of the copper-copper sulfate electrodes,
2-Ensure that the electrodes contain an adequate volume of electrolyte
with an excess of copper sulfate crystals. SAEP-332
B5
3-Inspect and test the electrodes one against another or against a Sec. 4.3.5.1
standard voltage source, periodically.
4-Make sure that the voltage difference shall not exceed a maximum
differential of 10 mV.
5-If this maximum is exceeded, a complete clean-up is needed.

In the clean-up,
-Remove the oxide layer on the copper rod by using fine sand paper
-Renew the copper sulfate electrolyte.
-Fill the electrode half full, as a minimum, with a saturated water solution SAEP-332
B6
of copper sulfate. Sec. 4.3.5.1
-Use only distilled water and chemically pure copper sulfate.
-add an excess of copper sulfate crystals, equal to approximately 10%
(by weight) of the saturated solution in the cell.

Inspect and test silver-silver chloride electrodes, one against another or


SAEP-332
B7 against a standard voltage source, periodically. A replacement is
Sec. 4.3.5.2
required if the voltage difference is larger than 10 mV.

Check test leads of voltmeters used for structure-to-electrolyte


SAEP-332
B8 measurements periodically, for continuity and integrity. Repair or replace
Sec. 4.3.6
faulty leads or connections before making measurements.

C. TEST PROCEDURE FOR CATHODIC PROTECTION OF TANK INTERNAL POTENTIAL SURVEY

After recording the "As-Found" potential measurements, set the current


SAEP-332
C1 output of the impressed current anode system to operate at
Sec. 4.1.7.5
approximately 90% of the design current requirement.

For tanks with access holes from the tank roof, measure the "On"
potential measurements at three depths:
1) the tank bottom,
SAEP-332
C2 2) the midpoint, and
Sec. 4.1.7.5
3) one foot below the water level.
Note: Do not place the reference electrode close to the anodes on an
anode string but rather between anodes.

For both the impressed current and galvanic anode CP systems


SAEP-332
C3 -Measure the current output of the anodes associated with each tank
Sec. 4.1.7.5
-and record these on the Appendix E Commissioning Report.

The measured potentials shall meet the CP potential criteria, as stated in


SAEP-332
C4 SAES-X-500. The potential survey data shall also be recorded on the
Sec. 4.1.7.5
Appendix E Commissioning Report

Commentary Note:
Stringent adherence to all required safety precautions, including the use SAEP-332
C5
of fall prevention devices, is required when personnel are taking Sec. 4.1.7.5 a
measurements through tank roof access holes.

Page 3 of 8
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - JUNE 2008) REV 3 30-Jun-08
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
SATR-X-3205
Internal Tank Bottom Testing CP-
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.

Commentary Note:
Tank internal CP system commissioning for water tanks should only be SAEP-332
C6
done when the tank is 100% full. This will ensure that the CP system is Sec. 4.1.7.5 b
set to provide protection for the full wetted surface area of the tank.

Commentary Note:
Measure potentials through the reference cell access holes that are
SAEP-332
C7 installed 150 mm from the tank shell (as shown on Standard Drawing No.
Sec. 4.1.7.5 c
AA-036353 or AA-036354). For existing tanks that do not have these
access holes, take the potentials as close to the shell as practical.

Report Forms:
Record all data relative to the commissioning and/or re-commissioning of
SAEP-332
C8 cathodic protection systems on the Commissioning Report forms
Sec. 5
attached in Appendix E of this Engineering Procedure. See Appendix E
Cathodic Protection, Tank Internal Commissioning Report

Evaluation of the Surveys -Forward the detailed data including raw data
and as-built data obtained during the commissioning surveys, to the
SAEP-332
C9 appropriate department for review. Determine the anomalies,
Sec. 4.2
discrepancies, and recommendations for upgrading or improving the
cathodic protection system (if any), and notify the appropriate agencies.

D. TEST EQUIPMENT AND MATERIALS CRITERIA FOR CP EXTERNAL TANK BOTTOM POTENTIAL SURVEY

Using 5XL Hand-Held, Portable Digital Multimeters by Wavetek

E. TEST RESULTS OF CP TANK INTERNAL POTENTIAL SURVEY

F. CONCLUSIONS

ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.

SAEP-332A
F1 Result were in accordance with the Appendix D Commissioning Report.
Appendix D

Test results are acceptable and in accordance with Saudi Aramco SAEP-332A
F2
Engineering Standards and contractual requirements. Appendix D

Test results are acceptable and in accordance with Saudi Aramco


F3 N/A
Engineering Standards and contractual requirements.

Page 4 of 8
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - JUNE 2008) REV 3 30-Jun-08
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
SATR-X-3205
Internal Tank Bottom Testing CP-
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
TEST RESULTS ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-TEST DATE
No.

REMARKS:

REFERENCE DOCUMENTS:
1. Schedule Q -- Quality Requirements (Pro Forma Contract), February 2008
2. Schedule G -- Material, Tools and Equipment (Pro Forma MP-IK-LS Contract), March 2006
3. SAEP-332 Cathodic Protection Commissioning 31 May, 2005
4. SAEP-332 A Appendix A through K, 31 May, 2005
5. SAES-X-600 Cathodic Protection of Plant Facilities, 25 June, 2007

NOTES:
1. Approved - Acceptable to the authority having jurisdiction (i.e., Saudi Aramco ID).
2. Identified - Recognizable as suitable for the specific application by a qualified testing laboratory (i.e., listing and/or labeling).
3. Listed - Equipment and materials included in a list published by an approved qualified organization concerned with evaluation of products
or services, that maintains periodic inspection of production of listed equipment or materials or periodic evaluation of services, and whose listing
states
that the equipment, material, or services either meets appropriate designated standards or has been tested and found suitable for a specified
purpose.
4. Labeled - Equipment or materials to which has been attached a label, symbol, or other identifying mark of an approved qualified organization
concerned
with product evaluation, that maintains periodic inspection of production of labeled equipment or materials, and by whose labeling the manufacturer
indicates compliance with appropriate standards or performance in a specified manner.

Contractor / Third-Party Saudi Aramco


Technician Performing Test* PMT Representative
Name, Title, Department, Test Performed Successfully and Results are Acceptable: T&I Witnessed QC Record Reviewed Work Verified
Company, Initials and Name, Initials and Date:
Date:

QC Inspector PID Representative


Witnessed Test Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Supervisor Proponent and Others


Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date:

*Person Responsible for Implementation of Test and Analysis of Results Y = YES N = NO F = FAILED

Page 5 of 8
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - JUNE 2008) REV 3 30-Jun-08
SATR NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO TEST REPORT
SATR-X-3205
Internal Tank Bottom Testing CP-

Attachment 1-Periodic Impressed Current CP Testing

Page 6 of 8
Page 7 of 8
CALIBRATION CERTIFICATE
Certification Agency:
Equipment Type, Model and Serial Number:

Calibration Start Date:

SURVEY DATA:

SKETCH FOR LOCATIONS OF ANODES AND TEST POINTS


ANODE ANODE OUTPUT
No. (AMPS)
1
2
3
4
5
6
7
8

STRUCTURE-TO-WATER POTENTIAL (-mV)


LOCATION TOP MIDDLE BOTTOM
ON OFF ON OFF ON OFF
1
2
3
4
5
6

Page 8 of 8

S-ar putea să vă placă și