Method Statement for External Stone Cladding. Form No. P07-F06 / Rev. 0 / Nov. 2012
AEB-CSD Quality Forms Page 1 of 7
Project Logo Project Name : BEACH VILLA (B+G+1+PH) ON BVN 55-60, PEARL QATAR
Table of Contents
1.Scope /Objectives
2.Reference
3.Access/Egress
4.Logistics
5.Health and Safety Hazards
6.Definitions
7.Responsibilities / Supervision
8.Procedures /Method to be Employed
9.Training
10.Working hours
11.House keeping
12.Manpower Requirement & Supervision
13.Material Requirement
14.Plant & Equipment Requirement
15.Q.C Approvals and other Documentation
16.Supporting documentation
17.Distribution
18.Other information
19.Site Safety Engineer’s Approval
Method Statement for External Stone Cladding. Form No. P07-F06 / Rev. 0 / Nov. 2012
AEB-CSD Quality Forms Page 2 of 11
Project Logo Project Name : BEACH VILLA (B+G+1+PH) ON BVN 55-60, PEARL QATAR
2. REFERENCES
2.1 QCS 2010 Section 24 and Section 27 and 29
2.2 Project specification Section 24 and Section 27
2.3 Project Health, Safety and Environmental Guidelines
2.4 Project Quality Plan
2.5 Project Inspection and Test Plan – Civil Works
2.6 Contract Drawing and Specification
3. ACCESS/ EGRESS
Adequate access and egress should be provided to the site. Access will be through designated entrance and exit
pathways only.
4. LOGISTICS
Contractor will deploy a dedicated team for the specified work.
6. DEFINITIONS
AEB – Arab Engineering Bureau (Consultant/Engineer)
AMTC – Abdullah Al Muftah Trading and Contracting Co., w.l.l (Main Contractor)
MS – Method Statement
QCP – Quality Control Procedures
ITP – Inspection and Test Plan
ITA – Independent Testing Agency
7. RESPONSIBILITIES / SUPERVISION
7.1 Project Engineer shall be responsible for the execution of this procedure and to ensure that works are undertaken in
Method Statement for External Stone Cladding. Form No. P07-F06 / Rev. 0 / Nov. 2012
AEB-CSD Quality Forms Page 3 of 11
Project Logo Project Name : BEACH
a safe manner to the requisite quality and toVILLA (B+G+1+PH)
the time ON BVN 55-60,
agreed timescale. PEARL
He shall QATAR
advise and coordinate with other
contractors pertaining to access and interface requirements.
7.2 Site Engineer shall be responsible for the site implementation of this procedure including control and the safety of the
workers.
7.3 Surveyor in coordination with Site Engineer has the responsibility to perform all survey works according to the
approved shop drawings.
7.4 QA/QC Inspector shall be responsible for the supervision of tests and inspection, control approvals for testing and
inspection plan and to arrange documentation required.
7.5 Safety Officer shall be responsible for the strict implementation of safety procedure during work commencements.
8.1.2.3 When the grout has firmed but is still slightly humid, wipe the tiles clean with a damp sponge.
8.1.2.4 Do not let the grout residue dry on the surface of the marble or granite.
8.1.3 FINAL INSPECTION AND HANDING OVER
8.1.3.1 The floors will be submitted for inspection area by area in the required format and comments if
any will be attended.
8.1.4 PROTECTION
8.1.4.1 After the floor, have been installed, must keep all traffic off the floors for at least 48 hours. After
the completion of work, the floor shall be protected from staining or damage by covering of polythene
sheet / and 3mm ply board panels.
Method Statement for External Stone Cladding. Form No. P07-F06 / Rev. 0 / Nov. 2012
AEB-CSD Quality Forms Page 4 of 11
Project Logo Project Name : BEACH VILLA (B+G+1+PH) ON BVN 55-60, PEARLFIXING)
QATAR
8.2 INSTALLATION METHOD FOR VERTICAL SURFACES (MECHANICAL
8.2.1 SURFACE PREPARATION
8.2.1.1 It is ensured that the surfaces to be cladded are sound, dimensionally stable, level, clean and free
from laitance, paint, oil, grease and mould release agent and residual curing compound.
8.2.1.2 All corners are thoroughly checked for right angles.
8.2.2 INSTALLATION
8.2.2.1 Holes are drilled in the stone and the wall for the pin and expansion bolt respectively at locations
marked as per the panel size.
8.2.2.2 Alternative slots may be made in the stone while using body anchor fixing of fixtures.
8.2.2.3 Anchor bolts are fixed to the holes in the wall and tightened.
8.2.2.4 The stone panel is placed on the fixtures to check alignment. Once the alignment is confirmed,
adhesive is smeared in the pin hole/slot and the panel is fixed in place.
8.2.2.5 Final adjustments are done by tightening the bolts in the expansion shell.
8.2.3 GROUTING
8.2.3.1 Joint filler is applied between panels with a rubber spatula.
8.2.3.2 The grout is compacted into the joints.
8.2.4 CLEANING
8.2.4.1 Final cleaning is carried out with a wet sponge/cloth after 48 hrs. of grouting.
8.2.4.2 Upon completion of a substantial area, inspection is carried out for approval.
9 TRAINING
Relevant trainings and orientations have been provided to person who will perform the specified task.
10 WORKING HOURS
As scheduled.
11 HOUSE KEEPING
Working Areas will be kept clean by disposing the waste materials at the designated areas. At the end of days’ work,
installation supervisor will ensure that the debris are disposed off.
13 MATERIAL REQUIREMENT
Method Statement for External Stone Cladding. Form No. P07-F06 / Rev. 0 / Nov. 2012
AEB-CSD Quality Forms Page 5 of 11
Project Logo
Marble and Granite Project Name : BEACH VILLA (B+G+1+PH) ON BVN 55-60, PEARL QATAR
Marble and Granite Grout
Marble and Granite Adhesive
Sand
Gravel
Water
16 SUPPORTING DOCUMENTATION:
This MS to be read in conjunction with the below referenced documents
Contract Specification & approved drawings.
Project Quality Plan
Project HSE Plan
17 DISTRIBUTION
Copies of this MS will be circulated to the following for Information & action
Sr. Construction Manager
Site Engineer
QA/QC Engineer
HSE Engineer
Method Statement for External Stone Cladding. Form No. P07-F06 / Rev. 0 / Nov. 2012
AEB-CSD Quality Forms Page 6 of 11
Project Logo Project Name : BEACH VILLA (B+G+1+PH) ON BVN 55-60, PEARL QATAR
18 OTHER INFORMATION
Ensure that all the activities have been carried out to suit the site conditions and involved
With Site –in – charge
Method Statement for External Stone Cladding. Form No. P07-F06 / Rev. 0 / Nov. 2012
AEB-CSD Quality Forms Page 7 of 11