Documente Academic
Documente Profesional
Documente Cultură
Program Magister
SIPIL - MK
1
Bagian Isi
2
Latihan Crashing
3
Latihan Crashing 1
4
Latihan Crashing 1
5
Latihan Crashing 1
Examining the unit change in cost, Rij shown in column 6 of Table 1, the
lowest rate of change occurs for activity E. Accordingly, a good heuristic
strategy might be to begin by crashing this activity. The result is that the
duration of activity E goes from 9 days to 5 days and the total project cost
increases by $8,000. After making this change, the project duration drops to
28 days and two critical paths exist: (1) activities C,X,E,F and G, and (2)
activities C, D, F, and G.
6
Latihan Crashing 1
Examining the unit changes in cost again, activity F has the lowest value of
Rijj. Crashing this activity results in an additional time savings of 6 days in
the project duration, an increase in project cost of $16,000, but no change
in the critical paths. The activity on the critical path with the next lowest
unit change in cost is activity C. Crashing this activity to its minimum
completion time would reduce its duration by 4 days at a cost increase of
$16,000. However, this reduction does not result in a reduction in the
duration of the project by 4 days. After activity C is reduced to 7 days, then
the alternate sequence of activities A and B lie on the critical path and
further reductions in the duration of activity C alone do not result in
project time savings. Accordingly, our heuristic corrections might be
limited to reducing activity C by only 1 day, thereby increasing costs by
$4,000 and reducing the project duration by 1 day.
7
Latihan Crashing 1
At this point, our choices for reducing the project duration are fairly limited.
We can either reduce the duration of activity G or, alternatively, reduce
activity C and either activity A or activity B by an identical amount.
Inspection of Table 1 and Figure 1 suggest that reducing activity A and
activity C is the best alternative. Accordingly, we can shorten activity A to its
crash duration (from 6 days to 4 days) and shorten the duration of activity C
(from 7 days to 5 days) at an additional cost of $6,000 + $8,000 = $14,000.
The result is a reduction in the project duration of 2 days.
8
Latihan Crashing 1
Our last option for reducing the project duration is to crash activity G from 3
days to 2 days at an increase in cost of $8,000. No further reductions are
possible in this time since each activity along a critical path (comprised of
activities A, B, E, F and G) are at minimum durations. At this point, the
project duration is 18 days and the project cost is $120,000., representing a
fifty percent reduction in project duration and a seventy percent increase in
cost. Note that not all the activities have been crashed. Activity C has been
reduced in duration to 5 days (rather than its 4 day crash duration), while
activity D has not been changed at all. If all activities had been crashed, the
total project cost would have been $138,000, representing a useless
expenditure of $18,000. The change in project cost with different project
durations is shown graphically in Figure 1.
9
Latihan Crashing 1
10
Latihan Crashing 2
11
Latihan Crashing
12
Pustaka
1. Hendrickson C and Tung Au, Project Management for Construction, Web Version, 2003
2. Barrie, Donald. S dan Boyd C. Paulson, Manajemen Konstruksi Profesional, terjemahan
Penerbit Erlangga , 1992.
13