Documente Academic
Documente Profesional
Documente Cultură
PREPARED BY
QTS/2014/006
ILE – IFE
APRIL, 2019
i
Department of Quantity Surveying,
Faculty of E.D.M,
Osun state.
The Coordinator,
Faculty of E.D.M,
Dear Sir,
LETTER OF TRANSMITTAL
I hereby write to inform you that I have successfully completed the compulsory six months
Students Industrial Work Experience Scheme (SIWES) program as expected. All works contained
in this report were compiled and completed by me. This report is therefore being submitted in partial
fulfilment of the requirements for the Students Industrial Work Experience Scheme (SIWES 400)
in Obafemi Awolowo University.
Yours Faithfully,
QTS/2014/006
Student Industrial Work Experience Scheme (SIWES) 400 program at the NBC (Coca-Cola) Asejire
I also certify that all the works contained in this report army work and it contains to the best of my
knowledge, all experiences, lessons and insights I have garnered in the past 6 months of my
HEAD OF DEPARTMENT
adoration, for He made me started and at the same time finished my industrial training well. I
appreciate the support and prayers of my parent throughout this period, may God always replenish
and bless them. I thank those God used to make this dream a reality - Mr Olusegun Oladejo
particularly, I pray God will always bless you sir. Finally, I appreciate all those who imparted me in
one way or the other during this period of my training, I pray your wisdom will never run dry.
(SIWES) program as well as the roles of all parties involved. Details about Arbico PLC as an
organisation as well as the mode of operation at the particular site where I undertook my industrial
training are covered in this report. All experiences and lessons I gained in terms of contractor’s
quantity surveying duties, real life construction, construction related Health Safety and Environment
(HSE), construction plants and equipment and lots of several other construction related and non-
1.1.1 Introduction
is compulsory students are excused from the academic environment for a stipulated period of time
in order to go out to the field which is the industry related to their particular course of study in
school. This will enable them attain the necessary practical experience that will make them become
knowledgeable students and eventually great professionals. In addition, it will ensure students are
equipped in the relevant practical aspects of their courses and expose them to the way things are
Sequel to this, I applied to Arbico PLC – a construction firm where I was thoroughly exposed to
construction works and the various quantity surveying practices in the contracting line.
This report is therefore written to communicate all I have learnt and exposed to out there in the
practices, Health Safety and Environment (HSE) practices and fundamentals, construction plants
and equipment and many others were all captured in this report.
The Students Industrial Work Experience Scheme (SIWES) is an accepted skills programme
that forms part of the approved academic standards in certain degree programs in Nigerian
Universities. In 1973, the Federal Government of Nigeria introduced the national policy on industrial
training, called the Students Industrial Work Experience Scheme (SIWES). However, it was until
1974 that students started going out to industries to obtain the required practical training. This
programme is under the umbrella of the Ministry of Education through the Industrial Training Fund
respective fields of study and it is charged with the responsibility of preparing students for life
The placement of students is always based on their course of study and it is limited to students
in the faculties of Technology and Environmental Design and Management. Courses taught at the
National colleges of Education and Polytechnics are also included. At present, an allowance of
N2,500 is paid to each student per month during the period of their training. The payment is made
by Industrial Training Fund (ITF) – the organisation saddled with the responsibility of administering
the programme. The SIWES programme is in two phases. The first known as SIWES 300 is usually
done at the end of the student’s third year while the second phase called SIWES 400 is always done
Students Industrial Work Experience Scheme was essentially created in order to bridge the
existing gap between the theory taught in the classroom and the practice of science, agriculture,
institutions. This programme is aimed at exposing the students to the use of various machines and
equipment, professional work methods and ways of safeguarding the work areas in industries as well
as other organisations. The programme was established basically to impact elaborate practical
understanding to students with respect to their various disciplines. SIWES also affords students the
opportunity to relate the academic knowledge they have acquired in their respective institutions with
the industrial experience and exposure they stand to gain in their various industrial placements. This
has proven as a means of ensuring students, which are prospective professionals, become better in
The various parties involved in the scheme are the institutions of learning, the employers, the
students, the Industrial Training Fund (ITF) and the National University Commission (NUC). Their
various roles and responsibilities as regards to SIWES are further expatiated below.
Institutions of Learning
The institutions of learning are saddled with the responsibility of preparing students for their
various industrial training schemes by orientating them shortly before the commencement of the
programme. They are expected to pay regular visits to the students at the various organisations they
were attached in order to evaluate each student’s performance and sign their logbooks. In addition,
the institutions of learning are required to submit returns of disbursement of funds received in respect
Employers
The employers of the students are required to work out relevant programmes with the
institutions. They are to ensure that students are exposed to real life working situations and
conditions through the process of engaging them in the various activities of the firm/organisation.
The employers must also assess the students’ logbooks on both weekly and monthly basis and make
Students
A major role of students on internship is to keep the logbooks obtained from their respective
institutions and record all activities and lessons learnt in it on a daily basis. They must equally be
present regularly at the respective organisations to which they have been attached. It is also
Industrial Training Fund was established upon the promulgation of the ITF decree of 1971.
It publishes the rules and regulations for the Student Industrial Work Experience Scheme (SIWES),
identifies and compiles list of suitable industries for placement and also assist institutions of learning
in facilitating placements for their students. The ITF also ensures that monthly allowances of
students are made available, ensures that the supervisory allowances to participating institutions are
received, conducts annual evaluation of the programme and liaises with the appropriate federal
ministries (NUC, NBTE and other concerned body) on issues concerning SIWES.
for supervised industrial attachment, vet all programme and placement lists submitted by the
institutions before resubmitting to the ITF for approval. The NUC also makes sure that the lists of
all accredited programmes in each school are submitted to the Industrial Training Fund.
A Greek engineer, who was born in 1925, founded Arbico PLC in 1958. ‘B.C.’ Economides,
as he was known, had come for a short visit to Nigeria in 1953 to convince his brother Peter
Economides, who resided in Lagos since the late 1930s, fleeing the incoming World War II, to return
to Greece as the war ended. His brother instead spoke with such passionate words about the greatness
of Nigeria and the country’s future post-independence that ‘B.C.’ was convinced to stay and
‘explore’. Arbico PLC was founded based on a strong foundation of collaboration, integrity, and a
dedication to provide construction services that will stand the test of time. As a family-oriented
business with a vision to build a lasting legacy, Arbico has consistently surpassed all expectations
attracting a diverse group of talented individuals through the years. In the face of tough economic
and political travails, Arbico continues to thrive. Our passion for quality and strong ethical values
Arbico is a full service, building and civil engineering contracting company. After its
establishment in the year 1958, it has been quoted on the Nigerian Stock Exchange since the year
1978. The company has become one of the foremost construction company in Nigeria with presence
across the geopolitical zones of the country. For sixty years, the company has been involved in the
groups as well as high net-worth individuals. Arbico’s services include pre-construction, general
residential, educational, corporate and commercial offices. We have established a proven track
record of managing and delivering construction projects on time, as well as an operational strategy
a large inventory of civil and building construction materials and equipment to ensure prompt
delivery of services. Our construction management team has vast construction build out experience
ranging from private residences, high-rise buildings, factories to plant and infrastructural projects.
These successful experiences have proven that the construction management team and systems
Arbico put in place are effective and efficient. By carefully managing information, people,
equipment and materials, and working closely with the design engineers and quality management
team, our qualified construction management team ensures that all construction projects are
At the passing of the founder, Basil C. Economides on 8 January 1994, Arbico was forced
to transition from a thriving family business to a publicly traded company. The Board of Directors
welcomed Sir Kensington Adebutu as Chairman in 2010. Adebisi Adebutu, heading the team, Elder
N.C.U. Okoro as acting Chairman, Olatunbosun Olukoya (tragically and untimely gone), Eyo
Asuquo and Afolabi Aiyeola, both Executive Directors and members of the managing team, Otunba
Ositade Aranmolate (late) and Alkimos Makaronidis as member of the management team and
transitional Managing Director. These are the top management team of Arbico PLC running the day-
to-day affairs of the company from its head office situated at Plot D, Block 7, Industrial Cresent,
Arbico PLC operates in such a way that all its various operations apart from construction are
centrally carried out in the head office. Its procurement, administrative, human resource, logistics,
estimating and other functions are implemented directly form the head office. Taking the
procurement department as an example, all materials to be used on site for construction have to be
procured directly from the head office no matter how large or small they might be. My experience
at the NBC Asejire site made me understand this more. For any material to be procured to the site,
officers, plants and equipment engineers and some others in order to come up with a list of materials
and equipmets needed on site for construction and other various purposes. When this has been done,
a requisition will sent directly to the head office notifying the procurement department of the need
My primary place of assignment, which is the Nigerian Bottling Company (NBC) Asejire
site of Arbico PLC, is a very large site where construction processes and operations have
commenced since the year 2014. Arbico PLC is the major civil engineering and building contractor
on this site and they are saddled with the responsibility of bringing into reality series of civil
engineering and building works located on the Greenfield area of this branch of Coca-Cola
Company. Right from the commencement of operations on this site, various projects have been
completed while several others are ongoing. The Energy Centre, Warehouse Building, Pet Line, Pre-
treatment Plant Building, Waste Management Building and many others have been successfully
completed and delivered to the client. The uniqueness of this site in terms of its largeness in size,
huge number of operatives, equipment and plants, and the various constructions projects going on
simultaneously at different sections of the site have made several standards to be put in place thereby
influencing how the various site operations are carried out. These site operations are discussed
At the NBC Asejire site of Arbico PLC, health and safety cultures are highly regarded. As a
result of this, before any activity, process or operation is carried out on site, certain laid down
sequence of steps must be followed. Collection of work/operation permit is a major condition that
must be acknowledged and obeyed before any work can be executed on site. These work permits
are always issued by an organisation in charge of general health and safety on site. This organisation
general Health Safety and Environment (HSE) practices on site. These permits are issued according
to work trades and they always contain all safety requirements all operatives that would be involved
in that trade must have satisfied. The main essence of these permits is to be able to monitor efficiently
the site operatives and how they are adhering to the safety conditions already stated in them.
Operatives on this site a divided into two groups: the staff and the casual workers. The staff are
the workers employed directly from the head office of Arbico PLC and comprise mainly of the
supervisors, engineers, quantity surveyors, site administrators, drivers, security personnel and some
plant operators. The casual workers on the other hand are those whose employment is restricted to
the ongoing project and in some cases some other projects. They comprise the skilled, semi-skilled
and unskilled labours and some plant operators. All casual worker on site have their individual job
card where they keep record of the number of hours they work each day. It is based on this recorded
hours worked per day that they will then be paid after they might have worked for two weeks.
The fact that this site covers a very large expense of land comprising of different construction
projects going on simultaneously made the mode of communication a unique one. The Walkie-
Talkie cellular phones that use radio signals are being used to facilitate effective communication on
the site. These phones are given to each department head, supervisors, and engineers in order to
ensure communication is possible anywhere they are within and around the site without having to
see each other physically. One of the advantage of this means of communication is that it facilitates
quick ordering of concrete on site. Whenever an engineer needs a particular volume of concrete to
be used at a section of the site, the batching plant (concrete mixing plant) operator can easily be
plant.
The site has well-organised storage facilities under the supervision of a storekeeper. Steel
containers are being used as the site stores and these are where all materials and equipment that can
be affected by the effects of weather and climate are stored. Other materials such as reinforcement
bars, structural steel members, pipes for plumbing works and so on are kept outside since the weather
cannot affect them. The storekeeper is saddled with responsibilities of keeping records of materials
brought to site, materials requested from the stores to be used on site, and those taken away from
the site.
On this site, various plants and equipment are being used to carry out the day-to-day construction
activities. The plants present on site are; excavator, dumper, vibratory compactor, batching plant,
backhoe/backactor, Actros concrete mixer (loaded by the batching plant), Mellow concrete mixer
(self-loading), stationary concrete mixer, mini-vibrating machine, skid steer loader, tippers, pay
loader, bulldozer and CIFA concrete pumping machine. Before any plant can be operated on site,
each plant operator is required to fill a checklist indicating the degree of functionality of different
parts of the plant. Most of the plants on site operates on diesel. Therefore, in order to allocate the
appropriate quantity of diesel to each plant, an operative responsible for reading the Odometer
(component of plants that shows the number of hours the plant has worked) of the plants carry out
this task every morning. This makes it possible for him to ascertain the number of hours the plant
has worked and to check the extents of diesel in the plant. When this has been done, the appropriate
At the NBC Asejire site of Arbico PLC, communication and responsibilities flows directly
from the project/site manager to the site engineers, heads of departments, supervisors, site
administrator and the chief security officer. It then moves on to the other site operatives subordinate
to the above mentioned. The organisation chart of the site is diagrammatically illustrated below.
PROJECT/SITE
MANAGER
HSE
MANAGER
FILTERS/IRON
PROJECT QUANTITY PROJECT LAND SITE CHIEF SECURITY
SITE ENGINEERS SURVEYIOR SURVEYOR
BENDERS QA/QC ENGINEER
ADMINISTRATOR OFFICER
SUPERVISOR
TRADE (CARPENTARY, MASON, ASSISTANT ASSISTANT LAND SKILLED IRON PLANT SECURITY
INTERNS
WELDING, SCAFFOLDING) HEAD PROJECT QS SURVEYOR BENDERS OPERATORS / PERSONELS
MEN DRIVERS
SURVEYOR UNSKILLD
QS INTERNS MATES LABOURERS UNSKILLED
SKILLED OPERATIVES LABOURERS
(CARPENTERS, MASONS,
WELDERS, SCAFFOLDERS)
SEMI-SKILLED
LABOURER
UNSKILLED
LABOURERS SURVEYING
INTERNS
ENGINEERING
INTERNS
In the course of my industrial training at the NBC Asejire site of Arbico PLC, I was exposed
to various aspects of the construction industry and I garnered knowledge and experience in the
following areas namely; contractor’s quantity surveyor’s duties, on-site construction works,
construction related Health Safety and Environment (HSE) practices and other construction related
and non-construction related areas. These aspects are individually explained below:
The privilege of staying in the site quantity surveyor’s office in the course of my industrial
training gave me the opportunity to learn the various duties of quantity surveyors in the contracting
line. This opportunity also made it possible for me to learn directly from the project quantity
surveyor and the assistant project quantity surveyors that were present on site. On-site physical
measurements of works executed, preparation of report (daily, weekly and projected) of works,
interim valuation for sub-contracted works, preparation of materials schedule, measurement and
preparation of B.O.Q for civil engineering and building works, reconciliation of the quantities of
materials (especially aggregates) brought to site with that measured on site and lots more were the
duties I was exposed to and which I ultimately learnt from. These duties are individually explained
below:
department on this site. This is because all reports (daily and weekly) of works usually prepared
depends solely on the measured works. Around the closing hour (usually 1hour to the closing time)
of every workday on site, we usually go round to all the site sections where works have been done
in order to measure the works done. In carrying out this measurement, we make use of the 15m
length tape rule and the 100m length tape rule for short distance and very long distance measurement
perform this same duty when the project quantity surveyor needs us to confirm a measurement for
him on site and when the consultant quantity surveyor comes around to site to carry out the monthly
valuation of works. This daily and reoccurring site task has enabled me to be conversant with the
identification of various materials used on site and their basics sizes. Identification of the various
sizes of reinforcement bars and length of formwork panels without measuring are very good
examples.
Another positive impact that the daily measurement of works executed on site has had on me
is that it has really improved my understanding of construction processes and at the same time
enhanced my relationship with site operatives. When carrying out the measurement of executed
works, you have to relate with the site engineer or any other operative on ground whenever
somethings are confusing which you need instant clarification on in order to input the correct
measurement.
Site reports are prepared to give an indication about a task, an occurrence or an event that
happened on site. The reports that are usually prepared by the quantity surveying departments on
this site always show the quantity of works that have been executed within a particular period of
time and their associated cost. These reports include the daily report of works executed on site on a
daily basis, weekly report of cumulative works done within a week, report of works cumulatively
done within four weeks - monthly report as well as the projected reports for works envisaged to be
In preparing the daily report, on-site measurement of works executed is the first point of call.
For instance, the physical measurement taken for works executed on site today will be used in
preparing the daily report very early the next day. Figure 1 and 2 in the appendices section show a
using the Microsoft Excel worksheet shows the heading/title of the work, description of the work,
engaged operatives, quantity budgeted in the B.O.Q, daily-executed quantity, cumulative quantity
of works, budgeted and actual labour cost, budgeted and actual cost of materials, value of the work
(daily executed quantity multiplied by the rate) and the remark which is the profit made on labour
Other important things the daily report indicates can be seen in figure 2 and they are; the
total cost of labour used on the site per day, total remark- the total profit made on labour & materials
and most importantly the total value of works executed each day. Cells I658, M658 and L658 shows
The weekly report is another important report usually prepared for works executed on site
within a week. It comes as a result of the accumulation of quantities of work done each day for a
week so as to give an indication of the total quantity of work that have been executed on site for that
particular week and their corresponding value. In preparing this weekly report, reference is usually
made to the cumulative executed quantity column of the daily report shown in figure 1 & 2. At the
end of a week, the total quantity of work obtained in this column will now be transferred to another
Microsoft Excel worksheet used for the preparation of the weekly report. Figure 3 in the appendices
section shows a typical weekly report prepared using the Microsoft excel worksheet. The cumulative
executed quantity transferred from the daily report can be seen in the actual quantity column of the
weekly report. The quantity in this column will then be multiplied by the appropriate rate to give the
The total value of works proposed to be executed on site for the whole week and works
actually done can be seen in cells K158 and L158 of figure 4 respectively. In addition, the value of
works done by each engineer handling a particular section of the site is usually indicated too. Cells
The very last report within the jurisdiction of the assistant site quantity surveyors and the
industrial trainees is the weekly work projection report. This report is prepared to give an
indication/idea of works that are envisaged to be carried out on site within a week. The concept
behind this report is not to accurately project the exact works that will be done on site but just to
give an idea of the works that are likely to be executed and their corresponding cost to an individual
going through the prepared report. Figure 5 in the appendices section shows a typical weekly
projection report prepared using the Microsoft Excel worksheet. The total value of projected works
for the week is shown in cell J110 while the value of works projected to be executed by a particular
Summarily, the time and resources I invested in learning how to prepare these reports were
really worthwhile because at the latter end of my industrial training at this site, I was the only one
available in the quantity surveying department to assist the project QS. Because of this, I had the
opportunity to prepare all these reports for about two and a half months. This opportunity really
helped me to improve on my Microsoft Excel usage skills and at the same time helped me to be
conversant with ways in which these types of reports can be prepared to suite any particular project.
measured on site.
The different types of aggregates that are often delivered to this site are; granite, stone dust,
sharp sand, plaster sand and hard-core. Both granite and stone dust are used for producing concrete
of any specified mix while the plaster sand is used for producing mortar used for plastering. Granite,
stone dust and hard-core are products of the quarry (a place where rocks are transformed into
fragments of different sizes) while both sharp sand and plaster sand are usually sourced locally from
weight and the tons loaded will all be shown on the delivery slip/waybill.
Using a typical delivery slip shown in figure 6 in the appendices section as a perfect example;
Gross Weight = the weight of the truck + loaded stone dust = 37400kg
The above illustration shows that 21890kg is the weight of stone dust loaded directly form the
quarry but when it gets to site another process of measurement will be done on the loaded stone dust
in order to reconcile the weight loaded from the quarry with that obtained on the site using the steps
illustrated below;
Step 1: An operative (usually the storekeeper on this site) will climb the truck in order to measure
three different depths of the loaded aggregate. This is done by dipping a long iron rod in three
different locations in the aggregate. The measured depth will then be written clearly on the delivery
Step 2: The delivery slip, which now has the tree different depths on it, will now be taken to the
Step 3: As shown in figure 6, the three measured depths will be added, their average will be obtained
and then multiplied with the length and width of the truck’s bucket to give the total volume of
aggregate loaded. Using the same figures shown in the given delivery slip as an example, the site
1.23 + 1.43 + 1.10 = 3.76 (the three measured depths and their sum)
average depth with the length & width of the truck’s bucket)
14.21 x 1.5 = 21.32 Tons (site weight obtained after multiplying the aggregate’s volume
21.32 tons or 21320kg is the new weight obtained on site and necessary payment will be
made based on this new weight. This same method is used when treating other aggregates like
granite, sharp sand and plaster sand but the exception to this method is the hard-core. Payment for
hard-core is made based on the weight loaded directly from the quarry since it is not easy to obtain
the depths of loaded hard-core like other aggregates. As used on this site, the density used when
treating stone dust, sharp sand and plaster sand is 1.50kg/m3, for granite 1.60kg/m3 is used while
Throughout the time I used on industrial training, various sub-contractors were engaged by
Arbico PLC to carry out various forms of specialist jobs. Some of the sub-contractors engaged are
specialist in structural steel works, painting, felting, tilling, treatment of walls & floors in order to
get rid of water seepage and lots more. To facilitate the payment of these sub-contractors, a periodic
process known as interim valuation is always carried out. On this site, preparation of interim
valuation is solely restricted to the project quantity surveyor but that has not stopped me from
learning more about the process. Through my understudying of the various interim valuations that
have been prepared, I have been able to build on what I was taught in the classroom and also identify
some disparities between the way I was taught in the classroom and how it is being done practically
on site.
Figure 7 in the appendices section of this report is a typical interim valuation prepared for a
particular sub-contractor responsible for laying bituminous felt to a tank base at a section of the site.
retentions are usually removed on every gross amount in every valuation and that the total retention
will be that removed from the gross amount of the last valuation.
Measurement and preparation of B.O.Q for civil engineering and building works
Several number of designs were given to me to study, measure (take-off) and prepare their bill
of quantities throughout my stay at quantity surveying department of this site. This provided me
with the opportunity to acquaint myself with diverse civil engineering and building designs and to
learn from the site quantity surveyors. I learnt on a particular day that it is safer cost wise to measure
bulk excavation for columns close to each other within an area or a straight line than individually
measuring the volume of their pits. This was after I have measured their pit excavation individually
without considering that it is not practically feasible and not cost saving. I was also able to develop
a template on Microsoft Excel, which I used whenever I want to take-off the quantities of any given
It is the duty of the quantity-surveying department to provide the quantities of various materials
needed on site for construction activities. This is important mainly because of materials requisition
purposes. After we might have obtained the quantity of a particular work through taking-off, we
then proceed to calculate the quantities of various materials needed for the work. This task has given
The privilege and opportunity to witness several real life civil engineering and building
construction works is another very important aspect of my industrial training at the NBC Asejire site
of Arbico PLC. On this site, I had the opportunity to witness the construction of several reinforced
plumbing works and building construction works. These various civil engineering and building
construction works have really broadened my understanding of construction and have enhanced my
Construction of hardstands, which are reinforced concrete pavements finished smoothly on the
surface by a power-floating machine, is the most reoccurring construction work I witnessed on this
site. This form of construction happens almost on all the days I used on this site. The hardstands are
being constructed to serve as access road for the various trucks and pedestrians coming in and out
of the Coca-Cola plant. Assuming earthworks (cutting and filling) has been completed and the
necessary levels have been given by the land surveyors, the steps and processes involved in the
Step 2: 50mm thick sharp sand will then be spread on the hard-core. Figure 9 in the appendices
Step 3: A hard drum roller will then be used to compact both the hard-core and sharp sand to
Step 4: D.P.M nylon will be laid on the compacted area to prevent rising of damp later in the
future.
Step 5: The appropriate quantity of concrete with 1:4:8 mix ratio will be poured on the D.P.M
nylon to a thickness of 50mm to serve as blinding. Step 4 & 5 are both shown in figure
Step 7: After the formwork is in place, the iron benders will now lay both the bottom and top
reinforcement mats of 10mm diameter bars in the hardstand panel. Both steps 6 & 7 are
Step 8: The appropriate volume of structural concrete of mix ratio 1:1.4:2.3 will now be poured
into the panel, vibrated using a concrete vibrator and then levelled by the masons using
their range and trowel. Figure 12 in the appendices section shows this step.
Step 9: This is the very last step of constructing a hardstand panel and it is the smoothening of
the concrete surface with a power-floating machine after a smoothening chemical has
been applied on the semi-dried concrete surface. The power-floating action and the
This hardstand construction offered me the opportunity to witness and relate with the practical
application of what I was thought in a civil engineering measurement class. On a particular day in
the civil engineering measurement class, we were taught that in road works (of which hardstand
construction is an example), filling moves from large aggregates to smaller ones (upward movement)
while in building works, filling moves from smaller aggregates first to larger ones. I have been able
to ascertain this fact on site through the construction of this rigid form of pavement where hard-core
Construction of drains
Construction of drains were also prominent throughout my stay on this site. These drains are
being constructed to enable the movement of wastewater from various sections of the Coca-Cola
plant to the outer drain leading to a stream. Some drains were constructed in line with the hardstands
constructed using concrete rings of various sizes as means by which wastewater moves from one
destination to the other. These drains constructed in line with hardstand construction are constructed
in such a way that the top surface of their wall when completed will be on the same level with the
excavation of the trench is the first step, which is then followed by levelling and compacting.
Blinding, fixing of drain reinforcement, erecting formwork to drain base, casting concrete in drain
base, erecting formwork to drain walls, casting concrete in drain walls, fixing of angle iron to upper
parts of drain walls, covering of drain with specified steel cover are all other steps involved in
constructing this type of drain in the stated order. Figures 14, 15 and 16 in the appendices section
The other dimension of drain construction on this site as earlier mentioned are those constructed
using concrete rings of various sizes. Depending on the quantity of wastewater that will be passing
through them, varying sizes of concrete rings ranging from 600mm, 900mm and 1200mm diameter
are usually used. The construction methodology of this type of drain are: filling with hard-core where
necessary, filling with 50mm thick sharp sand, blinding surface of sharp sand with 50mm thick
concrete of appropriate mix, putting the drain reinforcement in place, erection of formwork to drain
base, casting concrete in drain base, arranging concrete rings on drain base, erecting formwork to
both sides of the rings and lastly casting concrete in voids beside concrete rings. These given steps
are for concrete ring drains whose top surface will not be covered, that is, a little part of the concrete
ring will still be visible at the top. Where the whole ring will be casted in concrete, the above given
steps will continue with putting in place reinforcement for ring capping, erecting formwork to sides
of ring capping and then casting concrete in ring capping. When these three steps are done, the
concrete rings will not be visible. Figures 17, 18 and 19 in the appendices sections shows the various
According to Merriam Webster dictionary, retaining walls are walls built to resist lateral pressure
other than wind pressure; especially: one to prevent an earth slide. Due to the terrain of this site,
retaining wall are being constructed at various locations of the site where they are required. These
walls constructed mainly to hold back earth pressure are usually constructed in panels of 6m length.
A polystyrene material is always used to separate the panels of these retaining walls from one
another and this is so in order to be able to individually maintain or make corrective adjustments to
defective panels. Throughout my stay on this site, construction of retaining wall is a major activity
that brings a huge increase to the value of works executed on site. This is so because of the huge
On this site, 32mm and 16mm diameter bars are usually erected side by side as the main
reinforcement of the retaining walls while 12mm diameter bar serves as the runner. For the
construction of the retaining wall base, 32mm, 25mm, 16mm and 12mm diameter bars are the bulk
of reinforcement used. In constructing these earth retaining walls, excavation for the retaining wall
base is the first step, which is then followed by levelling and compacting. Blinding with 50mm thick
concrete of appropriate mix ratio, setting out the extent of the retaining wall base, erecting formwork
for the retaining wall base, fixing the retaining wall base reinforcement as well as starter bars for the
retaining wall and then casting of concrete in the retaining wall base are all the other steps involved
in the retaining wall base construction. When the retaining wall base has been constructed, kickers
as shown in figure 20 in the appendices section will now be put in place to indicate the region of the
retaining wall and to ensure the carpenters accurately erect the retaining wall formwork.
To construct the retaining wall when its base is already in place, the iron benders will have to
lap the retaining wall reinforcement with the starter bar after which the carpenters will erect
formworks to the retaining wall. When these are done, concrete can now come into the retaining
At some sections of this site, structural steel works were executed and this gave me the
opportunity to learn more on this aspect of construction. These structural steel works were handled
by a sub-contractor to Arbico PLC that specialises in this aspect of construction. The real life
execution of these works has enabled me to build on certain things I have learnt in the classroom
and at the same time learn new things. I was also able to develop my competency in studying and
accurately interpreting structural steel designs because there were quiet a number of them that I took
time to study and likewise ask questions concerning some confusing parts from engineers in charge.
Figures 22 in the appendices section shows some structural steel roof members while figure 23
Plumbing works
In line with the various civil engineering works that were executed on site, quite a number of
plumbing works were also carried out. These plumbing works comprise construction of manholes
with concrete rings where blockages in pipes can be inspected and corrected and construction of
agricultural drain which is a slotted/perforated PVC pipe placed into a trench that is backfilled with
rocks or sand to enable ground water or surface water that seeps into the trench falls through the
rocks and therefore carried away by the slotted PVC pipe. The main essence of these agricultural
drains is to prevent the foundations of buildings from being affected by water seeping into the ground
especially if the house is built in areas prone to high seepage of water. It is also important to wrap
the agricultural drain pipes with geofabrics/geotextiles in order to keep silt out of the soakage drain
and pipe. A manhole being constructed before the construction of hardstand can commence in that
Apart from the civil engineering works, some building construction works were also executed
during my stay on site. In executing these building works, 225mm thick stone dust made blocks
filled with weak concrete are usually used in order to make the walls strong and able to withstand
external forces. In line with these building works, I also witnessed construction of perimeter fence
with concrete coping as well as plastering/rendering works to block wall. Visual illustration of some
of these building works are shown by figures 25 & 26 in the appendices section.
Health Safety and Environment (HSE) practices are highly regarded on this site and are
usually the first point of call before any activity can be carried out on site. The Hybrid group, which
is a Health Safety and Environment organisation, are responsible for taking care of all safety matters
on all Coca-Cola plant and the Asejire plant is not an exemption. Safety officers of all contractors
on site are required to report directly to the Hybrid group concerning safety matters on site. To
expatiate on the fact that safety is the first point of call before any activity can be carried out on site,
All operative or anyone coming to the site to carry out one activity or the other must undergo
a medical test and thereafter submit the medical test certificate when being inducted into the
Anyone on site must put on all Personal Protective Equipment (PPE) required for the job
he/she is doing.
No operation can be allowed to proceed on site except approved permits are collected and
On a daily basis, it is required of every plant and equipment operator to fill a checklist made
purposely for the plant after he might have checked for all faults in the machine.
Throughout my stay on this site, I was able to learn a lot of things in relation to construction
health and safety practices. The various lessons I learnt through this safety concept are explained
below:
I was introduced to the concept of Toolbox Talk which is an informal safety meeting that
focuses on safety topics related to the specific job, such as workplace hazards and safe work
practices. These meetings are normally short in duration and are generally conducted at the
job site prior to the commencement of a job or work shift. On the NBC Asejire site, individual
contractor conducts their Toolbox Talk prior to commencement of work while the Hybrid
Group usually conduct a general Toolbox Talk for all contractors on site every Tuesday.
Through the various topics that were discussed on a daily basis in the Toolbox Talk, I was
able to deduce that Behavioural Based Safety (BBS) is the most important aspect of safety
while Personal Protective Equipment (PPE) compliance is the last point of call in the safety
hierarchy. A site operative whose behaviour and attitude to work is safety compliant will be
free from accidents and hazards but an operative whose behaviour is not safety compliant
even though he puts on the right PPE is highly prone to accidents and hazards while carrying
out his job. Personal Protective Equipment are required to protect operatives from accidents
after all other options have been exhausted. This is why PPE are regarded as the last point of
Identification of different Personal Protective Equipment and their various uses is another
thing I learnt as regards safety on this site. Apart from the common Hardhat (helmet),
reflective jacket and safety boot, I was exposed to new personal protective gears used for
(used by welders), mason googles, fire resistant apron used for hot-works, hand gloves
serving various purposes and so on. Concerning Personal Protective Equipment (PPE), I
learnt most importantly that their compatibility to the operation or work to be executed is the
most important things. When the wrong PPE are used for a particular job, it is more or less
Around the end of my industrial training on this site, I was introduced to two online Health
Safety and Environment courses by one of the site’s safety officers, which also helped in building
on my health and safety knowledge. These courses were conducted online by the National Health
Care Provider Solution (NHCPS) and I enrolled for two of their courses, which are the CPR
certification course & the BLS (Basic Life Support) certification course. These courses offered me
the opportunity to learn basic real life approaches to safe and render first aid to an unconscious
person or an accident victim. The certificates given to me after completing these courses online are
In addition to the experiences discussed above which I gained during my industrial training
period at the NBC Asejire site of Arbico PLC, there are also some others that I have categorised as
being construction related and non-construction related. The additional construction related
experiences I used my industrial training period to garner is the knowledge & skill of using the
AutoCAD design software and the understanding of the operations and usefulness of various
construction plants & equipment. During this period, I effectively utilized several YouTube training
videos as means of learning the basics and rudiments of this software. Through constant practise and
continuous learning, I can now effectively use the AutoCAD software to design building plans and
elevations. I was also able to discover how the AutoCAD software can be used by quantity surveyors
shown in figure 19, I made use of this technique after which I only have to multiply the surface area
obtained with the length casted in order to get the total volume of concrete in the ring capping. On
this site, I was also exposed to various construction plants and equipment that I have never come
across before. My experience on this site made me understand their uses and the various situations
where they can be used. The Batching plant – a concrete production plant was a notable plant I learnt
a lot about. Through my visit to this plant on a particular day, I was able to learn and understand the
basics of operating the machine as well as the usefulness of several component/part of this plant.
The batching plant used on this site is shown in figure 30 in the appendices section having some of
training, relational experience is noteworthy. The opportunity to relate with various people on site
has groomed me on how to relate rightly with different class of people in the society. I learnt how
to effectively communicate and relate with site operatives (artisans & labourers) and thereby
learning from them. I was also able to learn a lot from the senior construction professionals I met on
this site through my discussion with them. Administrative experience is another experience I gained
during the period of my industrial training not directly related to on-site construction. My closeness
to the site administrator gave me the opportunity to see and learn how the administrative aspects of
the site are taken care of. I sometimes help in carrying out some basic administrative tasks when not
busy.
4.1.1 Conclusion
The experiences I gained and lessons I learnt during my industrial training period at the NBC
Asejire site of Arbico PLC have in many ways broaden my understanding of construction and
quantity surveying practices, thereby making me a better student of quantity surveying and
ultimately groomed for the professional future that lies ahead. This period was indeed an avenue of
improving on all theoretical knowledge accumulated over the years in the classroom and an avenue
of learning how to put them into practical use in the industry. However, these classroom experiences
made it easy for me to promptly understand everything being done in the industry.
Above all, my time at the NBC Asejire site of Arbico PLC was worthwhile and extremely
4.1.2 Challenges
The major challenge I encountered during the period of my industrial training on this site
was a sudden increase in my workload around the latter end on my training. Around this time, one
of the site assistant quantity surveyor got a better job opportunity while the other had to leave the
site in order to participate in the mandatory National Youth Service Corps (NYSC) program. This
made the bulk of the office work being carried out by these people transferred to me. Aside the stress
this brought, I was excited the opportunity came because I was able to test my expertise on various
tasks and improve on some others. Above all, learning was made exciting due to the support I
To the Students:
Students must ensure they put all their attention and focus in what they are in the industry to
gain which is the on-the-job practical experience. They should have it at the back of their
Students should ensure they are of their best behaviour both on site and in the office. Good
Students must also make sure they give prompt attention to what they are being taught in
classrooms, as this will form the foundation upon which they will build in the industry.
To the Employers:
Employers should ensure they give the right attention to students on training and at the same
time make sure the core practices of the profession are exposed to them.
In any way within their capability, employers should try to encourage students being trained
To the Institution:
Institutions and departments most importantly should assist students in securing placement
Figure 10: Illustration of D.P.M nylon and 50mm thick concrete blinding to a hardstand panel
Figure 11: Illustration of formwork, reinforcement mats, hunch bend and concrete cover in a hardstand panel
POWER-FLOATING CHEMICAL
Figure 14: Typical drain reinforcement Figure 15: Illustration of angle iron and drain steel covers
Figure 18: Concrete ring drain awaiting concrete in voids beside rings and capping
Figure 26: Construction of a building with 225mm thick blocks made with stone dust