Documente Academic
Documente Profesional
Documente Cultură
4-0007
Rev. 2
1. INTRODUCTION
The procedure is to ensure for both Vibracoustic (VC) and suppliers that new and change projects
are carried out in trouble-free manner, on schedule and without any quality problems. Existing into
the automotive market along with attaining growth requires cost and continual improvements in the
area of quality and delivery along with rapid and flexible reaction times to requirements. Vibracoustic
has adopted a Zero Defect Strategy of which will enable customer satisfaction. This aim is only
attainable with the active co-operation of our suppliers. For this reason the existing specification was
compiled: “Quality assurance measures for procurement of purchased parts”
This procedure specification is handed over by purchasing in its valid form to the supplier and has to
be applied consequently by the supplier and VC for each project.
This Global Procedure is part of the framework contract with the supplier. Deviations from the defined
procedure have to be agreed in writing between VC and the supplier. The existing procedure
specification identifies the minimum requirements for the secure handling of new projects and series
production orders. In addition, the supplier is committed to employ suitable procedures and measures
which ensure that the work/product corresponds to the agreed requirements with regard to quality,
cost and target date.
Department/
Rev. Date Page(s) Modification notes
Name
Approver Approver
Producer / Department Date Status*
Management System Board of Directors
J. Höfle / QM - - 26.07.2012 completed
G. Staab / QM - 10.12.2014 approved
H.J. Goslar 30.01.2015 approved
J. Law 29.01.2015 approved
Page | 1
GP-01-7.4-0007
Rev. 2
TABLE OF CONTENTS
1. INTRODUCTION ............................................................................................................................... 1
2. PURPOSE ......................................................................................................................................... 4
3. SCOPE ............................................................................................................................................. 4
6. RESPONSIBILITIES ..........................................................................................................................25
7. APPENDIX / ENCLOSURES ................................................................................................................26
Page | 3
GP-01-7.4-0007
Rev. 2
2. PURPOSE
In this procedure specification the Procurement and Quality Assurance of purchased parts of
production material for all VC companies is specified. Thereby we want to ensure that
- new products are realized on schedule and without any quality problems
- quality problems are identified and robust solutions implemented prior to series production
- quality capability of processes and flows are evidenced at series approval and during series
production
3. SCOPE
This GP is valid for all procurement processes of production material for all VC companies with
partnership production and expands determinations of purchasing contracts and purchasing
conditions. Exceptions to this procedure instruction must be agreed in writing. Standard products
(e.g. catalogue goods, standard parts, standard colours, lubricating materials etc.) are excluded.
4.1 Definitions
SQMS
The Supplier Quality Management System describes the business process of supplier selection,
supplier evaluation, supplier development as well as actions for the protection of new projects and
series parts.
Initial Samples
Initial samples are parts/products which are produced with the planned equipment, procedures,
manufacturing staff, materials and semi-finished products produced exclusively for series production.
They serve as acceptance of production parts.
FMEA
Supplier
The term “supplier” basically refers to production facilities in this GP, not to trade organizations.
Therefore, an “Approval of Suppliers” always applies correspondingly to the audited production site
only, but not to the general trade organization.
Page | 4
GP-01-7.4-0007
Rev. 2
Sub-
Supplier VC Customer
contractor
Preliminary process capability examinations are short term inspections in order to maintain early
information in respect to efficiency of a new or amended process. (see point 4.4).
Specific Characteristics
Significant and critical characteristics must be clearly designated in the drawings. Basically there is a
distinction of
- Significant characteristic (Fit & function) = SC
- Critical characteristics = CC*
- Emphasis Characteristic = EC
* safety relevant!
EC
For specific characteristics preliminary process capability has to be determined by the supplier when
manufacturing first samples. In series production this has to be monitored by SPC.
The above mentioned identifications for specific characteristics will be used in general for drawings
for supplied parts. Only in case of an explicit request of a customer other, customer specific
identifications for special characteristics will be used.
Safety critical characteristics comprise in case of deviations a risk for life and limb. Therefore they
must be 100% tested. The tests should be defined in consultation with VC.
Production Part Approval Process (PPAP)
The procedure for inspection of production parts contains initial sampling of product features (Initial
sample test report) and proof of a controlled production (Production control plan, evidence of process
capability, FMEA etc.). OEM specific requirements (PPAP acc. AIAG resp.. EMPB acc. VDA2) have to
be assumed by supplier.
4.2 Abbreviations
AIAG Automotive Industry Action Group
APQP Advanced Product Quality Planning
BA Business Area
BUM Business Unit Manager
CM Commodity Management
CSR Customer Specific Requirements
DV Design Verification
EMPB ErstMusterPrüfBericht
EPC Early Production Containment
GP Global Procedure
IMDS International Material Data System
IR Inspection Report
ISIR Initial Sample Inspection Report
MS Microsoft
MSA Measurement System Analysis
QMS Quality Management System
QM-Site Quality Manager Site
PPAP Production Part Approval Process
Ppku Ppk(upper specification limit)
Ppkl Ppk(lower specification limit)
Page | 6
GP-01-7.4-0007
Rev. 2
Page | 7
GP-01-7.4-0007
Rev. 2
Page | 8
GP-01-7.4-0007
Rev. 2
The procedure specification in hand specifies exclusively the APQP - purchased parts and the phase
series production.
5.2 QM-system
It is the suppliers duty as a requirement, to employ a certified QM-System appropriate to the
regulatory standards ISO 9001. A continual further development of the QM-System is necessary for
system elements TS 16949 specific to the automotive industry. These demands specific to the
automotive industry on error avoidance and the procedure for inspection of production parts are to
be fully implemented corresponding to the following specification for all VC products. The supplier
should also incorporate any relevant Customer Specific Requirements into its QMS system that refer
to the specific product or service.
– Generally accessible guidelines/ standards (e.g. DIN, ISO, EN and ASTM-Norms) have to be
provided for corresponding positions.
– Guidelines/standards and documents of VC or its customers will be forwarded upon request to
the relevant purchasing area.
Page | 9
GP-01-7.4-0007
Rev. 2
www.vda-qmc.de
5.7 Audits
The supplier must audit its QM-System at regular intervals for effectiveness and consequential usage
of the requirements described here. VC is entitled to carry out – if necessary with the customers -
audits at the supplier and at its sub-contractors – after appointments were made. The supplier has
to support VC in carrying out the audit and to give particular insight into the required procedures,
data and recordings for analysis of the Quality Management System, as well as, in doing so, not
touching particularly upon the supplier’s interests of secrecy being justified.
Page | 10
GP-01-7.4-0007
Rev. 2
5.8 Staff
The supplier has to demonstrate that all employees who work in the areas planning, production and
inspection are qualified for the respective activity.
Page | 11
GP-01-7.4-0007
Rev. 2
Content:
1. Individual measures such as:
– production equipment and production tool planning,
– procurement of purchased ancillary items,
– compilation of Process-FMEA,
– compilation of a control plan for prototype, pre-series, series
– manufacturing of initial parts,
– manufacturing pre-series
– test scheduling pre-series, series
– Production parts approval process (PPAP).
Responsible persons have to be fixed by name and contact data (phone, mobile, email)
Project schedules should be structured corresponding to Appendix 1. Similarly other formats with
the same content will be accepted (e.g. MS-Project, etc.).
Once a month without solicitation, the supplier has to forward a current project status report “Ancillary
items” to the project manager VC* including tooling progress report by traffic-light evaluation.
*Name and Fax No. are stated in the status report for purchased items!
Page | 12
GP-01-7.4-0007
Rev. 2
*Name and Fax No. are stated in the status report for purchased items!
For functional critical parts the amount and frequency of testing defined in the control plan has to be
agreed upon between the SQA, SDE, QM (site), the VC development and the supplier. A member of
the technical as well as quality department of the supplier should participate.
The Control plan has to reflect entire process chain of contracted part-no., including outsourced
processes. The Control plan of the subcontractors should be provided upon request by VC.
The production control plan, which is approved by VC within the EMPB/PPAP procedure, is binding
for the entire life time of the product. Changes, which are relevant for method and scale of
inspections, have to be released by VC prior to implementation. In case of a loss of quality or product
risks and process risks not defined by the approval time, VC reserves the right to amend the QM
schedule corresponding to needs.
Content of control plans should be adopted according to the regulations of ISO/TS16949 latest
revision, or AIAG.
Remark: The process number sequence has to be the same through all documents
(Control plan, FMEA)
Page | 13
GP-01-7.4-0007
Rev. 2
5.12.3 Process-FMEA
The failure mode and effects analysis has to be carried out before series production as a method of
error avoidance. In order to be able - if needed - to carry out appropriate corrective actions with no
considerable cost, the FMEA has to take place within the earliest possible time-frame.
PFMEA has to reflect entire process chain of contracted part-no, including outsourced processes.
Method and formal structure must be executed corresponding to VDA 4, Part 2. OEM specific FMEA-
requirements (i.e. AIAG FMEA manual, Ford – FMEA ranking system) have to be assumed by supplier.
A prerequisite for a production parts release (initial samples approval) is the supplier’s confirmation
that the required Process-FMEA has been carried out on the first sample test report. On request FMEA
can be reviewed by VC.
Page | 14
GP-01-7.4-0007
Rev. 2
“Zero defects are only possible with controlled and quality-efficient processes.”
Short-term Prelimenary
process cability process capability Long-term process
examination examination capability
examination
Application to the evaluation:
• new equipment at the Application to the
manufacturer evaluation:
• new equipment after • the running series
installation in the defined production
process
• before finally approval
Process
Manu- Human
facturing machine
material
equip- method Permanent quality improvement
ment Environment
Time
Short-term process Prelimenary process Long-term
cability capability process cability
Page | 15
GP-01-7.4-0007
Rev. 2
Sample size:
At least 125 parts have to be withdrawn over the entire pre-series production lot and continually
tested. If the tools have more than one cavity, an equal distribution of all cavities must be assured.
125 samples = 25 subgroup of 5 parts. We recommend the following rule for sampling as preliminary
study
5 parts, skip 5 parts, 5 parts, skip 5 parts, etc.... If multi-cavities, we accept 125 samples for 1 feature
if cav. # randomly shared. If capability is not OK, than we accept the split of the cavities and that
supplier demonstrates capability of cavity per cavity. All distributions must be normal.
Recordings
The preliminary examinations of process capability are part of the production parts inspection
procedure as per AIAG – PPAP and VDA 2, and must be forwarded to VC as part of PPAP package.
Page | 16
GP-01-7.4-0007
Rev. 2
Since the preliminary process capability is only determined on one lot (pre-series/production trials),
systematic influences between the individual lots (human, material, etc.) are not taken into
consideration. Preliminary process capability gives only a statement to the current situation therefore
process capability has to be constantly monitored and documented in running production.
Some customers might request higher preliminary and long term process capabilities. Information
about deviating capability requirements to the above mentioned standard requirements will be
communicated during the project.
2. Step
The production parts approval procedure (PPAP) is carried out at the supplier’s, in the presence of a
member of VC staff or an external agent. Depending on product and project risk the project team
defines whether the release is done in one or two steps.
For critical or safety critical purchased parts (cc = critical characteristics) the 2 step
approval is mandatory.
If the one-step procedure is performed, the series release is given after receiving correct and
complete PPAP reports and approving the dimensional and functional characteristics of the first
samples.
In case of an agreed two-step procedure supplier receives the approval after successful production
trial at site (Step 2) and approved PPAP according to step 1.
Page | 17
GP-01-7.4-0007
Rev. 2
The production parts approval process (PPAP) must be carried out by the supplier in the following
cases:
- with new sampling (repeated sampling),
- amendments to product design / material,
- changes to production procedure,
- transfers to other production locations,
- use of new tools and cavities
- use of new suppliers,
- with an interruption to production longer than 12 months.
VC is to be informed, in each and any of the given instances, before implementation of the change,
and always with written agreement from VC.
The range of the production parts approval procedure has to be agreed with the responsible SQA.
Should a necessary repeat inspection for production parts be caused by the supplier, VC reserves
the right to charge appropriate cost to that supplier.
2. Limited Approval VC
Page | 18
GP-01-7.4-0007
Rev. 2
Notes:
to 1. In cases where the customer requires his own forms for supplier PPAPthe required forms have
to be used.
to 4. Test procedures/measuring devices must be included in the control plan.
to 8. Measurement results must be assigned to the individual parts
to 14. The testing of the function features is to be agreed between VC and the supplier (e.g. durability,
corrosion testing etc.).
PPAP documentation has to be sent to VC as a complete file in duplicate and together with the first
samples. In case of a Nexprise access. The delivery of initial samples with PPAP evidence must be
delivered separately of the series delivery! The delivery must be clearly be labeled as initial sample.
Page | 19
GP-01-7.4-0007
Rev. 2
- product design
- material
- sub-contractors
- production methods and equipment
- production location
during series production.
Changes must be reported!
Proposed changes must be notified in writing min. 3 month before implementation to VC and
approved by VC! The responsible supplier quality manager (SQA of receiving plant) decides in which
range the production parts approval procedure (PPAP) is to be employed.
Page | 20
GP-01-7.4-0007
Rev. 2
In order to be able, on VC’s part, to evaluate the requirement and success of these measures,
annual evaluation and rating of the supplier will be done by VC. Quality targets can be agreed with
the supplier in individual instances. The Zero Defect Target is valid.
Page | 21
GP-01-7.4-0007
Rev. 2
must be available.
5.15.7 Packaging
Packaging of products in each individual case is to be agreed with VC and documented with the
PPAP records.
Page | 22
GP-01-7.4-0007
Rev. 2
5.15.9 Deviations
Should parts at delivery or afterwards during production process be found faulty, then this can
lead to the return of the whole delivery. As soon as the supplier is aware of this he must make
sure that no further defective items are delivered. Stocks of finished parts have to be inspected
or replaced with inspected material and immediately effective remedial actions initiated.
The supplier obliges himself to inform VC immediately in the case of a delivery of faulty products
having been carried out already (self complaint). For the ensuring of efficiency of supplies, VC
reserves in case of a line stop the right to arrange directly inspection and rework, and to charge
any expences incurred by VC to the supplier if the supplier fails to respond to VC within 1 hour.
For each complaint the supplier will receive a notification (Inspection Report). Responses are
always to be done according to the 8D-Process principles.
The immediate measures taken must be notified to VC within 24 hours. The concluding report
must follow 10 days after receipt of the inspection report (see OPI-01-7.4-0002). Extra time is
possible when an evidence (e.g. defect sample part) is necessary for carrying out the root cause
analysis but is not available.
The risk analysis (FMEA), having the purpose of avoiding defects, is to be reviewed with respect
to the concern checked.
Page | 23
GP-01-7.4-0007
Rev. 2
1. Level 1: 8d-Process
2. Level 2: Supplier Quality Development Meeting (including strategic action plan)
3. Level 3: Q-Support
4. Level 4: New Business Hold (NBH)
5.15.13 Subcontractor
For series deliveries it is only allowed to consider subcontractors, whose parts have been used for
PPAP to VC. The Subcontractor must submitt a PPAP to the supplier and the supplier has to
evaluate and release it before submitting the whole PPAP to VC. A change is only allowed after
submission of new sample parts to VC (see 5.14. PPAP). For the new sampling it is only allowed
to use approved subcontractors.
For a subcontractor change during serial production VC has to be informed in advance (see 5.14.
PPAP). The order to the subcontractor is only allowed after written agreement by VC. A delivery
to VC is only allowed after full approval of PPAP by VC. In the case of a supplier change for safety
critical purchased parts the 2-step method is mandatory.
Page | 24
GP-01-7.4-0007
Rev. 2
6. RESPONSIBILITIES
Project
Project Deve-
QM- QM- QM- Pur- Supp- Produc-
Task / Function Manage lop- SDE SQA MGM
Region BA Site cha- lier tion
ment ment
sing
Contractual agreement of
C R C A
the VC Global Procedure
Individual agreements
deviating to the VC-Global I A C C I R I C I
Procedure
run&rate at supplier C I C C A R C
PPAP approval A I I I C R C
Approval of changes C I A C R I I
Approval of deviation
R A C C C I C
requests
Responsible: Process owner, responsible to carry out the business process (implementation,
execution)
Accountable: Approver, responsible for the result of the business process (objectives, design,
monitoring)
Page | 25
GP-01-7.4-0007
Rev. 2
7. APPENDIX / ENCLOSURES
9. DOCUMENTATION
VC will keep this procedure on file. In case of a revision the latest edition will be kept for at least 3
years after revision.
Page | 26