Sunteți pe pagina 1din 18

Estimate for laying of Distribution pipe line at Rohingya Camp (WDZ.8W.

7) under V
(UNICEF) (Item of Pipeline Installation from Storage Tank to Tap Stand)
SL. Description of Works Rate
Unit Qty.
No. (TK)
Cutting and removing the following types of road
pavements for pipeline to a width of pipe diameter
+ 0.4m including salvaging of materials, stacking
the withdrawn materials at a safe place for reusing
1 etc., all complete as per direction of Engineer in
Charge (EIC).
a. Brick soling m2 0.00
b. Herring bone bond over brick soling m2 8.00
c. Bituminous with khoa consolidation. m2 11.45
Excavation in all kinds of materials for trenches
upto depth of 1.00 m plus pipe diameter from
road surface or existing ground level and a width
of pipe diameter + 0.4m including layout,
2 excavating earth to the lines, grades and elevation m3 122.00
as shown in the drawing providing center lines,
local bench mark pillars, fixing bamboo spikes ,
carrying and disposing of all excavated materials
at a safe distance designated by the E-I-C in all
Supply of sand
type of soils such asof very
FM stiff
0.80(hard),
free clayey
from soil,/
clay,
vegetation
rubbish etc. andramming,
other organic matter
dressing andleveling
and filling and
of
compacting by sprinkling
trench bed, proper water,
stacking of dressing earth
the excavated and
leveling etc.
by the side in 100
of road at a mm thick aspipe
safe place bedding
per direction
surround
of EIC and (a) for pipes in road verges to a
3 height of 150 mm above the top of the pipe and m3 20.00
(b) for pipes in roads pavement/ road crossing
upto the bottom of the original road structure etc.
all complete as per direction of EIC.

Backfilling with excavated earth of the trench


above pipe zone (from 150mm above the top of
the pipe to road surface) including watering and
4 compacting in layers not exceeding 150mm all
complete as per direction of EIC.

a) Backfilling with excavated earth m3 102.00

Page 1 of 18
SL. Description of Works Rate
Unit Qty.
No. (TK)
Supply and Installation of HDPE Pipe, PN 10, SDR
17, PE 100) water pipelines (including supply of
materials, fittings, Equipment described in the
tender document in accordance with the technical
specification and the standard detailed drawings,
of any diameter specified below. The rate includes
for excavation in all kinds of soil, BFS/HBB/
Bituminous road, CC, RCC road surface except
rock to the full depth of trench required by the
specifications, precautions necessary to avoid
damage of underground utility services, (any
damage Contractor shall repair by his own cost)
including removing the excavated earth & stacking
the same to safe distance without any traffic
obstacles, de-watering of the trench to keep dry
condition at all times, including all necessary
shoring, boxing, must be protected from any
collapse of trench sides, preparation of trench
bottom, at depth of 1.2.M, transport (all kinds of
a) 50 mm dia
materials, equipment, pipes & fittings) to site, m 320
b) 75
laying, jointing and cleaning of the water pipes; m
mm dia 340
c)  110
disposalmm ofdiasurplus excavated material and m 113
transportmm
d)  160 back
dia surplus materials to the Clients (if m 3
necessary) as per specifications
Supply and installation and direction
of the following of
sizes gate
Engineering
valves in chargeto (cost
manufacturer of excess
confirming excavated
to ASME - B16,
earth- would
ISO 9001 /be BSdeducted
5150:1990 as standard.
per material rate).to:
Suitable
Sec. 7, sl. 3.1
withstand to 3.5, pg
a working 7.12) of 150 psi and in
pressure
6 complete in all respect with all accessories such as
flanges, nut - bolts, gaskets etc. Valves 80mm dia
and above shall be cast iron body flanged end
type, smaller than those shall be Brass/ bronze
type as per details shown on standard drawing
and at location indicated on network drawing all
a) 50 mmas
complete diaper direction of EIC .Country of Origin each 2
b) 75
: USA/mmUK/diaGermany/ Italy/ Korea/ Singapore/ OR each 4
c)  110
Licensedmm dia
manufacturing units located Globally. each 1
d)  160 mm dia each 2

Page 2 of 18
SL. Description of Works Rate
Unit Qty.
No. (TK)
Construction of new sluice valve chambers
(1500mm x 1200mm x 1200mm, inside size) with
kiln burnt 1st class bricks. Providing flat soling at
the bottom of the chamber, filling the gaps with
FM 0.1 sand and leveling, on which 100 mm C.C.
(1:2:4) to be casted. 250 mm brick work with 1:4
mortar of approved cement & sand. 150 mm thick
top RCC slab to be casted ( three parts, each part
size 1700 x 667 x 150mm ) with two no's uplifting
ring of 150 mm dia fitted with 16 mm dia rod at
two side of the slab, using coarse sand (FM = 2.2)
as fine aggregate and nominal maximum (19 mm)
7 size downgraded stone chips as coarse aggregate each 9
with 16 mm dia MS rod @ 100mm C/C in long
direction and @ 150mm C/C in short direction at
the bottom with Portland cement (1:1.5:3) as per
drawing. 13mm thick (1:4) cement plastering at
the inside of the chambers including neat cement
finishing with supplying of cement & sand of FM
1.5 and curing brick work, concrete & plastering
works etc. all complete as per drawing,
specification and direction of the Engineer in
charge.

Construction of concrete thrust and anchor blocks


made of cement concrete (1:3:6) as per drawing
& specification and detail measurements shown on
8 m3 8.50
drawing etc. all complete as per the direction of
the direction of the Engineer in charge.

Pressure Testing of pipe line: Pressure testing of


installed HDPE pipe lines for distribution at 6 bar
with supply of required testing equipment and
materials & repairing of any types of defects
detected during testing, replacement of damaged
9 pipes/fittings etc. test should be repeated at
contractor's own cost until satisfactory result is
achieved etc. all complete as per specification and
instruction of Engineer-in-Charge.

a) 50 mm dia m
b) 75 mm dia m
c)  110 mm dia m
d)  160 mm dia m

Page 3 of 18
SL. Description of Works Rate
Unit Qty.
No. (TK)
Disinfection of pipe lines: Disinfection of pipe lines
by supplying and using of required quantity
bleaching power (33% strength), making
chlorinated water having chlorine residual
concentration of at least 50 PPM. Available free
chlorine and applying to the pipe lines. After 24
hrs. of treatment a chlorine residual should be
10 minimum 20PPM, if it does not, steps to be
repeated. After successful completion of the above
test the system to be flushed until the chlorine
residual is 0.5 PPM or equivalent of the water
supply system, etc. all complete as per
specification and direction of the E-I-C.

a) 50 mm dia m 0.00


b) 75 mm dia m 0.00
c)  110 mm dia m 0.00
d)  160 mm dia m 0.00
Restoration of the following types of road to
original condition with supply of required materials
11 and using withdrawn materials as per specification
and direction of the Engineer.

a) Brick soling (95% reuse) m2 0.00


b) Herring bone bond over brick soling (95%
m2 8.00
reuse)
c) 25 mm compacted bituminous carpeting with
6.33mm seal coat and tack coat (95% reuse) m2 0.00

Supply and installing 25mm dia manual air release


valve made of Italy/ France/Taiwan in/c 3mm
thick MS steel protection box (Size 250mm
x250mm x300mm, made of 10mm MS bar 75mm
c/c) and fixing the box with GI/ MS pipe by
welding, nipple and 19mm gate valve, padlock
12 also be supplied with other necessary fittings as each 0
per instruction in any diameter pipe line ( at bridge
crossing and higher elevation) as shown in the
drawing etc., all complete as per direction of EIC

Total
Only satifactory result of test (as stated above) report, the contractor will be allowed to use the sa
Note : Rate includes all costs, benefits of contractor and Taxes (VAT & IT) applicable for this work

Page 4 of 18
mp (WDZ.8W.7) under VERC
ge Tank to Tap Stand)
Amount in
(TK)

Page 5 of 18
Amount in
(TK)

Page 6 of 18
Amount in
(TK)

Page 7 of 18
Amount in
(TK)

-
will be allowed to use the same in the work)
IT) applicable for this work

Page 8 of 18
T

Page 9 of 18
Estimate for laying of Distribution pipe line at Rohingya Camp (WDZ.8W.4) under VERC
(UNICEF) (Item of Pipeline Installation from Storage Tank to Tap Stand)
SL. Description of Works Rate
Unit Qty.
No. (TK)
Cutting and removing the following types of road
pavements for pipeline to a width of pipe diameter
+ 0.4m including salvaging of materials, stacking
the withdrawn materials at a safe place for reusing
1 etc., all complete as per direction of Engineer in
Charge (EIC).
a. Brick soling m2 0.00
b. Herring bone bond over brick soling m2 15.00
c. Bituminous with khoa consolidation. m2 0.00
Excavation in all kinds of materials for trenches
upto depth of 1.00 m plus pipe diameter from
road surface or existing ground level and a width
of pipe diameter + 0.4m including layout,
excavating earth to the lines, grades and elevation
2 as shown in the drawing providing center lines, m3 130.00
local bench mark pillars, fixing bamboo spikes ,
carrying and disposing of all excavated materials
at a safe distance designated by the E-I-C in all
type of soils such as very stiff (hard), clayey soil,/
rubbish etc. ramming, dressing and leveling of
Supply of proper
trench bed, sand of FM 0.80
stacking of thefree from earth
excavated clay,
vegetation
by the sideand otheratorganic
of road matterasand
a safe place perfilling and
direction
compacting
of EIC by sprinkling water, dressing and
leveling etc. in 100 mm thick pipe bedding
surround and (a) for pipes in road verges to a
3 height of 150 mm above the top of the pipe and m3 22.00
(b) for pipes in roads pavement/ road crossing
upto the bottom of the original road structure etc.
all complete as per direction of EIC.

Backfilling with excavated earth of the trench


above pipe zone (from 150mm above the top of
the pipe to road surface) including watering and
4 compacting in layers not exceeding 150mm all
complete as per direction of EIC.

a) Backfilling with excavated earth m3 110.00


Supply and Installation of HDPE Pipe, PN 10, SDR
17, PE 100) water pipelines (including supply of
materials, fittings, Equipment described in the
tender document in accordance with the technical
specification and the standard detailed drawings,
of any diameter specified below. The rate includes
for excavation in all kinds of soil, BFS/HBB/
Bituminous road, CC, RCC road surface except
rock to the full depth of trench required by the
specifications, precautions necessary to avoid
damage of underground utility services, (any
damage Contractor shall repair by his own cost)
including removing the excavated earth & stacking
the same to safe distance without any traffic
obstacles, de-watering of the trench to keep dry
condition at all times, including all necessary
shoring, boxing, must be protected from any
collapse of trench sides, preparation of trench
bottom, at depth of 1.2.M, transport (all kinds of
a) 50 mm dia
materials, equipment, pipes & fittings) to site, m 225
b) 75
laying,mm dia and cleaning of the water pipes; m
jointing 268
c)  110
disposalmm ofdiasurplus excavated material and m 335
transportmm
d)  160 back
dia surplus materials to the Clients (if m 3
necessary)
Supply and as per specifications
installation and direction
of the following of
sizes gate
Engineering in charge (cost of excess excavated
valves manufacturer to confirming to ASME - B16,
earth- would
ISO 9001 /be BSdeducted
5150:1990 as standard.
per material rate).to:
Suitable
Sec. 7, sl. 3.1
withstand to 3.5, pg
a working 7.12) of 150 psi and in
pressure
6 complete in all respect with all accessories such as
flanges, nut - bolts, gaskets etc. Valves 80mm dia
and above shall be cast iron body flanged end
type, smaller than those shall be Brass/ bronze
type as per details shown on standard drawing
and at location indicated on network drawing all
a) 50 mmas
complete diaper direction of EIC .Country of Origin each 2
b) 75
: USA/mmUK/diaGermany/ Italy/ Korea/ Singapore/ OR each 2
c)  110
Licensedmm dia
manufacturing units located Globally. each 2
d)  160 mm dia each 1
Construction of new sluice valve chambers
(1500mm x 1200mm x 1200mm, inside size) with
kiln burnt 1st class bricks. Providing flat soling at
the bottom of the chamber, filling the gaps with
FM 0.1 sand and leveling, on which 100 mm C.C.
(1:2:4) to be casted. 250 mm brick work with 1:4
mortar of approved cement & sand. 150 mm thick
top RCC slab to be casted ( three parts, each part
size 1700 x 667 x 150mm ) with two no's uplifting
ring of 150 mm dia fitted with 16 mm dia rod at
two side of the slab, using coarse sand (FM = 2.2)
as fine aggregate and nominal maximum (19 mm)
7 size downgraded stone chips as coarse aggregate each 7
with 16 mm dia MS rod @ 100mm C/C in long
direction and @ 150mm C/C in short direction at
the bottom with Portland cement (1:1.5:3) as per
drawing. 13mm thick (1:4) cement plastering at
the inside of the chambers including neat cement
finishing with supplying of cement & sand of FM
1.5 and curing brick work, concrete & plastering
works etc. all complete as per drawing,
specification and direction of the Engineer in
charge.

Construction of concrete thrust and anchor blocks


made of cement concrete (1:3:6) as per drawing
& specification and detail measurements shown on
8 m3 8.50
drawing etc. all complete as per the direction of
the direction of the Engineer in charge.

Pressure Testing of pipe line: Pressure testing of


installed HDPE pipe lines for distribution at 6 bar
with supply of required testing equipment and
materials & repairing of any types of defects
detected during testing, replacement of damaged
9 pipes/fittings etc. test should be repeated at
contractor's own cost until satisfactory result is
achieved etc. all complete as per specification and
instruction of Engineer-in-Charge.

a) 50 mm dia m
b) 75 mm dia m
c)  110 mm dia m
d)  160 mm dia m
Disinfection of pipe lines: Disinfection of pipe lines
by supplying and using of required quantity
bleaching power (33% strength), making
chlorinated water having chlorine residual
concentration of at least 50 PPM. Available free
chlorine and applying to the pipe lines. After 24
hrs. of treatment a chlorine residual should be
10 minimum 20PPM, if it does not, steps to be
repeated. After successful completion of the above
test the system to be flushed until the chlorine
residual is 0.5 PPM or equivalent of the water
supply system, etc. all complete as per
specification and direction of the E-I-C.

a) 50 mm dia m 0.00


b) 75 mm dia m 0.00
c)  110 mm dia m 0.00
d)  160 mm dia m 0.00
Restoration of the following types of road to
original condition with supply of required materials
11 and using withdrawn materials as per specification
and direction of the Engineer.

a) Brick soling (95% reuse) m2 0.00


b) Herring bone bond over brick soling (95%
m2 15.00
reuse)
c) 25 mm compacted bituminous carpeting with
6.33mm seal coat and tack coat (95% reuse) m2 0.00

Supply and installing 25mm dia manual air release


valve made of Italy/ France/Taiwan in/c 3mm
thick MS steel protection box (Size 250mm
x250mm x300mm, made of 10mm MS bar 75mm
c/c) and fixing the box with GI/ MS pipe by
welding, nipple and 19mm gate valve, padlock
12 also be supplied with other necessary fittings as each 0
per instruction in any diameter pipe line ( at bridge
crossing and higher elevation) as shown in the
drawing etc., all complete as per direction of EIC

Total
Only satifactory result of test (as stated above) report, the contractor will be allowed to use the same in th
Note : Rate includes all costs, benefits of contractor and Taxes (VAT & IT) applicable for this work
WDZ.8W.4) under VERC
ank to Tap Stand)
Amount in
(TK)
-
allowed to use the same in the work)
pplicable for this work
T

S-ar putea să vă placă și