Sunteți pe pagina 1din 2

PERMA-PIPE ®/ RICWIL®®

Preinsulated Piping Systems

ESCON-A ®

SA GD STEAM PIPING
· Underground High Temperature Piping
· Up to 30% Less Expensive than Aboveground Steam Piping
· Pre-insulated Off Site for Greater Savings
· Factory Prefabricated to Save Field Welds

ESCON-A
Why?
There is not a more cost effective means of conveying steam and high
temperature fluids below grade, at temperatures above 250°F (120°C),
than a DDT (Drainable, Dryable and Testable) air gap piping
system.

Why are these features important to an engineer or system owner?


A system that is drainable speeds the recovery of fluids in the event of
moisture entering the system during installation or in the event of a
leak. The dryable feature allows for the entire system, including the
insulation, to be dried in place in the trench. The testable feature in-
sures that the entire system is airtight right from the start. This testable
feature applies to all fittings, anchors, end terminations and field joints.
No other system supplied for fluids above 250°F (120°C) can provide
this type of integrity.

What else is important in a DDT system?


The thermal movement of the service pipe is critical. The system has
to be designed so that no undue stresses are caused to the service
pipe. The design of a DDT system allows the service pipe to expand within the outer conduit, thus eliminating stress
to the outer conduit. There is no damage to the service pipe insulation. This cannot be said for non-air gap systems.

The DDT system outer coating is another important area in the design of a DDT system. The conduit coating should
be designed to operate effectively in wet environments. The coating should provide the same protection at the fitting
assemblies as for the straight sections of the piping system. Any coating that cannot handle the temperature in wet
environments should be avoided. No cathodic protection system can be designed to protect a bad coating choice.
PERMA-PIPE’s elastomer coating provides the protection needed to perform in these critical environments.
SPECIFICATIONS

ESCON-A ® SAGD STEAM PIPING


INSULATION
GENERAL Service pipe insulation shall be mineral
All underground SAGD steam lines, as in- wool. Split insulation shall be held in place ports shall be designed to occupy not more
dicated on contract drawings, shall be by stainless steel bands installed on 18 inch than 10% of the annular air space. Sup-
drainable and dryable ESCON-A type as centers. The insulation shall have passed ports shall be of the type where calcium
manufactured by PERMA-PIPE. All straight a 96 hour boiling test. The insulation shall silicate pipe insulation thermally and elec-
sections, fittings, anchors and other ac- be applied to a thickness of ____ inches. trically isolates the service pipe from the
cessories shall be factory prefabricated to outer conduit. Supports which directly con-
job dimensions and designed to mini- OUTER CONDUIT tact both the service pipe and the outer
mize the number of field welds. Each sys- The steel conduit casing shall be smooth casing shall not be allowed. The surface
tem layout shall be computer analyzed by wall, welded steel conduit of the thickness of the insulation shall be protected at the
the piping system manufacturer to deter- specified below: support by a metal sleeve not less than 12
mine stresses on the service pipe and an- inches long, fitted with traverse and where
ticipated thermal movement of the service Conduit Size Conduit Thickness required, rotational arresters.
pipe. The system design shall be in strict 6" - 26" 10 gauge
conformance with ANSI B31.1, latest edi- 28" - 36" 6 gauge INSTALLATION
tion. Factory trained field technical assis- 38" - 42" 4 gauge The installing contractor shall handle the
tance shall be provided for the critical peri- system in accordance with the directions
ods of installation, i.e., unloading, field joint Changes in casing size required to allow furnished by the manufacturer and as ap-
instruction and testing. for service pipe expansion, shall be accom- proved by the architect and engineer.
plished by oversized casing and by eccen- The casing shall be air tested at 10 psig
SERVICE PIPE tric and/or concentric fittings to provide for and the service piping shall be hydrostati-
Internal pipe shall be standard weight car- continuous drainage. cally tested at 150 psig, or 1.5 times the
bon steel. All joints shall be buttwelded for operating pressure or as specified in the
sizes 2.5 inches and greater and socket CONDUIT COATING contract documents. The test pressure
welded for 2 inches and below. Where pos- The conduit system sections shall be cov- shall be held for not less than one hour.
sible, straight sections shall be supplied in ered with urethane elastomer coating. The contractor shall holiday test the
40 foot random lengths with 6 inches of Quality control at the manufacturing facil- entire conduit system at 5,000 volts. All
piping exposed at each end for field joint ity shall ensure that all coatings are able to holidays shall be repaired and tested.
fabrication. Socket weld couplings shall be pass a 5,000 volt holiday test. The coating
furnished by the installing contractor. shall be spray applied onto a shot-blasted BACKFILL
steel conduit to a thickness of 30 mils. All A 4 inch layer of sand or fine gravel shall
SUB-ASSEMBLIES field joints shall be covered with a heat be placed and tamped in the trench to pro-
End seals, gland seals and anchors shall shrinkable, adhesive backed sleeve. The vide a uniform bedding for the conduit. The
be designed and factory prefabricated to factory applied coating on the conduit entire trench shall be evenly back-
prevent the ingress of moisture into the fittings shall be spray applied urethane to filled with a similar material as the bed-
system. All sub-assemblies shall be de- the same requirements as the straights. ding in 6 inch compacted layers to a
signed to allow for complete draining and minimum height of 6 inches above the top
drying of the conduit system. PIPE SUPPORTS of the insulated piping system. The remain-
All pipes within the outer casing shall be ing trench shall be evenly and continu-
supported at not more than 14 foot inter- ously backfilled in uniform layers with suit-
vals. These supports shall be designed to able excavated soil.
allow for continuous airflow and drainage
of the conduit in place. The straight sup-

The information contained in this document is subject to change without notice. PERMA-PIPE, Inc.
believes the information contained herein to be reliable, but makes no representations as to its
©2007 PERMA-PIPE, Inc. All Rights Reserved SAGD (06/07 5M FGS) accuracy or completeness.

S-ar putea să vă placă și