Government of Nepal

Ministry of Physical Infrastructure & Transport


Department of Roads
Federal Road Supervision & Monitoring Office
Road Division , Biratnagar
Abstract Of Cost
Name of project:-Ganga Chowk Milan Chowk hudai Khadra sadak,Morang
Name Of Works : -Construction of Black Top Road including Drainage structure
SN Items of Works Unit Quantity

1 General works
Insurance for the loss of damage to works, plant, material, equipment
1.01 property and personnel injury or death and third party
LS 1.00
Supplying and erecting traffic sign in place including 50mm dia. Steel tube,
2mm. thick steel plate, cement concrete, painting, writing and supporting
steel angle nut and bolit etc. complete
1.02
b) 1.2m.x 0.75m. Size bigger traffic sign with back support and two or
more post.
Nos 2.00
2 Hume pipe culvert works
Earthwork excavation in soft soil for drain and trenches including
2.01 shoring, struting, bracing, sheeting and disposal upto 10 m and lift upto 3 m
etc. all complete as per specification. [Manual(20%), Machine(80%)]
m3 46.12
Providing and laying of dry Stone Masonry Work as per Drawing and
2.02 Technical Specifications.
m3 4.86
Providing and laying of Plain/Reinforced Cement Concrete in
2.03 Foundation complete as per Drawing and Technical Specifications.
PCC Grade M 15 m3 4.26
Providing and laying of Random Rubble Stone Masonry Work in
2.04 Cement Mortar 1:4 in Foundation complete as per Drawing and
Technical Specifications. m3 14.55
Providing and Pointing with cement mortar on masonry work in
2.05 structure as per Technical Specifications cement mortar (1:3 )
m2 21.00

Providing and Laying Reinforced cement concrete NP3 Flush jointed pipe
2.06 for culverts including fixing with cement mortar 1:2 as per Drawing and
Technical Specifications.( 900 mm internal dia.) Rm 15.00

Providing , Preparing and Installing form work including necessary


2.07 supports and removing after completion for walls. (Class F2 Finish),
vertical plain surface Using timber (soft wood ) Height upto 3m. m2 11.64
3 Pavement Construction Works
Loosening, leveling and Compacting original ground supporting
embankment to facilitate placement of first layer of embankment,
3.01 scarified to a depth of 150 mm, mixed with water at OMC and then
compacted by rolling so as to achieve dry density as per Drawing and
Technical Specifications.
m3 360.25
3.02 Providing, laying, spreading and compacting embankment material as per
Drawing and Technical Specifications. m3 2358.00
Providing and laying granular sub-base on prepared surface, mixing at
3.03 OMC, and compacting to achieve the desired density, complete as per
Drawing and Technical Specifications.(Mechanical means) m3 540.37
Providing, laying, spreading, watering, levelling and compaction of crusher
3.04 run materials for base course lead upto 10m.
(a) Machine works
m3 393.00
Providing and applying prime coat with Hot Bitumen ( including cutter) on
prepared surface of granular base including cleaning of road surface and
3.05 spraying by mechanical means as per Technical Specification
Lit 2620.00
Providing and applying tack coat with hot Bitumen at specified rate on the
prepared non-bituminous surfaces including cleaning as per Technical
3.06 Speciation .(Mechanical means)
Lit 1793.06
Providing and laying close-graded premix surfacing material of 20 mm
thickness composed of 11.2 mm to 0.09 mm aggregates using bitumen as
wearing course on a previously prepared base, including mixing in a
3.07
suitable plant as per Drawing and Technical Specifications.(Mechanical
means)
m3 73.68
Providing and laying seal coat sealing the voids in a bituminous surface as
3.08 per Drawing and Technical Specifications. m² 2456.25
Total
Contingency 4 %
Vat 13%
Grand Total

Prepared By: Checked By:


ransport

ring Office
ar

F/Y:- 076/077
Rate/ Unit Total Amount Remarks
(NRs.)

50000.00 50000.00

7547.09 15094.18
0.00

173.55 8004.12

3997.35 19427.12

10928.88 46557.02

8511.77 123850.08

209.90 4407.90

8702.26 130533.90

1032.66 12020.16
0.00

59.89 21575.37
367.26 865999.08

2314.35 1250605.30

2844.16 1117754.88

125.84 329700.80

119.32 213948.21

14034.17 1034037.64

81.86 201068.62
5444584.38
217783.38
707795.97
6370163.72

Approved By:
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
Federal Road Supervision & Monitoring Office
Road Division , Biratnagar
Calculation of Quantities

Name of project:-Ganga Chowk Milan Chowk hudai Khadra sadak,Morang


Name Of Works : -Construction of Black Top Road including Drainage structure
S.No. Description of Work No. Length Breadth
1 General works
Insurance for the loss of damage to works, plant,
1.01 material, equipment property and personnel injury or
death and third party 1.00

Supplying and Erecting informatory board and name plate


(contract details) in place including 50mm dia. steeel tube,
2mm thick steel plate sign board in place 1.2m.x 0.75m. Size
1.02 bigger with back support and two or more post as instructed
by the engineer all Complete as per Specification. [SS/SP-
1501]
2.00

2 Hume pipe culvert works


Earthwork excavation in soft soil for drain and trenches
including shoring, struting, bracing, sheeting and disposal
2.01 upto 10 m and lift upto 3 m etc. all complete as per
specification. [Manual(20%), Machine(80%)]

For 900mm dia Hume pipe culvert


Head wall 4.00 3.00 1.50
For beneath of pipe 2.00 7.50 1.50
Total
Providing and laying of hand pack Stone soling with 150 to
200 mm thick stones and packing with smaller stone on
2.02 prepared surface as per Drawing and Technical
Specifications.

For H/W 4.00 3.00 1.20


For beneath of pipe 2.00 7.50 1.20
Total
Providing and placing cement concrete for the non-
structural elements including compaction, curing,
2.03 testing and relevant lead etc. as per drawing all
complete as per specification [1:2:4 (cement : sand :
aggregate)][SS/SP-2000]

For head wall 4.00 3.00 1.20


Beneath pipe 2.00 7.50 1.20
Top of H/w 4.00 3.00 0.50
Total
Providing and laying Random rubble masonry in
cement sand (1:4) mortar including scaffolding, curing
2.04 etc. all complete as per Specification.[SS/SP-
2602,2603, 2607]

Head wall 4.00 3.00 0.75


Parapet 4.00 3.00 0.50
Deducation for pipe 4.00 0.71
Total
Providing, Mixing and Pointing cement mortar over
rubble mansory works including scaffolding
2.05 etc.complete as per specification (manual mixing)
(cement : sand) 1: 3(SS-2602,2603,2610)
side 4.00 3.00
Parapet 8.00 3.00
Total

Proving and laying RCC pipes of diameter 900mm (internal)


2.06 with or without collars jointed with stiff mixture of cement
mortar in the proportion of 1 : 2 ( 1 cement : 2 fine sand ) all
Complete as per Specification. [SS/SP-908]
6.00 2.50
Total
Providing , Preparing and Installing form work
including necessary supports and removing after
2.07 completion for walls all complete as per specification.
(1804,1805)
For head wall 8.00 3.00
8.00 1.20
Beneath pipe 4.00 7.50
4.00 1.10
Top of H/w 8.00 3.00
8.00 0.60
Total
3 Pavement Construction Works
Loosening, leveling and Compacting original ground
supporting embankment to facilitate placement of first
layer of embankment, scarified to a depth of 150 mm,
3.01 mixed with water at OMC and then compacted by
rolling so as to achieve dry density as per Drawing and
Technical Specifications.

1.00 655.00 5.50

Providing, laying, spreading and compacting embankment


3.02
material as per Drawing and Technical Specifications.

Roadway 1.00 655.00 4.00


Sides 2.00 655.00 0.75

Providing and laying granular sub-base on prepared surface,


3.03 mixing at OMC, and compacting to achieve the desired
density, complete as per Drawing and Technical
Specifications.(Mechanical means)
Carriageway 1.00 655.00 4.00
shoulder 2.00 655.00 0.75
Total

Providing, laying, spreading, watering, levelling and


3.04 compaction of crusher run materials for base course lead
upto 10m.
(a) Machine works
1.00 655.00 4.00
Total
Providing and applying prime coat with Hot Bitumen
( including cutter) on prepared surface of granular base
3.05 including cleaning of road surface and spraying by
mechanical means as per Technical Specification

1.00 655.00 4.00


spray rate 1lit/m2
Providing and applying tack coat with hot Bitumen at
specified rate on the prepared non-bituminous surfaces
3.06 including cleaning as per Technical Speciation .(Mechanical
means)

1.00 655.00 3.75


spray rate 0.73lit/m2
Providing and laying close-graded premix surfacing material
of 20 mm thickness composed of 11.2 mm to 0.09 mm
aggregates using bitumen as wearing course on a previously
3.07 prepared base, including mixing in a suitable plant as per
Drawing and Technical Specifications.(Mechanical means)

1.00 655.00 3.75


Providing and laying seal coat sealing the voids in a
3.08 bituminous surface as per Drawing and Technical
Specifications.
1.00 655.00 3.75

Prepared By: Checked By:


ransport

ing Office
r
ties

F/Y:- 076/077
Height Quantity Unit Remarks

1.00
Total 1.00 LS

2.00
Total 2.00 Nos

1.00 18.00
1.25 28.12
Total 46.12 m³

0.15 2.16
0.15 2.70
Total 4.86 m³
0.15 2.16
0.10 1.80
0.05 0.30
Total 4.26 m³

1.60 14.40
0.50 3.00
0.71 -2.85
Total 14.55 m³

(1+0.5)/2 9.00
0.50 12.00
Total 21.00 m²

15.00
Total 15.00 Rm

0.15 3.60
0.15 1.44
0.15 4.50
0.15 0.66
0.05 1.20
0.05 0.24
Total 11.64 m²
0.10 360.25 m3

0.60 1572.00
0.80 786.00
Total 2358.00 m3

0.15 393.00
0.15 147.37
Total 540.37 m3

0.15 393.00
Total 393.00 m³

2620.00 m²
spray rate 1lit/m2 2620.00 Litre

2456.25 m²
pray rate 0.73lit/m2 1793.06 Litre

0.03 73.68
Total 73.68 m³

2456.25
Total 2456.25 m²
Approved By: