Government of Nepal

Ministry of Physical Infrastructure & Transport


Department of Roads
Federal Road Supervision & Monitoring Office
Road Division , Biratnagar
Abstract Of Cost
Name of project:-Dadarbairiya chowk dekhi Kadmaha Nocha hudai bharatiya sima sadak,Morang
Name Of Works : -Construction of Black Top Road including Drainage structure F/Y:- 076/077
SN Items of Works Unit Quantity Rate/ Unit Total Amount Remarks
(NRs.)

1.00 General works


Insurance for the loss of damage to works, plant, material,
1.01 equipment property and personnel injury or death and third LS 1.00 45000.00 45000.00
party
Supplying and Erecting informatory board and name plate (contract
details) in place including 50mm dia. steeel tube, 2mm thick steel
plate sign board in place 1.2m.x 0.75m. Size bigger with back
1.02 support and two or more post as instructed by the engineer all Nos 1.00 7717.64 7717.64
Complete as per Specification. [SS/SP-1501]

2.00 Hume pipe culvert works


Earthwork excavation in all types of soil for drain and trenches
2.01 including shoring, struting, bracing, sheeting and disposal upto m3 23.06 193.13 4453.57
required lead and lift etc. all complete as per specification.

Providing and laying of hand pack Stone soling with 150 to 200
mm thick stones and packing with smaller stone on prepared
2.02 surface as per Drawing and Technical Specifications. m3 2.43 4918.32 11951.51

Providing and placing cement concrete for the non-structural


elements including compaction, curing, testing and relevant
2.03 lead etc. as per drawing all complete as per specification m3 2.13 10451.45 22261.58
(Grade M15)[SS/SP-2000]
Providing and laying Random rubble masonry in cement sand
2.04 (1:4) mortar including scaffolding, curing etc. all complete as m3 7.28 9776.65 71127.32
per Specification.[SS/SP-2602,2603, 2607]
Providing, Mixing and Pointing cement mortar over rubble
mansory works including scaffolding etc.complete as per
2.05 specification (manual mixing) (cement : sand) 1: 3(SS- m2 8.25 281.61 2323.28
2602,2603,2610)

Proving and laying RCC pipes of diameter 900mm (internal) with


2.06 or without collars jointed with stiff mixture of cement mortar in the Rm 7.50 8778.18 65836.35
proportion of 1 : 2 ( 1 cement : 2 fine sand ) all Complete as per
Specification. [SS/SP-908]

Providing , Preparing and Installing form work including necessary


2.07 supports and removing after completion for walls. (Class F2 m2 5.82 1055.43 6142.60
Finish), vertical plain surface Using timber (soft wood ) Height
upto 3m.
3.00 Pavement Construction Works
Loosening, leveling and Compacting original ground supporting
embankment to facilitate placement of first layer of embankment,
3.01 m2 1890.00 49.77 94065.30
scarified to a depth of 150 mm, mixed with water at OMC and then
compacted by rolling so as to achieve dry density as per Drawing
and Technical Specifications.
3.02 Providing, laying, spreading and compacting embankment with m3 567.00 368.64 209018.88
borrow material as per Drawing and Technical Specifications.

Providing and laying granular sub-base on prepared surface,


3.03 mixing at OMC, and compacting to achieve the desired density, m3 263.25 2895.62 762271.96
complete as per Drawing and Technical Specifications.

Providing, laying, spreading, watering, levelling and compaction of


3.04 crusher run materials for base course lead upto 10m. [1202 ] m3 243.00 3387.28 823109.04
Providing and applying prime coat with Hot Bitumen ( including
cutter) on prepared surface of granular base including cleaning of
3.05 road surface and spraying by mechanical means as per Technical Lit 1620.00 126.42 204800.40
Specification .

Providing and applying tack coat with hot Bitumen at specified rate
on the prepared non-bituminous surfaces including cleaning as per
3.06 Technical Specification . Lit 1182.60 119.28 141060.52

Providing, mixing, and laying asphalt concrete with compaction.


3.07 m3 59.40 21865.63 1298818.42

Total 3769958.37
Contingency 4 % 150798.33
Vat 13% 490094.59
Grand Total 4410851.29

Prepared By: Checked By: Approved By:


Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
Federal Road Supervision & Monitoring Office
Road Division , Biratnagar
Calculation of Quantities

Name of the Project :- Dadarberiya Chowak Uttar Raaya tole Huddai Bayarban Sadak, Morang
Name Of Works : -Construction of Black Top Road including Drainage structure F/Y:- 076/077
S.No. Description of Work No. Length Breadth Height Quantity Unit Remarks
1.00 General works
Insurance for the loss of damage to works, plant,
1.01 material, equipment property and personnel injury or
death and third party 1.00 1.00
Total 1.00 LS
Supplying and Erecting informatory board and name plate
(contract details) in place including 50mm dia. steeel tube,
2mm thick steel plate sign board in place 1.2m.x 0.75m. Size
1.02 bigger with back support and two or more post as instructed
by the engineer all Complete as per Specification. [SS/SP-
1501]
1.00 1.00
Total 1.00 Nos
2.00 Hume pipe culvert works
Earthwork excavation in all types of soil for drain and
trenches including shoring, struting, bracing, sheeting and
2.01
disposal upto required lead and lift etc. all complete as per
specification.
For 900mm dia Hume pipe culvert
Head wall 2.00 3.00 1.50 1.00 9.00
For beneath of pipe 1.00 7.50 1.50 1.25 14.06
Total 23.06 m³
Providing and laying of hand pack Stone soling with 150 to
200 mm thick stones and packing with smaller stone on
2.02 prepared surface as per Drawing and Technical
Specifications.

For pipe culvert


For H/W 2.00 3.00 1.20 0.15 1.08
For beneath of pipe 1.00 7.50 1.20 0.15 1.35
Total 2.43 m³
Providing and placing cement concrete for the non-
structural elements including compaction, curing,
2.03 testing and relevant lead etc. as per drawing all
complete as per specification (Grade M15)[SS/SP-
2000]

For pipe culvert


For head wall 2.00 3.00 1.20 0.15 1.08
Beneath pipe 1.00 7.50 1.20 0.10 0.90
Top of H/w 2.00 3.00 0.50 0.05 0.15
Total 2.13 m³
Providing and laying Random rubble masonry in
cement sand (1:4) mortar including scaffolding, curing
2.04 etc. all complete as per Specification.[SS/SP-
2602,2603, 2607]
For pipe culvert
Head wall 2.00 3.00 0.75 1.60 7.20
Parapet 2.00 3.00 0.50 0.50 1.50
Deducation for pipe 2.00 0.71 -1.42
Total 7.28 m³
Providing, Mixing and Pointing cement mortar over
rubble mansory works including scaffolding
2.05 etc.complete as per specification (manual mixing)
(cement : sand) 1: 3(SS-2602,2603,2610)
side 2.00 3.00 1.50 2.25
Parapet 4.00 3.00 - 0.50 6.00
Total 8.25 m²

Proving and laying RCC pipes of diameter 900mm (internal)


2.06 with or without collars jointed with stiff mixture of cement
mortar in the proportion of 1 : 2 ( 1 cement : 2 fine sand ) all
Complete as per Specification. [SS/SP-908]
3.00 2.50 7.50
Total 7.50 Rm
Providing , Preparing and Installing form work
including necessary supports and removing after
2.07 completion for walls. (Class F2 Finish), vertical plain
surface Using timber (soft wood ) Height upto 3m.
For head wall 4.00 3.00 0.15 1.80
4.00 1.20 0.15 0.72
Beneath pipe 2.00 7.50 0.15 2.25
2.00 1.10 0.15 0.33
Top of H/w 4.00 3.00 0.05 0.60
4.00 0.60 0.05 0.12
Total 5.82 m2
3.00 Pavement Construction Works
Loosening, leveling and Compacting original ground
supporting embankment to facilitate placement of first layer
of embankment, scarified to a depth of 150 mm, mixed with
3.01
water at OMC and then compacted by rolling so as to
achieve dry density as per Drawing and Technical
Specifications.

1.00 270.00 7.00 1890.00


Total 1890.00 m2
Providing, laying, spreading and compacting embankment
3.02 with borrow material as per Drawing and Technical
Specifications.
1.00 270.00 7.00 0.30 567.00
Total 567.00 m3
Providing and laying granular sub-base on prepared surface,
mixing at OMC, and compacting to achieve the desired
3.03 density, complete as per Drawing and Technical
Specifications.

Carriageway 1.00 270.00 5.50 0.15 222.75


shoulder 2.00 270.00 0.50 0.15 40.50
Total 263.25 m3

Providing, laying, spreading, watering, levelling and


3.04 compaction of crusher run materials for base course lead
upto 10m. [1202 ]
1.00 270.00 6.00 0.15 243.00
Total 243.00
Providing and applying prime coat with Hot Bitumen
( including cutter) on prepared surface of granular base
3.05 including cleaning of road surface and spraying by
mechanical means as per Technical Specification .

1.00 270.00 6.00 1620.00 m2


spray rate 1lit/m2 1620.00 Litre
Providing and applying tack coat with hot Bitumen at
specified rate on the prepared non-bituminous surfaces
3.06 including cleaning as per Technical Specification .

1.00 270.00 6.00 1620.00 m2


spray rate 0.73lit/m2 1182.60 Litre
Providing, mixing, and laying asphalt concrete with
3.07 compaction.
1.00 270.00 5.50 0.04 59.40 m3
Total 59.40

Prepared By: Checked By: Approved By: