Government of Nepal

Ministry of Physical Infrastructure & Transport


Department of Roads
Federal Road Supervision & Monitoring Office
Division Road Office , Biratnagar
Abstract Of Cost
Name of the Project :- Jahada-2 Harinagar,Muslim Tole Hudai Birpur sadak,Morang
Name Of Works : -Construction of Gravel Road With Cross Drainage Structure F/Y:- 076/077
SN Items of Works Unit Quantity Rate/ Unit Total Amount Remarks
(NRs.)

1.00 General works


Insurance for the loss of damage to works, plant,
1.01 material, equipment property and personnel injury or
death and third party LS 1.00 45000.00 45000.00
Supplying and Erecting informatory board and name
plate (contract details) in place including 50mm dia.
steeel tube, 2mm thick steel plate sign board in place
1.02 1.2m.x 0.75m. Size bigger with back support and two or
more post as instructed by the engineer all Complete as
per Specification. [SS/SP-1501]
Nos 1.00 7411.45 7411.45
2.00 Hume Pipe & Rcc Slab Culvert
Construction
Earthwork excavation in all types of soil for drain and
trenches including shoring, struting, bracing, sheeting
2.01 and disposal upto required lead and lift etc. all complete
as per specification. [SS/SP 905]
m3 104.73 193.13 20226.50
Providing and laying of hand pack Stone soling with 150
to 200 mm thick stones and packing with smaller stone
2.02 on prepared surface as per Drawing and Technical
Specifications.
m3 14.36 4709.48 67628.13
Providing and placing cement concrete for the non-
structural elements including compaction, curing,
2.03 testing and relevant lead etc. as per drawing all
complete as per specification.(Grade M15)[SS/SP-2000]

m3 27.08 11768.51 318691.25


Providing and laying Random rubble masonry in cement
sand (1:4) mortar including scaffolding, curing etc. all
2.04 complete as per Specification.[SS/SP-2602,2603, 2607]

m3 103.88 9543.14 991341.38


Providing, Mixing and Pointing cement mortar over
rubble mansory works including scaffolding etc.complete
2.05 as per specification (manual mixing) (cement : sand) 1:
3(SS-2602,2603,2610)
m2 40.80 281.16 11471.32
Proving and laying RCC pipes of diameter 900mm
(internal) with or without collars jointed with stiff
2.06 mixture of cement mortar in the proportion of 1 : 2 ( 1
cement : 2 fine sand ) all Complete as per Specification.
[SS/SP-908]
Rm 7.50 8777.50 65831.25
Providing , Preparing and Installing form work including
necessary supports and removing after completion for
2.07 walls. (Class F2 Finish), vertical plain surface Using
timber (soft wood ).
m2 35.14 1055.43 37087.81
Providing and laying reinforcement Fe500 including
cutting, bending, binding, fixing in position etc. all
2.08 complete as per specification and drawing.(Spec.2000)

MT 1.46 124563.98 181863.41


Providing and placing machine mixed cement concrete
for the foundation and footing etc. including compaction,
2.09 curing, testing and lead 30m. etc. all complete as per
specification and drawing.(M25/20) ( Spec. 2000)

m3 18.83 15901.49 299425.05


Providing suitable material and Back filling behind
2.10 abutment, wing wall and return wall complete as per
Drawing and Technical Specifications. m3 19.25 567.23 10919.17
3.00 Pavement Construction Works
Scarifying the existing road surface to a depth of 50 mm
and disposal of scarified Material with in all lifts and lead
3.01 as per Drawing and Technical Specifications.
(Mechanical means)
m2 8155.00 12.36 100795.80
Providing, laying, spreading and compacting
3.02 embankment with borrow material as per Drawing and
Technical Specification m3 8155.00 301.23 2456530.65
Providing and laying granular sub-base on prepared
surface, mixing at OMC, and compacting to achieve the
3.03 desired density, complete as per Drawing and Technical
Specifications.(Mechanical means)
m3 1398.00 2797.36 3910709.28
Total 8524932.45
Contingency 4% 340997.30
Vat 13% 1108241.22
Grand Total 9974170.97

Prepared By: Checked By: Approved By:


Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
Federal Road Supervision & Monitoring Office
Division Road Office , Biratnagar
Calculation of Quantities

Name of the Project :- Jahada-2 Harinagar,Muslim Tole Hudai Birpur sadak,Morang


Name Of Works : -Construction of Gravel Road With Cross Drainage Structure F/Y:- 076/077
S.No. Description of Work No. Length Breadth Height Quantity Unit Remarks
1.00 General works
Insurance for the loss of damage to works, plant,
1.01 material, equipment property and personnel injury or
death and third party 1.00 1.00 LS
Supplying and Erecting informatory board and name plate
(contract details) in place including 50mm dia. steeel tube,
2mm thick steel plate sign board in place 1.2m.x 0.75m. Size
1.02 bigger with back support and two or more post as instructed
by the engineer all Complete as per Specification. [SS/SP-
1501]
1.00 1.00 Nos

2.00
Hume Pipe & Rcc Slab Culvert
Construction
Earthwork excavation in all types of soil for drain and
trenches including shoring, struting, bracing, sheeting and
2.01
disposal upto required lead and lift etc. all complete as per
specification. [SS/SP 905]
For 900mm dia Hume pipe culvert
Head wall 2.00 3.00 1.50 1.00 9.00
For beneath of pipe 1.00 7.50 1.50 1.25 14.06
SubTotal(1) 23.06 m³
For Rcc slab
Abutment 2.00 7 2.2 (2+1.5)/2 53.90
Wing Wall 4.00 3 0.8 1 9.60
Apron 2.00 (7.0+3.8)/2 2 0.4 8.64
Cut -off Wall U/S and D/S 2.00 5.45 0.5 1.25 9.53
SubTotal(2) 81.67 m3
G-Total 104.73 m3
Providing and laying of hand pack Stone soling with 150 to
200 mm thick stones and packing with smaller stone on
2.02 prepared surface as per Drawing and Technical
Specifications.

For pipe culvert


For H/W 2.00 3.00 1.20 0.15 1.08
For beneath of pipe 1.00 7.50 1.20 0.15 1.35
SubTotal(1) 2.43 m³
For Rcc slab
Abutment 2.00 7.00 2.20 0.20 6.16
Wing Wall 4.00 3.00 0.60 0.20 1.44
Cut -off Wall U/S and D/S 2.00 5.45 0.50 0.20 1.09
Appron 2.007.0+3.8)/2 2.00 0.15 3.24
SubTotal(2) 11.93 m3
G-Total 14.36 m3
Providing and placing cement concrete for the non-
structural elements including compaction, curing,
2.03 testing and relevant lead etc. as per drawing all
complete as per specification.(Grade M15)[SS/SP-
2000]

For pipe culvert


For head wall 2.00 3.00 1.20 0.15 1.08
Beneath pipe 1.00 7.50 1.20 0.10 0.90
Top of H/w 4.00 3.00 0.50 0.05 0.30
SubTotal(1) 2.28 m³
For Rcc slab
Bed of Abutment 2.00 7 2.2 0.3 9.24
Bed of Wing wall 4.00 2.5 0.6 0.2 1.20
Bed of water Flow 1.00 7 3.8 0.2 5.32
Apron 2.00 (7+3.8)/2 3.8 0.2 8.20
Cut -off Wall U/S and D/S 2.00 7 0.6 0.1 0.84
SubTotal(2) 24.80 m³
G-Total 27.08 m³
Providing and laying Random rubble masonry in
cement sand (1:4) mortar including scaffolding, curing
2.04 etc. all complete as per Specification.[SS/SP-
2602,2603, 2607]
For pipe culvert
Head wall 2.00 3.00 (1+0.5)/2 1.60 7.20
Parapet 2.00 3.00 0.50 0.50 1.50
Deducation for pipe 2.00 0.59 -1.17
SubTotal(1) 7.53 m³
For Rcc slab
Abutment 2.00 7 (2.25+0.60)/2 4 79.80
Wing Wall 4.00 2.5 (.6+0.50)/2 (4+1)/2 13.75
Cut -off Wall U/S and D/S 2.00 7 (0.5+0.30)/2 0.5 2.80
SubTotal(2) 96.35 m³
G-Total 103.88 m3
Providing, Mixing and Pointing cement mortar over
rubble mansory works including scaffolding
2.05 etc.complete as per specification (manual mixing)
(cement : sand) 1: 3(SS-2602,2603,2610)
side 4.00 - (1+.5)/2 1.60 4.80
Parapet 4.00 3.00 - 0.50 6.00
SubTotal(1) 10.80 m²
For Rcc slab
Abutment 2.00 2.5 2 10.00
Wing Wall 4.00 2.5 (3+1)/2 20.00
SubTotal(2) 30.00 m²
G-Total 40.80 m2

Proving and laying RCC pipes of diameter 900mm (internal)


2.06 with or without collars jointed with stiff mixture of cement
mortar in the proportion of 1 : 2 ( 1 cement : 2 fine sand ) all
Complete as per Specification. [SS/SP-908]
3.00 2.50 7.50
G-Total 7.50 Rm
Providing , Preparing and Installing form work
including necessary supports and removing after
2.07 completion for walls. (Class F2 Finish), vertical plain
surface Using timber (soft wood ).
Head wall PCC 4.00 3.00 0.10 1.20
4.00 1.80 0.10 0.72
top of parapet wall
4.00 3.00 0.05 0.60
4.00 0.50 0.05 0.10
SubTotal(1) 2.62 m2
a) For foundation and footing.
Bed of Abutment 4.00 7.00 0.10 2.80
4.00 2.05 0.10 0.82
Bed of Wing wall 4.00 2.50 0.10 1.00
4.00 0.50 0.10 0.20
Bed of Cut off Wall 4.00 5.20 0.10 2.08
b) For slab & beam structure 0.00
Abutment Cap 4.00 7.00 0.20 5.60
4.00 0.60 0.20 0.48
Slab 2.00 7.00 0.46 6.44
2.00 5.20 0.46 4.78
Parapet 4.00 5.20 0.40 8.32
SubTotal(2) 32.52 m2
G-Total 35.14 m2
Providing and laying reinforcement Fe500 including
cutting, bending, binding, fixing in position etc. all
2.08 complete as per specification and drawing.(Spec.2000) According to calculation sheet 1.46 MT

Providing and placing machine mixed cement concrete


for the foundation and footing etc. including
2.09 compaction, curing, testing and lead 30m. etc. all
complete as per specification and drawing.(M25/20)
( Spec. 2000)

Abutment Sheet 2.00 7.00 0.52 0.2 1.45


2.00 7.00 0.2 0.46

Slab 1.00 7.00 5.2 0.46 16.74


Parapet 2.00 3.20 (0.30+0.20)/2 0.4 0.64
Total 18.83 m3
Providing suitable material and Back filling behind
2.10 abutment, wing wall and return wall complete as per m3
Drawing and Technical Specifications.
1.00 7.00 2.00 1.00 14.00
1.00 7.00 0.50 1.50 5.25
Total 19.25
3 Pavement Construction Works
Scarifying the existing road surface to a depth of 50 mm and
3.01 disposal of scarified Material with in all lifts and lead as per 1.00 1165.00 7.00 8155.00 m2
Drawing and Technical Specifications. (Mechanical means)

Providing, laying, spreading and compacting embankment


3.02
with borrow material as per Drawing and Technical
Specification
1.00 1165.00 7.00 1.00 8155.00 m3
Providing and laying granular sub-base on prepared surface,
3.03 mixing at OMC, and compacting to achieve the desired
density, complete as per Drawing and Technical
Specifications.(Mechanical means)
1.00 1165.00 6.00 0.20 1398.00 m3
Prepared By: Checked By: Approved By: