Abstract of Cost
Name of Project:Gachhiya Chowk dekhi mirgauliya bazar hudai haraicha jodane sadak,morang .
Name of Work:-Blacktopped Road Construction Works including Drainage Structures F.Y.: 076/077
2.2 Providing and laying of hand pack Stone soling with 150
to 200 mm thick stones and packing with smaller stone on
prepared surface as per Drawing and Technical m3 2.70 3956.04 10681.31
Specifications.ss/sp(2602,2603)
2.7
Abstract of Cost
Name of Project:Gachhiya Chowk dekhi mirgauliya bazar hudai haraicha jodane sadak,morang .
Name of Work:-Blacktopped Road Construction Works including Drainage Structures F.Y.: 076/077
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department Of Road
Central Road Supervision & Monitoring Office
Road Division , Biratnagar
Calculation of Quantities
Name of Project:Gachhiya Chowk dekhi mirgauliya bazar hudai haraicha jodane sadak,morang .
Name of Work:-Blacktopped Road Construction Works including Drainage Structures F.Y.: 076/077
Breadth(
S.No. Description of Work No. Length(m) Height(m) Quantity Unit Remarks
m)
1 General Works
1.1 Insurance for the loss or damage to works, materials and
contractor's equipments including personal injury or
death as per Contract Data all Complete. 1.00 1.00 LS
For Hpc Head wall/Tail wall 4.00 3.00 1.5 0.9 16.20
Total 16.20 m3
2.2 Providing and laying of hand pack Stone soling with
150 to 200 mm thick stones and packing with smaller
stone on prepared surface as per Drawing and Technical
Specifications.ss/sp(2602,2603)
For Hpc Head wall/Tail wall 4.00 3.00 1.5 0.15 2.70
Total 2.70 m3
2.3 Providing and placing cement concrete for the non-
structural elements including compaction, curing,
testing and relevant lead etc. as per drawing all
complete as per specification [1:2:4 (cement :
sand : aggregate)][SS/SP-2000]
For Hpc Head wall/Tail wall 4.00 3.00 1.5 0.1 1.80 m3
Top of HPC 4.00 3.00 0.5 0.05 0.30 m3
Total 2.10 m3
2.4 Providing and laying Random rubble masonry in
cement sand (1:4) mortar including scaffolding,
curing etc. all complete as per Specification.[SS/SP-
2602,2603, 2607]
For Hpc Head wall/Tail wall 4.00 3.00 0.95 2.5 28.50 m3
Total 28.50 m3
2.5 Providing, mixing, and Pointing cement mortar over
rubble masonry works in cement mortar [ cement(1)
: sand(3)] including scaffolding, curing, preparation
of mortar etc. complete, ss/sp(2602,2603,2610)
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department Of Road
Central Road Supervision & Monitoring Office
Road Division , Biratnagar
Calculation of Quantities
Name of Project:Gachhiya Chowk dekhi mirgauliya bazar hudai haraicha jodane sadak,morang .
Name of Work:-Blacktopped Road Construction Works including Drainage Structures F.Y.: 076/077
Breadth(
S.No. Description of Work No. Length(m) Height(m) Quantity Unit Remarks
m)
3.0 Pavement Construction Works
3.1
Formation of embankment including compaction in
layers not exceeding 150 mm compacted depth,
watering , rolling and transporting etc. all complete as
per specification [SS/SP- 907 ] 2 304 1.5 1.3 1185.6 m3
3.2
Subgrade preparation / Regrading of gravel surface by
scarifying with grader machine including watering,
levelling , formation of camber and compaction all
complete for sub grade preparation work all complete as
per Specification. [SS/SP- 1003]
3.5
Providing and spraying bituminious prime coat
including cleaning the road surface using wire, brushes, 1.00 358.00 5.50 1969.00 m2
broom etc. before applying prime coat all complete as
per Specification. [SS/SP-1301, 1302]
Total Spray rate 1lit/m2 1969.00 Lit
3.6
Providing and spraying bituminious tack coat including
cleaning the road surface using wire, brushes, broom
etc. before applying tack coat all Complete as per 1 358.00 5.50 2926.00 m2
Specification. [SS/SP-1301, 1302]
General Works
NA PS 1
Insurance for the loss or damage to works,
materials and contractor's equipments
including personal injury or death as per
Contract Data all Complete. LS 1.00 28000.00