Abstract of Cost

Name of Project:Gachhiya Chowk dekhi mirgauliya bazar hudai haraicha jodane sadak,morang .
Name of Work:-Blacktopped Road Construction Works including Drainage Structures F.Y.: 076/077

S.N. Description of Works Unit Quantity Rate(NRs) Amount(NRs) Remarks


1 General Works
1.1 Insurance for the loss or damage to works, materials and
contractor's equipments including personal injury or death LS 1.00 28000.00 28000.00
as per Contract Data all Complete.

1.2 Supplying and Erecting informatory board and name plate


(contract details) in place including 50mm dia. steeel tube,
2mm thick steel plate sign board in place 1.2m.x 0.75m.
Size bigger with back support and two or more post as Nos. 2.00 7130.72 14261.44
instructed by the engineer all Complete as per
Specification. [SS/SP-1501]

2.0 Drain Construction Works


2.1 Earthwork excavation in soft soil for drain and trenches
including shoring, struting, bracing, sheeting and disposal
upto 10 m and lift upto 3 m etc. all complete as per m3 16.20 114.35 1852.47
specification. [Manual(20%), Machine(80%)]ss/sp(905)

2.2 Providing and laying of hand pack Stone soling with 150
to 200 mm thick stones and packing with smaller stone on
prepared surface as per Drawing and Technical m3 2.70 3956.04 10681.31
Specifications.ss/sp(2602,2603)

2.3 Providing and placing cement concrete for the non-


structural elements including compaction, curing,
testing and relevant lead etc. as per drawing all m3 2.10 10845.83 22776.24
complete as per specification [1:2:4 (cement : sand :
aggregate)][SS/SP-2000]

2.4 Providing and laying Random rubble masonry in


cement sand (1:4) mortar including scaffolding,
curing etc. all complete as per Specification.[SS/SP- m3 28.50 8459.66 241100.31
2602,2603, 2607]
2.5 Providing, mixing, and Pointing cement mortar over
rubble masonry works in cement mortar [ cement(1) :
sand(3)] including scaffolding, curing, preparation of m2 9.00 263.10 2367.90
mortar etc. complete, ss/sp(2602,2603,2610)
2.6
Providing , Preparing and Installing form work including
necessary supports and removing after completion for m2 1.40 1032.66 1445.72
walls all complete as per specification.(1804,1805)

2.7

Proving and laying RCC pipes of diameter 600mm


(internal) with or without collars jointed with stiff mixture RM 20.00 6698.97 133979.40
of cement mortar in the proportion of 1 : 2 ( 1 cement : 2
fine sand ) all Complete as per Specification. [SS/SP-908]
2.8
Providing suitable material and Back filling behind
abutment, wing wall and return wall complete as per
Drawing and Technical Specifications.( Locally available m3 4.32 562.07 2428.14
material) (Without watering& Compction by Tamping
rod)ss/sp(908)

Prepared By........................... Checked By............................ Approved By..........................


Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
Central Road Supervision & Monitoring Office
Division Road Office, Biratnagar

Abstract of Cost

Name of Project:Gachhiya Chowk dekhi mirgauliya bazar hudai haraicha jodane sadak,morang .
Name of Work:-Blacktopped Road Construction Works including Drainage Structures F.Y.: 076/077

S.N. Description of Works Unit Quantity Rate(NRs) Amount(NRs) Remarks


2 Pavement Construction Works
2.1
Formation of embankment including compaction in layers
not exceeding 150 mm compacted depth, watering , rolling m3 1185.60 367.26 435423.46
and transporting etc. all complete as per specification
[SS/SP- 907 ]
2.2 Subgrade preparation / Regrading of gravel surface by
scarifying with grader machine including watering,
levelling , formation of camber and compaction all m2 2506.00 11.33 28392.98
complete for sub grade preparation work all complete as
per Specification. [SS/SP- 1003]
2.3 Providing, Laying, Spreading, watering, Leveling and
compaction as per required camber of riverbed gravel for
sub base course with all transportation all Complete as per m3 456.50 2216.08 1011640.52
Specification. [SS/SP-1201]

2.4 Providing, laying, spreading, watering, levelling and


compaction of crusher run materials for base course with
relevant lead and lift all complete as per Specification. m3 308.78 2752.03 849771.82
[SS/SP-1202]

2.5 Providing and spraying bituminious prime coat including


cleaning the road surface using wire, brushes, broom etc.
before applying prime coat all complete as per Lit 1969.00 125.47 247050.43
Specification. [SS/SP-1301, 1302]

2.6 Providing and spraying bituminious tack coat including


cleaning the road surface using wire, brushes, broom etc.
before applying tack coat all Complete as per Lit 2135.98 118.95 254074.82
Specification. [SS/SP-1301, 1302]

2.7 Providing, mixing, and laying asphalt concrete with


compaction all Complete as per Specification . [SS/SP-
m3 78.76 21442.75 1688830.99
1307, 1308]

Sub Total 4974077.95


Contingency @4 % 198963.12
VAT @13% 646630.13
Grand Total 5819671.20

Prepared By........................... Checked By............................ Approved By..........................


3 of 8

Government of Nepal
Ministry of Physical Infrastructure & Transport
Department Of Road
Central Road Supervision & Monitoring Office
Road Division , Biratnagar
Calculation of Quantities

Name of Project:Gachhiya Chowk dekhi mirgauliya bazar hudai haraicha jodane sadak,morang .
Name of Work:-Blacktopped Road Construction Works including Drainage Structures F.Y.: 076/077

Breadth(
S.No. Description of Work No. Length(m) Height(m) Quantity Unit Remarks
m)
1 General Works
1.1 Insurance for the loss or damage to works, materials and
contractor's equipments including personal injury or
death as per Contract Data all Complete. 1.00 1.00 LS

1.2 Supplying and Erecting informatory board and name


plate (contract details) in place including 50mm dia.
steeel tube, 2mm thick steel plate sign board in place
1.2m.x 0.75m. Size bigger with back support and two 2.00 2.00 Nos.
or more post as instructed by the engineer all Complete
as per Specification. [SS/SP-1501]

2.0 Hume pipe Culvert Construction Works


2.1 Earthwork excavation in soft soil for drain and
trenches including shoring, struting, bracing, sheeting
and disposal upto 10 m and lift upto 3 m etc. all
complete as per specification. [Manual(20%),
Machine(80%)]ss/sp(905)

For Hpc Head wall/Tail wall 4.00 3.00 1.5 0.9 16.20
Total 16.20 m3
2.2 Providing and laying of hand pack Stone soling with
150 to 200 mm thick stones and packing with smaller
stone on prepared surface as per Drawing and Technical
Specifications.ss/sp(2602,2603)

For Hpc Head wall/Tail wall 4.00 3.00 1.5 0.15 2.70
Total 2.70 m3
2.3 Providing and placing cement concrete for the non-
structural elements including compaction, curing,
testing and relevant lead etc. as per drawing all
complete as per specification [1:2:4 (cement :
sand : aggregate)][SS/SP-2000]

For Hpc Head wall/Tail wall 4.00 3.00 1.5 0.1 1.80 m3
Top of HPC 4.00 3.00 0.5 0.05 0.30 m3
Total 2.10 m3
2.4 Providing and laying Random rubble masonry in
cement sand (1:4) mortar including scaffolding,
curing etc. all complete as per Specification.[SS/SP-
2602,2603, 2607]
For Hpc Head wall/Tail wall 4.00 3.00 0.95 2.5 28.50 m3
Total 28.50 m3
2.5 Providing, mixing, and Pointing cement mortar over
rubble masonry works in cement mortar [ cement(1)
: sand(3)] including scaffolding, curing, preparation
of mortar etc. complete, ss/sp(2602,2603,2610)

For Hpc Head wall/Tail wall 4.00 3.00 0.75 9.00


Total 9.00 m2
2.6
Providing , Preparing and Installing form work
including necessary supports and removing after
completion for walls all complete as per specification.
(1804,1805)
For Hpc Head wall/Tail wall 4.00 7.00 0.05 1.40 m2
Total 1.40 m2
2.7
Proving and laying RCC pipes of diameter 600mm
(internal) with or without collars jointed with stiff
mixture of cement mortar in the proportion of 1 : 2 ( 1
cement : 2 fine sand ) all Complete as per Specification.
[SS/SP-908]
For HPC 8.00 2.50 20.00 RM.
Total 20.00 RM.
2.8
Providing suitable material and Back filling behind
abutment, wing wall and return wall complete as per
Drawing and Technical Specifications.( Locally
available material) (Without watering& Compction by
Tamping rod)ss/sp(908)
For HPC 2.00 3.00 0.8 0.9 4.32 m3
Total 4.32 m3

Prepared by: Checked by: Approved by:


4 of 8

Government of Nepal
Ministry of Physical Infrastructure & Transport
Department Of Road
Central Road Supervision & Monitoring Office
Road Division , Biratnagar
Calculation of Quantities

Name of Project:Gachhiya Chowk dekhi mirgauliya bazar hudai haraicha jodane sadak,morang .
Name of Work:-Blacktopped Road Construction Works including Drainage Structures F.Y.: 076/077

Breadth(
S.No. Description of Work No. Length(m) Height(m) Quantity Unit Remarks
m)
3.0 Pavement Construction Works
3.1
Formation of embankment including compaction in
layers not exceeding 150 mm compacted depth,
watering , rolling and transporting etc. all complete as
per specification [SS/SP- 907 ] 2 304 1.5 1.3 1185.6 m3
3.2
Subgrade preparation / Regrading of gravel surface by
scarifying with grader machine including watering,
levelling , formation of camber and compaction all
complete for sub grade preparation work all complete as
per Specification. [SS/SP- 1003]

1.00 358.00 7.00 2506.00 m2


3.3
Providing, Laying, Spreading, watering, Leveling and
compaction as per required camber of riverbed gravel
for sub base course with all transportation all Complete
as per Specification. [SS/SP-1201]
Carriageway 1 358.00 7.00 0.15 375.9 m3
shoulder 2 358.00 0.75 0.15 80.6
Total 456.50 m3
3.4 Providing, laying, spreading, watering, levelling and
compaction of crusher run materials for base course
with relevant lead and lift all complete as per 1.0 358.0 5.75 0.15 308.78 m3
Specification. [SS/SP-1202]

3.5
Providing and spraying bituminious prime coat
including cleaning the road surface using wire, brushes, 1.00 358.00 5.50 1969.00 m2
broom etc. before applying prime coat all complete as
per Specification. [SS/SP-1301, 1302]
Total Spray rate 1lit/m2 1969.00 Lit
3.6
Providing and spraying bituminious tack coat including
cleaning the road surface using wire, brushes, broom
etc. before applying tack coat all Complete as per 1 358.00 5.50 2926.00 m2
Specification. [SS/SP-1301, 1302]

Total Spray rate 0.73 lit/m2 2135.98 Lit


3.7 Providing, mixing, and laying asphalt concrete with
compaction all Complete as per Specification . [SS/SP- 1.00 358.00 5.50 0.04 78.76 m3
1307, 1308]

Prepared by: Checked by: Approved by:


Sector Group Sub - Title First Second
Group Custom Custom
Level(opti Level(opti
onal) onal)
(Provide (Provide
Descriptio Descriptio
n) n)

Provisional Sum #[XXX0001]

General Works

Pavement Construction Works


Third Item Name & Description Unit Quantity Official
Custom Rate
Level(opti
onal)
(Provide
Descriptio
n)

NA PS 1
Insurance for the loss or damage to works,
materials and contractor's equipments
including personal injury or death as per
Contract Data all Complete. LS 1.00 28000.00

Maintain traffic flow either by diversion or


traffic control and provide safety measures
during working hours as instructed by the
engineer (Flagman,traffic sign and diversion
etc.) all Complete. Job #REF! #REF!

Supplying and Erecting informatory board


and name plate (contract details) in place
including 50mm dia. steeel tube, 2mm thick
steel plate sign board in place 1.2m.x
0.75m. Size bigger with back support and
two or more post as instructed by the
engineer all Complete as per Specification.
[SS/SP-1501] Nos. 2.00 7130.72
Formation of embankment including
compaction in layers not exceeding 150 mm
compacted depth, watering , rolling and
transporting etc. all complete as per
specification [SS/SP- 907 ] m3 1185.60 367.26

Subgrade preparation / Regrading of gravel


surface by scarifying with grader machine
including watering, levelling , formation of
camber and compaction all complete for sub
grade preparation work all complete as per
Specification. [SS/SP- 1003] m2 2506.00 11.33
Providing, Laying, Spreading, watering,
Leveling and compaction as per required
camber of riverbed gravel for sub base m3
course with all transportation all Complete
as per Specification. [SS/SP-1201] 456.50 2216.08
Providing, laying, spreading, watering,
levelling and compaction of crusher run
materials for base course with relevant lead m3
and lift all complete as per Specification.
[SS/SP-1202] 308.78 2752.03
Providing and spraying bituminious prime
coat including cleaning the road surface
using wire, brushes, broom etc. before Lit
applying prime coat all complete as per
Specification. [SS/SP-1301, 1302] 1969.00 125.47

Providing and spraying bituminious tack


coat including cleaning the road surface
using wire, brushes, broom etc. before
applying tack coat all Complete as per
Specification. [SS/SP-1301, 1302]
Lit 2135.98 118.95
Providing, mixing, and laying asphalt
concrete with compaction all Complete as
per Specification . [SS/SP-1307, 1308] m3 78.76 21442.75