Millennium Erectors Corporation

9445 Retiro St., Guadalupe, Makati City

Project : Oriental Gardens Makati (Lilac Tower) Report No. : 066


Location : Don Chino Roces Ave. corner Export Drive, Makati City Date : July 1, 2014
Contract Package Shift : Day
Working Time : from 7:00AM to 4:00PM Weather : Sunny

Daily Construction Report


MANPOWER
Staff NO MH NO MH Equipments NO HRS.
1. Project Manager 1 8 1. Leadman 2 16 1. Cut off machine 1 8
2. QA/QC 1 8 2. Carpenter 2 16 2. Mini Dump Truck 0 0
3. Site Engineer 2 16 3. Mason 2 16 3. Circular Saw 1 8
4. Electrical Engineer 1 8 4. Tile Setter 3 24 4. Service Vehicle 1 8
5. Mechanical Coordinator 0 0 5. Welder 1 8 5. Power Washer 1 8

6. Cost Engineer 0 0 6. Laborer 32 256 6. Grinder 6 48


7. Safety Officer 1 13 Total 42 336 7. Auto level 1 8
8. Project Nurse 0 0 TRADECON 8. Mech.Concrete Vib. 1 8

9. CAD Operator 1 8 KALAYAAN 1 8 9. Hammer Drill & Rotary 5 40


10. Timekeeper 1 10 ICC 5 40 10. Chipping Gun 1 8

11. Foreman 1 8 ROSTRAM 2 16 11. Welding machine 1 8


Total 9 79 S&H 8 64 12. Hand Drill 6 48
ARLO 2 16 13. Cutting Tools 2 16

General Services NO MH YYD 2 16 14. Vacuum Cleaner 1 8

1. Spot Checker 1 13 V. ROQUE 5 40


2. Electrician 1 13 G. S. GO 2 16
3. Electrical Aide 2 26 CARSON 0 0

4. Line and Grade 0 0 CARDRIAN 1 8


5. L&G Helper 1 13 POLYGON 0 0

6. Warehouse Man 1 13 STELSEN 0 0


7. Warehouse Aide 1 13 SCHINDLER 2 16
8. Pump Tender 1 13 Total 30 240
9. Utility 3 39 SUBCON
Total 11 143 FIVE STAR 0 0
CHER 18 144

Operator NO MH FRANCISCAN 0 0
1. Driver 1 13 BIO 101 0 0

Total 1 13 MIGHTY 31 248


FMPI 0 0

Total 109 872 Prepared by :

NO MH ___________________________

Description of Activities Performed Today: MEC


GRAND TOTAL 172 1443
1. Final re-touch painting @ GF to 32nd floor

2. Painting works Interior retouching @ 25th -34th floor


3. Installation &Rectification of tiles ponding @ 24th - 32nd floor Received by:

4.Puchlisting @ 9th-32nd floor

5. Painting of Main Doors & T/B 31st-32nd __________________________________


DAAA
Millennium Erectors Corporation
9445 Retiro St., Guadalupe, Makati City

Project : Oriental Gardens Makati (Lilac Tower) Report No. : 002


Location : Don Chino Roces Ave. corner Export Drive, Makati City Date : August 24, 2011
Contract Package Shift : Night
Working Time : from to Weather :

Daily Construction Report


MANPOWER
Staff NO MH General Services NO MH Operator NO MH
1. Project Manager 1. Time Keeping 1. Driver

2. Superintendent 2. Warehouse 2. Tadano Oprt.


3. Site Engineer 3. Line & Grade 3. Backhoe Optr.

4. Quality Control 4. Electrician 4. Mini Loader Optr


5. Office Engineer 5. Utility 5. Genset Optr.

6. Autocad Operator 6. Leadman 6. Bulldozer Optr.

7. Safety Officer 7. Vibratory Roller Optr.


8. Project Nurse 8. Dumptruck Optr.

Total 0 0 Total 0 0 Total 0 0

Carpenter NO MH Welder NO MH Labor NO MH


1. Curanto 1. 1.

2. Total 2.

3. 3.
4. Steelman NO MH 4.

5. 1.

Total 0 0 Total 0 0 Total 0 0

Grand Total 0 0

Equipments NO HRS. Equipments NO HRS.


1. Backhoe
2. Mini Loader
3. L-300 FB

Description of Activities Performed Today:

Remarks:

Prepared by: Received by:

Jose P. Maaliw
MEC DAAA
\ NO MH
1. 5 87
Total 5 87