Sl. Date of Basic cost inc Storage charges @ Rate F.O.R at DSR-2019 rate
No Description Unit purchase transportation Rate at site 2% on basic cost Wastage % Wastage Cost site (Excluding CPOH)
(Rs)
Usk=Rs.558/day
SSk=Rs.617/day
Sk=738/day
1 2 3 4 5 6 7 8 9 10 11
2%
1 Reinforcement MT 41,189.00 41,189.00 824 7.00% 2941 44,954.00 46000
2 Cement MT 5,468.75 5,468.75 109 2.5% 139 5,717.00 4940
3 Aggregates MT 1,430.00 1,430.00 29 5% 73 1,532.00 912
4 Coarse Sand MT 1,430.00 1,430.00 29 10% 146 1,605.00 912
5 Structural Steel kg - 0 0 - 46000