Statement showing the details of material rates

Sl. Date of Basic cost inc Storage charges @ Rate F.O.R at DSR-2019 rate
No Description Unit purchase transportation Rate at site 2% on basic cost Wastage % Wastage Cost site (Excluding CPOH)
(Rs)

Usk=Rs.558/day
SSk=Rs.617/day
Sk=738/day
1 2 3 4 5 6 7 8 9 10 11
2%
1 Reinforcement MT 41,189.00 41,189.00 824 7.00% 2941 44,954.00 46000
2 Cement MT 5,468.75 5,468.75 109 2.5% 139 5,717.00 4940
3 Aggregates MT 1,430.00 1,430.00 29 5% 73 1,532.00 912
4 Coarse Sand MT 1,430.00 1,430.00 29 10% 146 1,605.00 912
5 Structural Steel kg - 0 0 - 46000

6 Admixture kg 69.00 69.00 1 0 70.00 36


7 HSD litre 66.37 66.37 0 66.37
8 Binding Wire kg 57.16 57.16 1 0 58.00 46
9 Curing Compound litre 46.00 46.00 1 0 47.00 38
10 Rebar Coupler Nos. 120.00 120.00 2 0 122.00 110
12 Shuttering Oil Litre 65.00 65.00 1 0 66.00 52
13 Bentonite MT 2,960.00 2,960.00 59 0 3,019.00 2960
14 POT/PTFE Bearing Nos. 102,884.62 102,884.62 2058 0 104,943.00
15 PVC pipe-100 mm rm 131.67 131.67 3 0 135.00 130
16 MS Clamp Nos. 65.00 65.00 1 0 66.00 45
17 Granular Material MT 900.00 900.00 18 5% 46 964.00 Not Available
18 Stone weighing not less than 40kg MT 650.00 650.00 13 5% 33 696.00 103.77
19 Stone spalls of minimum 25 mm size MT 1,430.00 1,430.00 29 5% 73 1,532.00
20 Graded stone aggregate of required size MT 1,430.00 1,430.00 29 0 1,459.00 912
21 Red Oxide Zinc Primer litre 82.00 82.00 2 0 84.00 110
22 MS Tubes - 50/40 NB pipe MT 49,879.00 49,879.00 998 0 50,877.00 59500
23 Elastomeric Bearing of size 500 x 400 x 96 CuCm 7,872.00 7,872.00 157 0 8,029.00
24 HTS Wire 15.2 mm MT 58,000.00 58,000.00 1160 0 59,160.00
25 Sheathing Duct - 110 mm rm 108.00 108.00 2 0 110.00
26 Anchorage System + Bearing Plate Nos. 1,326.00 1,326.00 27 0 1,353.00
27 Wedges Nos. 848.00 848.00 17 0 865.00
Item Rate L&T
Manpower Material Equipment Total
Concrete M15 4505 4953 1592 11050
M35 upto plinth level 4686 5496 2164 12345.8
M35 Above plinth level 7284 5399 2164 14847.4
DSR USSOR
Manpower Material Equipment Total Manpower Material Equipment Total
1792 3227 886 5905
1792 3575 886 6253
2841 3575 886 7302