PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)


Format For Consolidated Report of the STA
on the Project Proposals Under PMGSY.

1. State:- Odisha Phase:- Year:- 2011-12

2. Names of the Members of the STA involved in the Technical Scrutiny.

3. Whether Pre-DPR meeting was held with SRRDA and DPIUs.

4. Summary of the Project Proposals scrutinized indicating district wise road details of length and cost. The
summary including the No. of Packages and total value.

5. Whether schedule for scrutiny was fixed in advance (give details) and difficulty in adhering to schedule.

6. Actual scrutiny process and time taken for scrutiny (please indicate the datas).

7. Interaction of the Engineers of the Executing Agencies with the STAS.

8. Major deficiencies observed during scrutiny with details.

9. Reliability of data obtained through investigation and used in the design / estimation.

10. Compliance of the provision / instructions give in the guidelines/circlars/operation manual/IRC codes etc. in
the preparation of DPRs including Environmental/RR/Road safety aspects etc.

11. Levels of response from the Senior Engineers of the Executing Agencies for the suggestions given by the
STAs for revision/modification in the DPRs.

12. If DPRs outsourced, perceived level of competence of outsourced consultants and suggestions.

13. Overall comments and impressions of the STAs, if any on the process of the preparation of DPRs and their
technical scrutiny.
Annexure-7.3
See Para 7.4

Signature & Name of the Co-ordinator STA


PRADHAN MANTRI GRAM SADAK YOJANA
CONTRIBUTION OF DIFFERENT COMPONENTS ON THE COST ONE KM LENGTH B.T. ROAD
Name of Division:- R.W.Division, Nayagarh
Name of Section:- R. W. Section ,Odagaon

Other (Turfing &


Package Earth Work G.S.B W.B.M.-II W.B.M.-III P.M.C. & Seal Coat
Clearing) Total Cost of
Sl. No,./ Carriage Depth of
Amount Amount Amount Amount Amount Amount Km. of B.T.
No. Road No. Width Crust Average Average Average Average Average Average
Quantity (Rs. In Quantity (Rs. In Quantity (Rs. In Quantity (Rs. In Quantity (Rs. In (Rs. In Road.
(N/U) Rate Rate Rate Rate Rate Rate
Lakh) Lakh) Lakh) Lakh) Lakh) Lakh)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22

1. OR-23-265 3.75 325mm 2361.08 401803.91 4.02 562.43 382640.36 3.83 57.38 167403.62 1.67 300.94 856146.89 8.56 15300.00 893520.00 8.94 #NAME? #NAME? #NAME?
PRADHAN MANTRI GRAM SADAK YOJANA
CONTRIBUTION OF DIFFERENT COMPONENTS ON THE COST ONE KM LENGTH C.C. ROAD
Name of Division:- R.W.Division, Nayagarh
Name of Section:- R. W. Section ,Odagaon

Package Earth Work If any G.S.B W.B.M.-II Pavement Quality Concrete (M-30)
Total Cost of
Sl. No,./ Carriage Depth of
Km. of C.C.
No. Road No. Width Crust Average Amount (Rs. Average Amount (Rs. Average Amount (Rs. Average Amount (Rs.
Quantity Quantity Quantity Quantity Road
(N/U) Rate In Lakh) Rate In Lakh) Rate In Lakh) Rate In Lakh)

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

1. OR-23-265 3.75 330 mm 229.50 62440.06 0.62 67.50 312468.97 3.12 90.00 100683.90 1.01 60.00 0.00 0.00 4.76
PRADHAN MANTRI GRAM SADAK YOJANA
Package Summary
Name of Division:- R.W.Division, Nayagarh
0 R. W. Section ,Odagaon

Cost Rs. In Lakh


Length
Proposed Length (In Cost of Total Cost of Total Cost Length
Ro Carriag C.B.R. Type of Total Cost Total Total of Total Average Cost of Average
Sl. Name of Package Name of the Km.) B.T. Cost of C.C. of of Cost of Total
ad e width Value in Proposa of C.C. Nos. of Cost of Protectio Cost of Cost per Maintainc cost of
No. the Block No Road Road Per B.T. Road Per Protection Drain Others Cost e
No. in m. % l (N/U) Road C.D. C.D. n Wall Drain km. Maintaince
Total B.T. C.C. Km. Road Km. Wall

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

OR-23- Nandighore
1. Odagaon A 3.75 5.40% UG 6.00 2.54 3.46 34.35 87.24 31.64 109.49 2.00 3.69 460 25.71 0.0 0.00 3.48 229.60 38.27 20.26 3.38
265 to Saliajhari
HORIZONTAL CURVE DESIGN & LAYOUT

NAME OF THE ROAD: HATIKUCHA to RABGAMATIA SAHI BLOCK: Harichandanpur


0 DISTRICT: Keonjhar
Design Speed 40 KM/H
Curve IP Curve Hand of
No Chainage
Rc Lc ∆
Type Curve
PW
IP Chainage 70 m. PI
1 70 35 20 32 Transition R 6 ∆
PSE 0.07
E = 1.4
E = R(1/Cos∆/2)-1) 1.41048026 T= R Tan∆/2 0.1m
M= R(1-Cos∆/2) 1.35584064 PC = 69.9m M = 1.4 PT =70.1m

Super Elevation (S.E) R=35


R
I e=V2/(225 x R) 0.2031746 HENCE e=0.07 Ls = 123 M
Considering Max e = 0.15
S.E = 0.07
II f = (V2/(127 x R)-0.07) 0.28995501 > 0.15

Va (Velocity allowable)

III Here f>0.15 then


So New f =√(S.E + 0.15) x 127 x R 31.271393
Making it to divisor of 5 becomes 31.271393 SAY 40
So Va = 40 Km/H

Lc=∆/360x2πR 19.5564444
Length of transition (Ls)

I Ls=(0.0215 x V3)/CR 57.00 m


EI 0.42
II LS 63
III Ls = (2.7 x Va2)/R 123 m
C=(75/80+V) 0.69565217

Design Speed V= 40 KM/H


Curve IP Curve Hand of
No Chainage
Rc Lc ∆ Type Curve
PW
IP Chainage 690 m. PI
2 690 35 17 28 Transition R 6 ∆
PSE 0.07
E = 1.1
E = R(1/Cos∆/2)-1) 1.07147703 T= R Tan∆/2 8.726 8.7m
M= R(1-Cos∆/2) 1.03964958 PC = 681.3m M = 1 PT =698.7m

Super Elevation (S.E) R=35


R
I e=V2/(225 x R) 0.2031746 HENCE e=0.07 Ls = 63 M

S.E = 0.07
II f = (V2/(127 x R)-0.07) 0.28995501 > 0.15
Va (Velocity allowable)

III Here f>0.15 then


So New V =√(S.E + 0.15) x 127 x R 31.271393
Making it to divisor of 5 becomes 31.27139 SAY 40
So Va = 40 Km/H
Lc=∆/360x2πR 17.1118889
Length of transition (Ls)

I Ls=(0.0215 x V3)/CR 57.00 m


EI 0.42
II LS 63
III Ls = (2.7 x Va2)/R 123 m
C=(75/80+V) 0.69565217
Design Speed 40 KM/H
20
Curve IP Curve Hand of
No Chainage
Rc Lc ∆ Type Curve
PW
IP Chainage 1260 m. PI
3 1260 25 16 36 Transition L 6 ∆
PSE 0.07
E = 1.3
E = R(1/Cos∆/2)-1) 1.28655561 T= R Tan∆/2 8.123 8.1m
M= R(1-Cos∆/2) 1.22358709 PC = 1251.9m M = 1.2 PT =1268.1m

Super Elevation (S.E) R=25


R
I e=V2/(225 x R) 0.28444444 HENCE e=0.07 Ls = 63 M
Considering Max e = 0.15
S.E = 0.07
II f = (V2/(127 x R)-0.07) 0.43393701 > 0.15
Va (Velocity allowable)

III Here f>0.15 then


So New f =√(S.E + 0.15) x 127 x R 26.429151
Making it to divisor of 5 becomes 26.429151 SAY 40
So Va = 40 Km/H
Lc=∆/360x2πR 15.715
Length of transition (Ls)

I Ls=(0.0215 x V3)/CR 79.00 m


EI 0.42
II LS 63
III Ls = (2.7 x Va2)/R 173 m
C= 0.69565217

Design Speed 40 KM/H


25
Curve IP Curve Hand of
No Chainage
Rc Lc ∆ Type Curve
PW
IP Chainage 1800 m. PI
4 1800 20 9.429 27 Transition R 6 ∆
PSE 0.04
E = 0.6
E = R(1/Cos∆/2)-1) 0.56830387 T= R Tan∆/2 4.802 4.8m
M= R(1-Cos∆/2) 0.55260159 PC = 1795.2m M = 0.6 PT =1804.8m

Super Elevation (S.E) R=20


R
I e=V2/(225 x R) 0.35555556 Ls = 36 M
Considering Max e = 0.15
S.E = 0.07
II f = (V2/(127 x R)-0.07) 0.55992126 > 0.15

Va (Velocity allowable)

III Here f>0.15 then


So New f =√(S.E + 0.15) x 127 x R 23.638951
Making it to divisor of 5 becomes 23.638951 SAY 25
So Va = 25 Km/H

Lc=∆/360x2πR 9.429
Length of transition (Ls)

I Ls=(0.0215 x V3)/CR 21.00 m


EI 0.24
II LS 36
III Ls = (2.7 x Va2)/R 84 m
C= 0.8
Design Speed 40 KM/H
125
Curve IP Curve Hand of
No Chainage
Rc Lc ∆ Type Curve
PW
IP Chainage 3840 m. PI
5 3840 35 28.1123889 46 Transition R 6 ∆
PSE 0.06
E=3
E = R(1/Cos∆/2)-1) 3.02261321 T= R Tan∆/2 14.86 14.9m
M= R(1-Cos∆/2) 2.78233013 PC = 3825.1m M = 2.8 PT =3854.9m

Super Elevation (S.E) R=35


R
I e=V2/(225 x R) 0.2031746 Ls = 22 M
Considering Max e = 0.15
S.E = 0.07
II f = (V2/(127 x R)-0.07) 0.28995501 > 0.15
Va (Velocity allowable)

III Here f>0.15 then


So New f =√(S.E + 0.15) x 127 x R 31.271393
Making it to divisor of 5 becomes 31.271393 SAY 30
So Va = 30 Km/H
Lc=∆/360x2πR 28.1123889

Length of transition (Ls)

I Ls=(0.0215 x V3)/CR 22.00 m


EI 0.36
II LS 54
III Ls = (2.7 x Va2)/R 69 m
C= 0.76190476

Design Speed 40 KM/H


40
Curve IP Curve Hand of
No Chainage
Rc Lc ∆ Type Curve
PW
IP Chainage 6150 m. PI
6 6150 30 18.3341667 35 Transition R 6 ∆
PSE 0.07
E = 1.5
E = R(1/Cos∆/2)-1) 1.45587375 T= R Tan∆/2 9.459 9.5m
M= R(1-Cos∆/2) 1.38849148 PC = 6140.5m M = 1.4 PT =6159.5m

Super Elevation (S.E) R=30


R
I e=V2/(225 x R) 0.23703704 HENCE e=0.07 Ls = 25 M
Considering Max e = 0.15
S.E = 0.07
II f = (V2/(127 x R)-0.07) 0.34994751 > 0.15
Va (Velocity allowable)

III Here f>0.15 then


So New f =√(S.E + 0.15) x 127 x R 28.951684
Making it to divisor of 5 becomes 28.951684 SAY 30
So Va = 30 Km/H
Lc=∆/360x2πR 18.3341667

Length of transition (Ls)

I Ls=(0.0215 x V3)/CR 25.00 m


EI 0.42
II LS 63
III Ls = (2.7 x Va2)/R 81 m
C= 0.76190476
Detailed Project Report
DPR Preparation, Rural Works Department
Govt. of Odisha.
0 Name of the Road : HATIKUCHA to RABGAMATIA SAHI

CHAPTER 8
8 Alignment Design
8.1 General
The basic aim of highway design is to identify technically sound, environment-friendly and economically feasible
highway alignment. The ensuing sections deals with obligatory points, which control highway alignment, design of
cross-section, highway geometry.
The main components included in the highway design are:
Ø            Cross-sectional elements
Ø            Embankment
Ø            Horizontal alignment
Ø            Vertical profile
Ø            Junctions and/or Interchanges
Ø            Road furniture
Ø            Miscellaneous items
8.2 Horizontal alignment
{ Insert a table (example given below) on the physical features of the existing alignment and
possible geometric improvement required }
Table 8.1 – Features of Horizontal Alignment (Example
Chainage Length Description Reason for deviation from existing
alignment, if necessary
From (km) To (km) (km)
0 0.85 0.85 Retained existing
centre line
Checklist
{Tick the relevant box}
a) Centre line of the existing and proposed horizontal alignment coincide
b) Centre line of the existing and proposed horizontal alignment deviate at certain sections

Chaina LHS Existing RHS Chainag Approx


ge alignme e shift land
nt required
(m)
0
0.85

Figure
Various8.1horizontal
Schematicgeometric
diagram showing location and offsets from existing alignment
improvement
carried out and their details

Table 8.2 – Horizontal Curve details


CurCurve Type IP Radius Ls Speed Extra S.E Def Angle Lc Ltotal Hand Curve
ve Chain Widen of Area
No. age needed Curve BT/CC
(m) (m) (Kmph) in (m) D M S (m) (m) L/R
COMBINE
1 CURVE 70 35 123 40 0.6 0.07 32 20 266 R CC 85.53
COMBINE
2 CURVE 840 35 123 40 0.6 0.07 28 17 263 R BT 84.07
COMBINE
3 CURVE 1110 25 173 40 0.6 0.07 36 16 362 L BT 113.23
COMBINE
4 CURVE 1800 20 84 25 0.6 0.07 27 9 177 R CC 0.00
COMBINE
5 CURVE 3840 35 69 30 0.6 0.07 46 28 166 R BT 0.00
COMBINE
6 CURVE 6150 30 81 30 0.6 0.07 35 18 180 R CC 0.00
Total (L) 108 282.83

8.3 Total Curve Area in BT Road 201.17 Sqm


Total Curve Area in CC Road 85.53 Sqm
As the vertical gradient of the road alignment is less than 1%, Vertical curves are not proposed in this estimate.

Development of Junctions
No Chaina Junct Area of Description
of ge (M) ion Junctio
junc Type n
tion
s

1 0 0 At the beginning of subproject road


2 846 0 At the ending of subproject road
0
1 3.87

3
3.870 Sqm
.
0
AT JUNCTION =2X0.215Xr²
M
3.0 M
Granit Products Tapanga 107
Moorum Rohibanka 14
Sand Sidhamula 68
Cement Nayagarh 20
Steel. Nayagarh 20
Bitumen bhubaneswar 107
Emulsion Paharpur 393
Hump Pipe saranakula 21
Bricks Local 5
DETAILS OF ROADS UNDER P.M.G.S.Y DETAILS OF ROADS UNDER P.M.G.S.Y

32 Column Format of Rural Works Division:- R.W.Division, Nayagarh 32 Column Format of Rural Works Division:- R.W.Division, Nayagarh
Overhead Charge-15%
Type Road Proper Works Protection Work Other Like
Total Habitation Benefited Cost of Maintenance in lakhs Traffic Data Carriage
Road of Pavement C.C. Road No. of Cost of Cost of Total Cost Average Designed Remarks
Name of the Length Traffic Way
Sl.No
Block
Package No. Code L / Name of the road Propos CD CD DPR,Km
(7+9) in
(8+10+12+ Cost Per Total Cost of No. of C.B.R.
Category width in Value
Remarks TOTAL
T al Length Length Works Works Stone Misc. 14+15) KM 1st 2nd 3rd 4th 5th 6th COST
Cost Cost Length in M Cost km Name Population Maintenance Motorised ESAL m.
N/UG in km in km etc. Year Year Year Year Year Year (20 to 24) Vehicle
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 24 25 26 27 28 29 30 31 32
Waste
plastic-
Nandighara,Go
2.54
Nandighore to udaputa,Bandh
1. Odagaon OR-23-265 T-01 UG 2.54 95.25 3.46 122.62 460.00 28.79 2.00 4.13 6.36 6.00 257.15 42.86 6873,, 2.89 3.47 4.052 4.63 5.21 0 20.26 192 308674 T6 3.75 5.40% km,Panell 277.41
Saliajhari asahi,SALIAJH
ed
ARI,Tikarpali,,
concrete-
3.46 km
Overhead Charge-12.5%
Type Road Proper Works Protection Work Other Like
Total Habitation Benefited Cost of Maintenance in lakhs Traffic Data Carriage
Road of Pavement C.C. Road No. of Cost of Cost of Total Cost Average Designed Remarks
Name of the Length Traffic Way
Sl.No
Block
Package No. Code L / Name of the road Propos CD CD DPR,Km
(7+9) in
(8+10+12+ Cost Per Total Cost of No. of C.B.R.
Category width in Value
Remarks TOTAL
T al Length Length Works Works Stone Misc. 14+15) KM 1st 2nd 3rd 4th 5th 6th COST
Cost Cost Length in M Cost km Name Population Maintenance Motorised ESAL m.
N/UG in km in km etc. Year Year Year Year Year Year (20 to 24) Vehicle
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 24 25 26 27 28 29 30 Waste
31 32
plastic-
Nandighara,Go
2.54
Nandighore to udaputa,Bandh
1. Odagaon OR-23-265 T-01 UG 2.54 93.336 3.46 120.1589 460 28.21 2 4.0481 6.23 6 251.98 42.86 6873,, 2.84 3.40 3.97 4.54 5.11 0.00 19.85 192 308674 T6 3.75 5.40% km,Panell 271.83
Saliajhari asahi,SALIAJH
ed
ARI,Tikarpali,,
concrete-
3.46 km
Length in Km
Stage
Sl Package L Route/T Carriageway
District Block N/U I/Stage Name of road
no No route No width in m
II/Complete CC

1 2 3 4 5 6 7 8 9 10
OR-23- Nandighore to
Nayagarh Odagaon T-01 3.75 U 3.46
265 Saliajhari

Note : All earth work cost for pavement including cutting, filling, scarifying, earthwork for earthen drain, shoulder e
Sub Base - GSB or gravel soling for pavement
Base - WBM Gr II, III and WMM
Surfacing - Prime coat, Tack coat, PC with SC
If more than 6 m span slab culvert / box culvert, details of such CDs (no and cost) may be provided in the remark
Component wise cost of roads proposed

CD works
Length in Km Cost of pavement (Rs in Lakhs) Pucca drain
Hume pipe

CC
Earth Sub Surfacin Cost per Length
BT Total Base paveme Total Cost Nos
work base g Km in M
nt cost

11 12 13 14 15 16 17 18 19 20 21 22
2.54 6 #NAME? 10.89 29.12 25.42 122.62 #NAME? #NAME? 0.00 0.00 2.00

rk for earthen drain, shoulder earthwork.


nt

C
may be provided in the remarks column
Cost in Lakhs
CD works
Minor bridges Protection work
Hume pipe Slab culvert Total Traffic
Road
Others Total Cost per categor
Span in Lenth in furnitures
Cost Nos Cost Cost Cost Km y
m M

23 24 25 26 27 28 29 30 31 32 33 34
4.13 0.00 0.00 0.00 0.00 460.00 28.79 2.46 3.90 #NAME? #NAME? T6
Cost in Lakhs

Remark
CBR
s

35 36
5.40%
FORMAT F-9A

PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)


CERTIFICATE OF GROUND VERIFICATION FROM EXECUTIVE ENGINEER. HEAD PIU

Name of the Road :- Nandighore to Saliajhari PACKAGE NO


District:- Nayagarh
Block:- Odagaon

1. a). Certified that the Land Width for the Road is available and that no additional land is required; or
b). Certified that land width for the Road is likely to be available as certified by the Panchayats.

2. a). Certified that no forest land is involved along the entire road way; or
b). Certified that the case for permission under Forest conservation Act has been moved to the Forest
Department on Dated and File or Case no.

3. Certified that the DPR has been checked at site by

Executive Enginer
Head of PIU.

Assistant Executive Engineer Executive Enginer


R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh

Superintending Engineer
Central Circle,
COMMUNITY CONSULTATION CHECK LIST - ENGINEERING

Name of the Road :- Nandighore to Saliajhari


District:- Nayagarh
Block:- Odagaon

Sl. No. Question Yes No N/a


1. Are there any flood prone areas on the road?
If Yes:
1.1 Are locations specified and inspected?
1.2. Is high flood level specified for each stretch?
1.3 Are locations specified and inspected?
2. Are there any locations on the road where irrigations ducts need to
be provided?
If Yes:
2.1 Are locations specified and inspected?
3. Can the road be used as a shortcut by through traffic?
4. Does the road lead to any quarries, mining areas, brick kilns, logging
areas, tourist attractions etc.?
5. Are there plans to build new schools, hospitals, temples etc
6. Is there potential for double connectivity?
If yes on any of 3-6:
6.1 Is information on location, size and nature of additional traffic
generators and specific routes obtained?
7. Is there a need for deviations from existing track?
If yes:
7.1 Were the proposals for deviation shown on site and explained to the
community?
7.2 Is the land availability checked?
7.3 If there is a need for donation, were the owners consulted regarding
their agreement to donate the land?
8. Is there a need for speed breakers?
If yes:
8.1 Is location and rational for speed breakers identified?
8.2 Is rationale verified and checked on site?
8.3 Are alternative or additional locations discussed?
9.
Are all existing intersections checked with the community on site?
9.1 Is the use of intersecting roads identified (e.g. school children, farm
machinery, etc)?
10. Are proposed culvert locations verified with the community?
10.1 Is there a need for additional culverts?
10.2 If yes, are locations identified?
m
11.1 If yes, are locations identified?

Junior Engineer Assistant Executive Engineer Executive Enginer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh
REPORT
PACKAGE NO

1.0 PROJECT BACKGROUND & ESTIMATED COST.

Cost Estimate of the project has been framed amounting to Rs. 277.41 Lakh to meet the
probable cost for construction of the road with flexible and rigid pavement under the package.

N/ Length in Construction Maintaince


Sl. No. Name of the Road Total Cost in Lakh
UG Mtr. Cost Cost

1. Nandighore to Saliajhari UG 6000 257.15 20.26 277.41

TOTAL 277.41

2.0 GENERAL FEATURES OF THE TRACK ROAD

A. Nandighore to Saliajhari

The Proposed road starts from Nandighore altimately connected to Saliajhari


The condition of pavements are Earthen.The embankment height is varying between 0.2mtr.to0.4mtr.The
road is passing through barren land as well as agriculture land with intermittent villages.The population of
village served by the road is given bellow

Sl. No. Village Population


Nandighara,Goudaputa,Bandhasahi,SALIAJHARI,Tikarpali
1. 6873
3.0 ENVIRONMENTAL FACTORS
The proposed road would proved to be benefical to the villages mentioned the table above.The benefits mostly
of a socio-economicnature by way of access to health centre, educational institution & markets.Villagers will have
more opportunities to interact with Civic & Govt. bodies. With the present level of traffic, pollution effects from
motor vehicles will be negligible.Adequate numbers of cross drainage works longitudinal drains has been provided to
ensure that water is quickly drained off & no stagnation takes place.Most of the run off will be drained at surrounding
land.
4.0 PROPOSAL OF RIGHT OF WAY , ACQUISITION OF STRUCTURES-
The proposed road has present width of 3.0m and a right of way (ROW)of 9.0m.Where sufficient ROW is not
obtained such as in built up areas, the road width has been proved 6.0m.

5.0 SURVEY & INVESTIGATION


5.1 Clssified trafic volume counts
The classified volume counts where conducted for continues 3 days, accordingly the averages value of ESAL
has been calculated for design purpose.

5.2 Trafic forecast:


The total present motorized is less but is expected to grow higher when the construction of the road is
completed. For projecting the future design traffic a growth rate of 6% is adopted & projection made for the traffic
over the design of 10 years.

5.3 Condition survey


A detailed reconnaissance survey including a quick road inventory & condition survey was carried out along the
project road.

5.4 Material survey & Investigation


1. Construction materials required for road work was investigated during the site visit.
2. Soil investigation :-
Soil survey has been down by collecting samples of local soils from the road in accordance with the guidelines
of IRC : SP : 20. The test results are enclosed in the DPR.

5.5 Topographic Survey :-


Topographic survey was carried out using leveling instrument and prismatic compass. Temporary bench marks have
been left at permanent structures along the road.

6.0 ENGINEERING DESIGN:-


6.1 Geometric Design

6.1.1 Horizontal Curves :


There are few horizontal curves along the project road,however because of ROW restriction it may be difficult

to improve all curves. Horizontal curves have been designed for a design speed of 40 km / hr with appropriate

transition curves & super elevations.The maximum super elevation is 7.0% & minimum normal camber is 3.5%.

6.2 Pavement Design.


The rigid and flexible pavement design has been done as per the procedure described in Rural Roads
Manual i.e. SP-62-2014 & SP 72-2007. Generally carriage way width adopted is 3.750 mtr for both rigid &
flexible pavement. GSB Shouiders for flexible and rigid pavement are provided 1.00mtr. & 0.6mtr. width respectively.
Also the sub grade GSB has been extended to the entire width for drainage to a depth of 100mm basing upon the soil
nature.

6.3 Cross – Drainage works.


There are no existing culverts. The rain water over tops the existing low profile formetion as well as
scouring the road and creating the road ditches. So adequate culverts have been provided basing upon the
road condition.
6.4 Drainages & Protection works.
Existing road has no longitudinal drainage system as well as protection works along the road. Based
upon the requirement of the road, provision for the drainage & protection work has been proposed.

7.0 RECOMMENDATION
The following items of works have been provided in the estimate ;- Road-A (L)
1 Widening of road embankment - 2540
2 Provision of granular sub-base- 2540
3 WBM-Gr-II - 2540
4 WBM-Gr-III - 2540
5 Black topping with 20mm thick PMC and seal coat - 2540
6 Construction of 600mm single rowHPC– 0 Nos
7 Construction of 1000mm single rowHPC– 2 Nos
10 Construction of RCC Box cell Culvert- (1x4x4) 0 Nos
12 Construction of CC Road - 3460
14 Construction of Drain - 0.00

8.2 Cost Estimate.


Cost estimate of the project has been done for constructing the road with flexible and rigid pavement.
The format recommended for PMGSY works has been adopted for computing details of quantities & the
cost.
The road has to be maintained for 5 years. The cost of maintenance of the project road has
been calculated based on IRC SP : 20 manual for rural roads.

Junior Engineer Assistant Executive Engineer Executive Enginer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh
PRADHAN MANTRI GRAM SADAK YOJANA (P.M.G.S.Y.)

Name of the Road:- Nandighore to Saliajhari


PACKAGE NO
District:- Nayagarh Block:- Odagaon

ANNUAL RAINFALL DATA

Years
Sl.No Name of the Block Maximum
2006 2007 2008 2009 2010
1 2 3 4 5 6 7 8

1. Odagaon 1623.00 1782.00 973.00 973.00 1629.95 1638.24

Certified the Rainfall Data Collected from the District Office is correct.

Junior Engineer Assistant Executive Engineer Executive Enginer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh
PAVEMENT THICKNESS DESIGN

Name of the road: Nandighore to Saliajhari

PACKAGE NO

DESIGN DATA
(a). Cumulative Esal applications 308674
(b). C.B.R. of the sub-grade 5.40%
©. Maxmim Rainfall 1638.24 mm / year

Using Figure 4 of IRC SP 72 - 2007, the crust thickness required = 325mm


Provide
(a). Base Course (i). W.B.M.75 mm
(ii). W.B.M.75 mm
(b). Surface Course (i). PMC 20 mm
(ii). SC 6 mm

Hence pavement thickness 325mm provided is Safe.

Junior Engineer Assistant Executive Engineer Executive Enginer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh
Annexure-7.1
Format F-1
See Para 7.2

PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)


SUMMARY SHEET

Unconnected Habitations
Sl. Name of the Total No. of 250-499
Code Total Eligible
No. Block Habitations >1000 500-999 <250
Total Eligible Habitations
1 2 3 4 5 6 7 8 9 10
1. Odagaon T-01 1 ---- --- 1 1 ---- 1
2.

No. of Estimated Cost (Rs. Lakhs) No. of Unconnected


Total
Sl. Type of No. of New CD Pavement CD Structure Habitations
No. Length of Total= connected/connected
Proposal Roads Structure from from
Road (km) (6+7) habitations benefited
s Format-F-5 Format-F-6
1 2 3 4 5 6 7 8 9
1. NEW Nandighara,Goudaputa
,Bandhasahi,SALIAJH
1 6.00 2 225.91 3.69 229.60
ARI,Tikarpali = 6873,
=, =
2. Associated
Through
Route
3. Upgradation

4. Other
Upgradation
Total=

Junior Engineer Assistant Executive Engineer Executive Enginer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh
FORMAT F-7

PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)


COST ESTIMATE FOR ROADS CONSTRUCTION OF CROSS DRAINAGE WORKS

PACKAGE NO
Name of the Road :- Nandighore to Saliajhari
Length of Road(KM):- 6.000 District:-Nayagarh

Type of cross Drainage Works:- Block:- Odagaon

Sl. L B D
Description of item No. Quantity Unit Rate (Rs) Amount (Rs)
No. (m) (m) (m)
1 2 3 4 5 6 7 8 9 10
1. 1000mm 1Row 2 184427.04 368854.08

2. 1000mm 2Row 0 #DIV/0! #DIV/0!

3. 600mm 1Row 0 #DIV/0! #DIV/0!

4. RCC culvert (1x2x2) 0 #DIV/0! #DIV/0!

5. RCC culvert (2x3x2) 0 #DIV/0! #DIV/0!

12. Boxcell culvert (1x4x4) 0 #DIV/0! #DIV/0!

6. Boxcell culvert (2x4x4) 0 #DIV/0! #DIV/0!

14. Boxcell culvert (4x4x4) 0 #DIV/0! #DIV/0!

Total Nos.C.D 2 368854.08

Junior Engineer Assistant Executive Engineer Executive Enginer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh
FORMAT F-8

PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)


RATE ANALYSIS

Name of the Road :-Nandighore to Saliajhari PACKAGE NO


District:- Nayagarh
Block:- Odagaon

Material Source Lead (in km)


Stone Tapanga 107
Bituminous bhubaneswar 107
Cement Nayagarh 20
Hume Pipes saranakula 21
Any Other

Analysis of Rates:-
Sl No. as per
Sl.
No.
MORD SDB for Description Units Qty. Rate (Rs) Amount (Rs)
Rural Roads
A. Construction
Activities Earth Work Cum 14960.55 161.15 2410823.43
GSB Cum 2726.06 673.75 1836686.16
WBM GR-II Cum 457.14 1692.20 773571.48
WBM GR-III Cum 764.39 2844.90 2174613.11
Prime Coat sqm 9715.50 30.23 293699.57
Tack Coat sqm 9715.50 10.50 102012.75
OGPC sqm 9715.50 141.80 1377657.90
seal coat sqm 9715.50 51.07 496170.59
CD Structure Nos 2 184427.04 368854.08
Protection wall Mtre 460 931.35 428421.68
Concrete Drain Mtre 0 #DIV/0! 0.00
Road Logo, other Road Furniture etc. 219249.97
Total
B. Maintenance
Activities (year
Wise)
1st Year 258419.16
2nd Year 310103.04
3rd Year 361786.86
4th Year 413470.68
5th Year 465154.50
Total

Note:-
1. Rate Analysis shall cover all the items such as site clearance, Eart Work, Drainage, Granular Sub Base, &
Surface Course, CD works, Traffic Signs, PMGSY Board, Logo & Maintenance activities.
2. Where Local Material is used at site and the specifications & Rate analysis are not found in BOS & SDB, for
Rural Roads, the analysis & nomenclature of the item can be suitably used based on other standarda such as
3. PWD Schedule
Completed itemsorrates
Rateincluding
or assessment based
lead for on field
carriage of observation.
materials should shown.
FORMAT F-8

Junior Engineer Assistant Executive Engineer Executive Enginer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh
PMGSY DPR REVIEW CHECKLIST AND SCORESHEET
State:- Odisha Ranking
Road Number:- T-01 0 Not Included
Road Name:- Nandighore to Saliajhari 1 Poor Standard
District:- Nayagarh 2 Fair Standard
Block:- Odagaon 3 Good Standard

Sl.N
o Chapter Description Ranking Review 1 Review 2
1. Introduction: Name of work, its status vis-à-vis master plan, core network,
priority, terrain, geography, climatic conditions, habitation(s)
served, population of the habitation(s) connected, population
(direct + indirect) served by the proposed road, land use,
predominant type of agriculture.

2. Planning and IT IS MANDATORY THAT THIS CHAPTER MUST


Basic Design INCLUDE THE COMPLETE PHOTOGRAPH RECORD
Considerations: OF THE ROAD AND ALL EXISTING FEATURES AND
DESCRIBE THE FOLLOWING ASPECTS IN DETAIL.
Key map including district and block road hierarchy,
through road or link road, potential for future through road,
traffic destinations (eg markets, block centre), potential
developments and future traffic generators. Preliminary
alignment investigation strip plan including constrictions on
ROW, obligatory points including existing features and fixed
obstacles, existing tracks, intersections, schools and
government buildings. Existing road alignment and proposed
road alignment. Consideration of alternative alignments,
alignment improvements, bypasses. Site photographs at
maximum 100m intervals and all points of interest. Road
design brief. Transect walk summary.

3. Topographic Temporary bench marks, centre line, cross sections, digital


Survey: terrain model, setting out, actual road land width available.
4. Soil and Materials Borrow area, quarry charts, availability of local materials,
Survey: subgrade testing, soil testing, test results.
5. Traffic Survey: IT IS MANDATORY THAT ALL OF THE
FOLLOWING ASPECTS (AS A MINIMUM) ARE
ASSESSED. Different
types of rural vehicles plying per day, network transport and
traffic impacts, base year traffic data of motorised and non-
motorised vehicles, consideration of through road potential,
consideration of specific traffic generators (eg rice mills, sand
mining), comparison with similar roads already in use, growth
rate adopted and projected traffic for the horizon year based
on the design life.

6. Hydrological Local drainage system plan for the area of the road, catchment
Survey: identification, data required for hydraulic design of cross
drainage works, agricultural irrigation crossings.
7. Geometric Roadway width, carriageway width, shoulders, design speed,
Design horizontal curves, vertical gradient, cross slopes, etc.
Standards:
8. Alignment Horizontal profile, vertical profile, cross sections, utilities and
Design: services, intersection layouts, road safety treatments. Existing
road alignment and proposed road alignment. Consideration of
alternative alignments, alignment improvements, bypasses.
9. Pavement Design life, design traffic and ESALs, subgrade CBR, design
Design: alternatives, embankment design, type of pavement, thickness
design, use of local materials, type of surfacing adopted, layer
wise design of the pavement along with a sketch of
dimensioned cross section indicating the pavement layers,
carriageway, roadway and road land width. Location of earth
shoulders and hard shoulders. Location of BT pavement and
CC pavement.

10. Design of Cross Types of culverts, submersible bridges, paved dips, high level
Drainage: structures, bridges, irrigation crossings, catchment and
discharge calculations, high flood level estimates and
justification for selection.
11. Protective Retaining walls, breast walls, check walls, stone pitching,
Works: turfing and planting.
12. Land Obtain existing village plans from the revenue authorities,
Acquisition: determine requirement for land acquisition, prepare plans
showing the land acquisition.
13. Utility ShiftingIT IS MANDATORY THAT A COST ESTIMATE FOR
& Relocation: RELOCATION OF UTILITIES IS PROVIDED.
Details of existing utilities and
details of new locations of utilities to be relocated, the
departments responsible for each utility, the rules pertaining to
the shifting/relocation of utilities and cost estimates for
relocation of utilities.
14. Road Safety and Details and locations of speed breakers, line markings and
Traffic edge lines, traffic advisory and warning signs, stone markers
Management: and guide posts. Audit the design at a stage when the major
conceptual and layout decisions have already been made.
Ensure that safety measures are incorporated into design,
especially when design is constrained, eg narrow carriageway
section, or speed needs to be controlled.

15. Specifications: Choice of technology, specifications adopted.


16. Environmental Reinstatement of borrow areas, erosion control, filling of
Issues: ponds, vegetation and tree removal, forest areas, wildlife,
antiquities, historic and religious sites, environmentally
sensitive areas, construcion camps, permits and clearances
required, etc.
17. Analysis of Derivation of rates for all different items making up the
Rates: designed works.
18. Cost Estimate: Estimate of quantities for all items of work, provision for
contingencies, provision for quality control, provision for
supervision, provision for logo and other road furniture, total
cost of the proposed road, bridges and drainage, cost of land
acquisition and cost per km for the same.
19. Construction Brief methodology statement describing construction activities
Program: and sequence, estimated duration of activities, estimated
overall time required for construction and analysis of impact
of monsoon season on construction period.

Sl.
No. Chapter Description Ranking Review 1 Review 2
1. Key Map: Showing the state in relation to India, district in relation to
state, and a district map showing all the blocks, with the
names of each block marked.
2. Block Road Showing the master plan and the core network and the
Map: proposed road.
3. Index Road Showing the full road to a suitable scale, topographical
Map: features like rivers, canals, streams, railway lines, villages,
market centres, other roads and legend. Alternative
alignments, alignment improvements, bypasses.
4. Plan and IT IS MANDATORY THAT ALL OF THE
Longitudinal FOLLOWING INFORMATION (AS A MINIMUM) IS
Sections: SHOWN ON THE DRAWINGS. Drawings
showing 1 km in each sheet with chainage, level information,
gradient details, horizontal and vertical curve details. Utilities
and services, intersection layouts, road safety treatments,
longitudinal drainage and drainage in built up (village) areas.
Existing road alignment and proposed road alignment.
Location of earth shoulders and hard shoulders. Location of
BT pavement and CC pavement. Obligatory points including
existing features and fixed obstacles (eg bridges, ponds,
temples, etc), existing tracks, intersections, schools and
government buildings. LARGE SCALE DRAWINGS
WHERE ALIGNMENT DEVIATES FROM EXISTING
CENTRELINE AND WHERE CLEARANCE IS TIGHT.

5. Typical Cross Drawings showing typical road cross sections, pavement


Sections: details including BT and CC, hard shoulder and soft shoulder,
batter slopes, longitudinal drainage. Typical cross sections in
built up village areas and typical sections in normal rural
areas.
6. Detailed Cross Drawings showing detailed cross sections with level
Sections: information, centre line offset details and so on.
7. Cross Drainage: Drawings of culverts, submersible bridges, paved dips and
high level bridges, giving general arrangement drawings
(GAD), structural details.
8. Protective Drawings of protective works like retaining walls, breast
Work: walls, check walls, drains.
9. Traffic and Drawings like kilometre stones, traffic signs, hazard signs,
Miscellaneous: advisory signs, speed breakers, line marking, stone markers,
guide posts, project sign boards.
Reviewed By Name:
Position:
Organisation: Total Score
Total Score
Date:

Junior Engineer Assistant Executive Engineer Executive Enginer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
Instructions and Notes
1. Complete the road details in the title block and the reviewer details in the Reviewed By block.

2. Review DPR Report chapter by chapter. Rank each as not included (0), poor standard (1), fair
standard (2) or good standard (3) in the ranking cell.

3. Review Drawings section by section. Rank each as not included (0), poor standard (1), fair
standard (2) or good standard (3) in the ranking cell.

4. DPR Report chapters 2, 5 and 18 and Drawing sections 2, 3, 4, 5, 6 and 7 are critical categories
and have higher weighting.

5. If mandatory information is not included (Report Chapters 2 & 5 and Drawing Section 4), score is
zero and DPR will not be approved.

6. Ranking less than (1), or less than (2) for critical categories, means the chapter/drawing cannot
be reviewed and the DPR will not be approved.

7. The outcome for each chapter and section will be automatically displayed. If it is CHECKED (cell
highlights green), the review continues.

8. All report chapters and drawing sections must achieve CHECKED status to proceed to check the
overall score.

9. If any report chapter or drawing section does not achieve CHECKED status, the DPR will not be
approved and the overall score will not be checked.

10. If the Total Score is not greater than 70%, the DPR will not be approved.

11. If the Total Score is greater than 70%, the decision will automatically be APPROVED (cell
highlights green).

12. Only when all review cells give result of CHECKED and APPROVED (all review cells highlighted
green) will the DPR be approved for issue.

To be assessed by PIU and score indicated

Also to be assessed by STA and score indicated

Also to be assessed by NRRDA and score indicated


PRADHANMANTRI GRAM SADAK YOJANA (PMGSY) Format-F-7

COST ESTIMATE FOR CONSTRUCTION OF MASONRY INFORMATORY SIGN BOARD

Name of the road: Nandighore to Saliajhari


Number of Structure 2 Nos. PACKAGE NO
District : Nayagarh

Type of soil : All kinds of soil Block : 0.00


Sl. Ht / Th Amount in
Description of item Nos. Length Width Unit Quantity Rate in Rs.
No in M Rs.
1 2 3 4 5 6 7 8 9 10
1. Earthwork in excavation for foundation of structures in all
types of soil as per drawing and technical specification
Clause 305 and 1104 of MoRD includding setting out,
construction of shoring and bracing, removal of stumps and
other deleterious material and disposal upto all lead & lift,
dressing of sides and bottom and back filling with excavated
suitable material upto 3mt. as per direction of Engineer-in-
Charge.

1 × 2.05 × 0.56 × 0.12 Cum 0.14 @ 272.07 38.09


11.4 Providing concrete for plain / reinforced concrete in open
foundation complete as per drawing and MORD technical
specification Clause 800,1100,1200 and as per direction of
Engineer-in-Charge.
1 × 2.05 × 0.56 × 0.10 Cum 0.11 @ 4900.00 539.00
9.3 Brick masonry work in cement mortar in foundation complete
excluding pointing and plastering as per drawing and
technical specifications Clauses 600, 1202 & 1203.
1 × 1.95 × 0.45 × 0.45 Cum 0.39
1 × 1.73 × 0.23 × 1.15 Cum 0.46
Cum 0.85
Deduct 1 × 1.50 × 0.075 × 0.90 Cum (-) 0.10
0.75 @ 5154.49 3865.87
11.4 Plastering with cement mortar (1:4), 15 mm thick on
brickwork in substructure as per technical specification
Clauses 613.4 & 1204

2× 1.95 × 0.450 Sqm 1.76


2× 0.45 × 0.450 Sqm 0.41
2× 1.95 × 0.115 Sqm 0.45
2x 0.45 0.115 Sqm 0.10
2× 1.73 × 1.150 Sqm 3.98
2× 0.23 × 1.150 Sqm 0.53
Projection 2× 1.50 × 0.075 Sqm 0.23
2× 0.90 × 0.075 Sqm 0.14
Total Sqm 7.60 @ 146.08 1110.21

14.1 Supplying of fitting & fixing of logo size 600×600mm for


PMGSY work made out of M.S. Angle 40×40×5mm with CR
sheet etc. complete.

i) M.S. Angle 1.15 @ 3kg/Mtr 3.45 Kg 42.00 144.90


ii) Plate (area) 0.6 × 0.6 = 0.36 @ 30kg/sqm 10.80 Kg 42.00 453.60
Add 3% of cost of angle& plate towords cost of fabrication,
Drilling, Nuts,Bolts etc. 0.43 Kg 42.00 17.96
iii) Painting two coats including prime coat with epoxy paint of
approved brand on concrete/steel surfaces after through
cleaning of surface to give an even shade as per drawing
and Technical Specification Clause 1701 of MORD. 2 x 1.70 x 1.15 = 3.91
2 x 0.60 x 0.60 = 0.72
Total 4.63 @ 84.88 392.99
iv) Printing new letter and figures of any shade with synthetic
enamel paint black or any other approved colour to give an
even shade as per drawings and Technical Specification
Clause 1701.
Assuming total 200 nos. of letters × 6cm thick average 200 × 6 = 1200.00 Cm
Total 1200.00 Cm 0.91 1092.00
Rs. 7654.62
Cost for Masonry Signboard 2 x 7654.62 Rs. 15309.24
Junior Engineer Assistant Executive Engineer Executive Enginer
R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh
RURAL DEVELOPMENT DEPARTMENT

DETAILED ESTIMATE
FOR
IMPROVEMENT TO ROAD & CD WORK UNDER PMGSY

OFFICE OF THE EXECUTIVE ENGINEER


R.W.Division, NAYAGARH
DIST-NAYAGARH, ODISHA.

NAME OF THE ROAD:- Nandighore to Saliajhari

PACKAGE NO OR-23-265

VOLUME - I
ESTIMATED COST:-
Part-I - Rs. 231.57 LAKHS
Part-II - Rs. 18.09 LAKHS
Add GST- RS. 29.96 LAKHS
Total AMOUNT:-Rs. 279.62 LAKHS

Prepared By :
ASIAN GEOTECH RESEARCH SERVICES
PlOT NO-4704/5004,ADIMATA COLONY,NEAR SAINIK SCHOOL,BHUBANESWAR-17
GENERAL ABSTRACT

PART - I (ROAD)

1. Nandighore to Saliajhari Rs. 231.57

Total cost of Part - I = Rs. 231.57

PART - II (MAINTENANCE)

1. Nandighore to Saliajhari Rs. 18.09

Total cost of Part - II = Rs. 18.09

Total cost of Estimate(Part-I+Part- II) Rs. 249.66

Junior Engineer Assistant Executive Engineer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh

Executive Enginer Superintending Engineer


R.W.Division, Nayagarh Central Circle,

Chief Engineer
Rural Works -I, Odisha
Bhubaneswar
ABSTRACT
PACKAGE NO OR-23-265
Name of the Road :- Nandighore to Saliajhari
Total Length of Road (m) :- 6000 M
Length of Flexible Pavement (m) :- 2540 M District :- Nayagarh
Length of Rigid Pavement(m) :- 3460 M Block : Odagaon

PART - I (ROAD)
1. Road Work
i). Upto BT surface from 1/040 to 2/340,2/770 to 3/270, 4/050 to 4/590,5/800 2540 Mtrs. Rs. 8723755.23
to 6/000
0/000 to 1/040,2/340 to 2/770,3/270 to 4/050,4/590
ii). Concrete Road to 5/800 3460 Mtrs. Rs. 10948538.34

iv). Retaning Wall 460 Mtrs. Rs. 2570530.10

Rs. 22242823.67

2. Cross-Drainage Structures
i). 1000mm dia Single Row At RD-4/857,5/338,5/618,,,,, 2 Nos Rs. 368854.08
Total Nos. of C.D 2 Nos Rs. 368854.08

3. Miscellenious Cost Rs. 348214.00


4 contigency 197246.00
Total cost of Part - I = Rs. 23157137.75

PART - II (MAINTENANCE)
5 Maintenance of Road for five years
i). 1st Year 6 km 43069.86 Rs. 258419.16
ii). 2nd Year 6 km 51683.84 Rs. 310103.04
iii). 3rd Year 6 km 60297.81 Rs. 361786.86
iv). 4th Year 6 km 68911.78 Rs. 413470.68
v). 5th Year 6 km 77525.75 Rs. 465154.50

Total cost of Part - II = Rs. 1808934.24

Total cost (Part -I & part-II) Rs. 24966071.99


ADD GST 12 % Rs. 2995928.64

Total cost of Estimate Rs. 27962000.63

vi). 6th year Rs.


Total cost of Estimate Rs. 27962000.00
Or, Say Rs. 279.62 Lakhs

Junior Engineer Assistant Executive Engineer Executive Enginer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh
BILL OF QUANTITY
THE YEAR 2016-17 UNDER NAYAGARH DISTRICT

Tender inviting Authority - Chief Engineer , Rural Works-II,Odisha,Bhubaneswer

Name of the Work:-NANDIGHOR TO SALIAJHARI

Package No. - OR-23-265


Bidder Name:
(Rate &
Estimated Rate Amount are in
Rs.)
Sl. Amount
No. Items Quantity Unit Figure Words

1
Scarifying the existing bituminous road surface to a depth of
150mm (By Mechanical means) and disposal of scarified
material with a lift upto 3m and lead upto 1000m as per
technical specification clause 301.4 of MoRD & as per
direction of the Engineer-in-Charge.
Considering 70% area 5334.00 Sqm 6.70 35737.80
2
Dismantling of existing structures like culverts, bridges,
retaining walls and other structure comprising of masonry,
cement concrete, wood work, steel work, including T&P and
scaffolding wherever necessary, sorting the dismantled material,
6.75 Cum 390.48 2635.74
disposal of unserviceable material and stacking the serviceable
material with all lifts and lead as per Technical Specification
Clause 202 of MoRD by manual means & as per direction of the
Engineer-in-Charge.

Clearing grass and removal of rubbish up to a distance of 30 m


outside the periphery of the area as per Technical Specification
24000.00 Sqm 1.36 32640.00
Clause 201 of MoRD by Manual means & as per direction of
the Engineer-in-Charge.

3
Construction of embankment with approved material obtained
from borrow pits and transporting to site with all lifts & leads,
spreading, grading to required slope and compacting to meet
12389.31 Cum 192.04 2379243.09
requirement of Tables 300.1 and 300.2 as per Technical
Specification Clause 301.5 of MoRD & as per direction of the
Engineer-in-Charge.

4
Construction of embankment with approved materials deposited
at site from roadway cutting / excavation of foundation of CD
sturctures, retaining walls, drain etc. by mechanical means
1110.42 cum 28.44 31580.34
graded and compacted to meet requirement of Tables 300.1 and
300.2 as per Technical Specification Clause 301.5 & MORD
clause 301.5 as directed by Engineer in charge.

9
Earthwork in excavation for foundation of structures in all
types of soil as per drawing and technical specification Clause
305 and 1104 of MoRD includding setting out, construction of
shoring and bracing, removal of stumps and other deleterious 666.75 cum 272.07 181402.67
material and disposal upto all lead & lift, dressing of sides and
bottom and back filling with excavated suitable material upto
3mt. as per direction of Engineer-in-Charge.

10
Construction of Granular sub-base by providing well graded
material of moorum and sand admixture to required proportion,
spreading in uniform layers with grader on prepared surface,
mixing by mix in place method if required with rotavator to
1428.56 cum 680.34 971906.51
achieve P.I value less than 6 and compacting at OMC with
smooth wheel roller to achieve the the desired density complete
as per technical specification clause 401 of MoRD for rural
roads and as per direction of Engineer-in-Charge.
Sl. Amount
No. Items Quantity Unit Figure Words

12
Providing, laying, spreading and compacting stone aggregates
of specific sizes to water bound macadam specification
including spreading in uniform thickness, hand packing, rolling
with smooth wheel roller 80-100 kN in stages to proper grade
and camber, applying and brooming, stone screening to fill-up
the interstices of coarse aggregate, watering and compacting to
the required density as per Technical Specification Clause 405
of MoRD by mechanical means and as per direction of the
Engineer-in-Charge.

a.
Grading No. -II (63-45mm size) with crusable screening like
145.74 Cum 2917.56 425205.19
moorum and sand admixure

b. Grading No. -III (53-22.4 mm size) with crusable screening


764.39 Cum 2844.90 2174613.11
like moorum and sand admixure
13

Providing and applying primer coat with bitumen emulsion (SS)


on prepared surface of granular base including cleaning of road
surface and spraying primer at the rate of 0.70-1.0 kg/sqm using 9715.50 Sqm 30.23 293699.57
mechanical means as per Technical Specification Clause 502 of
MoRD and as per direction of the Engineer-in-Charge.

14

Providing and applying tack coat with Bitumen emulsion (RS)


using emulsion distributor at the rate of 0.25 to 0.30 kg per sqm
on the prepared bituminous primed surfaces cleaned with 9715.50 Sqm 10.50 102012.75
Hydraulic broom as per Technical Specification Clause 503 of
MoRD & as per direction of the Engineer-in-Charge.

15

Providing, laying and rolling of open-graded premix carpet of


20 mm thickness composed of 13.2 mm to 5.6 mm aggregates
using VG-30 grade bitumen to required line, grade and level to
serve as wearing course on a previously prepared base,
including mixing in a suitable plant, laying and rolling with a 9715.50 Sqm 141.80 1377657.90
three wheel 80-100 kN static roller capacity, finished to
required level and grades to be followed by seal coat of Type C
as per Technical Specification Clause 508 of MoRD & as per
direction of the Engineer-in-Charge.

13. Providing and laying seal coat sealing the voids in a bituminous
surface laid to the specified levels, grade and cross fall using
Type C as per Technical Specification Clause 510 of MORD 9715.50 Sqm 51.07 496170.59
with VG-30 grade bitumen & as per direction of the Engineer-
in-Charge.
Sl. Amount
No. Items Quantity Unit Figure Words

16

Construction of un-reinforced, plain cement concrete pavement,


thickness as per design, over a prepared sub base, with 43 grade
cement or any other type as per Clause 1501.2.2 M30 (Grade),
coarse and fine aggregates conforming to IS:383, maximum size
of coarse aggregate not exceeding 25 mm, mixed in a concrete
mixer of not less than 0.2 cum capacity using approved mix
design, laid in approved fixed side formwork (steel channel,
laying and fixing of 125 micron thick polythene film, wedges,
steel plates including levelling the formwork as per drawing),
1505.10 Cum 5749.95 8654249.75
spreading the concrete with shovels, rakes, compacted using
needle, screed and plate vibrators and finished in continuous
operation including provision of contraction and expansion,
construction joints, applying debonding strips, primer, sealant,
dowel bars, near approaches to bridge/culvert and construction
joints, admixtures as approved, curing of concrete slabs for 14-
days, curing compound (where specified) and water finishing to
lines and grade as per drawing and technical specification as
per clause 1501and direction of Engineer in Charge.

17
Earthwork in excavation of foundation of structures upto 3 m
depth in ordinary soil as per drawing and technical specification
Clause 305.1(11.1) includding setting out, construction of
shoring and bracing, removal of stumps and other deleterious 1246.03 Cum 272.07 339007.38
material and disposal upto a lead of 50m, dressing of sides and
bottom and backfilling with approved material and as per
direction of the Engineer-in-Charge.

18 Filling in Foundation trenches with sand as per Drawing &


Technical Specification clause 305.3.9 of MoRD & as per 420.89 Cum 1118.71 470853.85
direction of Engineer-in-Charge.

Providing concrete for plain / reinforced concrete in open


foundation complete as per drawing and MORD technical
specification Clause 800,1100,1200 and as per direction of
Engineer-in-Charge.P.C.C grade M 10
19 3.66 cum 4812.46 17613.60
P.C.C grade M 10
P.C.C grade M 15 Nominal mix (1:2.5:5) 310.20 Cum 4629.17 1435968.53

M15 Plain/reinforced cement concrete in sub-structure


complete as per drawings and MORD technical specification 449.94 Cum 4889.19 2199842.15
Clauses 800,1200 and as per direction of the Engineer in charge

21

Filling berms with Gravel including cost, conveyance,royality


1297.50 cum 499.99 648737.03
etc complete as per direction of EIC.

28
Providing and laying reinforced cement concrete NP3 pipe for
culverts jointing with cement mortar 1:2 but excluding
excavation, protection works, backfilling, concrete and masonry
works in head walls and parapets as per Clause 1100 of MoRD
& as per direction of Engineer-in-Charge.

iii 1000 mm dia Single row 15.00 Rmt 6453.77 96806.55

Providing and laying of Type-B(first class) bedding for laying


of Hume Pipe on well compacted moorum or approved granular
29 0.00 Cum 471.32 0.00
material as per MORD Technical Specification clause 1105(ii)
and as per direction of the engineer-in-charge.
Sl. Amount
No. Items Quantity Unit Figure Words

30
Providing weepholes in brick masonry/stone masonry,
plain/reinforced concrete abutment, wing wall, return wall with
100 mm dia AC pipe extending through the full width of the 184 Nos. 135.02 24843.68
structures with slope of 1(V):20(H) towards drawing face
complete as per drawing

31

Providing and fixing of typical masonry PMGSY


informatory sign board with Logo as per MORD
specifications and drawing. Brick masonry board with writting
area 1.5mx0.9m and 0.115m border. All M.S. will be stove
enameled on both sides. Lettering and printing arrows, border
etc. will be painted with ready mixed synthetic enamel paint of 2 No 8656.90 17313.80
superior quality in required shade and colour. All sections of
framed posts and steel tube will be painted with primer and two
coats of epoxy paint as per drawing Clause 1701 and Annexure
1700.1 of MoRD etc. complete and as per direction of the
Engineer -in- charge.

32

Providing and fixing of typical OMBADC citizen information


board as per MORD specifications and drawing. Three MS
Plates of 50x5mm mm thick, back plate duly welded with
75mm dia steel tubes back on edges as per drawings. The upper
& lower plate will be welded with MS flat iron frame of
50mmx5mm. The steel tubes duly embedded in cement concrete
M-15 grade blocks of 600mm x 600mm x 750mm below ground 3 No 12777.33 38331.99
level.All M.S. will be stove enameled on both sides. Lettering
and printing arrows, border etc. will be painted with ready
mixed synthetic enamel paint of superior quality in required
shade and colour. All sections of framed posts and steel tube
will be painted with primer and two coats of epoxy paint as per
drawing Clause 1701 and Annexture 1700.1.

33

Providing and fixing of semi reflective cautionary, mandatory


and informatory sign board as per IRC:67 made of 2 mm thick
MS Sheet duly stove white colour in front and gray colour on
back with red reflective border of 65 mm width and required
letters and figures with reflective tape engineering grade as per
Clause 1701.3.9 of MORD for Rural Roads of required shade
2 No 1968.58 3937.16
and colour supported and welded on 47mm x 47 mm x 12 SWG
sheet tube firmly fixed to the ground by mean of properly
designed foundations with M-15 grade cement concrete
450x450x600 mm, 600 mm below ground level as per approved
drawing Clause 300,800,1700 as per direction of the Engineer in
charge.(600 mm square)

34

Providing and fixing of semi reflective cautionary, mandatory


and informatory sign board as per IRC:67 made of 1.5 mm thick
MS Sheet duly stove white colour in front and gray colour on
back with red reflective border of 65 mm width and required
letters and figures with reflective tape engineering grade as per
Clause 1701.3.9 of MORD for Rural Roads of required shade
and colour supported and welded on 47mm x 47 mm x 12 SWG
sheet tube firmly fixed to the ground by mean of properly
designed foundations with M-15 grade cement concrete
450x450x600 mm, 600 mm below ground level as per approved
drawing Clause 300,800,1700 as per direction of the Engineer in
charge.(600 mm square)

i) 900mm equilateral triangle ( turn & reduced carriage way ) 10 NO 1638.31 16383.10

iii) 600x450 mm square ( school & padestrians ) 10 NO 1608.40 16084.00


Sl. Amount
No. Items Quantity Unit Figure Words

iv)600 mm dia circular ( hurn prohibited speed limit , side


10 NO 1613.26 16132.60
road & sound hurn)
ii Guide post 130 Nos. 628.74 81736.20
35
Reinforced cement concrete M15 grade Kilomitre stoneof
Standard design as per IRC:8 fixing in position including
painting, lettering in accordance with the specifications Clause
1703 of MoRD . etc. complete and as per direction of the
Engineer -in- charge.

i Fixing of Km. Stone 1 No 3156.85 3156.85

ii Fixing or 200m Stone 24 No 526.87 12644.88

iii Fixing Ordinary Kilometer stone 7 No 1932.77 13529.39

Total Road Proper 22611677.76


36 Routine Maintenance after completion of construction works for 1st 6.00 Km 258419.16 258419.16
Year
37 Routine Maintenance after completion of construction works for 2nd 6.00 Km 310103.04
Year 310103.04
38 Routine Maintenance after completion of construction works for 3rd 6.00 Km 361786.86 361786.86
Year
39 Routine Maintenance after completion of construction works for 4th 6.00 Km 17227.95 413470.68
Year
40 Routine Maintenance after completion of construction works for 5th 6.00 Km 19381.44 465154.50
Year
Total Maintenance:= 1808934.24
Total in Figures Grand Total:= 24420612.00

Total in Figures(Says) Or say:= 24420612.00

Total in Words

Executive Engineer
Rural Works Division,Nayagarh
ABSTRACT
Name of the Road :- Nandighore to Saliajhari
Total Length of Road (m) :- 6000 M
Length of Flexible Pavement (m) :- 2540 M District :- Nayagarh
Length of Rigid Pavement(m) :- 3460 M Block : Odagaon

PART - I (ROAD)
1. Road Work
i). Upto BT surface from 1/040 to 2/340,2/770 to 3/270, 4/050 to 4/590,5/800 2540 Mtrs. Rs. 9770605.86
to 6/000
0/000 to 1/040,2/340 to 2/770,3/270 to 4/050,4/590
ii). Concrete Road to 5/800 3460 Mtrs. Rs. 12262362.94

iv). Retaning Wall 4/700 TO 4/900 460 Mtrs. Rs. 2878993.71

2/350 TO 2/450,3/344 to 3/544,4/590 TO 4/690


vi). Cement Cooncrete Drain 0 Mtrs. Rs. 0.00

Rs. 24911962.51

2. Cross-Drainage Structures
i). 1000mm dia Single Row At RD-4/857,5/338,5/618,,,,, 2 Nos Rs. 413116.57
Total Nos. of C.D 2 Nos Rs. 413116.57

3. Miscellenious Cost Rs. 389999.68


Total cost of Part - I = Rs. 25715078.76

PART - II (MAINTENANCE)
5. Maintenance of Road for five years
i). 1st Year Rs. 262893.49
ii). 2nd Year Rs. 322914.35
iii). 3rd Year Rs. 380164.24
iv). 4th Year Rs. 642185.34
v). 5th Year Rs. 862469.99

Total cost of Part - II = Rs. 2470627.41

Total cost (Part -I & part-II) Rs. 28185706.17

vi). 6th year Rs. 3381958.84


Total cost of Estimate Rs. 31567665.01
Or, Say Rs. 315.68 Lakhs

Junior Engineer Assistant Executive Engineer Executive Enginer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh
PROFORMA- B

Package Summary
overhead charges 15%
PACKAGE NO OR-23-265 State:-ODISHA . District:- Nayagarh Cost Rs. In Lakh
No. of Cost of
Type of Proposed Cost of
Name of the Road CD Cost of CD works Protection Misc. Total estimated cost Average cost per Km.
Sl. Name of the proposal length pavement Works
works
No. Block
Rs Rs.
From To *N/U Km Rs. Nos. Rs. Rs. Rs.
Constn. Maintaince Constn. Maintaince

1. Odagaon Nandighore Saliajhari U 6.000 220.33 2 4.13 28.79 3.90 257.15 20.26 42.86 3.38
TOTAL 6.000 220.33 2 4.13 28.79 3.90 257.15 20.26 42.86 3.38

No. of Cost of
Type of Proposed Cost of
Name of the Road CD Cost of CD works Protection Misc. Total estimated cost Average cost per Km.
Sl. Name of the proposal length pavement Works
works
No. Block
Rs Rs.
From To *N/U Km Rs. Nos. Rs. Rs. Rs.
Constn. Maintaince Constn. Maintaince

1. 2540 Nandighore Saliajhari U 6.000 215.55 2 4.04 28.17 3.82 251.57 19.82 41.93 3.30
TOTAL 6.000 215.55 2 4.04 28.17 3.82 251.57 19.82 41.93 3.30
DIFFERENECE 5.58 0.44
Total Estimated cost of the package : Rs. 277.41 Lakhs
*N-New connectivity *U-Upgradation (UG)

Prepared by:- Signature


Name

Designation Assistant Executive Engineer


R.W.Sub-Division, Nayagarh

Checked by:- Signature


Name
Designation Excutive Engineer(P.I.U)
R.W.Division, Nayagarh

Scrutinised by:- Signature


Name
Designation Superintending Engineer
Central Circle,
PROFORMA- C
PMGSY
CHECK LIST FOR P.I.U. & S.T.A.
(For Individual Road Works)
To be filled by PIU
1. Location:- State :- Odisha District :- Nayagarh Block :- Odagaon
2. PACKAGE NO OR-23-265
3. Name of the Road : From :- Nandighore to Saliajhari
4. Length (Km): Total: 6.000 Km In Built up area :- 3.46 Km In Open Area :- 2.540 Km
5. Estimated Cost Rs. 231.57 Lakhs Average Cost 38.60 Lakhs
Item Total cost in Rs. Cost per Km in Lakh

Flexible Pavement 9770605.86 38.47


Rigid pavement 12262362.94 35.44
Protection Works 2878993.71 4.80
CD Works 413116.57 0.69
Others 389999.68 0.65
Total 25715078.76 42.86
6. Type of Proposal:- New Connectivity/Up gradation:- UG
* If the proposed road is a New connectivity NO
- Is the road a part core network.
- If Yes, Through / Link Rout Number T-01
- Name of the unconnected Target Habitation(s)(to be cross checked withCN-6)
-list of Habitations connected enroute

- Population sub served by the proposed road


- Does the Proposed Road lead up to the Habitation for which it is supposed to provide connectivity (In
other words are you sure that the road is not being made partially ?) Yes
-   Does the Proposed Road connect the unconnected Habitation to
(A).    Another Habitation having All-weather road (A) (B)
(B).    Directly to an All weather road.
If (B), indicate the nature of road to which the proposed road leads. RR MDR SH NH
* If the proposal is for up gradation Yes
- Is the road a part of core net work
- Is it associated Through Route or not Yes(T 01)
- PCI Value 1
- Age of the Road 20 Years
Habitation
Benefitted- Nandighara,Goudaputa,Bandhasahi,SALIAJHARI,Tikarpali6873,,,,, 6873

7. a). Whether the Proposed Road has the desired carriage way with, Roadway width and
Road Land Width (RLW). YES / NO
b). Indicate the actual widths of the following for the Proposed road. In the Built Up Area(m) In the open Area (m)

a). Carriageway 3.75 3.75


b). Roadway 7.50 7.50
8. Base year traffic volume 10500MM
Existing Road
Month & Year of Traffic volume OCT 2018
Count= Motorised Traffic Non Motorised Traffic
Days Cars/Vans/ Two Mini bus / Trucks Agricultural Buses Cycle Cycle Animal drawn Vehicle
jeeps/ wheelers Pick up / Tractors , Rickshaw
Three Vans Trallers
wheelers
L U OL L U OL L U OL SWC Num. Tyred
Day 1 18 79 13 14 14 0 14 13 0 0 0 0 120 14 0 0

Day 2 18 113 6 12 18 0 13 16 0 0 0 0 144 10 0 0


Day 3 18 119 16 16 15 0 16 12 0 0 0 0 116 14 0 0
Average 18 104 12 14 16 0 14 14 0 0 0 0 127 13 0 0
Before opening of road to traffic AADT i.e. after 1 year
FIELD DATA SHEET FOR TRAFFIC CENSUS
Annexure 5.3(a)
Name of Road : Nandighore to Saliajhari

9See Para 5.6)


Location of Road : 6.000 Km Date:- 27/10/2018

District : Nayagarh

State : Odisha
Vehicle Class
Cars,Jeeps Motorised Mini bus / Trucks Agricultural Tractors- Trailers Buses Cycles Cycle Animal Drawn Remarks Season:Post Harvest /
Hour Three two- Pick up / Rickshaw Vehicle Monsoon Weather:
wheelers wheelers Vans
Laden Unladen Over Laden Unladen Over Laden Unladen Over SWC Num.Tyred
Loaded Loaded Loaded
From 5.00Hrs.
To 9.00 Hrs. 4 21 2 3 3 0 3 3 0 0 0 0 31 3 0 0

From 9.00 Hrs.


To 13.00Hrs. 5 19 3 4 4 0 4 4 0 0 0 0 27 4 0 0

From 13.00 Hrs.


Post Harvest
To 17.00Hrs. 4 18 4 4 3 0 4 4 0 0 0 0 41 3 0 0

From 17.00Hrs.
To 21.00 Hrs. 5 21 4 3 4 0 3 2 0 0 0 0 21 4 0 0

Total for day 18 79 13 14 14 0 14 13 0 0 0 0 120 14 0 0

Junior Engineer Assistant Executive Engineer Executive Enginer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh
FIELD DATA SHEET FOR TRAFFIC CENSUS
Annexure 5.3(a)
Name of Road : Nandighore to Saliajhari

9See Para 5.6)


Location of Road : 6.000 Km Date:- 28/10/2018

District : Nayagarh

State : Odisha
Vehicle Class
Cars,Jeeps Motorised Mini bus / Trucks Agricultural Tractors- Trailers Buses Cycles Cycle Animal Drawn Remarks Season:Post Harvest /
Hour Three two- Pick up / Rickshaw Vehicle Monsoon Weather:
wheelers wheelers Vans
Laden Unladen Over Laden Unladen Over Laden Unladen Over SWC Num.Tyred
Loaded Loaded Loaded
From 5.00Hrs.
To 9.00 Hrs. 4 21 2 2 4 0 2 3 0 0 0 0 38 2 0 0

From 9.00 Hrs.


To 13.00Hrs. 5 32 3 3 5 0 3 4 0 0 0 0 32 3 0 0

From 13.00 Hrs.


Post Harvest
To 17.00Hrs. 4 23 4 3 5 0 4 5 0 0 0 0 43 2 0 0

From 17.00Hrs.
To 21.00 Hrs. 5 37 3 4 4 0 4 4 0 0 0 0 31 3 0 0

Total for day 18 113 12 12 18 0 13 16 0 0 0 0 144 10 0 0

Junior Engineer Assistant Executive Engineer Executive Enginer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh
FIELD DATA SHEET FOR TRAFFIC CENSUS
Annexure 5.3(a)
Name of Road : Nandighore to Saliajhari

9See Para 5.6)


Location of Road : 6.000 Km Date:- 29/10/2018

District : Nayagarh

State : Odisha
Vehicle Class
Cars,Jeeps Motorised Mini bus / Trucks Agricultural Tractors- Trailers Buses Cycles Cycle Animal Drawn Remarks Season:Post Harvest /
Three two- Pick up / Rickshaw Vehicle Monsoon Weather:
Hour wheelers wheelers Vans
Laden Unladen Over Laden Unladen Over Laden Unladen Over SWC Num.Tyred
Loaded Loaded Loaded
From 5.00Hrs.
To 9.00 Hrs. 5 26 3 3 2 0 3 2 0 0 0 0 25 3 0 0

From 9.00 Hrs.


To 13.00Hrs. 4 28 4 4 4 0 4 3 0 0 0 0 23 3 0 0

From 13.00 Hrs.


Post Harvest
To 17.00Hrs. 5 37 5 4 5 0 4 3 0 0 0 0 42 4 0 0

From 17.00Hrs.
To 21.00 Hrs. 4 28 4 5 4 0 5 4 0 0 0 0 26 4 0 0

Total for day 18 119 16 16 15 0 16 12 0 0 0 0 116 14 0 0

Junior Engineer Assistant Executive Engineer Executive Enginer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh
SUMMARY OF 3 DAY COUNTS
Name of Road : Nandighore to Saliajhari
Location of Road: 6.000 Km
District : Nayagarh
State : Odisha
Vehicle Class
Car, Jeeps, Motorised Pick up Trucks Agricultural Tractors- Trailers Buses Cycles Cycle Animal Drawn Vehicles Total
Day Three- two- Vans Rickshaw (SWC)
Wheelers wheelers
Laden Unladen O-loaded Laden Unladen O-loaded Laden Unladen O-loaded SWC Num.Tyred
Day 1 18 79 13 14 14 0 14 13 0 0 0 0 120 14 0 0 299
Day 2 18 113 6 12 18 0 13 16 0 0 0 0 144 10 0 0 350
Day 3 18 119 16 16 15 0 16 12 0 0 0 0 116 14 0 0 342
Total: 54 311 35 42 47 0 43 41 0 0 0 0 380 38 0 0 991
Average Daily
Traffic
18 104 12 14 16 0 14 14 0 0 0 0 127 13 0 0 330

ADT Total (T)= 330


No of harvesting season (a ) = 1
No of times traffic in peak period than in lean period n1 1 n2 0
Value of t (assumed in days) = t1 75 t2 0
Design Traffic AADT =T+(0.6 n a T t )/365 = 371
Corrected AADT for Solid Wheeled Cart = 371 1.00 371
Before opening of road to traffic AADT i.e. after 1 year (2nd
year) @6% growth rate = 417

Accordingly Laden Heavy Commercial Vehicles = 18 Laden Medium Commercial Vehicles = 18


Unladen Heavy Commercial Vehicles = 20 Unladen Medium Commercial Vehicles = 18
Overloaded Heavy Commercial Vehicles = 0 Overloaded Medium Commercial Vehicles = 0
CVPD for Design ( taking the traffic at the time of opening) = 74
Cumulative ESAL applications per day as per V.D.F. values in para 3.4.4 of SP-72-2015 Values of V.D.F.
Laden HCV = 51.48 Vehicle Laden Unladen O-Loaded
Unladen HCV = 6.20 HCV 2.86 0.31
Overloaded HCV = 0.00 MCV 0.34 0.02
Laden MCV = 6.12
Unladen MCV = 0.36
Overloaded MCV = 0.00
Total (T0) =64.16
Cumulative ESAL applications over 10 year @6% growth rate = T0 x 4811 X L (ESAL)= 308674

Junior Engineer Assistant Executive Engineer Executive Enginer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh
TRAFFIC ESTIMATE
Name of the Road:- Nandighore to Saliajhari
Package No.:-
A). DESCRIPTION:
Traffic count was conducted from dt. 27/10/2018 to dt 29/10/2018 on Nandighore to Saliajhari Road
and it is expected that on completion of the proposed road the same traffic will operate.

There is only one harvesting period in a year for which the post harvest traffic occurs only once a year. Which is normaly a
post harvest traffic period in a year .
It is informed by the local people that the lean traffic during non harvesting season will be about half of that in post harvest
traffic. Also it was known locally that the post harvest traffic period last for about 75 days in a year in which it takes about 20% of time to
built from lean to peak and then rremain at its peak for 20% of time and then recedes to lean traffic again in 20% of post harvest traffic
period.
The Traffic Survey yielded the following results for the Average Daily Traffic.
Car, Jeep, Van, Three Wheelers = 18
Motorised two Wheelers = 104
Pick up / Vans = 12
Trucks = 30 L UL OL
Agricultural tractors/ Trailers = 28 MCV 14 14 0
Buses = 0 HCV 14 16 0
Cycles = 127
Cycle Riksaw = 13
Animal Drawn Vehicles = 0
(Motorised and Non-Motorised/day) = 331
B). TRAFFIC (ESAL) CALCULATIONS:
Computation of the Design Traffic Parameter
Average daily traffic = 331
From the above T = Average daily traffic in lean season = 330
Post harvest traffic period factor
Durarion of peak period (t1) = 75 days t2 = 0 days
No of times traffic in peak period than in lean period n1 = 1 n2 = 0
(0.6 n1 x T x t1) +(0.6n2 x T x t2)
AADT = T + = 371
365
Before opening of road to traffic AADT after 1 year (cosidering construction period as 1 year) ,
assuming initial growth rate @6% AADT = 371
(1.06)2 417
From the above traffic count data, the proprtions of HCV and MCV out of the AADT work out as under
14
Laden HCV (Truck & Bus) = 417 18
330
16
Un-Laden HCV (Truck & Bus) = 417 20
330
0
Over Loaded HCV (Truck & Bus) = 417 0
330
14
Laden MCV (Mini Bus /Tractor) = 417 18
330
14
Un-Laden MCV (Mini Bus/ Tractor) = 417 18
330
0
Over Loaded MCV (Mini Bus / Tractoar) = 417 0
330
Taking VDF value as per para 3.4.4 of IRC-SP-72, the ESAL application per day
To= 18 2.86 20 0.31 0 0 18 0.34 18 0.02
0 = 0 64.16
Assuming a uniform traffic growth rate of 6% over 10 years cumulative ESAL applications(N)over the design life will be as
per the formula (as per IRC SP-72)
To x 365 x (1+0.01 r)n x L
N =
0.01 r
Where To = ESAL per day = number of commercial vehicles per day in year of opening X VDF, and L= lane distribution factor, L=1 for
single lane/ intermidiate lane

= To x 4811 x L = 308674
Hence it comes under traffic category T 6 of IRC, SP-72, 2015
C). SUBGRADE STRENGTH EVALUATION:
The properties of subgraded soil given by Asian Geatech Research Services is attached.
It was observed from the field and also local inquary that the ground water table at various points on proposed road during or just after
rainy season was about 1.8 mtr from normal ground surface.

Shallowest water table from road surface 1.80 1.00 2.80 mtr.
PI value = 21%
Maximum rain fall of the area (collected from block office) = 1535.00 mm
As water table will within 3m of road surface and the soil is clayey type (CI), with P.I. Value= 21% (i.e. between 0 to 20%)
4 days soaked C.B.R. is considered.
Soaked CBR (4days) of subgrade in %= 0.00 0.00 0.00
Hence design CBR = 3.0% to 4.0 %
D). PAVEMENT DESIGN:
Design ESAL = 308674 T6 Category as per IRC, SP-72-2015 )
Sub-grade strength = 3.0% to 4.0 %
Design Catalogues as (given in IRC-SP-72) pavement crust is provided as follows:
Pavement crust required = 325mm
Design crust to be provided = 325mm

As per Pavement design Catalogues

75 mm Bituminous surface treated WBM Grade III

75 mm WBM GradeIII

175 mm Granular Subbase

Total reqd. = 325 MM

As annual rainfal is 1535.00 mm, 20mm thick P.M.C. with 6mm thick seal coat surfacing has been provided.

Junior Engineer Assistant Executive Engineer Executive Enginer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh
COST ESTIMATE FOR CONSTRUCTION OF ROAD (bt Road)
Name of the Road :- Nandighore to Saliajhari
Total Length of Road : (m) 6000 M 1/040 to 2/340,2/770 to
Length of Flexible Pavement (m) :- 2540 M 3/270, 4/050 to 4/590,5/800 District : Nayagarh
to 6/000
M Block :
Length of New Flexible Pavement (m) :- 2540
Sr. Claus
Description of Items Nos L(m) B(m) D(m) Unit Quantity Rate Amount
No. e No.
1 2 3 4 5 6 7 8 9 10 11
2.0 SITE CLEARANCE
Scarifying Existing Bituminous Surface to a Depth of 150 mm by
Mechanical Means and disposal of scarified material with a lift upto 3 m
and lead upto 1000 m as per Technical Specification Clause 301.4.

BT Damaged Area 70% 2540.0 3.000 Sqm 5334.00 6.70 35737.80


2.1 201 Clearing grass and remocval of rubbish up to a
distance of 30m outside the periphry of the area as
per technical specification 2 6000.0 2.000 Sqm 24000.00 1.36 32640.00

2.5 202 Dismantling of existing structures like culverts, bridges, retaining walls
and other sturcture comprising of masonry, cement concrete wood work,
steel work, including T&P and scaffolding wherever necessary, sorting
the dismantled material, disposal of unserviceable materials and
stacking the serviceable materials with all lifts and lead of 1000m as per
Technical Specification Clause 202

1 7.5 3.000 0.300 Cum 6.75 390.48 2635.74


3.0 EARTHWORK
State Construction of embankment with approved material obtained from
S/R borrow pits with all lead and lift, transporting to site, spreading, grading
to required slope and compacting to meet requirement as per MoRD
Rural roads Specification Clause 301as per the direction of Engineer in
charge by manual means.

As per calculation Sheet attached Cum 17997.00

DEDUCTION
i). Granular Sub-base Cum 1428.56
ii). Quantity of Earth work reused from exacavation
(70% of culverts) Cum 45.89
iii). Quantity of Earth work from roadway cutting 100%
Cum 666.75
iii). Quantity of Earth work reused from exacavation
(70% of Retaining Wall, Toe Wall & Drain)
Cum 270.48
iv). WBM Gr-II & Gr-III Cum 910.13
v). Less Earth work due to R.Wall & T.Wall Cum 0.00
Vi). PMC & SC Cum 194.31
vi). Quantity from concrete road Cum 794.07
vi). Quantity from Shoulder Cum 1297.50
Cum 5607.69
Net quantity = (Final Section - Deduction) 17997.00 --- 5607.69 Cum 12389.31

3.4 (B) With mechanical lead upto 1000m 100% Cum 12389.31 192.04 2379243.09
3.3 301.5 Construction of embankment with approved materials deposited at site

from roadway cutting and excavation from drain and foundation of other

structures graded and compacted to meet requirement as per MORD

technical Specification Clause 301 and direction of the Engineer in

Charge (excluding cost of excavation and transportation to site).


Take 70% of Excavation soil (From Culvert, Toe
Wall & Drain + 100% CC Road) Cum 1110.42
Total= Cum 1110.42 28.44 31580.34
Sr. Claus
Description of Items Nos L(m) B(m) D(m) Unit Quantity Rate Amount
No. e No.
1 2 3 4 5 6 7 8 9 10 11
3.40 301.5( Earthwork in excavation for foundation of structures in all types of soil
III) as per drawing and technical specification Clause 305 and 1104 of
MoRD includding setting out, construction of shoring and bracing,
removal of stumps and other deleterious material and disposal upto all
lead & lift, dressing of sides and bottom and back filling with excavated
suitable material upto 3mt. as per direction of Engineer-in-Charge.

Sub-grade 2 2540 0.525 0.250 Cum 666.75


666.75 272.07 181402.67

4.10 402.0 Construction of Gravel/soil Aggregate Sub Base/Base by providing well


graded material of nominal maximum size grading 20 mm as per Table
2.3 of IRCSP 77-2008 spreading in uniform layers with tractor mount
appropriate grading arrangements on prepared surface, mixing by place
in method at OMC with tractor mount appropriate rotavator attachment
& compaction with 3 wheel 80-100 KNstatic roller capacity to achieve
the desired density complete as per specification contained in para
2.2,3.6&of IRCSP 77-2008.

Granular Sub-Base
Carraige way(G.S.B) Widening portion 2 2540.00 0.525 0.175 Cum 466.730
Add extra for widening 2% 466.73 Cum 9.335
2 2540.00 1.875 0.100 Cum 952.500
Cum 1428.560 680.340 971906.510

4.8 405 Providing, laying, spreading and compacting stone aggregates of


specific sizes to water bound macadam specification including
spreading in uniform thickness, hand packing, rolling with three wheel
80-100 kN static roller in stages to proper grade and camber, applying
and brooming, crushable screening(morum and sand admixture) to fill-
up the interstices of coarse aggregate, watering and compacting to the
required density as per Technical Specification Clause 405 of MoRD &
as per direction of Engineer-in-Charge.

Grading No. -II (63-45 mm size) with crusable


screening

Widening Portion 2 2540.00 0.375 0.075 Cum 142.880 0.000


Add extra for widening 2% 142.88
Cum 2.858
Cum 145.740 2917.560 425205.190

Grading No. -III (53-22.4 mm size) with crusable


screening 0.000 0.000
Add extra for widening at junction 1 2540.00 3.750 0.075 Cum 714.380
POTHOLES 5% 0.000 Cum 35.719 0.000
Add extra for widening 2% 714.4 Cum 14.288
Cum 764.390 2844.900 2174613.110
5.0 BITUMINOUS WORKS
5.10 502.0 Providing and applying primer coat with bitumen emulsion (SS-1) on
prepared surface of granular base including cleaning of road surface
and spraying primer at the rate of 0.70-1.0 kg/sqm using mechanical
means as per MORD Technical Specification Clause 502 for low
porosity surface and as per direction of Engineer-in-Charge.

PRIME COAT-> 0.000 0.000


on Total road 1 2540.00 3.750 Sqm 9525.000
Add extra for widening 2% 9525.00 Sqm 190.500
9715.500 30.230 293699.570
Sr. Claus
Description of Items Nos L(m) B(m) D(m) Unit Quantity Rate Amount
No. e No.
1 2 3 4 5 6 7 8 9 10 11
5.20 503.0 Providing and applying tack coat with Bitumen emulsion (RS-1) using
emulsion distributor at the rate of 0.25 to 0.30 kg per sqm on the
prepared granular surfaces treated with primer & cleaned with Hydraulic
broom as per Technical Specification Clause 503 of MoRD & as per
direction of Engineer-in-Charge.

TACK COAT> 1 2540.00 3.750 Sqm 9525.000


Add extra for widening 2% 9525.00 Sqm 190.500 0.000
Sqm 9715.500 10.500 102012.750
Providing, laying and rolling of open-graded premix carpet of 20 mm
thickness composed of 13.2 mm to 5.6 mm aggregates using S-65
penetration grade bitumen @ 14.6 kg/10 sqm to required line, grade and
level to serve as wearing course on a previously prepared base,
including mixing in a suitable hot mix plant, laying and rolling with a
three wheel 80-100 kN static roller capacity, finished to required level
and grades to be followed by seal coat of Type C as per Technical
Specification Clause 508 of MoRD and as per direction of Engineer-in-
Charge (Excluding cost of Seal Coat).

PREMIC CARPET 1 2540.00 3.750 Sqm 9525.000


Add for extra widening 2% 9525.00 Sqm 190.500
Sqm 9715.500 141.800 1377657.900
5.12 510.0 Providing and laying seal coat sealing the voids in a bituminous surface
laid to the specified levels, grade and cross fall using Type A, Type B
and Type C as per Technical Specification Clause 510

SEAL COAT - 1 2540.00 3.750 Sqm 9525.000


Add extra for widening 2% Sqm 190.500 0.000
Sqm 9715.500 51.070 496170.590
(A) 8504505.26
ROAD FURNITURE

I. Providing and fixing of typical informatory sign board with Logo as per
MORD specifications and drawing. Three MS Plates of 1.6 mm thick,
top and middle plate duly welded with MS flat iron 25mm x 5m size on
back on edges. The lower plate will be welded with MS angle iron frame
of 25mm x 25mm x 5mm. The angle iron frame of the lower most plate
and flat iron frame of middle plate will be welded to 2 nos. 75mm x 75
mm of 12 SWG sheet tubes posts duly embedded in cement concrete
M-15 grade blocks of 450mm x 450mm x 600mm, 600mm below ground
level. The top most diamond plate will be welded to middle plate by
47mm x 47mm of 12 SWG steel plate tube. All M.S. will be stove
enameled on both sides. Lettering and printing arrows, border etc. will
be painted with ready mixed synthetic enamel paint of superior quality in
required shade and colour. All sections of framed posts and steel tube
will be painted with primer and two coats of epoxy paint as per drawing
Clause Annexure 300,800,1700 of MORD as per direction of the
Engineer in charge

Nos. 2.00 8656.90 17313.80


Sr. Claus
Description of Items Nos L(m) B(m) D(m) Unit Quantity Rate Amount
No. e No.
1 2 3 4 5 6 7 8 9 10 11
II. Providing and fixing of typical citizen information board as per MORD
specifications and drawing. Three MS Plates of 50x5mm mm thick, back
plate duly welded with 75mm dia steel tubes back on edges as per
drawings. The upper & lower plate will be welded with MS flat iron
frame of 50mmx5mm. The steel tubes duly embedded in cement
concrete M-15 grade blocks of 600mm x 600mm x 750mm below
ground level.All M.S. will be stove enameled on both sides. Lettering
and printing arrows, border etc. will be painted with ready mixed
synthetic enamel paint of superior quality in required shade and colour.
All sections of framed posts and steel tube will be painted with primer
and two coats of epoxy paint as per drawing Clause 1701 and
Annexture 1700.1.

Nos. 3.00 12777.33 38331.99


IV. Providing and fixing of semi reflective cautionary, mandatory and
informatory sign board as per IRC:67 made of 2 mm thick MS Sheet
duly stove white colour in front and gray colour on back with red
reflective border of 65 mm width and required letters and figures with
reflective tape engineering grade as per Clause 1701.3.9 of MORD for
Rural Roads of required shade and colour supported and welded on
47mm x 47 mm x 12 SWG sheet tube firmly fixed to the ground by mean
of properly designed foundations with M-15 grade cement concrete
450x450x600 mm, 600 mm below ground level as per approved drawing
Clause 300,800,1700 as per direction of the Engineer in charge.(600
mm square)

Nos. 2.00 1968.58 3937.16


Providing and fixing of semi reflective cautionary, mandatory and
informatory sign board as per IRC:67 made of 1.5 mm thick MS Sheet
duly stove white colour in front and gray colour on back with red
reflective border of 65 mm width and required letters and figures with
reflective tape engineering grade as per Clause 1701.3.9 of MORD for
Rural Roads of required shade and colour supported and welded on
47mm x 47 mm x 12 SWG sheet tube firmly fixed to the ground by mean
of properly designed foundations with M-15 grade cement concrete
450x450x600 mm, 600 mm below ground level as per approved drawing
Clause 300,800,1700 as per direction of the Engineer in charge.(600
mm square)

i) 900mm equilateral triangle ( turn & reduced


carriage way ) Nos. 10.00 1638.31 16383.10
iii) 600x450 mm square ( school & padestrians )
Nos. 10.00 1608.40 16084.00
iv)600 mm dia circular ( hurn prohibited speed
limit , side road & sound hurn)
Nos. 10.00 1613.26 16132.60

V Reinforced cement concrete M15 grade kilometre stone of standard


design as per IRC:8 fixing in position including painting and printing, etc
as per drawing and MORD technical Specification Clause 1703 as per
direction of the Engineer in charge

1 Fixing of 5th KM stone No. 1.00 3156.85 3156.85


2 Fixing of Ordinary KM stone Nos. 7.00 1932.77 13529.39
3 Fixing of 200mtr stone Nos. 24.00 526.87 12644.88
VII. Guide post Nos. 130.00 628.74 81736.20
(B) 219249.97

I. Shifting of Electri Poles & Telephone poles Nos. 60.00 4464.29 267857.00
I. Add for prepearation for project report. L.S. Km 6.00 13392.86 80357.00
(C) 348214.00
Total :- (A+B) 8723755.2300
Sr. Claus
Description of Items Nos L(m) B(m) D(m) Unit Quantity Rate Amount
No. e No.
1 2 3 4 5 6 7 8 9 10 11

Junior Engineer Assistant Executive Engineer Executive Enginer

R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh


COST ESTIMATE FOR CONSTRUCTION OF CONCRETE ROAD (CC ROAD)

Name of the Road : Nandighore to Saliajhari


Total Length of Road : (m) 6000 M 0/000 to 1/040,2/340 to
2/770,3/270 to 4/050,4/590 to
Length of Rigid Pavement (m) : 3460 M 5/800 District : Nayagarh
Length of New Rigid Pavement (m) : 3460 M
Sr. Clause Nos Description of Items
No. Description of Items Unit Quantity Rate Amount
No. . L(m) B(m) D(m)
1 2 3 4 5 6 7 8 9 10 11

1 300 Earthwork in excavation for foundation of structures in all


types of soil as per drawing and technical specification Clause
305 and 1104 of MoRD includding setting out, construction of
shoring and bracing, removal of stumps and other deleterious
material and disposal upto all lead & lift, dressing of sides and
bottom and back filling with excavated suitable material upto
3mt. as per direction of Engineer-in-Charge.

CC portion 2 3460.0 0.450 0.255 Cum 794.07


794.07 272.07 216042.62
2 402.0 Filling Sand in foundation in trenches as per drawing and
technical specification clause 305.3.9.
CC portion 2 3460.0 0.450 0.100 Cum 311.40
311.40 1118.71 348366.29
3 Providing concrete for plain / reinforced concrete in open
foundation complete as per drawing and MORD technical
specification Clause 800,1100,1200 and as per direction of
Engineer-in-Charge.M15

2 3460.0 0.450 0.075 Cum 233.55


Cum 233.55 4629.17 1081142.65
4 Filling berms with Gravel including cost,
conveyance,royality etc complete as per
direction of EIC.
2 3460 1.875 0.100 Cum 1297.50
Cum 1297.50 499.99 648737.03
5 1500 Construction of un-reinforced, plain cement
Panelled(0.75mx.75m) concrete pavement of 100mm thickn
as per design, over a prepared sub-base, with 43 grade
cement or any other type as per Clause 1501.2.2, M30
(grade) coarse and fine aggregates conforming to IS:383,
maximum size of coarse aggregate not exceeding 25mm
mixed in a concrete mixer of not less than 0.2 cum capacity
and appropriate weigh batcher using approved mix design,
laid in approved fixed side formwork (steel channel, laying
and fixing of 125 micron thick polythene film, wedges, steel
plates including levelling the form work as per drawing),
spreading the concrete with shovels, rakes, compacted using
needle, screed and plate vibrators and finished in continuous
operation including provision of contraction and expansion,
construction joints, applying debonding strips, primer, sealant
near approaches to bridges and culverts (expansion joints),
admixtures as approved, curing of concrete slabs for 14 days,
curing compound and water finishing to lines and grade as
per drawing and Technical Specification Clause 1501.Panels
are to be made by cutting grooves of 3 to 5mm thick and 25 to
30mm deep in CC slab.The grooves are to be filled with VG-
30 Bitumen with a spray of fine sand at top.

over old cc 1 3460.0 3.750 0.100 Cum 1297.50


Widening portion 2 3460.0 0.375 0.080 Cum 207.60
1505.10 5749.95 8654249.75

TOTAL Rs 10948538.34
Sr. Clause Nos Description of Items
Description of Items Unit Quantity Rate Amount
No. No. . L(m) B(m) D(m)
1 2 3 4 5 6 7 8 9 10 11
Junior Engineer Assistant Executive Engineer Executive Enginer
R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh
OMBAD C
COST ESTIMATE FOR CONSTRUCTION OF R.C.C. SLAB CULVERT

Name of the road:- Nandighore to Saliajhari PACKAGE NO


Type of cross Drainage Work:- 1 Span R.C.C. Slab Culvert of
( 3.000 x 2.000 m) At RD-,,
Nos. of Culvert :- 0 Nos
Sl. Description of item Nos. Length Width Ht / Th Unit Quantity Rate in Amount in
No in M Rs. Rs.
1 2 3 4 5 6 7 8 9 10
1 Earthwork in excavation for foundation of structures in all types of soil
as per drawing and technical specification Clause 305 and 1104 of
MoRD includding setting out, construction of shoring and bracing,
removal of stumps and other deleterious material and disposal upto all
lead & lift, dressing of sides and bottom and back filling with excavated
suitable material upto 3mt. as per direction of Engineer-in-Charge.

Foundation
Abutments 2 × 7.40 × 3.20 × 1.50 Cum 71.04
Piers 0 × 7.33 × 1.97 × 1.50 Cum 0.00
Cut off U/S 1 × 3.50 × 1.00 × 1.20 Cum 4.20
Cut off D/S 1 × 4.50 × 1.00 × 1.50 Cum 6.75
D/S Bed 1 × -0.50 × 1.70 × 0.60 Cum -0.51
U/S Bed 1 × -0.50 × 1.20 × 0.60 Cum -0.36
CD Bed 1 × 6.00 × 3.40 × 0.60 Cum 12.24
Wing walls 4 × 1.65 × 2.52 × 1.50 Cum 24.95
Total Cum 0.00 @ 272.07 0.00
3 Providing concrete for plain / reinforced concrete in open foundation
complete as per drawing and MORD technical specification Clause
800,1100,1200 and as per direction of Engineer-in-Charge.

PCC M 10
in Foundation
Abutments 1st Step 2 × 7.40 × 3.20 × 0.20 Cum 9.47
Cut off D/S 1st step 1 × 4.50 × 1.00 × 0.30 Cum 1.35
Cut off D/S 2nd step 1 × 4.50 × 0.60 × 1.00 Cum 2.70
Cut off U/S 1st step 1 × 3.50 × 1.00 × 0.30 Cum 1.05
Cut off U/S 2nd step 1 × 3.50 × 0.60 × 0.70 Cum 1.47
Wing 1st Step 4 × 1.65 × 2.52 × 0.40 Cum 6.65
CD Bed 1 × 6.00 × 2.50 × 0.15 Cum 2.25
U/S Bed 1 × -0.50 × 1.40 × 0.15 Cum -0.11
D/S Bed 1 × -0.50 × 1.90 × 0.15 Cum -0.14
Toe wall 4 × 15.00 × 0.60 × 1.20 Cum 43.20
Total Cum 0.00 @ 4,696.88 0.00
4 Plain/reinforced cement concrete in sub-structure complete as per
drawings and MORD technical specification Clauses 800,1200 and as
per direction of the Engineer in charge
PCC M 15
A. In Sub-structure
Abutments 2nd Step 2 × 7.00 × 2.80 × 0.20 Cum 7.84

Abutments 3rd step 2 × 6.60 × 2.40 × 0.40 Cum 12.67


4th Step 2 x 6.6+5.6 x 2.4+2.0 x 0.40 Cum 10.91
2 2
Above G.L. 2 × 5.4+6.0 × 1.6+0.7 × 2.10 Cum 27.53
2 2
Pier 3rd Step 0 × 6.53 × 1.17 × 0.40 Cum 0.00
Above G.L. 0 × 6.13 × .77+0.7 × 2.10 Cum 0.00
2
Wing 4 × 1.85 × 2.12 × 0.40 Cum 6.28
4 × 2.05 × 1.92 × 0.40 Cum 6.3
4 × 3.0+2.05 × 1.72+.4 × 2.35 Cum 25.16
2 2
Total Cum 0@ 4,960.82 0.00
Sl. Description of item Nos. Length Width Ht / Th Unit Quantity Rate in Amount in
No in M Rs. Rs.
1 2 3 4 5 6 7 8 9 10
5 Providing and laying reinforced cement concrete of M-25 grade in
Super structure complete as per drawings and technical specifications
Clause 800 & 1200 of MoRD and as per the direction of the Engineer-
in-charge

RCC M 25
Deck Slab 1 × 3.80 × 6.00 × 0.275 Cum 0
Parapet 0 × 3.80 × 0.40 × 0.400 Cum 0.00
0.00 @ 6806.73 0.00
Providing and laying reinforced cement concrete of M-25 grade in Sub-
structure complete as per drawings and technical specifications Clause
800 & 1200 of MoRD and as per the direction of the Engineer-in-charge

Abutment Cap 2 × 6.00 × 0.45 × 0.150 Cum 0.81


Dirt wall 2 × 6.00 × 0.30 × 0.500 Cum 1.80
Cum 0.00 @ 6276.55 0.00
6 Providing and laying cement concrete wearing course M 30 grade
including reinforcement complete as per drawing and technical
specifications Clauses 800 and 1206.3
Wearing Coat 2 × 3.80 × 6.00 × 0.075 Cum 0.00 @ 10,559.25 0.00

7 Supplying, fitting and placing HYSD bar reinforcement (Fe 415)


complete as per drawings and MORD technical specification Clauses
1000,1200 as per direction of the Engineer in charge
In super structure
a - Deck Slab - R.C.C 0.00 Cum @ 1.00 Qntl. 0.000 6,185.95 0.00
In sub structure
b- Cap & Dirt wall 0.00 Cum @ 1.00 Qntl. 0.000
c.- Abutments Piers 25.16 Cum @ 0.08 Qntl. 2.013
Total Qntl. 0.000 @ 6,040.09 0.00
8 Providing weepholes in brick masonry/stone masonry, plain/reinforced
concrete abutment, wing wall, return wall with 100 mm dia AC pipe
extending through the full width of the structures with slope of
1(V):20(H) towards drawing face complete as per drawing and MORD
technical specification Clauses 614, 709, 1204 and as per direction of
the Engineer in charge

Abutment 2 × 11 Nos. Nos. 22


Wing wall 4 × 8 Nos. Nos. 32
Nos. 0.00 @ 155.57 0.00

9 Providing and laying filter media with granular crushed aggregates as


per specification to a thickness of not less than 600 mm with smaller
size towards the soil and bigger size towards the wall and providing
over the entire surface behind abutment, wing wall, return wall to the
full height, compacted to firm condition complete as per drawing and
MORD technical specification Clause 1204.3.8 and as per direction of
the Engineer in charge

In between Wing wall and Abutment


Behind Abutments 2 × 6.00 × 2.00 × 0.60 Cum 14.40
Behind Wing wall 4 × 2.53 × 2.35 × 0.60 Cum 14.24
Cum 0.00 @ 2463.69 0.00

Total 0.00

Rs.

Junior Engineer Assistant Executive Engineer Executive Enginer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh
COST ESTIMATE FOR CONSTRUCTION OF CROSS DRAINAGE WORKS.

Name of the road: Nandighore to Saliajhari


Type of cross Drainage Work: Hume Pipe Culvert (1000mm dia Single row)
Total Nos. of Culvert : 2 Nos. At RD-4/857,5/338,5/618,,,,, District : Nayagarh
Type of soil : All kinds of soil Block : Odagaon

Sl. Ht / Th
No
Description of item Nos. Length Width Unit Quantity Rate in Rs. Amount in Rs.
in M
1 2 3 4 5 6 7 8 9 10
1. Earthwork in excavation for foundation of structures in all types of soil as per
drawing and technical specification Clause 305 and 1104 of MoRD includding
setting out, construction of shoring and bracing, removal of stumps and other
deleterious material and disposal upto all lead & lift, dressing of sides and
bottom and back filling with excavated suitable material upto 3mt. as per
direction of Engineer-in-Charge.

Head wall 2 × 5.00 × 1.40 × 0.20 Cum 2.80


below pipe 1 x 5.33 x 2.23 x 0.20 Cum 2.38
Filling gaps 1 × 6.00 × 2.23 × 1.53 Cum 20.47
Deduct for pipe 1 × 6.00 × 0.785 × (1.23)2 Cum 7.13
Total 32.78
For 2 no culverts 32.78 x 2 Cum 65.56 @ 272.07 17836.91
2 Filling Sand in foundation in trenches as per drawing and technical specification
clause 305.3.9.
Sand Filling
Head wall 2 × 5.00 × 1.40 × 0.20 Cum 2.80
below pipe 1 x 5.33 x 2.23 x 0.20 Cum 2.38
Filling gaps 1 × 6.00 × 2.23 × 1.53 Cum 20.47
Deduct for pipe 1 × 6.00 × 0.785 × (1.23)2 Cum 7.13
Total 18.52
Total 18.52
For 2 no culverts 18.52 x 2 Cum 37.04 @ 1118.71 41437.02
3 Providing M15 concrete for plain / reinforced concrete in open foundation
complete as per drawing and MORD technical specification Clause
800,1100,1200 and as per direction of Engineer-in-Charge.

Head wall 2 × 5.00 × 1.40 × 0.15 Cum 2.10


Total Cum 2.10
For 2 no culverts 2.10 x 2.00 Cum 4.20 @ 4629.17 19442.51
4 P.C.C grade M 10,Nominal mix 1:3:6 plain / reinforced concrete in open
foundation complete as per drawing and MORD technical specification Clause
800,1100,1200 and as per direction of Engineer-in-Charge.

Below Pipe 1 × 5.46 × 2.23 × 0.150 Cum 1.83


For 2 no culverts 1.83 x 2.00 Cum 3.66 @ 4812.46 17613.60
5 Providing and laying reinforced cement concrete NP3 pipe for culverts jointing
with cement mortar 1:2 but excluding excavation, protection works, backfilling,
concrete and masonry works in head walls and parapets as per Clause 1100 of
MoRD & as per direction of Engineer-in-Charge.

1000 mm dia Single row 2 × 7.50 RM 15.00 @ 6453.77 96806.55


7 Plain/reinforced cement concrete M-15 in sub-structure complete as per
drawings and MORD technical specification Clauses 800,1200 and as per
direction of the Engineer in charge M-15

Head wall 2 × 4.85 × 0.825 × 2.18 Cum 17.45


Parapet 2 × 4.85 × 0.40 × 0.40 Cum 1.55
Collar Joint 2 × 2.23 × 0.20 × 1.58 Cum 1.41
Toe Wall 0 x 5.00 x 0.65 x 1.20 Cum 0.00
Total 20.41
Deduction in Pipe from Head Wall 2 × (1.23)2 × 0.785 × 0.825 Cum (-) 1.96
Deduct for Pipe joint 2 × (1.23)2 × 0.785 × 0.20 Cum (-) 0.48
Total 17.97
For 2 no culverts 17.97 x 2 Cum 35.94 @ 4889.19 175717.49
2 Nos. of Hume Pipe Culverts Total Cost 368854.0800

Junior Engineer Assistant Executive Engineer Executive Enginer


1
Sl. Ht / Th
No Description of item Nos. Length Width
in M
Unit Quantity Rate in Rs. Amount in Rs.

1 2 3 4 5 6 7 8 9 10
R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh

1
COST ESTIMATE FOR CONSTRUCTION OF CROSS DRAINAGE WORKS.

Name of the road: Nandighore to Saliajhari


Type of cross Drainage Work: Hume Pipe Culvert (600mm dia Single row)
Total Nos. of Culvert : 0 Nos. At RD-,,,,,,, District : Nayagarh

Type of soil : All kinds of soil Block : Odagaon


Sl. Ht / Th Amount in
Description of item Nos. Length Width Unit Quantity Rate in Rs.
No in M Rs.
1 2 3 4 5 6 7 8 9 10
1. Earthwork in excavation for foundation of structures in all
types of soil as per drawing and technical specification Clause
305 and 1104 of MoRD includding setting out, construction of
shoring and bracing, removal of stumps and other deleterious
material and disposal upto all lead & lift, dressing of sides and
bottom and back filling with excavated suitable material upto
3mt. as per direction of Engineer-in-Charge.

Head wall 2 × 3.48 × 1.500 × 1.00 Cum 10.44


Pipe Portion 1 × 4.65 × 1.36 × 0.90 Cum 5.69
Total 16.13
For 0 no culverts 16.13 x 0 Cum 0.00 @ 272.07 0.00
4 Providing M15 concrete for plain / reinforced concrete in open
foundation complete as per drawing and MORD technical
specification Clause 800,1100,1200 and as per direction of
Engineer-in-Charge.

Head wall 2 × 3.48 × 1.500 × 0.15 Cum 1.57


Total 1.57
For 0 no culverts 1.57 x 0 Cum 0.00 @ 4696.88 0.00
Providing and laying of Type-B(first class) bedding for laying of
Hume Pipe on well compacted moorum or approved granular
material as per MORD Technical Specification clause 1105(ii)
and as per direction of the engineer-in-charge.

Below Pipe 1 × 4.65 × 1.36 × 0.15 Cum 0.95


For 0 no culverts 0.95 x 0 Cum 0.00 @ 471.32 0.00
5 Providing and laying reinforced cement concrete NP3 pipe for
culverts jointing with cement mortar 1:2 but excluding
excavation, protection works, backfilling, concrete and
masonry works in head walls and parapets as per Clause
1100 of MoRD & as per direction of Engineer-in-Charge.

600 mm dia Single row 0 × 7.50 RM 0.00 @ 2384.25 0.00


7 Plain/reinforced cement concrete in sub-structure complete as
per drawings and MORD technical specification Clauses
800,1200 and as per direction of the Engineer in charge

Head wall 2 × 3.48 × (1.35+0.4)/2 × 2.10 Cum 12.79


Collar Joint 2 × 0.20 × 1.20 × 1.00 Cum 0.48
Total 13.27
Deduction in Pipe joint 2 × 0.2 × p /4 × (0.76)2 um (-) 0.18
Deduct for Pipe 2 × 0.760 × 0.785 × (0.76)2 um (-) 0.69
12.40
For 0 no culverts 12.40 x 0 Cum 0.00 @ 4960.82 0.00

0 Nos. of Hume Pipe Culverts Total Cost Rs. 0.00

Junior Engineer Assistant Executive Engineer Executive Enginer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh
PRADHANMANTRI GRAM SADAK YOJANA (PMGSY)
COST ESTIMATE FOR CONSTRUCTION OF R.C.C. SLAB CULVERT

Name of the road: Nandighore to Saliajhari PACKAGE NO


Type of cross Drainage Work: 2 Span R.C.C. Slab Culvert of
( 3.000 x 1.500 m) At RD-,,
Nos. of Culvert : 0 Nos
Sl. Description of item Nos. Length Width Ht / Th Unit Quantity Rate in Rs. Amount in Rs.
No in M
1 2 3 4 5 6 7 8 9 10
1 Earthwork in excavation for foundation of structures in all
types of soil as per drawing and technical specification Clause
305 and 1104 of MoRD includding setting out, construction of
shoring and bracing, removal of stumps and other deleterious
material and disposal upto all lead & lift, dressing of sides and
bottom and back filling with excavated suitable material upto
3mt. as per direction of Engineer-in-Charge.

Foundation
Abutments 2 × 7.40 × 3.20 × 1.50 Cum 71.04
Cut off U/S 1 × 9.70 × 1.00 × 1.20 Cum 11.64
Cut off D/S 1 × 10.70 × 1.00 × 1.50 Cum 16.05
D/S Bed 1 × 5.70 × 1.70 × 0.60 Cum 5.81
U/S Bed 1 × 5.70 × 1.20 × 0.60 Cum 4.10
CD Bed 2 × 6.00 × 3.40 × 0.60 Cum 24.48
Wing walls 4 × 1.65 × 2.52 × 1.50 Cum 24.95
179.42
No of culverts=3 Total Cum 0.00 @ 272.07 0.00
2 Filling Sand in foundation in trenches as per drawing and
technical specification clause 305.3.9.

Foundation
Abutments 2 × 7.40 × 3.20 × 0.20 Cum 9.47
Cut off U/S 1 × 9.70 × 1.00 × 0.20 Cum 1.94
Cut off D/S 1 × 10.70 × 1.00 × 0.20 Cum 2.14
Wing walls 4 × 1.65 × 2.52 × 0.20 Cum 3.33
D/S Bed 1 × 5.70 × 1.90 × 0.20 Cum 2.17
U/S Bed 1 × 5.70 × 1.40 × 0.20 Cum 1.60
CD Bed 2 × 6.00 × 2.50 × 0.20 Cum 6.00
29.50
No of culverts=3 Total Cum 0.00 @ 1125.35 0.00
3 Providing concrete for plain / reinforced concrete in open
foundation complete as per drawing and MORD technical
specification Clause 800,1100,1200 and as per direction of
Engineer-in-Charge.

PCC M 10

Abutments 1st Step 2 × 7.40 × 3.20 × 0.20 Cum 9.47


Cut off D/S 1st step 1 × 10.70 × 1.00 × 0.30 Cum 3.21
Cut off D/S 2nd step 1 × 10.70 × 0.60 × 1.00 Cum 6.42
Cut off U/S 1st step 1 × 9.70 × 1.00 × 0.30 Cum 2.91
Cut off U/S 2nd step 1 × 9.70 × 0.60 × 0.70 Cum 4.07
Wing 1st Step 4 × 1.65 × 2.52 × 0.40 Cum 6.65
CD Bed 2 × 6.00 × 2.50 × 0.15 Cum 4.5
U/S Bed 1 × 5.70 × 1.40 × 0.15 Cum 1.2
D/S Bed 1 × 5.70 × 1.90 × 0.15 Cum 1.62
Toe wall 4 × 15.00 × 0.60 × 1.20 Cum 43.20
88.94
No of culverts=3 Cum 0.00 @ 4,696.88 0.00
4 Plain/reinforced cement concrete in sub-structure complete as
per drawings and MORD technical specification Clauses
800,1200 and as per direction of the Engineer in charge

PCC M 15
A. In Sub-structure
Abutments 2nd Step 2 × 7.00 × 2.80 × 0.20 Cum 7.84

Abutments 3rd step 2 × 6.60 × 2.40 × 0.40 Cum 12.67


4th Step 2 x 6.6+5.6 x 2.4+2.0 x 0.40 Cum 10.91
2 2
Above G.L. 2 × 5.4+6.0 × 1.6+0.7 × 1.60 Cum 20.98
2 2
Sl. Description of item Nos. Length Width Ht / Th Unit Quantity Rate in Rs. Amount in Rs.
No in M
1 2 3 4 5 6 7 8 9 10
Wing 4 × 1.85 × 2.12 × 0.40 Cum 6.28
4 × 2.05 × 1.92 × 0.40 Cum 6.3
4 × 3.0+2.05 × 1.72+.4 × 1.85 Cum 19.81
2 2
99.14
No of culverts=3 Total Cum 0@ 4,960.82 0.00
5 Providing and laying reinforced cement concrete of M-25 grade
in Super structure complete as per drawings and technical
specifications Clause 800 & 1200 of MoRD and as per the
direction of the Engineer-in-charge.

RCC M 25
Deck Slab 2 × 3.80 × 6.00 × 0.275 Cum 12.54
Parapet 2 × 3.80 × 0.40 × 0.400 Cum 1.22
No of culverts=3 0.00 6806.73 0.00
Providing and laying reinforced cement concrete of M-25 grade
in Sub-structure complete as per drawings and technical
specifications Clause 800 & 1200 of MoRD and as per the
direction of the Engineer-in-charge
6
Abutment Cap 2 × 6.00 × 0.45 × 0.150 Cum 0.81
Dirt wall 2 × 6.00 × 0.30 × 0.500 Cum 1.80
No of culverts=3 Cum 0.00 @ 6276.55 0.00
7 Providing and laying cement concrete wearing course M 30
grade including reinforcement complete as per drawing and
technical specifications Clauses 800 and 1206.3

Wearing Coat 2 × 3.80 × 6.00 × 0.075 Cum 3.42


No of culverts=3 0.00 @ 10,559.25 0.00

8 Supplying, fitting and placing HYSD bar reinforcement (Fe 415)


complete as per drawings and MORD technical specification
Clauses 1000,1200 as per direction of the Engineer in charge

In super structure
a - Deck Slab - R.C.C 12.54 Cum @ 1.00 Qntl. 12.540
No of culverts=3 0.000 @ 6,185.95 0.00
In sub structure
b- Cap & Dirt wall 0.00 Cum @ 1.00 Qntl. 0.000
c.- Abutments Piers 19.81 Cum @ 0.08 Qntl. 1.585
1.585
No of culverts=3 Qntl. 0.000 @ 6,040.09 0.00
9 Providing weepholes in brick masonry/stone masonry,
plain/reinforced concrete abutment, wing wall, return wall with
100 mm dia AC pipe extending through the full width of the
structures with slope of 1(V):20(H) towards drawing face
complete as per drawing and MORD technical specification
Clauses 614, 709, 1204 and as per direction of the Engineer in
charge
Abutment 2 × 11 Nos. Nos. 22
Wing wall 4 × 8 Nos. Nos. 32
54
No of culverts=3 Nos. 0.00 @ 155.57 0.00
10 Providing and laying filter media with granular crushed
aggregates as per specification to a thickness of not less than
600 mm with smaller size towards the soil and bigger size
towards the wall and providing over the entire surface behind
abutment, wing wall, return wall to the full height, compacted to
firm condition complete as per drawing and MORD technical
specification Clause 1204.3.8 and as per direction of the
Engineer in charge

In between Wing wall and Abutment


Behind Abutments 2 × 6.00 × 1.50 × 0.60 Cum 10.80
Behind Wing wall 4 × 2.53 × 1.85 × 0.60 Cum 11.21
22.01
No of culverts=3 Cum 0.00 @ 2463.69 0.00
Total 0.00
For
Rs. 0.00

Junior Engineer Assistant Executive Engineer Executive Enginer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh
COST ESTIMATE FOR CONSTRUCTION OF R.C.C. BOX-CELL CULVERT

Name of the road: Nandighore to Saliajhari


Type of cross Drainage Work: 1 Span Box-cell Culvert ( 2.00 m x 2.00 m) size
Total Nos. of Culvert : 0 Nos
Type of soil : All kinds of soil
Sl. Ht / Th
Description of item Nos. Length Width Unit Quantity Rate in Rs. Amount in Rs.
No in M
1 2 3 4 5 6 7 8 9 10
1 Earthwork in excavation for foundation of structures in all types of
soil as per drawing and technical specification Clause 305 and
1104 of MoRD includding setting out, construction of shoring and
bracing, removal of stumps and other deleterious material and
disposal upto all lead & lift, dressing of sides and bottom and back
filling with excavated suitable material upto 3mt. as per direction
of
CutEngineer-in-Charge.
off U/S(with side cut off) 1 × 13.50 × 1.00 × 2.00 Cum 27.00
Cut off D/S 1 × 14.50 × 1.00 × 2.50 Cum 36.25
Bridge proper and appron 1 × 7.90 × 2.50 × 0.80 Cum 15.80
Flexible appron U/S 1 × 3.70 × 1.50 × 1.00 Cum 5.55
Flexible appron D/S 1 × 3.70 × 2.00 × 1.00 Cum 7.40
Wing walls 4 × 2.20 × 2.52 × 2.00 Cum 44.35
Total Cum 0.00 @ 272.07 0
2 Filling Sand in foundation in trenches as per drawing and technical
specification clause 305.3.9.

Below raft 1 × 8.30 × 2.90 × 0.20 Cum 4.81


Cut off wall U/S 1 × 13.50 × 1.00 × 0.20 Cum 2.70
Cut off wall D/S 1 × 14.50 × 1.00 × 0.20 Cum 2.90
Wing walls 4 × 2.20 × 2.52 × 0.20 Cum 4.44
Total Cum 0.00 @ 1125.35 0
3 Providing concrete for plain / reinforced concrete in open
foundation complete as per drawing and MORD technical
specification Clause 800,1100,1200 and as per direction of
Engineer-in-Charge.
Below bed level
Below raft 1 × 8.30 × 2.90 × 0.15 Cum 3.61
Wing walls 4 × 2.20 × 2.52 × 0.40 Cum 8.87
Cut off D/S 1st step 1 × 13.50 × 1.00 × 0.50 Cum 6.75
Cut off U/S 1st step 1 × 14.50 × 1.00 × 0.50 Cum 7.25
Toe wall 4 × 15.00 × 0.60 × 1.20 Cum 43.20
Cut off D/S 2nd step 1 × 13.50 × 0.60 × 1.00 Cum 8.10
Cut off U/S 2nd step 1 × 14.50 × 0.60 × 1.50 Cum 13.05
0.00 @ 4,696.88 0
4 Plain/reinforced cement concrete in sub-structure complete as per
drawings and MORD technical specification Clauses 800,1200
and as per direction of the Engineer in charge

DEWATERING ( Below bed)


Rigid Appron U/S 1 × 4.10 × 1.50 × 0.30 Cum 1.85
D/S 1 × 4.10 × 2.00 × 0.30 Cum 2.46
Wing 4 × 2.20 × 2.12 × 0.40 Cum 7.46
Cum 0.00 @ 4,960.82 0
SHUTTERING(above bed)
Wing walls 4 × 2.20 × 1.92 × 0.40 Cum 6.76
4 × 3.00 × 1.06 × 3.60 Cum 45.79
Total Cum 0.00 @ 4,960.82 0
Sl. Ht / Th
Description of item Nos. Length Width Unit Quantity Rate in Rs. Amount in Rs.
No in M
1 2 3 4 5 6 7 8 9 10
5 Providing and laying reinforced cement concrete in superstructure
as per drawing and technical specifications Clauses 800, 1205.4
and 1205.5

(a) Raft 1 × 6.00 × 2.50 × 0.25 Cum 0.00 @ 5740.92 0


(b) Deck Slab 1 × 6.00 × 2.50 × 0.25 Cum 0.00 @ 6806.73 0
c) Rib 2 x 6.00 × 0.25 × 2.00 Cum 6.00
Pier Rib 0 x 6.00 × 0.00 × 2.00 Cum 0.00
Hunch 4 x 6.00 × 0.15/2 × 0.15 Cum 0.27
Cum 0.00 @ 6,276.55 0
d) Construction of R.C.C. railing of M 25 grade in cast-in-situ with 20
mm nominal size aggregate, true to line and grade, tolerance of
vertical railing post not to exceed 1 in 500, centre-to-centre
spacing between vertical posts not to exceed 2000 mm as per
drawing and technical specifications Clauses 800, 900 and 1208.3

2 × 2.50 Rm 0.00 @ 2,581.32 0


6 Providing and laying cement concrete wearing course M 30 grade
including reinforcement complete as per drawing and technical
specifications Clauses 800 and 1206.3

1 × 6.00 × 2.50 × 0.075 Cum 0.00 @ 10,559.25 0


7 Supplying, fitting and placing HYSD bar reinforcement (Fe 415)
complete as per drawings and MORD technical specification
Clauses 1000,1200 as per direction of the Engineer in charge

a - Deck Slab 0.00 Cum @ 1.00 Qntl. 0@ 6,185.95 0


c.- Raft 0.00 Cum @ 1.00 Qntl. 0
d-Rib & Hunch 0.00 Cum @ 0.80 Qntl. 0.000
e-Wing wall 45.79 Cum @ 0.075 Qntl. 3.434
Total Qntl. 0@ 6,040.09 0
8 Providing weepholes in brick masonry/stone masonry,
plain/reinforced concrete abutment, wing wall, return wall with 100
mm dia AC pipe extending through the full width of the structures
with slope of 1(V):20(H) towards drawing face complete as per
drawing and MORD technical specification Clauses 614, 709,
1204 and as per direction of the Engineer in charge

Abutment 2 × 10 Nos. Nos. 20


Wing wall 4 × 8 Nos. Nos. 32
Nos. 0@ 155.57 0
9 Providing and laying boulder appron for bed protection & pitching
on slopes with stone boulders of minimum size and weight as per
Table 1300.1, no fragment weighing less than 25 kg laid dry
complete as per drawing and technical specifications Clause 1301
& 1302

U/S Appron 1 × 4.10 × 1.50 × 0.6 Cum 3.69


D/S Appron 2 × 4.10 × 2.00 × 0.6 Cum 9.84
Revertment 4 × 3.00 × 4.00 × 0.3 Cum 14.40
Cum 0.00 @ 2112.13 0
10 Providing and laying filter media with granular crushed aggregates
as per specification to a thickness of not less than 600 mm with
smaller size towards the soil and bigger size towards the wall and
providing over the entire surface behind abutment, wing wall,
return wall to the full height, compacted to firm condition complete
as per drawing and MORD technical specification Clause
1204.3.8 and as per direction of the Engineer in charge

In between Wing wall and Abutment


Behind Abutment Ribs 2 × 3.88 × 1.70 × 0.60 Cum 7.92
Behind Wing wall 4 × 3.00 × 1.70 × 0.60 Cum 12.24
Sl. Ht / Th
Description of item Nos. Length Width Unit Quantity Rate in Rs. Amount in Rs.
No in M
1 2 3 4 5 6 7 8 9 10
Cum 0.00 @ 2,463.69 0
Total 0.00

Rs. 0.00

Junior Engineer Assistant Executive Engineer Executive Enginer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh
COST ESTIMATE FOR PROTECTION WORK WITH RETANING WALL

Name of the road: Nandighore to Saliajhari PACKAGE NO


Total length of Protection work : 460 Mtr 0 District : Nayagarh
Type of soil : All kinds of soil Block : Odagaon
Sl. Length Debth
Description of item Nos. Base in m Unit Quantity Rate in Rs. Amount in Rs.
No in m in M
1 2 3 4 5 6 7 8 9 10
1. Earthwork in excavation for foundation of structures in all types of
soil as per drawing and technical specification Clause 305 and
1104 of MoRD includding setting out, construction of shoring and
bracing, removal of stumps and other deleterious material and
disposal upto all lead & lift, dressing of sides and bottom and back
filling with excavated suitable material upto 3mt. as per direction
of Engineer-in-Charge.

Quantity 1 × 460 × 1.050 × 0.800 Cum 386.40


Total 386.40 @ 272.07 105127.85
2. Filling Sand in foundation in trenches as per drawing and
technical specification clause 305.3.9.
SAND Filling
Retaning Wall 1 × 460 × 1.050 × 0.150 Cum 72.45
Total 72.45 @ 1118.71 81050.54
3. Providing M15 concrete for plain / reinforced concrete in open
foundation complete as per drawing and MORD technical
specification Clause 800,1100,1200 and as per direction of
Engineer-in-Charge.

Retaning Wall BASE 1 × 460 × 1.050 × 0.150 Cum 72.45


Total 72.45 @ 4629.17 335383.37

4. M15 Plain/reinforced cement concrete in sub-structure complete


as per drawings and MORD technical specification Clauses
800,1200 and as per direction of the Engineer in charge

Retaning Wall 1 × 460 × 0.90+0.300 × 1.50 Cum 414.00


2
Total 414.00 @ 4889.19 2024124.66
5. Providing weepholes in brick masonry/stone masonry,
plain/reinforced concrete abutment, wing wall, return wall with 100
mm dia AC pipe extending through the full width of the structures
with slope of 1(V):20(H) towards drawing face complete as per
drawing and MORD technical specification Clauses 614, 709,
1204 and as per direction of the Engineer in charge

RMT 184 @ 135.02 24843.68


Total Rs. 2570530.10

Junior Engineer Assistant Executive Engineer Executive Enginer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh
PRADHANMANTRI GRAM SADAK YOJANA (PMGSY) Format-F-7

COST ESTIMATE FOR CONSTRUCTION OF CONCRETE DRAIN

Name of the road: Nandighore to Saliajhari PACKAGE NO


Total length of Concrete Drain : 0 x 1 =0M 2/350 TO 2/450,3/344 to District : Nayagarh
Type of soil : All kinds of soil 3/544,4/590 TO 4/690 Block : Odagaon
Sl. Ht / Th Quantit Amount in
Description of item Nos. Length Width Unit Rate in Rs.
No in M y Rs.
1 2 3 4 5 6 7 8 9 10
1. Earthwork in excavation for foundation of structures in all types of
soil as per drawing and technical specification Clause 305 and
1104 of MoRD includding setting out, construction of shoring and
bracing, removal of stumps and other deleterious material and
disposal upto all lead & lift, dressing of sides and bottom and
back filling with excavated suitable material upto 3mt. as per
direction of Engineer-in-Charge.

0 x 1 × 1.300 × 0.650 Cum 0.00 @ 272.07 0.00


2. Filling Sand in foundation in trenches as per drawing and
technical specification clause 305.3.9.

0 x 1 × 1.300 × 0.100 Cum 0.00 @ 1125.35 0.00

3. Providing M15 concrete for plain / reinforced concrete in open


foundation complete as per drawing and MORD technical
specification Clause 800,1100,1200 and as per direction of
Engineer-in-Charge.

0 0 1 × 1.300 × 0.100 Cum 0.00 @ 4696.88 0.00

4. Providing concrete for plain / reinforced concrete in open


foundation complete as per drawing and MORD technical
specification Clause 800,1100,1200 and as per direction of
Engineer-in-Charge.

Drain wall 2 x 1 × (0.3+0.4)/2 × 0.450 Cum 0.32


Cum 0.00 @ 4911.70 0.00

Total 0.00

Junior Engineer Assistant Executive Engineer Executive Enginer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh
COST ESTIMATE FOR FIXING OF LOGO

Name of the road: Nandighore to Saliajhari


Number of Structure 2 Nos.
District : Nayagarh
Type of soil : All kinds of soil Block : 0.00
Sl. Ht / Th Amount in
Description of item Nos. Length Width Unit Quantity Rate in Rs.
No in M Rs.
1 2 3 4 5 6 7 8 9 10
1. Earthwork in excavation for foundation of structures in all
types of soil as per drawing and technical specification
Clause 305 and 1104 of MoRD includding setting out,
construction of shoring and bracing, removal of stumps
and other deleterious material and disposal upto all lead &
lift, dressing of sides and bottom and back filling with
excavated suitable material upto 3mt. as per direction of
Engineer-in-Charge.

1 × 0.45 × 0.45 × 0.60 Cum 0.122 @ 272.07 33.19


11.4 Providing concrete for plain / reinforced concrete in open
foundation complete as per drawing and MORD technical
specification Clause 800,1100,1200 and as per direction
of Engineer-in-Charge.
1 × 0.45 × 0.45 × 0.60 Cum 0.122 @ 4900.00 597.80
3 Logo 600×600mm size fixed with M.S. Angle 75x75x6mm
including cost of all materials etc complete

i) M.S. Angle Length 3.50 m @ 6.8kg/Mtr 23.80 Kg 42.00 999.60

ii) Plate (area) 0.6 × 0.6 = 0.360


0.9 × 0.25 = 0.225
0.585 @ 30kg/sqm 17.550 Kg 42.00 737.10
Add 3% of cost of angle & plate towords cost of
fabrication,Drilling, Nuts,Bolts etc. 1.24 Kg 42.00 52.08
iii) Painting two coats including prime coat with epoxy paint of

approved brand on concrete/steel surfaces after through

cleaning of surface to give an even shade as per drawing

and Technical Specification Clause 1701 of MORD. 2 × 0.9 × 0.25 = 0.45


2 × 0.6 × 0.6 = 0.72 @ 84.88 99.31
Logo border 60x4x5=1200 1200.00
iv) Printing new letter and figures of any shade with synthetic
enamel paint black or any other approved colour to give an
even shade as per drawings and Technical Specification
(30 lettersx6cm
Clause 1701. average height) 30.0 x 6 = 180.00
1380.00 @ 0.91 1255.80
v) Transportation and fixing same as 5th Km stone
50 HP Tractor with trolley for 6 no hour 6.00 231.00 231.00

Rs. 4005.88
The Cost for fixing of Logo 2 x 4005.88 Rs. 8011.76

Junior Engineer Assistant Executive Engineer Executive Enginer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh
COST ESTIMATE FOR PROTECTION WORK WITH TOE WALL

Name of the road: Nandighore to Saliajhari PACKAGE NO


Total length of Protection work : 0 Mtr 0 District : Nayagarh
Block : Odagaon

Type of soil : All kinds of soil


Sl. Debth Amount in
Description of item Nos. Length in m Base in m Unit Quantity Rate in Rs.
No in M Rs.
1 2 3 4 5 6 7 8 9 10
1. Earthwork in excavation for foundation of structures in all
types of soil as per drawing and technical specification
Clause 305 and 1104 of MoRD includding setting out,
construction of shoring and bracing, removal of stumps
and other deleterious material and disposal upto all lead
& lift, dressing of sides and bottom and back filling with
excavated suitable material upto 3mt. as per direction of
Engineer-in-Charge.

Quantity 1 × 0 × 0.600 × 0.500 Cum 0.00


Total 0.00 @ 272.07 0.00
3. Providing M15 concrete for plain / reinforced concrete in
open foundation complete as per drawing and MORD
technical specification Clause 800,1100,1200 and as per
direction of Engineer-in-Charge.

TOE WALL BASE 1 × 0 × 0.600 × 0.150 Cum 0.00


Total 0.00 @ 4696.88 0.00
4 M15 Plain/reinforced cement concrete in sub-structure
complete as per drawings and MORD technical
specification Clauses 800,1200 and as per direction of
the Engineer in charge

Toe Wall 1 x 0 x (0.5+0.3)/2 x 1.00 Cum 0.00 @ 4960.82 0.00


5 Providing weepholes in brick masonry/stone masonry,
plain/reinforced concrete abutment, wing wall, return wall
with 100 mm dia AC pipe extending through the full width
of the structures with slope of 1(V):20(H) towards drawing
face complete as per drawing and MORD technical
specification Clauses 614, 709, 1204 and as per
direction of the Engineer in charge

Nos. 0 @ 155.57 0.00


Total Rs. 0.00

Junior Engineer Assistant Executive Engineer Executive Enginer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh

73/218 - (Twall) of 480488552.xlsx


COST ESTIMATE FOR FIXING OF GUIDE-POST

Name of the road: Nandighore to Saliajhari


Number of Structure 130 Nos.
District : Nayagarh
Type of soil : All kinds of soil Block : Odagaon

Ht / Th Quant Amount in
Sl. No Description of item Nos. Length Width Unit Rate in Rs.
in M ity Rs.

1 2 3 4 5 6 7 8 9
1. Earthwork in excavation for foundation of structures in
all types of soil as per drawing and technical
specification Clause 305 and 1104 of MoRD includding
setting out, construction of shoring and bracing,
removal of stumps and other deleterious material and
disposal upto all lead & lift, dressing of sides and
bottom and back filling with excavated suitable material
upto 3mt. as per direction of Engineer-in-Charge.

1 × 0.30 × 0.30 × 0.55 Cum 0.05 @ 272.07 13.60


11.4 Providing concrete for plain / reinforced concrete in
open foundation complete as per drawing and MORD
technical specification Clause 800,1100,1200 and as
per direction of Engineer-in-Charge.

1 × 0.30 × 0.30 × 0.55 Cum 0.05


Deduct for part of guide-post 1 x 0.786 x (0.2x0.2) x 0.35 Cum 0.01
0.04 @ 4900.00 196.00
12.5 Plain/reinforced cement concrete in sub-structure
complete as per drawings and MORD technical
specification Clauses 800,1200 and as per direction of
the Engineer in charge

i) R.C.C grade M 20
1 × 0.786 × (.175x.175) × 1.10 Cum 0.03 @ 6276.55 188.30
ii) Supplying, fitting and placing HYSD bar reinforcement

(Fe 415) complete as per drawings and MORD

technical specification Clauses 1000,1200 as per

direction of the Engineer in charge


Steel reinforcement @ 1Qntlper cum @ 1Qntl per cum t 0.003 @ 60400.87 181.20
iii) Painting two coats including prime coat with epoxy paint
of approved brand on concrete/steel surfaces after
through cleaning of surface to give an even shade as
per drawing and Technical Specification Clause 1701 of
MORD.

1 × 3.14 × 0.175 × 0.75 Sqm 0.41 @ 84.88 34.80


Transportation and fixing same as 200Mtr stone
Considering 50 HP Tractor with trolley for 33 no
for 1 no hour 6.00 231.00 42.00
Rs. 655.90
The Cost for fixing ofGuide-post 130 x 655.90 Rs. 85267.00

Junior Engineer Assistant Executive Engineer Executive Enginer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh
DETAILED ESTIMATE FOR MAINTENANCE OF ROAD

Name of the Road :- Nandighore to Saliajhari


Factors considered :-
1). Average annual rainfall-1400mm(medium) 2). Traffic intensity-15 to 45 (medium)
Length of road in K.M.: 2.540
Sl.
Items of works Quantity Unit Rate Amount
No.
1 2 3 4 5 6
1. Restoration of rain cuts with soil, clearing the loose soil, benching for 300mm width
laying fresh material in layers not exceeding 250 mm and compaction with plate
compactor or power rammer to restore the original alignment, level and slopes as per
drawings and MORD technical specifications Clause 1902 by manual means as per
direction of the Engineer in charge

Quantity /Km 2159.00 Sqm


1st year Take 10% of the area 685.80 Cum 262.68 180145.94
2nd year 20% excess over 1st year 754.38 Cum 262.68 198160.54
3rd year 40% excess over 1st year 822.96 Cum 262.68 216175.13
4th year 60% excess over 1st year 1440.18 Cum 262.68 378306.48
5th year 80% excess over 1st year 1851.66 Cum 262.68 486394.05

2. Making up loss of material/irregularities on shoulders to the design level by adding fresh


approved selected soil and compacting it with appropriate equipment at OMC upto a
lead of 1000 m as per MORD technical specification Clause 1903 as per direction of
the Engineer in charge
Area/Km 2x1000x1.125=3000.00Sqm
1st year Take 10% of the area 228.60 Sqm 32.72 7479.79
2nd year 20% excess over 1st year 251.46 Sqm 32.72 8227.77
3rd year 40% excess over 1st year 320.04 Sqm 32.72 10471.71
4th year 60% excess over 1st year 525.78 Sqm 32.72 17203.52
5th year 80% excess over 1st year 548.64 Sqm 32.72 17951.50

3. Stripping excess soil from the shoulder surface to achieve the approved level and
compacting with plate compactor at OMC as per drawings and Technical Specification
Clause 1903.
Area/Km 2x1000x1.125=3000.00Sqm
1st year Take 10% of the area 228.60 Sqm 12.79 2923.79
2nd year 20% excess over 1st year 342.90 Sqm 12.79 4385.69
3rd year 40% excess over 1st year 342.90 Sqm 12.79 4385.69
4th year 60% excess over 1st year 662.94 Sqm 12.79 8479.00
5th year 80% excess over 1st year 582.93 Sqm 12.79 7455.67

4. Repair to pot holes and removal of loose material, trimming of sides, cleaning of surface
by providing tack coat, 20 mm thick pre-mix carpet and seal coat type C as per MORD
technical specification Clause 503,508,510,1904 as per direction of the Engineer in
charge.

Area/Km 1000x3.75=3000.00Sqm
1st year Take 0.7% of the area 137.16 Sqm 222.61 30533.19
2nd year 2 times of 1st year 274.32 Sqm 222.61 61066.38
3rd year 3 times of 1st year 425.20 Sqm 222.61 94652.88
4th year 4 times of 1st year 685.80 Sqm 222.61 152665.94
5th year 5 times of 1st year 1097.28 Sqm 222.61 244265.50

6. Maintenance of road signs by way of cleaning and repainting of mandatory / requlatory /


cautionary / informatory and place identifications sign board as perdrawings and
technical specification Clause 1910 of MORD as per direction of the Engineer in charge.

1st year No maintainance 0.00 Km 0.00 0.00


2nd year 100% maintainance 2.540 Km 1094.77 2780.72
3rd year No maintainance 0.00 Km 0.00 0.00
4th year Same as 2nd year 2.540 Km 1094.77 2780.72
5th year No maintainance 0.00 Km 0.00 0.00

7. Maintenance of 200 metre, km stones & 5th Km stones by way of refiting of tilted stones
repairing with cement mortar, cleaning, repairing and lettering on 200 metre km stone
and 5th km stone as per drawing and technical specification Clause 1912 of MORD as
per direction of the Engineer in charge.

1st year Take100% for maintainance 2.540 Km 698.46 1774.09


2nd year Same as 1st year 2.540 Km 698.46 1774.09
3rd year Same as 1st year 2.540 Km 698.46 1774.09
4th year Same as 1st year 2.540 Km 698.46 1774.09
5th year Same as 1st year 2.540 Km 698.46 1774.09
Sl.
Items of works Quantity Unit Rate Amount
No.
1 2 3 4 5 6
8. Cutting of branches of trees from the road way or with in R.O.W including disposal of
wood and leaves to suitable location as per technical specification Clause 1914 of
MORD as per direction of the Engineer in charge.

Considering 10 Nos per Km


1st year 10 Nos per Km 25.00 Nos. 112.48 2812.00
2nd year Same as 1st year 25.00 Nos. 112.48 2812.00
3rd year Same as 1st year 25.00 Nos. 112.48 2812.00
4th year Same as 1st year 25.00 Nos. 112.48 2812.00
5th year Same as 1st year 25.00 Nos. 112.48 2812.00

9. Cutting of shurb from the road way or with in R.O.W including disposal of wood and
leaves to suitable location as per technical specification Clause 1914 of MORD as per
direction of the Engineer in charge.
Considering 40 Nos per Km
1st year 40 Nos per Km 102.00 Nos. 6.80 693.60
2nd year Same as 1st year 102.00 Nos. 6.80 693.60
3rd year Same as 1st year 102.00 Nos. 6.80 693.60
4th year Same as 1st year 102.00 Nos. 6.80 693.60
5th year Same as 1st year 102.00 Nos. 6.80 693.60

10. Maintenance and repair of RCC railing to bring it to the original shape cleaning and
repainting as per drawings and technical specification clause 1911 as per direction of
Engineer in Charge.
Considering 0.540 per Km
1st year per Km 1.370 RM 1350.62 1850.35
2nd year Same as 1st year 1.370 RM 1350.62 1850.35
3rd year Same as 1st year 1.370 RM 1350.62 1850.35
4th year Same as 1st year 1.370 RM 1350.62 1850.35
5th year Same as 1st year 1.370 RM 1350.62 1850.35

11. Maintenance of Slab type Culverts by way of clearing, Cleaning, Erosion repair, repairs
to cracks, parapet walls and Protection works as per drawing and technical specification
Clasue 1908 of MORD as per direction of the Engineer in charge.

Considering 0.540 per Km


1st year per Km 2.000 Nos. 2211.50 4423.00
2nd year Same as 1st year 2.000 Nos. 2211.50 4423.00
3rd year Same as 1st year 2.000 Nos. 2211.50 4423.00
4th year Same as 1st year 2.000 Nos. 2211.50 4423.00
5th year Same as 1st year 2.000 Nos. 2211.50 4423.00

12. Triming of grass and weeds from the shoulder/berms and disposal the same to suitable
location as per technical specification Clause 1914 of MORD as per direction of the
Engineer in charge
Area/Km 2x1000x1.125=3000.00Sqm
1st year Take11.5% of the area 114.30 Sqm 2.26 258.32
2nd year 20% excess over 1st year 137.16 Sqm 2.26 309.98
3rd year 40% excess over 1st year 160.02 Sqm 2.26 361.65
4th year 60% excess over 1st year 182.88 Sqm 2.26 413.31
5th year 80% excess over 1st year 205.74 Sqm 2.26 464.97

13. White washing two coats on parapet walls and tree trunks including preparation of
surface by cleaning scraping etc. as per MORD technical specifications Clause 1915
as per direction of the Engineer in charge.
Considering 24 Sqm per Km
1st year Take 24 Sqm / Km 60.96 Sqm 27.67 1686.76
2nd year Same as 1st year 60.96 Sqm 27.67 1686.76
3rd year Same as 1st year 60.96 Sqm 27.67 1686.76
4th year Same as 1st year 60.96 Sqm 27.67 1686.76
5th year Same as 1st year 60.96 Sqm 27.67 1686.76

Total 2205917.33

Cost of % of Costn.
YEAR Maintain- ance Total Cost

For the 1st year 234726.33 234726.33 1.01


For the 2nd year 288316.38 288316.38 1.25
For the 3rd year 339432.36 339432.36 1.47
For the 4th year 573379.77 573379.77 2.48
For the 5th year 770062.49 770062.49 3.33
Grand Total 2205917.33 2205917.33 9.53%

6TH Year Maintenance


SDBC 2540 3.75 0.025 1713830.49
Primer 2540 3.75 287940.75
Restoration of Rain cuts 2540 0.5 0.2 66720.72
2068491.96

Junior Engineer Assistant Executive Engineer Executive Enginer


Sl.
Items of works Quantity Unit Rate Amount
No.
1 2 3 4 5 6

R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh


BASIC RATES
(B) USAGE RATES OF PLANT & MACHINERY
Description of Output of Machine Usage Rates in Rs.
Sr. No.
Machine Activity Unit Output Unit Rate

Supplying
PM-001 Air Compressor 210 cfm cfm 210.00 per hour 179.13
compressed air
BM, DBM,
PM-002 Batch mix HMP 100 TPH t/h 50.00 per hour 6,217.39
SDBC, PM
Applying
PM-003 Bitumen emulsion pressure distributor bitumen tack sqm/h 1750.00 per hour 448.70
coat
Electricity
PM-004 Electric generator set, 125 KVA KVA 100.00 per hour 786.96
generation
Loading
PM-005 Front end-loader 1 cum bucket capacity @ 45 cum/h 45.00 452.17
Aggregates per hour
cum/hour
Loading Soil cum/h 100.00 452.17
PM-006 Hydraulic broom with tractor Surface cleaning sqm/h 1250.00 per hour 200.00
PM-007 Tractor Grader per hour 251.30
Paver finisher Hydrostatic with sensor control
PM-008 Laying/spreading t/h 75.00 per hour 1,605.22
100TPH
Compaction of
PM-009 Smooth wheeled 80-100 kN tandem roller Sub-base/ cum/h 30.00 per hour 641.74
Asphalt
Compaction/
PM-010 Three wheel 80-100 kN Static Roller 294.78
Rolling
Earth:-
Embankment or
sub-grade cum/h 80/70 294.78

Sub-base G-I cum/h 10.00 294.78


Sub-base G-II/G- per hour
cum/h 8.00 294.78
III
WMM cum/h 16.00 294.78
BUSG cum/h 10.00 294.78
BM 50/75 mm cum/h 12.00 294.78
Premix 20 mm sqm/h 250.00 294.78
Seal Coat sqm/h 500.00 294.78
PM-011 Tipper 5.5 cum/10 t Carriage cum/trip 5.50 per hour 506.09
PM-012 Tractor with Rotavator Scarifier cum/h 25.00 per hour 210.44
Compaction of
PM-013 cum/h 100.00 864.35
soil WMM
Vibratory roller 80-100 kN per hour
Compaction of
cum/h 60.00 864.35
BM
PM-014 Water tanker 6 kl capacity (Truck Mounted) Carriage of water litre / h 12000.00 per hour 506.09
PM-015 Tractor with Trolley pulling per hour 200.87
PM-016 Hydraulic excavator 1 cum bucket capacity soil cum / h 60.00 per hour 730.43
PM-017 Dozer D-50- A 15 spreading cum / h 200.00 per hour 1,592.17
PM-018 Motor Grader spreading cum / h 200.00 per hour 1,343.48

Plant-Machinary
0 Block:- HarichandanpDist:- Keonjhar
Name of the Road :
Usage Rates of Plant and Machinery
(Ref : MORTH Data Book Chapter-17/Page-555)
Sr. Description of Machine Output of Usage Rates in Govt. of Accepted Rate
No Machine Rupees Orissa Rate by GOO
Machine Activity Unit Output Unit Rates Unit Rates Unit Rates
1 Dozer D-50- Spreading cum/hour 200 per hour 1592.17 1592.17
A 15 Cutting cum/hour 100 1592.17 1592.17
Cleaning cum/hour 150
2 Dozer D-80- Spreading cum/hour 300 per hour 2190.43 2190.43
A 12 Cutting cum/hour 150 2190.43 2190.43
Cleaning cum/hour 250 2190.43 2190.43
3 Tractor with Cleaning cum/hour 200 per hour 251.30 251.30
ordinary Spreading cum/hour 200
Grader 3.35 GSB cum/hour 50
meter blade WMM cum/hour 50
4 Hydraulic per hour 730.43 730.43
Excavater of Soil Ordinarry cum/hour 60
1 cum Soil Marshy cum/hour 60
bucket Soil Unsuitable cum/hour 60
5 Front end Soil Loading cum/hour 60 per hour 452.17 452.17
loader 1 Aggregate
cum bucket loading cum/hour 45
6 capacity
Tipper-5 Transportation Capacity 5.5 Per km 20.87 0 20.87
cum of soil, GSB, in cum Per
WMM, Hotmix tonne.k
etc. m 2.17 2.17

Per hour 506.09 506.09


7 Vibratory Earth/Soil Cum/hour 100 Per 864.35 864.35
Roller 8 GSB Cum/hour 60 Hour
tonne WMM Cum/hour 60
8 Smooth Soil per hour per
Wheeled Compaction cum/hour 70 294.78 hour 294.78
Roller 8 BM
tonne Compaction cum/hour 25
9 Truck
mounted
Water Water Capacity Per
Tanker Transport in KL 6 Hour 506.09 506.09
10 Tractor Puling Capacity
in H.P. 50 per hour 200.87 200.87
11 Rotavator
Scarifying cum/hour 25 per hour 9.57 9.57
12 Riper
Scarifying cum/hour 60 per hour 15.65 15.65
13 Air General capacity in 170/
Compressor Purpose cfm 250 per hour 179.13
179.13
14 Wetmix
Plant 60
TPH Wet Mix cum/hour 25 per hour 675.65 675.65
Sr. Description of Machine Output of Usage Rates in Govt. of Accepted Rate
No Machine Rupees Orissa Rate by GOO
Machine Activity Unit Output Unit Rates Unit Rates Unit Rates
15 Mechanical
broom Surface
Hydraulic Dressing sqm./hour 1250 per hour 200.00 200.00
16 Bitumen Applying
Pressure bitumen tack
Distributer coat sqm/hour 1750 per hour 601.74 601.74
17 Emulsion applying
Pressure emulsion tack
Distributer coat sqm/hour 1750 per hour 448.70 448.70
18 Hotmix
Plant- 120
TPH DBM/BM/SDC/
capacity Premix cum/hour 40 per hour 13130.43 13130.43
19 Hotmix
Plant- 100
TPH DBM/BM/SDC/
capacity Premix cum/hour 30 per hour 9710.43 9710.43
20 Hotmix
Plant-60 to
90TPH DBM/BM/SDC/
capacity Premix cum/hour 25 per hour 7765.22 7765.22
21 Hotmix
Plant-40 to
60 TPH DBM/BM/SDC/
capacity Premix cum/hour 17 per hour 6217.39 6217.39
22 Paver
Finisher
Hydrostatic
with sensor
controll 100 Paving of
TPH DBM/BM/
SDC/ Premix cum/hour 40 per hour 1500.00 1500.00
23 Paver Paving of
Finisher WMM cum/hour 40 per hour 642.61 642.61
Mechanical1
00 TPH Paving of DLC cum/hour 30 per hour 642.61 642.61
24 Hydraulic
Chip Surface
Spreader Dressing sqm/hour 1500 per hour 1478.26 1478.26
25 Tandem Rolling of
road Roller Asphalt
Surface cum/hour 30 per hour 641.74 641.74
26 Pneumatic Rolling of
Road Roller Asphalt
Surface cum/hour 25 per hour 697.39 697.39
27 Pot-hole
Repair Repair of pot-
Machine holes cum/hour 4 per hour 508.70 508.70
28 Bitumen
Boiler Oil Bitumen capacity in
Fired Spraying litre 1500 per hour 111.30 111.30
29 GSB Plant Producing
GSB cum/hour 40 per hour 582.61 582.61
Sr. Description of Machine Output of Usage Rates in Govt. of Accepted Rate
No Machine Rupees Orissa Rate by GOO
Machine Activity Unit Output Unit Rates Unit Rates Unit Rates
30 Mastic Mastic capacity in
Cooker Wearing Coat tonne 1 per hour 1379.13 1379.13
31(a Concrete Concrete
) Mixture Mixing cum/hour 7.5 per hour 153.91 153.91
31 Batching
(b) and Mixing
Plant 15-20
Cum Concrete
capacity Mixing cum/hour 13 per hour 1043.48 1043.48
32 Transit Transportation cum/hour 4.5 per hour 521.74 521.74
Mixer of Concrete
Mix to Site cum/hour 3 per hour 478.26 478.26
33(a Concrete
) Pump of 45
cum Pumping of
capacity Concrete cum/hour 33 per hour 143.48 143.48
33(b Concrete
) Pump of 30
cum Pumping of
capacity Concrete cum/hour 22 per hour 143.48 143.48
34(aCranes 80
) tonnes Lifting purpose per hour 717.39 717.39
34(bCranes 35
) tonnes Lifting purpose per hour 478.26 478.26
34© Cranes 3
tonnes Lifting purpose per hour 200.00 200.00
35 Cocrete For Pouring capacity in
Bucket Cocrete cum 1 per hour 8.70 8.70
36 Kerb
Casting
Machine Kerb Making Rm/hour 80 per hour 173.91 173.91
37(a Concrete
) Mixing . Concrete
4/0.28 cum Mixing cum/hour 2.5 per hour 153.91
153.91
37(b Concrete
) Mixing 01 Concrete
cum Mixing cum/hour 7.5 per hour 153.91 153.91
38 Piling Rig 0.75m dia to
with 1.2met. Dia
Bantonite Boring
Pump attachment rm/hour 2.5 per hour 3065.22 3065.22
39 Concrete
Paver
Finisher with
Paving of
40 HP Motor
Concrete
Surface cum/hour 20 per hour 1608.70 1608.70
40 Integrated
Stone TPH 100 per hour 4860.87 4860.87
Crushing of
Crusher
Spalls TPH 200 per hour 10226.09 10226.09
Sr. Description of Machine Output of Usage Rates in Govt. of Accepted Rate
No Machine Rupees Orissa Rate by GOO
Machine Activity Unit Output Unit Rates Unit Rates Unit Rates
41 Prestressng
Jack with Stressing of
Pump & Steel
access wire/stands per hour 72.17 72.17
42(a Generater Generation of
) 100kva Electricity KVA 100 per hour 391.30 391.30
42(b Generater Generation of
) 33kva Electricity KVA 50 per hour 208.70 208.70
43 Pneumatic Pneumatic
Sinking Sinking of
Plant Wells cum/hour 1.75 per hour 2339.13 2339.13
44(a Truck 5.5
) cum per 10 Material Capacity/
tonnes Transport cum 4.5 per km 17.39 17.39
44(b Truck 5.5
) cum per 10 Material Capacity/
tonnes Transport cum Per hour 484.35 484.35
45 Road
Making
Machine Road Making sqm/hour 100 per hour 52.17 52.17
46 Mobile Mixing and
Slurry Seal laying slurry
equipment seal sqm/hour 2700 per hour 565.22 565.22
47 Concrete
joint cutting
machine for
initial and
final cut
hour per hour 293.91 293.91
48 Mixal 6-10T For admixing
Capacity bitumen &
chips hour per hour 891.30 891.30
49 Needle/ For Concrete
Screed/ compaction
Plate
Vibrator hour per hour 92.17 92.17
50
per hour 1,343.48 1,343.48
MOTOR GRADER
HIRE CHARGES OF MACHINARIES
Sl. No. Description Unit Rate of Mechinaries
M-001 Drum mix plant 40-60TPH Hour -
M-002 Batch mix HMP 100 TPH Hour 6,217.39
Mixcell 6-10 t capacity Hour 891.30
M-003 Truck 10 ton (as per S/R) Hour 484.35
M-004 Truck load(5Km)(as per S/R) Trip 1,320.57
M-005 Bitumen pressure distributor with Bitumen Hour 601.74
M-006 Bitumen pressure distributor with Emulsion Hour 448.70
M-007 Generator of 125KVA Hour 786.96
M-008 Front end loader 1cum capacity Hour 452.17
M-009 PRR 8-10 ton Hour 294.78
M-010 Tractor with ordinary grader Hour 251.30
M-011 Vibrator Roller 10Ton Hour 864.35
M-012 Tractor 50H.P. with trolly Hour 231.00
M-013 Tractor 50H.P. with ripper Hour 216.52
M-014 Tractor 50H.P. with rotovator Hour 210.44
M-015 Air compressor 170 CFM Hour 179.13
M-016 Bitumen boiler 4.5ton (1000 litre) Hour 111.30
M-017 Niddle vibrator/ Plate vibrator Hour 92.17
M-018 Tipper 10 ton Hour 506.09
M-019 Water tanker 6kl capacity Hour 506.09
M-020 Hydraulic broom with tractor Hour 200.00
M-021 Concrete Mixer Hour 153.91
M-022 Tandem roller 80-100 KN Hour 641.74
M-023 Hydraulic excavator 0.9 cum bucket capacity Hour 730.43
M-024 Joint cutting machine with 2-3 blades Hour 300.00
M-025 Tipper 10 ton t.km 2.17
M-026 Wet mix plant Hour 675.65
M-027 Dozer D-50 Hour 1,592.17
M-028 Plate compactor Hour 92.17
Motor graded 110hp @ 50 cum per hour Hour 1,343.48
LABOUR RATE
1. Highly skilled Day 430.00
2. Skilled Day 370.00
3. Semi-skilled Day 320.00
4. Mazdor Day 280.00

ROYALTY

1. Sand & Moorum 35.00


2. Stone Product 130.00
LEAD STATEMENT
Name of the Road : Nandighore to Saliajhari
District : Nayagarh Block : Odagaon

Lead in Lead Basic Rate of


Sl. No. Description Unit Name of Quarry Total
KM Cost. Keonjhar

M-001
AC pipe 100mm mtr. Keonjhar 70.52 70.52
M-002
Aggregate 10 mm cum Tapanga 107.00 900.21 1066.67 1966.88
M-003
Aggregate 20 mm cum Tapanga 107.00 900.21 1007.62 1907.83
M-004
Aggregate 25 mm cum Tapanga 107.00 900.21 738.52 1638.73
M-004
Aggregate 40 mm chips cum Tapanga 107.00 900.21 706.67 1606.88

M-005 Aggregate- Crushable type such as moorum or


Gravel for Grading III cum Rohibanka 5.00 149.67 45.71 195.38
M-006 Aggregate-Grading I 90 mm to 45 mm cum 107.00 900.21 597.14 1497.35
Tapanga

M-007 Aggregate-Grading II 63 mm to 45 mm cum 107.00 900.21 661.90 1562.11


Tapanga

M-008 Aggregate-Grading III 53 mm to 22.4 mm cum 107.00 900.21 704.76 1604.97


Tapanga

M-009 Binding wire kg 149.67 67.23 216.90


M-010
Binding material (stone screening) cum Tapanga 107.00 900.21 730.00 1630.21

M-011
Deduct for empty Drums Bitumen (S-65) MT bhubaneswar 107.00 930.50 30169.58 31100.08

M-012
Deduct for empty Drums Bitumen Emulsion RS-1 MT Paharpur 393.00 2929.64 26080.70 29010.34

M-013
Deduct for empty Drums Bitumen Emulsion SS-1 MT Paharpur 393.00 2929.64 25520.70 28450.34

M-014
Deduct for empty Drums Bitumen Emulsion MS MT Paharpur 393.00 2929.64 26280.70 29210.34
M-015
Cement(excluding cost of empty gunny bags) MT Nayagarh 20.00 285.02 4776.80 5061.82
M-016
Cement Primer litre 119.69 119.69
M-017
Compressible fibre board sqm 850.14 850.14

M-018 Crushed Stone Aggregate 53 mm to 9.5mm


=(45mm+22.4mm+12mm)/3 cum Tapanga 107.00 900.21 789.32 1689.53
M-019
Crushed Stone chipping 13.2 mm nominal size cum Tapanga 107.00 900.21 1024.76 1924.97

M-020 Crushed Stone Chipping 6.7 mm size


( passing 11.2 mm and retained on 2.36 mm) cum Tapanga 107.00 900.21 704.16 1604.37

M-021 Crushed Stone Chipping 6.7 mm size (passing 9.5


mm and retained on 2.36 mm) cum Tapanga 107.00 900.21 704.76 1604.97
M-022 Fevicol adhesive kg 149.67 171.65 321.32
M-023 Filter media (45mm hand broken) cum Tapanga 107.00 900.21 489.52 1389.73
M-024 Indigo kg 59.06 59.06
M-025
Jute rope 12 mm dia mtr. 9.45 9.45
M-026 Lime MT 19000.00 19000.00
M-027 MS clamps Nos. 75.00 75.00
M-028 RCC Pipe NP3 (350 mm dia) mtr. saranakula 21.00 262.84 727.92 990.76
M-029 RCC Pipe NP3 (600 mm dia) mtr. saranakula 21.00 262.84 1730.98 1993.82
M-030 RCC Pipe NP3 (1000 mm dia) mtr. saranakula 21.00 262.84 4048.20 4311.04
Lead in Lead Basic Rate of
Sl. No. Description Unit Name of Quarry Total
KM Cost. Keonjhar

M-031 RCC Pipe NP3 (1200 mm dia) mtr. saranakula 21.00 262.84 4367.21 4630.05
M-032 Red-oxide Primer litre 96.06 96.06
M-033 Road marking paint litre 108.34 108.34
M-034 Sand for filling cum Sidhamula 68.00 657.63 46.67 704.30
M-035 Sand for mortar cum Sidhamula 68.00 657.63 41.90 699.53
M-036 Steel HYSD Bars (8mm to 16mm) MT Nayagarh 20.00 285.02 45460.00 45745.02
M-037 Steel HYSD Bars (20mm to 25mm) MT Nayagarh 20.00 285.02 45460.00 45745.02

M-038
Stone Chips 12 mm size cum Tapanga 107.00 900.21 1047.62 1947.83

M-039 Stone Chips 11.2mm (passing 13.2 mm to retained


5.6 mm) cum Tapanga 107.00 900.21 1049.52 1949.73
M-040 Random Rubble H.G.Stone cum Tapanga 107.00 900.21 200.87 1101.08
M-041 Stone spall cum Tapanga 107.00 900.21 141.90 1042.11

M-042 Stone Screened Dust Passing through 2.36mm


Sieveb and retained on 0.075mm sieve. cum Tapanga 107.00 900.21 76.19 976.40
M-042 Moorum cum Rohibanka 14.00 228.87 47.63 276.50

M-043 Well Graded Material for Sub-Base - Grading III 2.36


mm below cum Sidhamula 68.00 657.63 976.00 1633.63

M-044 Well Graded Material for Sub-Base - Grading III 4.75


mm to 2.36 mm cum Rohibanka 5.00 149.67 745.00 894.67

M-045 Well Graded Material for Sub-Base - Grading III 9.5


mm to 4.75 mm cum Rohibanka 5.00 149.67 999.50 1149.17
M-046 Bituminous sealant litre 20.00 20.00
M-047 Curing compound litre 30.00 30.00
M-048 Plasticizer litre 40.00 40.00
M-049 Polythene sheet (125 micron) sqm 3.00 3.00
M-050 Polythene Sheething Nos. 8.00 8.00
M-051
Debonding strips mtr. 60.00 60.00
M-052 M.S.Angle Kg 42.00 42.00
M-053 Joint filler board (20mm) sqm 852.94 852.94
M-158 H.G. Stone Grainte Cum 182.00 182.00
M-043 Bond Stone (400mm x 150mm x 150mm) Nos. 12.00 12.00

Certified that the leads provided in this statement are correct to the best of my knowledge.

Junior Engineer Assistant Executive Engineer Executive Enginer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh
CHAPTER-1
SITE CLEARANCE
Name of the Road : Nandighore to Saliajhari Format - 8

Sr. Ref. to Rate Amount


Description Unit Quantity
No. MORD Spe (Rs.) (Rs.)

1.1 Loading and Unloading of Lime, Aggregate, Stone boulder,


Brick aggergates, Building rubbish, Crushed slag, by Manual
means
(ii) Loading by Manual means including a lead upto 30m
Unit = cum
Taking output = 5.5 cum
a) Labour
Mate day 0.01 320.00 3.20
Mazdoor (Unskilled) day 0.25 280.00 70.00
b) Machinery
Truck 10 ton hour 0.2273 484.35 110.09
c) Overheads @ 15 % on (a+b) 0.00

Cost for 5.5 cum=(a+b+c) 183.29


Rate per cum = (a+b+c)/5.5 33.33
Labour welfare Cess 1% 0.33
33.66
(iv) Loading by Manual means including a lead upto 30m
Unit = cum
Taking output = 5.5 cum
a) Labour
Mate day 0.005 320.00 1.60
Mazdoor (Unskilled) day 0.125 280.00 35.00
b) Machinery
Truck 10 ton hour 0.151 484.35 73.14
c) Overheads @ 15 % on (a+b) 0.00

Cost for 5.5 cum=(a+b+c) 109.74


Rate per cum = (a+b+c)/5.5 19.95
Labour welfare Cess 1% 0.20
20.15

(i). Speed Breaker


* * Construction of rounded (17 meter radius,3.7 m width and 10 cms
height) Hump type of speed breaker for general traffic at prefered
crossing of 25 kmph" including cleaning for dust and loose
particles and tack coad is applied and hot premix bitumen is pour
as per the direction of the Engineer in charge.
Unit = Nos
Volume of One Humpon carriageway portion 0.555cum
Consume of PMC Volume Cum 0.555 0.00 0.00
Consume of Tack Coat Area Sqm 11.100 10.09 112.00
Consume of GSB Volume Cum 0.370 686.48 254.00
Rate Per 1 No 366.00
CHAPTER-2
SITE CLEARANCE
Name of the Road : Nandighore to Saliajhari Format - 8

Sr. Ref. to Rate


Description Unit Quantity Amount (Rs.)
No. MORD Spe. (Rs.)

2.1 201 Clearing Grass and Removal of Rubbish


Clearing grass and remocval of rubbish up to a distance of 30m outside the
periphry of the area as per technical specification
By Manual Means
Unit = hectare
Taking output = 1 hectare
a) Labour
Mate day 1.60 320.00 512.00
Mazdoor (Unskilled) day 40.00 280.00 11,200.00
b) Overheads @ 15 % on (a) 1,756.80

Rate per hectare = a+b 13,468.80


Rate per Sqm 1.35
Labour welfare Cess 1% 0.0135
1.36

2.2 201 Clearing and Grubbing Road Land


Clearing and grubbing road land including uprooting wild vegetation, grass,
bushes, shrubs, saplings and trees of girth upto 300 mm, removal of stumps of
such trees cut earlier and disposal of unserviceable materials and stacking of
serviceable material to be used or auctioned, upto a lead of 1000 m including
removal and disposal of top organic soil not exceeding 150 mm in thickness as
per Technical Specification Clause 201.

Unit = hectare
Taking output = 1 hectare
(I) By Manual Means
(A) In area of non-thorny jungle
a) Labour
Mate day 6.00 320.00 1,920.00
Mazdoor (Unskilled) day 150.00 280.00 42,000.00
b) Machinery
Tractor with trolley hour 1.00 231.00 231.00
c) Overheads @ 15 % on (a+b) 6,622.65

Rate per hectare = a+b+c 50,773.65


Rate per Sqm 5.08
Labour welfare Cess 1% 0.05
5.13

2.5 202 Dismantling of Structure


Dismantling of existing structures like culverts, bridges, retaining walls and other
sturcture comprising of masonry, cement concrete wood work, steel work,
including T&P and scaffolding wherever necessary, sorting the dismantled
material, disposal of unserviceable materials and stacking the serviceable
materials with all lifts and lead of 1000m as per Technical Specification Clause
202

Unit = cum
Tacking output = 1.25 cum
(i) By Manual Means
(C) Reinforced Cement Concrete
a) Labour
Mate day 0.15 320.00 48.00
Blacksmit day 0.25 370.00 92.50
Mazdoor (Unskilled) day 3.5 280.00 980.00
Sr. Ref. to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spe. (Rs.)

b) Machinery
Tractor with trolley hour 0.27 231.00 62.37
c) Overheads @ 15% on (a+b) 177.43
Cost for 1.25 cum = a+b+c 1,360.30
Rate per Cum (a+b+c+d)/1.25 1088.24
Labour welfare Cess 1% 10.88
1,099.12

(B) Cement Concrete


a) Labour
Mate day 0.05 320.00 16.00
Mazdoor (Unskilled) day 1.25 280.00 350.00

b) Machinery
Tractor with trolley hour 0.27 231.00 62.37
c) Overheads @ 15% on (a+b) 64.26
Cost for 1.25 cum = a+b+c 492.63
Rate per Cum (a+b+c+d)/1.25 394.10
Labour welfare Cess 1% 3.94
398.04
CHAPTER -3
EARTHWORK, EROSION CONTROL AND DRAINAGE
Name of the Road : Nandighore to Saliajhari

Ref. to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Spe.

3.3 Construction of Embankment with Materials obtained


301.5(I) Construction of Embankment with Material Obtained fron Borrow Pits
(B) By mechanical carraige with a lead upto 1000m
Construction of subgrade / Earthern shoulder with approved
materials obtained from borrow pits, transporting to site, spreading,
grading to required slope and compacting to meet requirement as
per MORD technical Specification Clause 303 with all leads & lift as
per direction of the Engineer in charge (By mechanical means).
for 100 cum
a) Labour
Mate day 0.04 320.00 12.80
Mazdoor(Unskilled) day 1.00 280.00 280.00

b) Machinery
Hydraulic excavator 0.9 cum bucket capacity @60 cum per hour Hour 1.67 730.43 1,219.82
Tipper 5.5 cum with 10t capacity Hour 8.59 506.09 4,347.31
Loading of earth as per item 1.1(ii) cum 100.00 33.33 3,332.55
Unloading of earth as per item 1.1(iv) cum 100.00 19.95 1,995.27
Dozer D-50 for spreading @200 cum per hour Hour 0.50 1,592.17 796.09
Tractor grader for grading @200 cum per hour Hour 0.50 251.30 125.65
Three wheel 80-100 kN static roller hour 1.43 294.78 421.54
Water tanker 6 kl capacity hour 2.00 506.09 1,012.18
c) Material
Water kl 12.00 0.00 0.00
Compensation for earth cum 100.00
d) Over head charge 15% on (a+b+c) 2,031.48

Cost per 100Cum 15,574.68


d) Royalty cum 100.00 35.00 3,500.00
Cost per cum =(a+b+c+d) 190.75
Labour welfare Cess 1% 1.91
192.66

301.5
(B) From road way cutting & excavation of Foudation
for 100 cum
a) Labour
Mate day 0.02 320.00 6.40
Mazdoor(Unskilled) day 0.50 280.00 140.00

b) Machinery
Dozer D-50 for spreading @200 cum per hour Hour 0.50 1,592.17 796.09
Tractor motor grader for grading @200 cum per hour Hour 0.50 251.30 125.65
Three wheel 80-100 kN static roller hour 1.25 294.78 368.48
Water tanker 6 kl capacity hour 2.00 506.09 1,012.18
c) Material
Water kl 12.00
d) Over head charge 15% on (a+b+c) 367.32

Cost per 100Cum 2,816.11


Cost per cum =(a+b+c+d) 28.16
Labour welfare Cess 1% 0.28
28.44

State S/R Fine Dressing & Turfing


Fine dressing and turfing including transportation by mechanical means with all lead
and lift and placing of turf in position and ramming with thapies and including watering
and cost of all labour, materials etc. complete as per Clause 309 of MORD
Specification and as per direction of the Engineer in Charge.
Ref. to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Spe.
Unit = 1sqm
Talking output = 100 sqm
a) Labour
Male Mulia (for fine dressing earth & cutting turf) day 1.40 280.00 392.00
Male Mulia (for placing turf & ramming) day 0.74 280.00 207.20
b) Material
Quantity of turf required 6.25 cum (av. Thick-6.25cm)
Conveyance charges cum 6.25 149.67 935.44
c) Watering charges L.S.
d) Over head charge @ 15% on (a) 230.20
Cost for 100 sqm = a+b+c+d+e 1,764.84
Rate per sqm = (a+b+c+d)/100 17.65
Labour welfare Cess 1% 0.18
17.83
3.3 301.5 Construction of Embankment with Material Obtained from Roadway Cutting
Construction of embankment with approved materials deposited at site from roadway
cutting and excavation from drain and foundation of other structures graded and
compacted to meet requirement as per MORD technical Specification Clause 301 and
direction of the Engineer in Charge (excluding cost of excavation and transportation to
site).

Unit = Cum
Talking output = 100 Cum
a) Labour
Mate day 0.02 320.00 6.40
Mazdoor (Unskilled) day 0.50 280.00 140.00
b) machinery
Dozer D-50 for Spreading @ 200cum per hour Hour 0.50 1,592.17 796.09
Tractor mounted ordinary grade for grading @ 200cum per hour Hour 0.50 251.30 125.65
Water tanker 6 KL Capacity Hour 2.00 506.09 1,012.18
Three wheel 80-100 KN static Roller Hour 1.25 294.78 368.48
c) Material 0.00
Water KL 12.00 0.0 0.0
d) Over head charge @ 15% on (a+b+c) 367.32
Rate Cost for 100 sqm = a+b+c+d 2,816.12
Rate per sqm = (a+b+c+d)/100 28.16
Labour welfare Cess 1% 0.28
28.44
2.4 302 Excavation
Excavation for road work in soil with hydraulic excavator of 0.9 cum bucket capacity
including cutting and loading in tippers, trimming bottom and side slopes, inaccordance
with requirements of lines, grades and cross sections, and transporting to the
embankement location with a lift of up to 1.5m and lead up to 1000m as per techincal
specification clause 302.3.

Unit = Cum
Talking output = 360 Cum
a) Labour
Mate day 0.08 320.00 25.60
Mazdoor (Unskilled) day 2.00 280.00 560.00
b) Machinery
Tipper Hour 15.00 506.09 7,591.35
Hydraulic Excavation Hour 3.60 730.43 2,629.55
c) Over head charge @ 15% on (a+b) 1,620.98
Rate Cost for 100 sqm = a+b+c+d 12,427.48
Rate per sqm = (a+b+c+d)/360 34.52
Labour welfare Cess 1% 0.35
34.87
1. Excavation in Hard Rock
a. Excavation in Hard Rock (blasting prohibited by mechanical means) as per technical specificaation clause 302

Unit = Cum
Talking output = 36 Cum
a) Labour
Mate day 0.40 320.00 128.00
Mazdoor (Unskilled) day 10.00 280.00 2,800.00
b) Machinery
Hydraulic excavator 0.9 cum bucket capacity @60 cum per hour Hour 6.00 730.43 4,382.58
Ref. to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Spe.
Tipper 6.05 cum with 10t capacity Hour 5.909 506.09 2,990.49
Credit for excavated rock found suitable for use @ 50% of excavated quantity 3,564.00
Cum 18.000 198.00
6,737.07

c) Over head charge @ 15% on (a+b) 1,010.56


Rate Cost for 100 sqm = a+b+c 7,747.63
Rate per sqm = (a+b+c)/360 215.21
Labour welfare Cess 1% 2.15
217.36
8.3 1600 & Earth work in stoney Earth not Requiring Blasting
300

(ii). Excavation in ordinary rockusing hydraullic ecavator of 0.9cum bucket capacity


including Cutting and loading in tippers,transporting to embankment embnankment site
with a lead upto 1000m. , Trimming buttom nd side slopes in accordance with
requirements of lines, grades and cross-sections as[er technical specification
clause302.3.5.

Unit = Cum
Talking output = 240 Cum
a) Labour
Mate day 0.08 320.00 25.60
Mazdoor (Unskilled) day 2.00 280.00 560.00
b) Machinery
Hydraulic Excavator 0.9cum Bucket capacity @60cum/hour Hour 6.00 840.00 5,040.00
Tipper 6.05cum with 10T capacity Hour 10.00 582.00 5,820.00
c) Over head charge @ 15% on (a+b) 1,716.84
Rate Cost for 100 sqm = a+b+c 13,162.44
Rate per sqm = (a+b+c)/240 54.84
Labour welfare Cess 1% 0.55
55.39

8.3 1600 & Cutting D.I. Rocks


300

(iv). Cuting in Disintegrated rocks not requiring blasting to be removed by picked axes and
crow bars and depositing materials with 50m. Initial lead and 1.5m initial lift including
rock dressing as per direction and specification of thhe department including stacking
the usefull materials separately as order .

Unit = Cum
Talking output = 100 Cum
a) Labour
Mate day 55.00 280.00 15,400.00
Mazdoor (Unskilled) day 54.00 280.00 15,120.00
Mazdoor For Disposing of Earth upto 20m day 0.00 280.00 0.00
c) Over head charge @ 15% on (a+b) 4,578.00
Rate Cost for 100 sqm = a+b+c 35,098.00
Rate per sqm = (a+b+c)/100 350.98
Labour welfare Cess 1% 3.51
354.49
CHAPTER -4
GRANULAR SUB-BASES, BASES (NON-BITUMINOUS) SHOULDER
Name of the Road : Nandighore to Saliajhari Format - 8
Ref. to
Sr. Rate
MORD Description Unit Quantity Amount (Rs.)
No. (Rs.)
Spe.

300 Filling Sand in foundation in trenches as per drawing and technical specification
&
11.2
1200 clause 305.3.9.
1 Sand filling
Unit cum
a) Labour
Mate day 0.01 320.00 3.20
Mazdoor (Skilled) day 0.30 280.00 84.00
c) Material
Sand (assuming 20 percent voids) cum 1.20 704.30 845.16
d) Overheads @ 15% on (a+b) 139.85
e) Royalty
Sand (assuming 20 percent voids) cum 1.20 35.00 42.00
Rate per cum (a+b+c+d) 1,114.21
Labour welfare Cess 1% 11.14
1,125.35

Construction of Shoulder with approaved materials like Moorum obtained from


locality with all lift and leads transporting to site, spreading, grading to required
slope and compacting to meet requirement of tables 300.2 with all lead and lifts
as per Technical Specification clause 303.1.

(iii) (Moorum )
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.04 320.00 12.80
Mazdoor (Skilled) day 1.00 280.00 280.00
b) Machinery
Hydraulic excavator 0.9 cum bucket capacity @ 60cum per hour hour 1.00 730.43 730.43
Tipper 6.05 Cum hour 4.09 506.09 2,069.91
loading of earth as per item 1.1(ii) Cum 100.00 33.66 3,366.00
unloading of earth as per item 1.1(iv) Cum 100.00 20.15 2,015.00
Dozer D-50 for spreading @ 200 Cum per hour hour 0.50 1,592.17 796.09
Tractor Grader hour 0.50 251.30 125.65
Water Tanker 6kl capacity hour 2.00 506.09 1,012.18
Three wheel 80-100kN Static Roller @ 80 Cum hour 1.43 641.74 917.69
c) Material
Moorum cum 100.00 276.50 27,650.00

d) Overheads @ 15% on (a+b+c) 5,846.36


Cost for 300 cum = a+b+c+d+e 44,822.10
Labour welfare Cess 1% 448.22
Rate per cum = (a+b+c+d+e)/100 452.70
e) Royalty
Moorum % sand cum 1.00 35.00 35.00

487.70

4.2 402 Gravel Aggregate Sub-base (Table 400.1)


(iii) By Mix in Place Method
Ref. to
Sr. Rate
MORD Description Unit Quantity Amount (Rs.)
No. (Rs.)
Spe.
Construction of granular sub-base (sand & admixture) by providing well graded
material, spreading in uniform layers with grader on prepared surface, mixing by
mix in place method with rotavator at OMC and compacting with smooth wheel
roller to achieve the desired density,complete as per MORD Technical
Specification Clause 401 as per direction of Engineer-in-Charge.

(iii) For Grading III Material


Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.48 320.00 153.60
Mazdoor (Skilled) day 2.00 370.00 740.00
Mazdoor (Unskilled) day 10.00 280.00 2,800.00
b) Machinery
Tractor with ordinary Grader @ 50 cum per hour hour 6.00 251.30 1,507.80
Three wheel 80-100 kN static roller @ 10 cum per hour hour 30.00 294.78 8,843.40
Water tanker 6 kl capacity hour 5.00 506.09 2,530.45
c) Material
Well graded granular sub-base material as per Table 400.1

53 mm to 9.5 mm @ 50 per cent cum 192.00 1,689.53 324,390.40


9.5 mm to 2.36 mm @ 20 per cent cum 77.00 1,149.17 88,486.09
2.36 mm below @ 30 per cent cum 115.00 1,633.63 187,867.45
Water kl 30.00 0.00
d) Overheads @ 15% on (a+b+c) 92,597.88
e) Royalty
53 mm to 9.5 mm @ 50 per cent cum 192.00 130.00 24,960.00
9.5 mm to 4.75 mm @ 70 per cent cum 77.00 35.00 2,695.00
2.36 mm below @ 30 per cent cum 115.00 35.00 4,025.00
Cost for 300 cum = a+b+c+d+e 741,597.07

Rate per cum = (a+b+c+d+e)/300 2,471.99


Labour welfare Cess 1% 24.72
2,496.71

(iii) For (Moorum & Sand admixure)


Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.48 320.00 153.60
Mazdoor (Skilled) day 2.00 370.00 740.00
Mazdoor (Unskilled) day 10.00 280.00 2,800.00
b) Machinery
Tractor with Mount Grader @ 25 cum per hour hour 12.00 251.30 3,015.60
Three wheel 80-100 kN static roller @ 10 cum per hour hour 30.00 294.78 8,843.40

Water tanker 6 kl capacity hour 5.00 506.09 2,530.45


Tractor with Rotavater @ 25 cum per hour hour 12.00 210.44 2,525.28
c) Material
Well graded granular sub-base material as per Table 400.1
cum 360.00

70 per cent (Moorum) cum 252.00 276.50 69,678.00


30 per cent (Sand) cum 108.00 704.30 76,064.40
Water kl 30.00 0.00
d) Overheads @ 15% on (a+b+c) 24,952.61
e) Royalty
70 per cent (Moorum) cum 252.00 35.00 8,820.00
30 per cent (Sand) cum 108.00 35.00 3,780.00
Cost for 300 cum = a+b+c+d+e 203,903.34

Rate per cum = (a+b+c+d+e)/300 679.68


Ref. to
Sr. Rate
MORD Description Unit Quantity Amount (Rs.)
No. (Rs.)
Spe.
Labour welfare Cess 1%
6.80
686.48

Construction of Gravel/soil Aggregate Sub Base/Base by providing well graded


material of nominal maximum size grading 20 mm as per Table 2.3 of IRCSP 77-2008
dpreading in uniform layers with tractor mount appropriate grading arrangements on
prepared surface, mixing by place in method at OMC with tractor mount appropriate
rotavator attachment & compaction with 3 wheel 80-100 KNstatic roller capacity to
achieve the desired density complete as per specification contained in para 2.2,3.6&of
IRCSP 77-2008.

(iii) For Grading III Material


Unit = cum
Taking output =225 cum
a) Labour
Mate day 0.48 370 177.60
Mazdoor (Skilled) day 2 320 640.00
Mazdoor (Unskilled) day 10 280 2,800.00
b) Machinery
Tractor mounted Grader 110 HP @ 25 cum per hour hour 6.00 1,343.48 8,060.88
Three wheel 80-100 kN static roller 10 cum per hour hour 6.00 864.35 5,186.10
Tractor with Rotavator 25 cum per hour hour 12.00 210.44 2,525.28
Water tanker 6 kl capacity hour 3.00 506.09 1,518.27

c) Material

9.5mm to 4.75 mm cum 110.80 859.53 95,235.92


4.75 mm to 2.36 mm cum 36.00 638.10 22,971.60
stone screened dust cum 151.20 80.95 12,239.64
cost of water kl 27 10 270.00

d) Overheads @ 15% on (a+b+c) 22,743.79


e) Add for Royalty
9.5mm to 4.75 mm cum 110.80 1030.21 114,147.27
4.75 mm to 2.36 mm cum 36.00 1030.21 37,087.56
stone screened dust cum 151.20 935.21 141,403.75
Cost for 225 cum = a+b+c+d+e 467,007.66

Rate per cum = (a+b+c+d+e)/225 2,075.59


Labour welfare Cess 1% 20.76
2,096.35
Ref. to
Sr. Rate
MORD Description Unit Quantity Amount (Rs.)
No. (Rs.)
Spe.

4.8 405 Water Bound Macadam with Crushable Screenings


Providing, laying, spreading and compacting stone aggregates of specific sizes
to water bound macadam specification including spreading in uniform thickness,
hand packing, rolling with three wheel 80-100 kN static roller in stages to proper
grade and camber, applying and brooming, crushable screening(morum and
sand admixture) to fill-up the interstices of coarse aggregate, watering and
compacting to the required density as per Technical Specification Clause 405 of
MoRD & as per direction of Engineer-in-Charge.
2) WBM Grade -II
(A) By Manual Means
Unit = cum
Taking output = 360 cum
a) Labour
Mate day 10.08 320.00 3,225.60
Mazdoor (Skilled) day 2.00 370.00 740.00
Mazdoor (Unskilled) day 250.00 280.00 70,000.00
b) Machinery
80-100 kN static roller @ 8 cum per hour hour 45.00 294.78 13,265.10
Motor graded 110hp @ 50 cum per hour hour 7.20 1,343.48 9,673.06
Water tanker 6 kl capacity hour 24.00 506.09 12,146.16
c) Material (Refer Tables 400.7, 8, 9 and 10)
Aggregate
Grade-II ( 63 mm to 45 mm) @ 0.91 cum per 10 sqm for compacted cum 435.60 661.90 288,323.64
thickness
11.2 of 75
MM stone mm
screening cum 96.01 1,049.52 100,764.42

Stone screened dust cum 28.80 76.19 2,194.27

Water kl 144.00
d) Overheads @ 15% on (a+b+c) 75,049.84

e) Royalty
Aggregate
Grade-II ( 63 mm to 45 mm) @ 0.91 cum per 10 sqm cum 435.60 1,030.21 448,759.48
11.2 MM stone screening cum 96.01 1,030.21 98,910.46

Stone screened dust cum 28.80 935.21 26,934.05

Cost for 360 cum = a+b+c+d+e 1,149,986.07


Rate per cum = (a+b+c+d+e)/360 3,194.41
Labour welfare Cess 1% 31.94
3,226.35

3) WBM Grade -III


(A) By Manual Means
Unit = cum
Taking output = 360 cum
a) Labour
Mate day 10.08 320.00 3,225.60
Mazdoor (Skilled) day 2.00 370.00 740.00
Mazdoor (Unskilled) day 250.00 280.00 70,000.00
b) Machinery
80-100 kN static roller @ 8 cum per hour hour 45.00 294.78 13,265.10
Motor graded 110hp @ 50 cum per hour. hour 7.20 1,343.48
Water tanker 6 kl capacity hour 24.00 506.09 12,146.16
c) Material (Refer Tables 400.7, 8, 9 and 10)
Aggregate
Grade-III 53 mm to 22.4 mm @ 0.91 cum per 10 sqm for compacted cum 435.60 704.76 306,993.46
thickness of 75screening
11.2 MM stone mm cum 86.40 1,049.52 90,678.53

d) Overheads @ 15% on (a+b+c) 74,557.33

e) Carriage & Royalty


Aggregate
Grade-III 53 mm to 22.4 mm cum 435.60 1,030.21 448,759.48
Crushable type Moorum or gravel for Grade-III cum 86.40 935.21 80,802.14
Ref. to
Sr. Rate
MORD Description Unit Quantity Amount (Rs.)
No. (Rs.)
Spe.
Cost for 360 cum = a+b+c+d+e 1,101,167.79
Rate per cum = (a+b+c+d+e)/360 3,058.80
Labour welfare Cess 1% 30.59
3,089.39
4.6 404 Cement Treated Soil Sub-Base
Construction of Gravel/soil Aggregate Sub Base/Base by providing well
graded material of nominal maximum size grading 20 mm as per Table
2.3 of IRCSP 77-2008 spreading in uniform layers with tractor mount
appropriate grading arrangements on prepared surface, mixing by place in
method at OMC with tractor mount appropriate rotavator attachment &
compaction with 3 wheel 80-100 KNstatic roller capacity to achieve the
desired density complete as per specification contained in para 2.2,3.6&of
IRCSP 77-2008.

Unit = cum
Taking output = 300 cum (525t)
For 3 percent quantity of cement by weight of soil.
a) Labour
Mate day 0.4 320.00 128.00
Mazdoor (Skilled) day 2.00 370.00 740.00
Mazdoor (Un-Skilled) day 8.00 280.00 2240.00
Ref. to
Sr. Rate
MORD Description Unit Quantity Amount (Rs.)
No. (Rs.)
Spe.
b) Material
Cement at site @ 3% (of 525t) day 15.75 5,061.82 79723.67
Moorum 97% day 349.20 276.50 96553.80
Water day 30.00
c) Machinary
Hydraulic Excavator 0.90 cum bucket capacity@60 cum per
hour hour 5.00 840.00 4200.00
Tipper 5.5 cum,4 trips per hour hour 14.00 582.00 8148.00
Motor grader 110 HP @ 50 cum per hour hour 6.00 1545.00 9270.00
Three wheel 80-100 KN static roller @ 70 percent per hour hour 4.30 339.00 1457.70
Tractor with rotavator and blade @ 25 cum per hour hour 12.00 242.00 2904.00
Water tanker 6 kl capacity hour 5.00 582.00 2910.00
208275.17
d) Overhead charges @ 15 % on (a+b+c) 31241.27
e) Carriage & Royalty
Moorum 349.20 - 0.00

Cost for 100 cum = a+b+c+d+e 239516.44


Rate per cum = (a+b+c+d)/300 798.39
Add cess 1 % 7.98
806.37
4.6 404 Cement Treated Soil Base
Providing, laying, spreading and compacting stone aggregates of specific
sizes to water bound macadam specification including spreading in
uniform thickness, hand packing, rolling with three wheel 80-100 kN static
roller in stages to proper grade and camber, applying and brooming,
crushable screening(morum and sand admixture) to fill-up the interstices
of coarse aggregate, watering and compacting to the required density as
per Technical Specification Clause 405 of MoRD & as per direction of
Engineer-in-Charge.

Unit = cum
Taking output = 300 cum (525t)
For 6 percent quantity of cement by weight of soil.
a) Labour
Mate day 0.4 320.00 128.00
Mazdoor (Skilled) day 2.00 370.00 740.00
Mazdoor (Un-Skilled) day 8.00 280.00 2240.00

b) Material
Cement at site @ 6% (of 525t) day 31.50 5,061.82 159447.33
Moorum 94% day 338.40 276.50 93567.60
Water day 30.00
c) Machinary
Hydraulic Excavator 0.90 cum bucket capacity@60 cum per
hour hour 5.00 840.00 4200.00
Tipper 5.5 cum,4 trips per hour hour 14.00 582.00 8148.00
Motor grader 110 HP @ 50 cum per hour hour 6.00 1545.00 9270.00

Three wheel 80-100 KN static roller @ 70 percent per hour hour 4.30 339.00 1457.70
Tractor with rotavator and blade @ 25 cum per hour hour 12.00 242.00 2904.00
Water tanker 6 kl capacity hour 5.00 582.00 2910.00
285012.63
d) Overhead charges @ 15 % on (a+b+c) 42751.89
e) Carriage & Royalty
Moorum 338.40 - 0.00

Cost for 100 cum = a+b+c+d+e 327764.52


Rate per cum = (a+b+c+d)/300 1092.55
Add cess 1 % 10.93
1103.48
CHAPTER -5
BASES AND SURFACE COURSES (BITUMINOUS)
Name of the Road Nandighore to Saliajhari

Ref. to
Sr. Rate
MORD Description Unit Quantity Amount (Rs.)
No. (Rs.)
Spe.

5.1 502 Prime Coat


(ii) Low porosity
Providing and applying primer coat with bitumen emulsion (SS-1) on prepared
surface of granular base including cleaning of road surface and spraying primer
at the rate of 0.70-1.0 kg/sqm using mechanical means as per MORD Technical
Specification Clause 502 for low porosity surface and as per direction of
Engineer-in-Charge.
Unit = sqm
Taking output = 1750 sqm
a) Labour
Mate day 0.04 320.00 12.80
Mazdoor (Unskilled) day 1.00 280.00 280.00
b) Machinery
Hydraulic broom @ 1250 sqm per hour hour 1.40 200.00 280.00
Air compressor 210 cfm hour 1.40 179.13 250.78
Bitumen emulsion pressure distributor @ 1750 sqm per hour hour 1.00 448.70 448.70
Water tanker 6 kl capacity 1 trip per hour hour 0.50 506.09 253.05
c) Material
Bitumen emulsion (SS-1) @0.85 kg per sqm t 1.48 28,450.34 42,106.50
Water kl 3.00 0.00 0.00
d)  Overheads @ 15% on (a+b+c) 6,544.77

Cost of 1750 sqm = a+b+c+d 50,176.60


Rate per sqm = (a+b+c+d)/1750 28.67
Labour welfare Cess 1% 0.29
28.96
5.2 503 Tack Coat
(iii) Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion
distributor at the rate of 0.25 to 0.30 kg per sqm on the prepared granular surfaces
treated with primer & cleaned with Hydraulic broom as per Technical Specification
Clause 503 of MoRD & as per direction of Engineer-in-Charge.
Unit = sqm
Taking output = 1750 sqm
a)  Labour
Mate day 0.04 320.00 12.80
Mazdoor (Unskilled) day 1.00 280.00 280.00
b) Machinery
Hydraulic broom @ 1250 sqm per hour hour 1.40 200.00 280.00
Air compressor 210 cfm hour 1.40 179.13 250.78
Emulsion pressure distributor @1750 sqm per hour hour 1.00 448.70 448.70
c) Material
Bitumen emulsion (RS-1) @ 0.275 kg per sqm t 0.48 29,010.34 13,924.96
d) Overheads @ 15% on (a+b+c) 2,279.59

Cost of 1750 sqm = a+b+c+d 17,476.83


Rate per sqm = (a+b+c+d)/1750 9.99
Labour welfare Cess 1% 0.10
10.09
Ref. to
Sr. Rate
MORD Description Unit Quantity Amount (Rs.)
No. (Rs.)
Spe.

5.9 508 20mm thick Open-Graded Premix Carpet using Bituminous (penetration
grade/modified bitumen)
Providing, laying and Binder
rolling of open-graded premix carpet of 20 mm thickness composed of 13.2 mm to 5.6 mm
aggregates using S-65 penetration grade bitumen @ 14.6 kg/10 sqm to required line, grade and level to serve as
wearing course on a previously prepared base, including mixing in a suitable hot mix plant, laying and rolling with a three
wheel 80-100 kN static roller capacity, finished to required level and grades to be followed by seal coat of Type C as per
Technical Specification Clause 508 of MoRD and as per direction of Engineer-in-Charge (Excluding cost of Seal Coat).
Case - I By Manual Means
(II) Bitumen (S-65)
Unit = sqm
Taking output = 500 sqm (10 cum)
a) Labour
Mate day 1.08 320.00 345.60
Mazdoor (Unskilled) day 21.00 280.00 5,880.00
Mazdoor (Semi-Skilled) day 6.00 320.00 1,920.00
b)  Machinery
Mixall 6/10 t capacity hour 4.00 891.30 3,565.20
Bitumen boiler oil fired1000 litre capacity fitted with spray set hour 4.00 111.30 445.20
Three wheel 80-100 kN static roller hour 2.00 294.78 589.56
c) Material
Bitumen (S-65) @ 14.60 kg per 10 sqm t 0.73 31,100.08 22,703.06
Crushed stone chipps 13.2 mm @ 0.18 cum / 10 sqm cum 9.00 1,924.97 17,324.73
Crushed stone chipps 11.2mm @ 0..09 cum / 10 sqm cum 4.50 1,949.73 8,773.79
d) Overheads @ 15% on (a+b+c) 9,232.07
e) Royalty
Crushed stone chipping, 13.2 mm to 5.6 mm cum 13.50 130.00 1,755.00
Cost of 500 sqm = a+b+c+d 72,534.20
Rate per sqm = (a+b+c+d+e)/500 145.07
Labour welfare Cess 1% 1.45
146.52
5.9 508 20mm thick Open-Graded Premix Carpet using Bituminous (penetration grade/modified bitumen)
Binder(Waste Plastic)

Providing, laying and rolling of open-graded premix carpet of 20 mm thickness composed of 13.2 mm to 5.6 mm
aggregates using S-65 penetration grade bitumen @ 14.6 kg/10 sqm to required line, grade and level to serve as
wearing course on a previously prepared base, including mixing in a suitable hot mix plant, laying and rolling with a three
wheel 80-100 kN static roller capacity, finished to required level and grades to be followed by seal coat of Type C as per
Technical Specification Clause 508 of MoRD and as per direction of Engineer-in-Charge (Excluding cost of Seal Coat).
Case - I By Manual Means (Waste plastic)
(II) Bitumen (S-65)
Unit = sqm
Taking output = 500 sqm (10 cum)
a) Labour
Mate day 1.08 320.00 345.60
Mazdoor (Unskilled) day 21.00 280.00 5,880.00
Mazdoor (Semi-Skilled) day 6.00 320.00 1,920.00
b)  Machinery
Mixall 6/10 t capacity hour 4.00 891.30 3,565.20
Bitumen boiler oil fired1000 litre capacity fitted with spray set hour 4.00 111.30 445.20
Three wheel 80-100 kN static roller hour 2.00 294.78 589.56
c) Material
Bitumen (S-65) @ 14.60 kg per 10 sqm t 0.67 31,100.08 20,886.81
Cost of waste plastic t 0.06 30,000.00 1,800.00
Crushed stone chipps 13.2 mm @ 0.18 cum / 10 sqm cum 9.00 1,924.97 17,324.73
Crushed stone chipps 11.2mm @ 0..09 cum / 10 sqm cum 4.50 1,949.73 8,773.79
d) Overheads @ 15% on (a+b+c) 9,229.63
e) Royalty
Crushed stone chipping, 13.2 mm to 5.6 mm cum 13.50 130.00 1,755.00
Cost of 500 sqm = a+b+c+d 72,515.52
Rate per sqm = (a+b+c+d+e)/500 145.03
Labour welfare Cess 1% 1.45
146.48
5.12 510 Seal Coat
Providing and laying seal coat sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall
using Type C as per Technical Specification Clause 510 of MORD with S-65 grade bitumen laid by manual means and
as per direction of Engineer-in-Charge.
A. By Manual Means
Ref. to
Sr. Rate
MORD Description Unit Quantity Amount (Rs.)
No. (Rs.)
Spe.

Case - III : Type C


(II) Bitumen (S-65)
Unit = sqm
Taking output = 1250 sqm
a) Labour
Mate day 0.85 320.00 272.00
Mazdoor (Unskilled) day 15.00 280.00 4,200.00
Mazdoor (Semi-Skilled) day 2.00 320.00 640.00
b) Machinery
Bitumen boiler oil fired 1000 litre capacity fitted with spray set hour 2.50 111.30 278.25
Three wheel 80-100 kN static roller hour 2.50 294.78 736.95
Mixall 6/10 t capacity hour 2.50 891.30 2,228.25
c) Material
Bitumen (S-65) @ 6.50 kg per 10 sqm t 0.813 31,100.08 25,284.37
Crushed stone chipping of 6.7 mm size defined as 100% passing 9.5 mm cum 11.25 1,604.97 18,055.91

sieve and retained on 2.36 mm sieve applied @ 0.09 cum/10sqm.


d) Overheads @ 15% on (a+b+c) 7,754.36
e) Royalty
Crushed stone chipping of 6.7 mm size cum 11.25 130.00 1,462.50
Cost of 1250 sqm = a+b+c+d+e 60,912.59
Rate per sqm = (a+b+c+d+e)/1250 48.73
Labour welfare Cess 1% 0.49
49.22
5.12 510 Seal Coat (Waste plastic)
Providing and laying seal coat sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall
using Type C as per Technical Specification Clause 510 of MORD with S-65 grade bitumen laid by manual means and
as per direction of Engineer-in-Charge.
A. By Manual Means
Case - III : Type C
(II) Bitumen (S-65)
Unit = sqm
Taking output = 1250 sqm
a) Labour
Mate day 0.85 320.00 272.00
Mazdoor (Unskilled) day 15.00 280.00 4,200.00
Mazdoor (Semi-Skilled) day 2.00 320.00 640.00
b) Machinery
Bitumen boiler oil fired 1000 litre capacity fitted with spray set hour 2.50 111.30 278.25
Three wheel 80-100 kN static roller hour 2.50 294.78 736.95
Mixall 6/10 t capacity hour 2.50 891.30 2,228.25
c) Material
Bitumen (S-65) @ 6.50 kg per 10 sqm t 0.748 31,100.08 23,262.86
Cost of waste plastic t 0.06 30,000.00 1,800.00
Crushed stone chipping of 6.7 mm size defined as 100% passing 9.5 mm cum 11.25 1,149.17 12,928.16

sieve and retained on 2.36 mm sieve applied @ 0.09 cum/10sqm.


d) Overheads @ 15% on (a+b+c) 6,951.97
e) Royalty
Crushed stone chipping of 6.7 mm size cum 11.25 130.00 1,462.50
Cost of 1250 sqm = a+b+c+d+e 54,760.94
Rate per sqm = (a+b+c+d+e)/1250 43.81
Labour welfare Cess 1% 0.44
44.25
20mm thick Open-Graded Premix Carpet using Bitumen Emulsion(Cold Mix)
508.2 Providing, laying and rolling of open-graded premix carpet of 20 mm thickness compacted of 13.2 mm to 5.6 mm
aggregates using Bitumen Emulsion(Cold Mix) @ 21.5 kg/10 sqm to required line, grade and level to serve as
wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a three
wheel 80-100 kN static roller capacity, finished to required level and grades to be followed by seal coat of Type C
as per Technical Specification Clause 508.2 of MoRD and as per direction of Engineer-in-Charge.

Unit = sqm
(II) Bitumen (MS)
Taking output = 900 sqm (24.3 cum)
a) Labour
Mate day 0.80 320.00 256.00
Mazdoor (Unskilled) day 18.00 280.00 5040.00
Ref. to
Sr. Rate
MORD Description Unit Quantity Amount (Rs.)
No. (Rs.)
Spe.

Mazdoor (Skilled) day 2.00 264.30 528.60


b) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 6.00 153.91 923.46
Three wheel 80-100 kN static roller hour 3.60 294.78 1061.21
c) Material
Bitumen
Crushed emulsion (Premix type)
stone aggregates 13.2 @
mm21.50
to 5.6kgmm
per@
100.27
sqmcum per t 1.94 26745.70 51886.658
10 sqm cum 24.30 1949.73 47378.439
d) Overheads & Contractor's profit @ 15% on (a+b+c) 16061.15
e) Crushed
Royality stone aggregates 13.2 mm to 5.6 mm @ 0.27 cum per 10
sqm 24.30 130.00 3,159.00
Cost of 900 sqm = a+b+c+d 126294.52
Rate per sqm = (a+b+c+d)/900 140.33
Labour welfare Cess 1% 141.73

2 Seal Coat(Cold Mix)


Providing and laying seal coat sealing the voids in a bituminous
surface laid to the specified levels, grade and cross fall using Type
A, Type B and Type C as per Technical Specification Clause 510

(III) Polymer Modified Bitumen


Unit = sqm
(II) Bitumen
Taking output = 1250sqm
a) Labour
Mate day 0.80 320.00 256.00
Mazdoor (Unskilled) day 14.00 280.00 3920.00
Mazdoor (Semi-Skilled) day 4.00 320.00 1280.00
b) Machinery
Concrete Mixer 0.4/0.28 cum capacity hour 2.00 177.00 354.00
Three wheel 80-100 kN static roller hour 2.00 339.00 678.00
c) Material
Bitumen
Crushed Emulsion (Seal of
stone chipping coat
6.7Type) @ 10Kg
mm size per
defined
10 sqm passing 9.5 mm sieve and retained on
as 100% t 1.25 26745.70 33432.125
2.36 mm sieve applied @ 0.09 cum. cum 9.90 1604.97 15889.203
d) Overheads & Contractor's profit @ 15% on (a+b+c) 8371.40
e) Royality
Crushed stone chipping of 6.7 mm size defined
as 100% passing 9.5 mm sieve and retained on
2.36 mm sieve applied @ 0.09 cum.
9.90 130.00 1,287.00
Cost of 1250 sqm = a+b+c+d 65467.73
Rate per sqm =(a+b+c+d)/1250 52.37
Labour welfare Cess 1% 52.89
5.3 507 Surface Dressing with Bitumen Emulsion
Providing and laying surface dressing as wearing course consisting of a layer of bitumen
Binder(-65) laid on the prepared surface,followed by a cover of crushed stone chippings
of 13.2 mm nominal size and rolling with Three wheel 80-100KN Static roller including
cleaning the road surface as per Technical specification clause 506.(First coat surface
dressing)
Bitumen VG-30
A. By manual Means
Case-I: Nominal Chipping size -13.2 mm
Unit = sqm
Taking output = 900 sqm
a)  Labour
Mate day 2.60 320.00 832.00
Bitumen Emulsion Sprayer day 1.00 320.00 320.00
Mazdoor (Unskilled) day 58.00 280.00 16,240.00
Mazdoor (Semi skilled) day 6.00 320.00 1,920.00

b) Machinery
Emulsion sprayer, capacity 1000 litre fitted with spray hour 2.25 128.00 288.00
set
Three wheel 80-100 KN static roller hour 2.25 339.00 762.75
Add : 0.5 Percent of (a) Labour for Sundries LS 86.96
c) Material
Bitumen(VG-30@0.9kg/sqm) t 0.90 31,100.08 27,990.07
Ref. to
Sr. Rate
MORD Description Unit Quantity Amount (Rs.)
No. (Rs.)
Spe.

crushed stone chipping,13.2mm nominal size @ 0.010 cum 9.00 1,924.97 17,324.73
cum per sqm
d) Overheads @ 15% on (a+b+c) 9,864.68
e) Royalty
crushed stone chipping,13.2mm nominal size @ 0.010 cum 9.00 130.00 1,170.00
cum per sqm
Cost of 900 sqm = a+b+c+d+e 76,799.19
Rate per sqm = (a+b+c+d+e)/900 85.33
Labour welfare Cess 1% 0.85
86.19
5.4 508 Providing and laying surface dressing as wearing course consisting of a layer of bitumen
Binder(-65) laid on the prepared surface,followed by a cover of crushed stone chippings of 9.5
mm nominal Precoat Chips with1% bitumen by weight of chips crushed stone chipping 9.5mm
size and rolling with Three wheel 80-100KN Static roller including cleaning the road surface as
per Technical specification clause 506.(Second coat surface dressing)
A)  By Manual Means
Bitumen VG-30
Case-II:Nominal Chipping size -9.5 mm

Unit = sqm
Taking output = 1000 sqm
Taki Labour
a)  Labour
Mate day 2.60 320.00 832.00
Bitumen Emulsion Sprayer day 1.00 320.00 320.00
Mazdoor (Unskilled) day 58.00 280.00 16,240.00
Mazdoor ( Semi skilled) day 6.00 320.00 1,920.00
0.00
b) Machinery
Emulsion sprayer, capacity 1000 litre fitted with spray hour 2.00 128.00 256.00
set
Three wheel 80-100 KN static roller hour 2.00 339.00 678.00
c) Material
BitumenEmulsion Rs 0.7 Kg/sqm t 0.70 31,100.08 21,770.06
crushed stone chipping,9.5mm nominal size @ 0.008 cum 8.00 1,966.88 15,735.04
cum per sqm
d) Overheads @ 15% on (a+b+c) 8,662.66
e) Royalty
crushed stone chipping,9.5mm nominal size @ 0.008 cum 8.00 130.00 1,040.00
cum per sqm
Cost of 1000 sqm = a+b+c+d+e 67,453.76
Rate per sqm = (a+b+c+d+e)/1000 67.45
Labour welfare Cess 1% 0.67
68.13

Add for Precoating of chips with 1% of Bitumen by weight of


chips crushed stone Chipping 9.5 mm size cum 0.008 1,028.79 8.230
76.36
5.5 509 Precoating of chips
Precoating of chips with 1 percent bitumen by
weight of chips in asuitable mixer duly heated to
160 C as per Technical Specification clause
507.2.5
Unit = sqm
Taking output = 30 Cum
a)  Labour
Mate day 0.60 320.00 192.00
Bitumen Sprayer day 15.00 320.00 4,800.00
b) Machinery
Bitumen Boiler oil fired 1000 litre capacity fitted with hour 6.00 128.00 768.00
spray Test
Mixall 6-10 t capacity hour 6.00 1,025.00 6,150.00
c) Material
Bitumen (VG-30)@ 1% by weight of chips (30x1.6/1) t 0.480 31,100.08 14,928.04

d) Contractors profit & Overheads @15% on (a+b+c) 4,025.71


Ref. to
Sr. Rate
MORD Description Unit Quantity Amount (Rs.)
No. (Rs.)
Spe.

Cost of 30 Cum=(a+b+c+d 30,863.74


Rate per sqm = (a+b+c+d+e)/30 1028.79
Labour welfare Cess 1% 10.288
1,039.08

69 504 Bituminous Macadam


Providing and laying Bituminous Macadam with Hot Mix
Plant using crushed aggregates of specified grading,
premixed with bituminous binder of 60/70 grade of
Bitumen, transported to site, laid over a previously
prepared surface with a hydroustatic paver finisher with
sensor control to the required grade, level and alignment
and rolling with smooth wheeled, vibratory and tandem
rollers to achieve the desired compaction as per clause
504 of MoSRT&H Specifications for Road and Bridge work

(Ref. A/R-2006.Page-169,Item No- 45)


Unit = cum
Taking output = 205 cum(450 tonnes)
a) Labour
Mate
Mulia (Unskilled) day 0.76 320.00 243.20
Mulia (Skilled) day 14.00 280.00 3,920.00
b)  Machinery day 5.00 370.00 1,850.00

Batch mix HMP 100 - 120 TPH @ 75 tonne per hour hour 6.00 6217.39 37,304.34
Paver finisher Hydrostatic with sensor control @ hour 6.00 1605.22 9,631.32
75 cum per hour
Generator 250 KVA hour 6.00 1125.00 6,750.00
Front end loader 1 cum capacity hour 6.00 452.17 2,713.02
Tipper 10 tonne capacity ton.Km 2.00 506.09 1,012.18
Add 10% of cost of carriage to cover cost of 101.22
loading and unloading
Smooth whelled Roller 8 - 10 tonne for initial hour 3.90 641.74 2,502.79
break down rolling
Vibratory Roller 8 tonne for intermediate rolling hour 3.90 864.35 3,370.97
Finishing rolling with 6-8 tonne smooth wheeled hour 3.90 738.00 2,878.20
tandem roller
c) Grading - II (19mm nominal size)
i Material
ii Bitumen (S-65) @ 3.3% of weight of mix t 14.85 31100.08 461,836.19
iii Crushed stone chipping, 25 mm to 10mm @ 40% cum 116.04 1638.73 190,158.23

iv Crushed stone chipping, 10 mm to 5mm @ 40% cum 116.04 1966.88 228,236.76

d) Crushed stone chipping, 5 mm & below @ 20% cum 58.02 1604.97 93,120.36

1,045,628.76
e) Overheads @ 15% on (a+b+c) 156,844.31
Royality
Crushed stone chipping, 25 mm to 10mm @ 40% cum 116.04 15,085.20
130.00
Crushed stone chipping, 10 mm to 5mm @ 40% cum 116.04 15,085.20
130.00
CostCrushed stone chipping, 5 mm & below @ 20% cum 58.02 7,542.60
130.00
1,240,186.07
Rate Add for Cess@1% 124018.61
5,456.82
70 508 Semi Dense Bituminous Concrete
Ref. to
Sr. Rate
MORD Description Unit Quantity Amount (Rs.)
No. (Rs.)
Spe.

Providing and laying semi dense bituminous


concrete with batch type hot mix plant using
crushed aggregates of specified grading,
premixed with bituminous binder of 60/70
penetration grade of bitumen, transporting the hot
mix to work site, laying with a hydrostatic paver
finisher with sensor control to the required grade,
level and alignment, rolling with smooth
wheelede, vibratory and tandem rollers to achieve
the desired compaction as per Clause 508 of
MoSRT&H Specifications for Road & Bridge
works (4th Revision)

(Ref. A/R-2006.Page-177,Item No- 48)


Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour each 0.76 320.00 243.20
Mate each 14.00 280.00 3920.00
Mulia unskilled working with HMP,mechanical each
broom, paver, roller, asphalt cutter and
assistance for setting out lines, levels and layout
5.00 370.00 1,850.00
Mulia Skilled for checking line & levels 6,013.20

b) Machinery
Batch mix HMP 100-120TPH hour 6.00 6217.39 37,304.34
@ 75 tonne per hour -
Paver finisher hydrostatic with sensor hour 6.00 1605.22 9,631.32
control @ 75 cum per hour -
Generator 250 KVA hour 6.00 1125.00 6,750.00
Front end loader 1 cum bucket hour 6.00 452.17 2,713.02
Tipper 10 tonne capacity tonne.km 2.00 506.09 1,012.18
Add 10 per cent of cost of carriage to cover cost
of loading and unloading 101.22
Smooth wheeled roller 8-10 tonnes for initial
break down rolling (6.00 X 0.65* = 3.90) hour 3.90 641.74 2,502.79
Vibratory roller 8 tonnes for intermediate rolling
(6.00 x 0.65* = 3.90) hour 3.90 864.35 3,370.97
Finish rolling with 6-8 tonnes smooth wheeled
tandem roller.(6.00 x 0.65* = 3.90) hour 3.90 738.00 2,878.20
66,264.03
Add for Cess@1% 6626.40
72890.43
(A) c) Material
Grading II (25 mm Nominal Size) -
i) 60/70 penetration grade of Bitumen @ 4.5
per cent of mix tonne.km20.250 31100.08 629,776.62

ii) Aggregate -
Total weight of mix = 450 tonnes -
Weight of bitumen = 20.25 tonnes -
Weight of aggregate = 450.00 - 20.25 =429.75 tonnes -
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 286.50 cum
25 - 10 mm @ 30 per cent cum 85.950 1638.73 140,848.84
10 - 5 mm @ 28 per cent cum 80.220 1966.88 157,783.11
5 mm and below @ 40 per cent cum 114.600 1604.97 183,929.56
Filler @2 percent of weight of aggregates. cum 5.730 50.00 1,112,338.14
d) Overhead charges @ 15% on (a+b+c) 178,686.27
e) Royalty
25 - 10 mm @ 45 per cent cum 85.950 130.00 11,173.50
10 - 5 mm @ 25 per cent cum 80.220 130.00 10,428.60
5 mm and below @ 15 per cent cum 114.600 130.00 14,898.00
36,500.10
Add for Cess@1% 3650.01
1403451.74
Ref. to
Sr. Rate
MORD Description Unit Quantity Amount (Rs.)
No. (Rs.)
Spe.

7,197.19
70 508 20mm thick Open-Graded Premix Carpet using Bituminous (Paver finisher)

Providing, laying and rolling of open - graded


premix surfacing of 20 mm thickness composed
of 13.2 mm to 5.6 mm aggregates either using
penetration grade bitumen or cut-back or
emulsion to required line, grade and level to serve
as wearing course on a previously prepared base,
including mixing in a suitable plant, laying and
rolling with a smooth wheeled roller 8-10 tonne
capacity, finished to required level and grades.

(Ref. A/R-2006.Page-177,Item No- 48)


Unit = cum
Taking output = 10250 sqm (205 cum)
a) Labour each 0.84 370.00 310.80
Mate each 16.00 280.00 4480.00
Mulia unskilled working with HMP,mechanical broom, paver, each
rol 5.00 370.00 1850.00
Skilled mazdoor for checking line & levels.

b) Machinery
i) Batch type HMP 75 tonne per hour . hour 6.00 6217.39 37,304.34
-
ii) Electric Generator Set 250 KVA hour 6.00 1125.00 6,750.00
-
iii) Front end loader 1 cum bucket capacity hour 6.00 452.17 2,713.02
Tipper 10 tonne capacity tonne.km 45*l 2.17 6,640.20
Add 10 per cent of cost of carriage to cover cost
of loading and unloading 664.02
v) Paver finisher hydrostatic with sensor
attachment hour 6.00 1605.22 9,631.32
iv) Smooth wheeled/tandom roller 8-10 tonnes
weight hour 6.00 641.74 3,850.44
(A) c) Material
-
Bitumen@
Crushed 14.60
stone kg per 10 sqm
chipping,13.2 mm to 5.6 mm @ tonne 14.970 31100.08 465,568.20
0.27 cum per 10 sqm cum 276.65 1764.67 488,195.96
1,027,958.29
d) Overhead charges @ 15% on (a+b+c) 155,273.32
TOTAL 1,183,231.62
Rate per SQM SQM 115.44

70 508 Seal coat (paver finisher)

Providing and laying of premix sand seal coat


with HMP of appropriate capacity not less than 75
tonnes/ hours using crushed stone chipping 6.7
mm size and penetration bitumen of suitable
grade.

Unit = cum
Taking output = 7858 sqm (47.16 cum)
a) Labour
Mate each 0.16 320.00 51.20
Mulia unskilled working with HMP,mechanical broom, paver, each
rol 4.00 280.00 1120.00

b) Machinery
HMP of 75 tonnes/hour. hour 2.00 13130.43 26,260.86
-
Electric Generator Set 250 KVA hour 2.00 1125.00 2,250.00
-
Front end loader 1 cum bucket capacity hour 2.00 452.17 904.34
Tipper 10 tonne capacity tonne.km 104*l 2.17 10,155.60
Add 10 per cent of cost of carriage to cover cost
of loading and unloading 1,015.56
Ref. to
Sr. Rate
MORD Description Unit Quantity Amount (Rs.)
No. (Rs.)
Spe.

v) Paver finisher hydrostatic with sensor


attachment hour 2.00 1605.22 3,210.44
iv) Smooth wheeled/tandom roller 8-10 tonnes
weight hour 2.00 641.74 1,283.48
(A) c) Material
-
Bitumen@ 6.8chipping,13.2
Crushed stone kg per 10 mmsqmto 5.6 mm @ tonne 5.340 31100.08 166,074.43
0.27 cum per 10 sqm cum 47.16 1604.67 75,676.24
288,002.14
d) Overhead charges @ 15% on (a+b+c) 220,685.06
TOTAL 508,687.21
Rate per SQM SQM 64.73
CHAPTER -6
CEMENT CONCRETE PAVEMENT
Name of the Road : Nandighore to Saliajhari
Sr. Ref. to Rate
Description Unit Quantity Amount (Rs.)
No. MORD Spe. (Rs.)
6.1 400 Granual Sub-base
Rate as per item No.4.1 of Chapter 4
6.3 1500 & Water Bound Macadam (WBM) - Sub-base
400
(A) By Manual Means
As per item No.4.7 of Chapter 4
6.4 1500 Cement Concrete Pavement
Construction of un-reinforced, plain cement Panelled(0.75mx.75m) concrete pavement of 100mm thickn as per design, over a prepared
sub-base, with 43 grade cement or any other type as per Clause 1501.2.2, M30 (grade) coarse and fine aggregates conforming to IS:383,
maximum size of coarse aggregate not exceeding 25mm mixed in a concrete mixer of not less than 0.2 cum capacity and appropriate
weigh batcher using approved mix design, laid in approved fixed side formwork (steel channel, laying and fixing of 125 micron thick
polythene film, wedges, steel plates including levelling the form work as per drawing), spreading the concrete with shovels, rakes,
compacted using needle, screed and plate vibrators and finished in continuous operation including provision of contraction and expansion,
construction joints, applying debonding strips, primer, sealant near approaches to bridges and culverts (expansion joints), admixtures as
approved, curing of concrete slabs for 14 days, curing compound and water finishing to lines and grade as per drawing and Technical
Specification Clause 1501.Panels are to be made by cutting grooves of 3 to 5mm thick and 25 to 30mm deep in CC slab.The grooves are
to be filled with VG-30 Bitumen with a spray of fine sand at top.
Unit = cum
Taking output = 75 cum (172.50 t)
(100 x 3.75 x 0.200)
a) Labour
Mate day 7.00 320.00 2,240.00
Mason (1st class) day 5.00 430.00 2,150.00
Mason (2nd class) day 5.00 370.00 1,850.00
Mazdoor (Unskilled) day 129.00 280.00 36,120.00
Mazdoor (Skilled) day 6.00 370.00 2,220.00
Surveyor day 2.00 430.00 860.00
Mazdoor (Semi-Skilled) day 6.00 320.00 1,920.00
Bhisti day 14.00 320.00 4,480.00
b) Machinery
Concrete mixer 0.28 / 0.4 cum capacity (6 mixers) with weigh batcher and suitable hour 36.00 153.91 5,540.76
capacity calibrated water tank
Screed Vibrator hour 9.00 92.17 829.53
Needle vibrator hour 9.00 92.17 829.53
Plate vibrator hour 9.00 92.17 829.53
Concrete joint cutting machine for initial & final cuts hour 4.00 300.00 1,200.00
Water tanker 6 kl capacity hour 5.00 506.09 2,530.45
Air Compressor (1 hour initial + 1 hour final) hour 2.00 179.13 358.26
c) Material
(i) Crushed stone coarse aggregates, grading will be as per Clause 1501.2.4.1 (Table 1500.1) of cum 67.50 1,826.56 123,292.80
specifications @ 0.90 cum/ cum of concrete (Rate=(20mm+10mm+6.7mm)/3)

(ii) Sand as per IS:383 and conforming to Clause 1500.2.4.2 @ 0.45 cum/cum of cum 33.75 699.53 23,609.14
concrete
(iii) Cement @ 350 kg/cum of concrete t 26.25 5,061.82 132,872.78
(iv) Polythene sheet 125 micron sqm 412.50 3.00 1,237.50
(v) Bitumen primer @ 200 ml per joint for 23 joints t 0.005 28,450.34 142.25
Bituminous sealant 800 ml per joint for 23 joints litre 19.00 20.00 380.00
Plasticizer 0.5 per cent by weight of cement litre 122.00 40.00 4,880.00
Curing compound litre 131.25 20.00 2,625.00
Joint filler board 20 mm thick as per IS:1838 (4 x 3.75 x 0.200 = 3 sqm) sqm 3.00 852.94 2,558.82
d) Formwork @ 3% of (a+b+c) 10,666.69
e) Overheads @ 15% on (a+b+c+d) 54,933.46
f) Royalty
(i) Crushed stone coarse aggregates ,grading will be as per Clause cum 67.50 130.00 8,775.00
1501.2.4.1 (Table 1500.1) of specifications @ 0.90 cum/cum of concrete

(ii) Sand as per IS:383 and conforming to Clause 1500.2.4.2 @ 0.45 cum 33.75 35.00 1,181.25
Cost for 75 cumcum/cum of concrete
= a+b+c+d+e+f 431,112.74
Rate per cum = (a+b+c+d+e+f)/75 5,748.17
Labour welfare Cess 1% 57.48
5,805.65
CHAPTER -9
PIPE CULVERTS
Name of the Road : Nandighore to Saliajhari

Sr. Ref. to Rate


MORD Description Unit Quantity Amount (Rs.)
No. Spe. (Rs.)

9.3 1100 Providing and Laying Reinforced Cement Concrete Pipe NP3 as per design in
Single Row
Providing and laying reinforced cement concrete NP3 pipe for culverts jointing
with cement mortar 1:2 but excluding excavation, protection works, backfilling,
concrete and masonry works in head walls and parapets as per Clause 1100 of
MoRD & as per direction of Engineer-in-Charge.
Unit = m
Taking output = 7.5 m
(3 pipes of 2.5 m length each)
(C) 1200 mm dia
a) Labour
Mate day 0.14 320.00 44.80
Mason (1st Class) day 0.50 430.00 215.00
Mazdoor (Unskilled) day 3.00 280.00 840.00
b) Material
Sand cum 0.050 699.53 34.98
Cement t 0.070 5,061.82 354.33
RCC pipe NP3 concrete pipe including collar at site m 7.50 4,630.05 34,725.37
c) Overheads @ 15% (a+b) 5,432.17

d) Royalty
Sand cum 0.050 35.00 1.75
Cost for 7.5 m = a+b+c+d 41,648.39
Rate per m = (a+b+c+d)/7.5 5,553.12
Labour welfare Cess 1% 55.53
5,608.65

(C) 1000 mm dia


a) Labour
Mate day 0.090 320.00 28.80
Mason (1st Class) day 0.250 430.00 107.50
Mazdoor (Unskilled) day 2.00 280.00 560.00
b) Material
Sand cum 0.04 699.53 27.98
Cement t 0.03 5,061.82 151.85
RCC pipe NP3 concrete pipe including collar at site m 7.50 4,311.04 32,332.79
c) Overheads @ 15% (a+b) 4,981.34

d) Royalty
Sand cum 0.04 35.00 1.40
Cost for 7.5 m = a+b+c+d 38,191.66
Rate per m = (a+b+c+d)/7.5 5,092.22
Labour welfare Cess 1% 50.92
5,143.14

(C) 600 mm dia


a) Labour
Mate day 0.04 320.00 12.80
Mason (1st Class) day 0.12 430.00 51.60
Mazdoor (Unskilled) day 0.96 280.00 268.80

b) Material
Sand cum 0.024 699.53 16.79
Cement t 0.018 5,061.82 91.11
RCC pipe NP3 concrete pipe including collar at site m 7.50 1,993.82 14,953.64
Sr. Ref. to Rate
MORD Description Unit Quantity Amount (Rs.)
No. Spe. (Rs.)
c) Overheads @ 15% (a+b) 2,309.21
d) Royalty
Sand cum 0.024 35.00 0.84
Cost for 7.5 m = a+b+c+d+e 17,704.79
Rate per m = (a+b+c+d)/7.5 2,360.64
Labour welfare Cess 1% 23.61
2,384.25

(D) 350mm dia


As per state S/R
Rate per m 17.80
RCC pipe NP3 concrete pipe including collar at site m 1.00 990.76 990.76
Rate per m 1,008.56
Labour welfare Cess 1% 10.09
1,018.64
9.5 1100 Providing and Laying Reinforced Cement Concrete Pipe NP3 as per Design
in Double and
Providing Rowlaying reinforced cement concrete NP3 Double Row pipe for

culverts jointing with cement mortar 1:2 but excluding excavation, protection
works, backfilling, concrete and masonry works in head walls and parapets as per
Clause 1100 of MoRD & as per direction of Engineer-in-Charge.
Unit = m
Taking output = 7.5 m
(6 pipes of 2.5 m length each in two rows)
(C) 1000 mm dia
a) Labour
Mate day 0.220 320.00 70.40
Mason 1st Class day 0.60 430.00 258.00
Mazdoor (Unskilled) day 4.80 280.00 1,344.00
b) Material
Sand cum 0.08 699.53 55.96
Cement t 0.060 5,061.82 303.71
RCC pipe NP3 pipe including collar at site m 15.00 4,311.04 64,665.58
c) Overheads @ 15% on (a+b) 10,004.65
d) Royalty
Sand cum 0.08 35.00 2.80
Cost for 7.5 m = a+b+c+d 76,705.10
Rate per m = (a+b+c+d)/7.5 10,227.35
Labour welfare Cess 1% 102.27
10,329.62

(C) 600 mm dia


a) Labour
Mate day 0.09 320.00 28.80
Mason 1st Class day 0.24 430.00 103.20
Mazdoor (Unskilled) day 1.92 280.00 537.60
b) Material
Sand at site cum 0.04 699.53 27.98
Cement at site t 0.036 5,061.82 182.23
RCC pipe NP3 pipe including collar at site m 15.00 1,993.82 29,907.28
c) Overheads @ 15% on (a+b) 4,618.06

d) Royalty
Sand at site cum 0.04 35.00 1.40
Cost for 7.5 m = a+b+c+d 35,406.55
Rate per m = (a+b+c+d)/7.5 4,720.87
Labour welfare Cess 1% 47.21
Sr. Ref. to Rate
MORD Description Unit Quantity Amount (Rs.)
No. Spe. (Rs.)

4,768.08
CHAPTER -10
TRAFFIC SIGNS, MARKING AND OTHER ROAD APPURTENANCES
Name of the Road Nandighore to Saliajhari

Ref. to
Sr. Rate Amount
MORD Description Unit Quantity
No. Spe. (Rs.) (Rs.)

10.1 1700 Printing New Letters and Figures of any Shade


Printing new letter and figures of any shade with synthetic enamel paint black or
any other approved colour to give an even shade as per drawings and Technical
Specification Clause 1701.
i) Oriya
Matras, commas and the like not to be measured and paid for. Half letters shall
be counted as half only. Detail for 100 letters of 160 mm height, i.e., 1600
cm
Unit = per cm height per letter
a) Labour
Mate day 0.12 320.00 38.40
Painter Ist class day 2.00 430.00 860.00
Mazdoor day 1.00 280.00 280.00
b) Material
Paint litre 0.70 108.34 75.84
c) Overheads @ 15% on (a+b) 188.14

Cost for 1600 cm = a+b+c 1,442.37


Rate per cm height per letter = (a+b+c )/1600 0.90
Labour welfare Cess 1% 0.01
0.91

ii) English and Roman


Hyphens, commas and the like not to be measured and paid for. Detail for 100
letters of 160 mm height, i.e., 1600 cm
Unit = per cm height per letter
a) Labour
Mate day 0.07 320.00 22.40
Painter Ist class day 1.25 430.00 537.50
Mazdoor day 0.50 280.00 140.00
b) Material
Paint litre 0.50 108.34 54.17
c) Overheads @ 15% on (a+b) 113.11

Cost for 1600 cm = a+b+c 867.18


Rate per cm height per letter = (a+b+c )/1600 0.54
Labour welfare Cess 1% 0.01
0.55

10.5 1700 Painting Two Coats on New Concrete Surfaces


Painting two coats including prime coat with epoxy paint of approved brand on
concrete/steel surfaces after through cleaning of surface to give an even shade as
per drawing and Technical Specification Clause 1701 of MORD.
Unit = sqm
Taking output = 40 sqm
a) Labour
Mate day 0.20 320.00 64.00
Painter (1st Class) day 3.00 430.00 1,290.00
Mazdoor (Unskilled) day 2.00 280.00 560.00
b) Material
Cement Primer as per specifications litre 3.00 119.69 359.07
Paint conforming to requirement of Clause 1701.3.8 litre 6.00 108.34 650.04
c) Overheads @ 15% on (a+b) 438.47

Cost for 40 sqm = a+b+c 3,361.58


Rate per sqm = (a+b+c)/40 84.04
Labour welfare Cess 1% 0.84
84.88
Ref. to
Sr. Rate Amount
MORD Description Unit Quantity
No. Spe. (Rs.) (Rs.)

10.6 1700 Painting Two Coats on steel Surfaces


Painting two coats including prime coat with epoxy paint of approved brand on
concrete/steel surfaces after through cleaning of surface to give an even shade as
per drawing and Technical Specification Clause 1701 of MORD.
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.25 320.00 80.00
Painter (1st Class) day 0.60 430.00 258.00
Mazdoor (Unskilled) day 0.40 280.00 112.00
b) Material
Red-oxide Primer as per specifications litre 0.60 96.06 57.64
Epoxy paint litre 1.25 178.00 222.50
Add for scaffolding @ 1 per cent of labour cost where required
c) Overheads @ 15% on (a+b) 109.52
Cost for 10 sqm = a+b+c 839.66
Rate per sqm = (a+b+c)/10 83.97
Labour welfare Cess 1% 0.84
84.81

10.2 1700 Cautionary and mandatory Signs


Providing and fixing of semi reflective cautionary, mandatory and informatory sign board
as per IRC:67 made of 1.5 mm thick MS Sheet duly stove white colour in front and gray
colour on back with red reflective border of 65 mm width and required letters and figures
with reflective tape engineering grade as per Clause 1701.3.9 of MORD for Rural Roads of
required shade and colour supported and welded on 47mm x 47 mm x 12 SWG sheet tube
firmly fixed to the ground by mean of properly designed foundations with M-15 grade
cement concrete 450x450x600 mm, 600 mm below ground level as per approved drawing
Clause 300,800,1700 as per direction of the Engineer in charge.(600 mm square)
Unit = each
Taking output = 1 No.
i) Exacavation of foundation
As per item No.11.1 of Chapter 11 cum 0.126 269.38 33.94
ii) C.C. M15 grade
As per item No.11.4 of Chapter 11 cum 0.126 4,650.38 585.95
iii) Painting two coats of approved paint &primer
As per item No.10.6 of this Chapter sqm 0.460 83.97 38.63
a) Labour(for fixing at site)
Mate day 0.010 320.00 3.20
Mazdoor(unskilled) day 0.250 280.00 70.00
b) Materials
47mmx47mmx12 SWG MS sheet tube 3.05m long kg 12.126 42.00 509.29
Mild steel angle iron 50x50x6mm for hold fast including 5% wastage
kg 1.060 42.00 44.52
1.5mm thick Iron sheeting of 900mm equilaterial triangle (0.36sqm) duly
painted withstove enamelled paint including lettering, signs, border, with
reflective tape of engineering grade sqm 0.156 426.00 66.46
Add 3% of cost of angle towords cost of fabrication,Drilling,Nuts,Bolts
etc. 16.61
c) Tractor with trolley hour 0.080 231.00 18.48
d) Overhead charges@15% on (a+b+c) 109.28
Rate per traffic sign=(i+ii+iii+a+b+c+d+e) 1496.36
Labour welfare Cess 1% 14.96
1,511.32
Ref. to
Sr. Rate Amount
MORD Description Unit Quantity
No. Spe. (Rs.) (Rs.)

10.3 1700, Direction & place identification signs


800, Providing and erecting direction and place identifications of semi reflective sign
300 boards of size upto 0.90 Sqm. as per IRC:67 made of 2 mm thick M.S. Sheet duly
stove enameled paint in white colour in front and grey colour on back with red
reflective border of 70 mm width and required message, letters, figures with
reflective engineering grade tape as per MORD specifications of required shade
and colour. Supported and welded on 47 mm x 47mm of 12 SWG Square tube of
3050 mm height duly strengthened by 25 mm x 5 mm M/s flat iron on edges on
back firmly fixed to the ground by means of properly designed foundations with M-
15 grade cement concrete 450 mm x 450 mm x 600 mm, 600 mm below ground
level as per approved drawing and MORD technical Specification Clause
300,800,1700 as per direction of the Engineer in charge (Inter mediate Board)
Unit =sqm
Taking output = .9sqm
i) Exacavation of foundation
As per item No.11.1 of Chapter 11 cum 0.126 269.38 33.94
ii) C.C. M15 grade
As per item No.11.4 of Chapter 11 cum 0.126 4,650.38 585.95
iii) Painting two coats of epoxy paint &primer
As per item No.10.7 of this Chapter sqm 0.59 83.97 49.54
a) Labour(for fixing at site)
Mate day 0.01 320.00 3.20
Mazdoor(unskilled) day 0.25 280.00 70.00
b) Materials
47mmx47mmx12 SWG MS sheet tube 3.05m long kg 12.40 42.00 520.80
Mild steel angle iron 50x50x6mm for hold fast
including 5% wastage kg 1.06 42.00 44.52
2mm thick MS sheet strengthened by
25mmx5mm flat iron duly painted withstove
enamelled paint including lettering, signs,
border, with reflective tape of engineering sqm 0.90 570.00 513.00
grade
Add 3% of cost of angle towords cost of fabrication,Drilling,Nuts,Bolts
etc. 32.35
c) Tractor with trolley hour 0.08 231.00 18.48
d) Overhead charges@15% on (a+b+c) 180.35
Rate per sqm=(i+ii+iii+a+b+c+d+e) 2052.13
Labour welfare Cess 1% 20.52
2,072.65

10.16 1700, Providing and fixing 'Logo' of OMBADC Project


Providing and fixing of typical OMBADC informatory sign board with Logo as per MORD specifications and
drawing. Three MS Plates of 1.6 mm thick, top and middle plate duly welded with MS flat iron 25mm x 5m size on
back on edges. The lower plate will be welded with MS angle iron frame of 25mm x 25mm x 5mm. The angle iron
frame of the lower most plate and flat iron frame of middle plate will be welded to 2 nos. 75mm x 75 mm of 12
SWG sheet tubes posts duly embedded in cement concrete M-15 grade blocks of 450mm x 450mm x 600mm,
600mm below ground level. The top most diamond plate will be welded to middle plate by 47mm x 47mm of 12
SWG steel plate tube. All M.S. will be stove enameled on both sides. Lettering and printing arrows, border etc.
will be painted with ready mixed synthetic enamel paint of superior quality in required shade and colour. All
sections of framed posts and steel tube will be painted with primer and two coats of epoxy paint as per drawing
Clause Annexure 300,800,1700 of MORD as per direction of the Engineer in charge
Unit =Each
Taking output = one typical board
i) Exacavation of foundation
As per item No.11.1 of Chapter 11 cum 0.252 269.38 67.88
ii) C.C. M15 grade 0
As per item No.11.4 of Chapter 11 cum 0.252 4,650.38 1171.9
iii) Painting two coats of epoxy paint &primer
As per item No.10.6 of this Chapter sqm 1.80 83.97 151.15
iv) Printing new letter and figures of any shade with synthetic enamel paint black or

any other approved colour to give an even shade


Logo border 2x330x1.5=990
Hrading border 1x90x8.5=765
Plate words 49x2.5=122.5
150x1.7=255
Information area 63.5x87=5524.5
Ref. to
Sr. Rate Amount
MORD Description Unit Quantity
No. Spe. (Rs.) (Rs.)

960x1.7=1632
Words 80x3=240
Total 9289 per cm height per letter
As per item no 10.1 per cm height per letter
4532.50 0.54 2447.55
a) Labour(for fixing at site)
Mazdoor(unskilled) day 0.75 280.00 210.00
Mate day 0.03 320.00 9.60
b) Materials
MS tubes 75mmx75mm of 12SWG sheet 8400mm long kg 63.15 42.00 2652.30
Mild steel flat iron 50x5mm for lugs kg 2.12 42.00 89.04
2mm thick MS sheet strengthened by 25mmx5MS flat iron on Logo & middle
plate angle iron 25mmx25mmx5mm on bottom plate painting with stove enamel
paint on both sides (1.375 sqm) sqm 1.440 570.00 820.80
Add 3% of cost of MS tube & angle towords cost of fabrication,
Drilling,Nuts,Bolts etc. 106.86
c) Tractor with trolley hour 0.24 231.00 55.44
d) Overhead charges@15% on (a+b+c) 591.61

Rate per sqm=(i+ii+iii+iv+a+b+c) 8374.13


Labour welfare Cess 1% 83.74
8,457.87

10.10 1700 Reinforced cement concrete M15 grade kilometre stone of standard design as
per IRC:8 fixing in position including painting and printing, etc as per drawing and
MORD technical Specification Clause 1703 as per direction of the Engineer in
charge

i) 5th Kilometre Stone (precast)


Unit = each
Taking output = 6 Nos.
a) M-15 grade of concrete
As per item No.12.5 of Chapter 12 cum 2.35 4,911.70 11,542.50
b) Steel reinforcement @ 5 kg per sqm
As per item No.12.6 of Chapter 12 kg 22.08 59.80 1,320.45
c) Excavation in soil for foundation
As per item No.11.1 of Chapter 11 cum 1.68 269.38 452.56

d) Painting two coats on concrete surface


As per item No.10.5 of Chapter 10 sqm 9.85 84.04 827.79
e) Lettering on km post (average 30 letters of 10 cm per cm high per litre 1,560.0 0.660 1,029.60
height each) as per item no 10.1(ii)

Transportation and fixing


f) Labour
Mate day 0.26 320.00 83.20
Mason (1st Class) day 0.60 430.00 258.00
Mazdoor (Unskilled) day 6.00 280.00 1,680.00
g) Machinery
50 HP Tractor with trolley hour 6.00 231.00 1,386.00
h) Overheads @ 15% on (f+g) 511.08

Cost for 6 Nos. 5th km stone = a+b+c+d+e+f+g+h 19,091.17


Rate for each 5th km stone = (a+b+c+d+e+f+g+h)/6 3,181.86
Labour welfare Cess 1% 31.82
3,213.68

ii) Ordinary Kilometer Stone (Precast)


Unit = each
Taking output = 14 Nos.
a) M15 grade of concrete
As per item No.12.5 of Chapter 12 cum 3.77 4,911.70 18,517.11
b) Steel reinforcement @ 5 kg per sqm
As per item No.12.6 of Chapter 12 kg 26.32 59.80 1,574.01
c) Excavation in soil for foundation
As per item No.11.1 of Chapter 11 cum 2.77 269.38 746.18
d) Painting two coats on concrete surface
As per item No.10.5 of Chapter 10 sqm 10.20 84.04 857.21
Ref. to
Sr. Rate Amount
MORD Description Unit Quantity
No. Spe. (Rs.) (Rs.)

e) lettering on km post (average 12 letters of 10 cm height each)


As per item No.10.1 of Chapter 10 per cm high per letter 1,676 0.66 1,106.16
Ref. to
Sr. Rate Amount
MORD Description Unit Quantity
No. Spe. (Rs.) (Rs.)

Transportation and fixing


f) Labour
Mate day 0.32 320.00 102.40
Mason (1st Class) day 1.00 430.00 430.00
Mazdoor (Unskilled) day 7.00 280.00 1,960.00
g) Machinery
50 HP Tractor with trolley hour 6.00 231.00 1,386.00
h) Overheads @ 15% on (f+g) 581.76
Cost for 14 Nos. ordinary km stone = (a+b+c+d+e+f+g+h) 27,260.83
Rate for each ordinary km stone = (a+b+c+d+e+f+g+h+i)/14 1,947.20
Labour welfare Cess 1% 19.47
1,966.67

iii) 200 m stone (precast)


Unit = each
Taking output = 33 Nos.
a) M15 grade of concrete
As per item No.12.5 of Chapter 12 cum 1.58 4,911.70 7,760.49
b) Steel reinforcement @ 5 kg per sqm
As per item No.12.6 of Chapter 12 kg 66.00 59.80 3,946.99
c) Excavation in soil for foundation
As per item No.11.1 of Chapter 11 cum 1.39 269.38 374.44
d) Painting two coats on concrete surface
As per item No.10.5 of Chapter 10 sqm 6.27 84.04 526.93
e) lettering on km post (average 1 letter of 10 cm height each)
As per item No. 10.1 of Chapter 10 per cm per letter 330.00 0.54 178.20
Transportation and fixing
f) Labour
Mate day 0.34 320.00 108.80
Mason (1st Class) day 1.50 430.00 645.00
Mazdoor (Unskilled) day 7.00 280.00 1,960.00
g) Machinery
50 HP Tractor with trolley hour 6.00 231.00 1,386.00
h) Overheads @ 15% on (f+g) 614.97

Cost for 33 Nos. 200 m stone = (a+b+c+d+e+f+g+h) 17,501.81


Rate for each 200 m stone = (a+b+c+d+e+f+g+h)/33 530.36
Labour welfare Cess 1% 5.30
535.66
10.16 1700, Providing and Fixing of OMBADC Citizen Information board.
Providing and fixing of typical OMBADC citizen information board as per MORD specifications and drawing. Three
MS Plates of 50x5mm mm thick, back plate duly welded with 75mm dia steel tubes back on edges as per
drawings. The upper & lower plate will be welded with MS flat iron frame of 50mmx5mm. The steel tubes duly
embedded in cement concrete M-15 grade blocks of 600mm x 600mm x 750mm below ground level.All M.S. will
be stove enameled on both sides. Lettering and printing arrows, border etc. will be painted with ready mixed
synthetic enamel paint of superior quality in required shade and colour. All sections of framed posts and steel
tube will be painted with primer and two coats of epoxy paint as per drawing Clause 1701 and Annexture 1700.1.
Unit =Each
Taking output = one typical board
i). Exacavation of foundation
As per item No.11.1 of Chapter 11 cum 0.54 84.71 45.74
ii). C.C. M15 grade
As per item No.11.4 of Chapter 11 cum 0.54 4,650.38 2511.21
iii). Painting two coats of epoxy paint &primer
As per item No.10.6 of this Chapter sqm 3.70 83.97 310.69
iv). Printing new letter and figures of any shade with synthetic
enamel paint black or any other approved colour to give an
even shade
Heading boarder-90*10=900 per cm height per letter
Figure 63.5*8.70=5524.50 per cm height per letter
Border 90*3*1.50=405 per cm height per letter
Border 75*4*1.50=450 per cm height per letter
Heading band words- 36*2.5=90 per cm height per letter
Letter in formation words- 56*1.70=95.20 per cm heitht per letter
Ref. to
Sr. Rate Amount
MORD Description Unit Quantity
No. Spe. (Rs.) (Rs.)

Sub heading words- 21*2.5=52.5 per cm height per letter


Specification wordds-550*1.70=585 per cm height per letter
Total 8102.50 per cm height per letter
As per item No. 10.1 of Chapter 10 per cm 8102.50 0.17 1377.43
a). Labour (for fixing at site)
Mate day 0.03 80 2.40
Mazdoor (Unskilled) day 0.75 70 52.5
b). Material
Ms tubes 75 mm dia of 8100 mm long Mtr 8.10 350 2835
50mm*6mm steel plate 7.30 mtr @ 2.40 kg Kg 17.52 42.00 735.84
25mm*5mm flat 6.60m @ 1.20kg/m Kg 7.92 42.00 332.64
1.6mm thick Ms sheet strengthened by Sqm 1.35 350 472.5
Add 3% cost of Ms tube and angle iron 3% 131.28
c). Machinery
Tractor with trolley Hour 0.24 231.00 55.44
d). overhead charges on (a+b+c) 15.00% 692.64
Rate for Each 9555.31
Labour welfare Cess 1% 95.55
9,650.86
CHAPTER -11
FOUNDATION
Name of the : Nandighore to Saliajhari

Ref. to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Spe.
11.1 300 Excavation for Structures
Earthwork in excavation for foundation of structures in all types of soil as per
drawing and technical specification Clause 305 and 1104 of MoRD includding setting
out, construction of shoring and bracing, removal of stumps and other deleterious
material and disposal upto all lead & lift, dressing of sides and bottom and back
filling with excavated suitable material upto 3mt. as per direction of Engineer-in-
Charge.
I. Ordinary soil
A. Without dewatering and shoring, shuttering
(i) Upto 3 m depth
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.32 320.00 102.40
Mazdoor (Unskilled) day 8.00 280.00 2,240.00
b) Overheads @ 15% on (a) 351.36
Cost for 10 cum = a+b 2,693.76
Rate per cum = (a+b)/10 269.38
Labour welfare Cess 1% 2.69
272.07
11.2 300 & Providing and constructing well compacted drainage layer above the subgrade of roadwork with
1200 approved quality of dust free washed coarse to medium sand as per Clauses 5.8 and 6.6 of
SP:20-2002.
I. Sand filling
Unit = cum
a) Labour
Mate day 0.01 320.00 3.20
Mazdoor (Unskilled) day 0.30 280.00 84.00

b) Material
Sand (assuming 20 percent voids) cum 1.20 704.30 845.16
c) Overheads @ 15% on (a+b) 139.85
d) Royalty
Sand (assuming 20 per cent voids) cum 1.20 35.00 42.00
Rate per cum = a+b+c+d 1,114.21
Labour welfare Cess 1% 11.14
1,125.35

11.4 800 & Providing concrete for plain / reinforced concrete in open foundation complete as per drawing
1200 and MORD technical specification Clause 800,1100,1200 and as per direction of Engineer-in-
Charge.
I. P.C.C grade M 10 Nominal mix (1:3:6)
Unit = cum
a) Material
Cement t 0.250 5,061.82 1,265.46
Coarse sand cum 0.48 699.53 335.77
40 mm aggregate cum 0.576 1,606.88 925.56
20 mm aggregate cum 0.288 1,907.83 549.46
10 mm aggregate cum 0.096 1,966.88 188.82
b) Labour
Mate day 0.08 320.00 25.60
Mason (1st Class) day 0.10 430.00 43.00
Mazdoor (Unskilled) day 1.63 280.00 456.40
Bhisti day 0.27 320.00 86.40
c) Machinery
Mechnical concrete mixer 0.4/0.28 cum capacity fitted with water hour 0.40 153.91 61.56
d) measuring device@
Add for formwork and
4%preferably
on cost ofalso with load
material, cell.
labour and machinery 157.52
(a+b+c)
e) Overheads @ 15% on (a+b+c+d) 614.33
f) Royalty
Fine sand cum 0.48 35.00 16.80
40 mm aggregate cum 0.576 130.00 74.88
Ref. to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Spe.
20 mm aggregate cum 0.288 130.00 37.44
10 mm aggregate cum 0.096 130.00 12.48
Rate per cum = a+b+c+d+e+f 4,851.49
Labour welfare Cess 1% 48.51
4,900.00
II. P.C.C grade M 15 Nominal mix (1:2.5:5)
Unit = cum
a) Material
Cement t 0.275 5,061.82 1,392.00
Fine sand cum 0.480 699.53 335.77
40 mm aggregate cum 0.480 1,606.88 771.30
20 mm aggregate cum 0.240 1,907.83 457.88
10 mm aggregate cum 0.080 1,966.88 157.35
b) Labour
Mate day 0.080 320.00 25.60
Mason (1st Class) day 0.100 430.00 43.00
Mazdoor (Unskilled) day 1.630 280.00 456.40
Bhisti day 0.270 320.00 86.40
c) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 0.400 153.91 61.56
d) Formwork @ 4% on cost of material, labour and machinery (a+b+c) 151.49
e) Overheads @ 15% on (a+b+c+d) 590.81
f) Royalty
Fine sand cum 0.480 35.00 16.80
40 mm aggregate cum 0.480 130.00 62.40
20 mm aggregate cum 0.240 130.00 31.20
10 mm aggregate cum 0.080 130.00 10.40
Rate per cum = a+b+c+d+e+f 4,650.38
Labour welfare Cess 1% 46.50
4,696.88

III. P.C.C grade M 15 Nominal mix (1:2.5:5) ( HAND MIX )


Unit = cum
a) Material
Cement t 0.275 5,061.82 1,392.00
Fine sand cum 0.480 699.53 335.77
40 mm aggregate cum 0.480 1,606.88 771.30
20 mm aggregate cum 0.240 1,907.83 457.88
10 mm aggregate cum 0.080 1,966.88 157.35
b) Labour
Mate day 0.090 320.00 28.80
Mason (1st Class) day 0.100 430.00 43.00
Mazdoor (Unskilled) day 2.000 280.00 560.00
Bhisti day 0.270 320.00 86.40
c) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 0.000 0.00 0.00
d) Formwork @ 4% on cost of material, labour and machinery (a+b+c) 153.30
e) Overheads @ 15% on (a+b+c+d) 597.87
f) Royalty
Fine sand cum 0.480 35.00 16.80
40 mm aggregate cum 0.480 130.00 62.40
20 mm aggregate cum 0.240 130.00 31.20
10 mm aggregate cum 0.080 130.00 10.40
Rate per cum = a+b+c+d+e+f 4,704.48
Labour welfare Cess 1% 47.04
4,751.52
Ref. to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Spe.

III. P.C.C. grade M 20 Nominal mix(1:2:4)


Unit = cum
a) Material
Cement t 0.330 5,061.82 1,670.40
Sand cum 0.450 699.53 314.79
40 mm aggregate cum 0.360 1,606.88 578.48
20 mm aggregate cum 0.360 1,907.83 686.82
10 mm aggregate cum 0.180 1,966.88 354.04
b) Labour
Mate day 0.080 320.00 25.60
Mason (1st Class) day 0.100 430.00 43.00
Mazdoor (Unskilled) day 1.630 280.00 456.40
Bhisti day 0.270 320.00 86.40
c) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 0.400 153.91 61.56
d) Formwork @ 4% on (a+b+c) 171.10
e) Overheads @ 15% on (a+b+c+d) 667.29
f) Royalty
Sand cum 0.450 35.00 15.75
40 mm aggregate cum 0.360 130.00 46.80
20 mm aggregate cum 0.360 130.00 46.80
10 mm aggregate cum 0.180 130.00 23.40
Rate per cum = a+b+c+d+e+f 5,248.62
Labour welfare Cess 1% 52.49
5,301.11
IV. R.C.C grade M 25
Unit = cum
a) Material
Cement t 0.404 5,061.82 2,044.98
Sand cum 0.450 699.53 314.79
20 mm aggregate cum 0.540 1,907.83 1,030.23
10 mm aggregate cum 0.360 1,966.88 708.08

b) Labour
Mate day 0.080 233.50 18.68
Mason (1st Class) day 0.120 273.50 32.82
Mazdoor (Unskilled) day 1.730 213.50 369.36
Bhisti day 0.270 233.50 63.05
c) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 0.400 177.00 70.80
d) Formwork @ 3.75% on (a+b+c) 174.48
e) Overhead Charges @ 15% 15.0% 724.09
g) carriage and Royalty
Cement t 0.404 0.00 0.00
Coarse sand cum 0.450 35.00 15.75
20 mm aggregate cum 0.540 130.00 70.20
10 mm aggregate cum 0.360 130.00 46.80
Rate per cum = a+b+c+d+e+f 5,684.08
Labour welfare Cess 1% 56.84
5,740.92
12.6 1000 Supplying, fitting and placing HYSD bar reinforcement (Fe 415) complete as per

drawings and MORD technical specification Clauses 1000,1200 as per direction of

the Engineer in charge


Unit = t
Foundation
a) Material
HYSD bars including 5 per cent overlaps and wastage t 1.05 45,745.02 48,032.27
Binding wire kg 6.00 79.00 474.00
Ref. to
Sr. Rate Amount
MORD Description Unit Quantity
No. (Rs.) (Rs.)
Spe.
b) Labour for cutting, bending, shifting to site, tying, and placing in position
Mate day 0.40 233.50 93.40
Blacksmith day 2.00 253.50 507.00
Mazdoor (Unskilled) day 6.00 213.50 1,281.00
c) Overhead charges @ 15% on (a+b) 15.0% 7,558.15
Carriage
Carriage of Steel t 1.05 0.00 0.00
Rate per t = a+b+c 57,945.82
Labour welfare Cess 1% 579.46
58,525.28
Providing and laying of Type-B(first class) bedding for laying of Hume

Pipe on well compacted moorum or approved granular material as per

MORD Technical Specification clause 1105(ii) and as per direction of the

engineer-in-charge.
I. Moorum
Unit = cum
a) Labour
Mate day 0.01 233.50 2.34
Mazdoor (Unskilled) day 0.30 213.50 64.05
b) Material
Moorum assuming 20% void cum 1.20 252.40 302.88
C) Overhead charges @ 15% on (a) 15.0% 55.39
d) Royalty
Moorum assuming 20% void cum 1.20 35.00 42.00
Rate per cum = a+b+c+d 466.65
Labour welfare Cess 1% 4.67
471.32
CHAPTER -12
SUBSTRUCTURE
Name of the Road : Nandighore to Saliajhari
Ref. to
Sr. Rate
MORD Description Unit Quantity Amount (Rs.)
No. Spe. (Rs.)

12.1 600 Brick masonry work in cement mortar in foundation complete excluding
pointing and plastering as per drawing and technical specifications Clauses
600, 1202 & 1203.
Unit = cum
II. Brick masonry in 1:3 cement mortar
Unit = cum
a) Material
Brick Nos. 500.00 4.92 2,460.00
Cement mortar 1:4 cum 0.24 3,643.18 874.36
Rates as per sub-analysis
b) Labour
Mate day 0.09 320.00 28.80
Mason (1st Class) day 0.80 430.00 344.00
Mazdoor (Unskilled) day 1.60 280.00 448.00
Bhisti day 0.20 320.00 64.00
Add for formwork @ 5% on cost of material, labour and machinery 210.96
(a+b)
c) Overheads @ 15% on (a+b) 664.52
Royality
Sand cum 0.25 35.00 8.82

Rate per cum = a+b+c 5,103.46


Labour welfare Cess 1% 51.03
5,154.49
Sub-analysis
Cement mortar 1:4 (1 cement : 4 sand)
Unit = cum
a) Material
Cement t 0.38 5,061.82 1,923.49
Sand cum 1.05 699.53 734.51
b) Labour
Mate day 0.04 320.00 12.80
Mazdoor (Unskilled) day 0.90 280.00 252.00
Bhisti day 0.08 320.00 25.60
c) Royalty
Sand cum 1.05 35.00 36.75
Total material and labour = (a+b+c) 2,985.15
Labour welfare Cess 1% 29.85
3,015.00
Sub-analysis
Cement mortar 1:3 (1 cement : 3 sand)
Unit = cum
a) Material
Cement t 0.51 5,061.82 2,581.53
Sand cum 1.05 699.53 734.51
b) Labour
Mate day 0.04 320.00 12.80
Mazdoor (Unskilled) day 0.90 280.00 252.00
Bhisti day 0.08 320.00 25.60
c) Royalty
Sand cum 1.05 35.00 36.75
Total material and labour = (a+b+c) 3,643.18
Labour welfare Cess 1% 36.43
3,679.61
12.3 600 Plastering with cement mortar (1:4), 15 mm thick on brickwork in substructure
as per technical specification Clauses 613.4 & 1204
Unit = 10 sqm
Taking output = 10 sqm
a) Material
Cement mortar 1:4 (Rate as in item 11.5 II ) cum 0.24 2,985.15 716.44
b) Labour
Mate day 0.06 320.00 19.20
Mason 1st Class day 0.60 430.00 258.00
Mazdoor (Unskilled) day 0.60 280.00 168.00
Bhisti day 0.30 320.00 96.00
Ref. to
Sr. Rate
MORD Description Unit Quantity Amount (Rs.)
No. Spe. (Rs.)

c) Overheads @ 15% on (a+b) 188.65


Rate per 10 sqm = a+b+c 1,446.28
Rate per Sqm 144.63
Labour welfare Cess 1% 1.45
146.08

12.5 800 Plain/reinforced cement concrete in sub-structure complete as per drawings


and MORD technical specification Clauses 800,1200 and as per direction of
the Engineer in charge
I. P.C.C grade M 15(Nominal mix)
(i) Nominal mix (1:2.5:5)
Unit = cum
a) Material
Cement t 0.275 5,061.82 1,392.00
Sand cum 0.480 699.53 335.77
40 mm aggregate cum 0.480 1,606.88 771.30
20 mm aggregate cum 0.240 1,907.83 457.88
10 mm aggregate cum 0.080 1,966.88 157.35
b) Labour
Mate day 0.080 320.00 25.60
Mason (1st Class) day 0.100 430.00 43.00
Mazdoor (Unskilled) day 1.630 280.00 456.40
Bhisti day 0.270 320.00 86.40
c) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 0.400 153.91 61.56
d) Formwork @ 10% on (a+b+c) 378.73
e) Overheads @ 15% on (a+b+c+d) 624.90
g) Royalty
Coarse sand cum 0.480 35.00 16.80
40 mm aggregate cum 0.480 130.00 62.40
20 mm aggregate cum 0.240 130.00 31.20
10 mm aggregate cum 0.080 130.00 10.40
Rate per cum = a+b+c+d+e+f 4,911.70
Labour welfare Cess 1% 49.12
4,960.82
III. P.C.C grade M 20
(i) Nominal mix (1:2:4)
Unit = cum
a) Material
Cement t 0.330 5,061.82 1,670.40
Sand cum 0.450 699.53 314.79
40 mm aggregate cum 0.360 1,606.88 578.48
20 mm aggregate cum 0.360 1,907.83 686.82
10 mm aggregate cum 0.180 1,966.88 354.04
b) Labour
Mate day 0.080 320.00 25.60
Mason (1st Class) day 0.100 430.00 43.00
Mazdoor (Unskilled) day 1.630 280.00 456.40
Bhisti day 0.270 320.00 86.40
c) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 0.400 153.91
d) Formwork @ 10% on (a+b+c) 421.59
e) Overheads @ 15% on (a+b+c+d) 695.63
g) Royalty
Coarse sand cum 0.450 35.00 15.75
40 mm aggregate cum 0.360 130.00 46.80
20 mm aggregate cum 0.360 130.00 46.80
10 mm aggregate cum 0.180 130.00 23.40
Rate per cum = a+b+c+d+e+f 5,465.89
Labour welfare Cess 1% 54.66
5,520.55

IV. R.C.C grade M 25


Unit = cum
a) Material
Cement t 0.404 5,061.82 2,044.98
Sand cum 0.450 699.53 314.79
20 mm aggregate cum 0.540 1,907.83 1,030.23
10 mm aggregate cum 0.360 1,966.88 708.08

b) Labour
Ref. to
Sr. Rate
MORD Description Unit Quantity Amount (Rs.)
No. Spe. (Rs.)

Mate day 0.080 320.00 25.60


Mason (1st Class) day 0.120 430.00 51.60
Mazdoor (Unskilled) day 1.730 280.00 484.40
Bhisti day 0.270 320.00 86.40
c) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 0.400 153.91 61.56
d) Formwork @ 10% on (a+b+c) 480.76
e) Overheads @ 15% on (a+b+c+d) 793.26
g) Royalty
Coarse sand cum 0.450 35.00 15.75
20 mm aggregate cum 0.540 130.00 70.20
10 mm aggregate cum 0.360 130.00 46.80
Rate per cum = a+b+c+d+e+f 6,214.41
Labour welfare Cess 1% 62.14
6,276.55

a) Rib (Boxcell)
Basic Rate 6,214.41
Add shuttering 1.75 Sqm @Rs 228.90 400.58
6,614.99
Labour welfare Cess 1% 66.15
6,681.13
12.6 1000 Supplying, fitting and placing HYSD bar reinforcement (Fe 415) complete as
per drawings and MORD technical specification Clauses 1000,1200 as per
direction of the Engineer in charge
Unit = t
Sub-Structure
a) Material
HYSD bars including 5 per cent overlaps and wastage t 1.05 45,745.02 48,032.27
Binding wire kg 6.00 216.90 1,301.40
b) Labour for cutting, bending, shifting to site, tying, and placing in
position
Mate day 0.34 320.00 108.80
Blacksmith day 2.00 370.00 740.00
Mazdoor (Unskilled) day 6.50 280.00 1,820.00
c) Overheads @ 15% on (a+b) 7,800.37
Rate per t = a+b+c 59,802.84
Labour welfare Cess 1% 598.03
60,400.87

12.9 600 Providing weepholes in brick masonry/stone masonry, plain/reinforced


concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending
through the full width of the structures with slope of 1(V):20(H) towards drawing
face complete as per drawing and MORD technical specification Clauses 614,
709, 1204 and as per direction of the Engineer in charge
Unit = Nos
Taking output = 30 Nos
a) Material
AC pipe 100 mm dia including wastage @ 5 per cent. Average length of m 31.50 70.52 2,221.38
weep hole is taken as one metre for the purpose of estimating
MS clamps Nos. 30.00 44.00 1,320.00
Cement mortar 1:3 (For rate refer to item 11.5 II) cum 0.05 3,643.18 182.16
b) Labour
Mate day 0.03 320.00 9.60
Mason 1st Class day 0.50 430.00 215.00
Mazdoor (Unskilled) day 0.25 280.00 70.00
c) Overheads @ 15% on (a+b) 602.72
Cost for 30 Nos = (a+b+c) 4,620.86
Rate per No = (a+b+c)/30 154.03
Labour welfare Cess 1% 1.54
155.57

12.10 1200 Backfilling behind abutment, wing wall and return wall complete as per
drawings & technical specification Clause 1204.3.8
Unit = cum
Taking output = 10 cum
I) Granular material
Ref. to
Sr. Rate
MORD Description Unit Quantity Amount (Rs.)
No. Spe. (Rs.)

a) Material
Sand cum 12.00 704.30 8,451.60
b) Labour
Mate day 0.40 320.00 128.00
Mazdoor (Unskilled) day 10.00 280.00 2,800.00
Bhisti day 0.40 320.00 128.00
c) Overheads @ 15% on (a+b) 1,726.14
d) Royalty
Granular material cum 12.00 35.00 420.00
Cost for 10 cum of granular backfill = a+b+c+d 13,653.74
Rate per cum = (a+b+c+d)/10 1,365.37
Labour welfare Cess 1% 13.65
1,379.02
12.11 1200 Providing and laying filter media with granular crushed aggregates as per
specification to a thickness of not less than 600 mm with smaller size towards
the soil and bigger size towards the wall and providing over the entire surface
behind abutment, wing wall, return wall to the full height, compacted to firm
condition complete as per drawing and MORD technical specification Clause
1204.3.8 and as per direction of the Engineer in charge
Unit = cum
Taking output = 10 cum
a) Material
Filter media as per specification cum 12.00 1,389.73 16,676.76
b) Labour
Mate day 0.40 320.00 128.00
Mazdoor (Unskilled) day 9.00 280.00 2,520.00
Mazdoor (Skilled) day 1.00 370.00 370.00
Bhisti day 0.50 320.00 160.00
c) Overheads @ 15% on (a+b) 2,978.21

d) Royalty
Filter Media cum 12.00 130.00 1,560.00
Cost for 10 cum of filter media = a+b+c+d 24,392.97
Rate per cum = (a+b+c+d)/10 2,439.30
Labour welfare Cess 1% 24.39
2,463.69
12.14 1200 Providing pressure relief pipes 100 mm dia in bottom slab of box cell on a filter
media base of 500 mm x 500 mm as per drawing and technical specification
Clause 1205.5.7
Unit = Nos
a) Material
AC pipe 100 mm dia i/c wastage of 5 per cent 600 mm long upto the m 0.63 70.52 44.43
bottom of levelling
Filter media course
base with stone aggregate 0.5 m x 0.5 m area 1 m deep cum 0.25 1,389.73 347.43
b) Labour
Mate day 0.031 320.00 9.92
Mason 1st Class day 0.016 430.00 6.88
Mazdoor (Unskilled) day 0.80 280.00 224.00
c) Overheads @ 15% on (a+b) 94.90
d) Royalty
Filter Media cum 0.25 130.00 32.50
Rate per No = (a+b+c+d) 760.06
Labour welfare Cess 1% 7.60
767.66
CHAPTER -13
SUPER STRUCTURE
Name of the Road : Nandighore to Saliajhari

Ref. to
Sr. Rate Amount
MORD Description Unit Quantity
No. Spe. (Rs.) (Rs.)

13.1 800 Providing and laying reinforced cement concrete in superstructure as per
drawing and technical specifications Clauses 800, 1205.4 and 1205.5
I. R.C.C grade M- 20
(i) For nominal mix 1:2:4
Unit = cum
a) Material
Cement t 0.35 5,061.82 1,771.64
Coarse sand cum 0.45 699.53 314.79
20 mm aggregate cum 0.54 1,907.83 1,030.23
10 mm aggregate cum 0.36 1,966.88 708.08
b) Labour
Mate day 0.08 320.00 25.60
Mason (1st Class) day 0.12 430.00 51.60
Mazdoor (Unskilled) day 1.73 280.00 484.40
Bhisti day 0.27 320.00 86.40
c) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 0.40 153.91 61.56
d) Add for formwork and staging
Height upto 5 m @20% of (a+b+c) 906.86
e) Overheads @ 15% on (a+b+c+d) 816.17
f) Royalty
Coarse sand cum 0.45 35.00 15.75
20 mm aggregate cum 0.54 130.00 70.20
10 mm aggregate cum 0.36 130.00 46.80
Rate per cum = a+b+c+d+e+f 6,390.08
Labour welfare Cess 1% 63.90
6,453.98

(ii) For nominal mix 1:2:4 (Hand mixed)


Unit = cum
a) Material
Cement t 0.35 5,061.82 1,771.64
Coarse sand cum 0.45 699.53 314.79
20 cum aggregates cum 0.54 1,907.83 1,030.23
10 mm aggregate cum 0.36 1,966.88 708.08
b) Labour
Mate day 0.09 320.00 28.80
Mason (1st Class) day 0.10 430.00 43.00
Mazdoor (Unskilled) day 2.00 280.00 560.00
Bhisti day 0.27 320.00 86.40
c) For formwork and staging add the following
percentage of (a+b)
Height upto 5 m @ 20 % of (a+b) 908.59
Height from 5 m to 10 m @ 25% of (a+b)
Height above 10 m @ 30% of (a+b)
d) Overheads @ 15% on (a+b+c) 817.73
e) Royalty
Coarse sand cum 0.45 35.00 15.75
20 cum aggregates cum 0.54 130.00 70.20
10 mm aggregate cum 0.36 130.00 46.80
Rate per cum = a+b+c+d+e 6,401.99
Labour welfare Cess 1% 64.02
6,466.01

(iii) For design mix RCC M 20


a) Material
Cement t 0.33 5,061.82 1,670.40
Coarse sand cum 0.45 699.53 314.79
Ref. to
Sr. Rate Amount
MORD Description Unit Quantity
No. Spe. (Rs.) (Rs.)

20 mm aggregate cum 0.54 1,907.83 1,030.23


10 mm aggregate cum 0.36 1,966.88 708.08
b) Labour
Mate day 0.08 320.00 25.60
Mason (1st Class) day 0.12 430.00 51.60
Mazdoor (Unskilled) day 1.73 280.00 484.40
Bhisti day 0.27 320.00 86.40
c) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 0.40 153.91 61.56
d) For formwork and staging add the following percentage of
(a+b+c):
Height upto 5 m @ 20 per cent 886.61
e) Overheads @ 15% on (a+b+c+d) 797.95

f) Royalty
Coarse sand cum 0.45 35.00 15.75
20 cum aggregates cum 0.54 130.00 70.20
10 mm aggregate cum 0.36 130.00 46.80
Rate per cum = a+b+c+d+e+f 6,250.37
Labour welfare Cess 1% 62.50
6,312.87

II. R.C.C. - M- 25
Unit =cum
a) Material
Cement t 0.400 5,061.82 2,024.73
Coarse sand cum 0.45 699.53 314.79
20 mm aggregate cum 0.54 1,907.83 1,030.23
10 mm aggregate cum 0.36 1,966.88 708.08
b) Labour
Mate day 0.08 320.00 25.60
Mason (1st Class) day 0.12 430.00 51.60
Mazdoor (Unskilled) day 1.73 280.00 484.40
Bhisti day 0.27 320.00 86.40
c) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 0.40 153.91 61.56
d) For formwork and staging add 20% of (a+b+c) for height upto 5m 957.48

e) Overheads @ 15% on (a+b+c+d) 861.73


f) Royalty
Coarse sand cum 0.45 35.00 15.75
20 mm aggregate cum 0.54 130.00 70.20
10 mm aggregate cum 0.36 130.00 46.80
Rate per cum = a+b+c+d+e+f 6,739.34
Labour welfare Cess 1% 67.39
6,806.73
III. R.C.C. Grade M 30
Unit =cum
a) Material
Cement t 0.43 5,061.82 2,176.58
Sand cum 0.45 699.53 314.79
20 mm aggregate cum 0.54 1,907.83 1,030.23
10 mm aggregate cum 0.36 1,966.88 708.08
b) Labour
Mate day 0.08 320.00 25.60
Mason (1st Class) day 0.12 430.00 51.60
Mazdoor (Unskilled) day 1.73 280.00 484.40
Bhisti day 0.27 320.00 86.40
c) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 0.40 153.91 61.56
e) Overheads @ 15% on (a+b+c+d) 740.89
f) Royalty
Sand cum 0.45 35.00 15.75
20 mm aggregate cum 0.54 130.00 70.20
10 mm aggregate cum 0.36 130.00 46.80
Rate per cum = a+b+c+d+e+f 5,812.88
Ref. to
Sr. Rate Amount
MORD Description Unit Quantity
No. Spe. (Rs.) (Rs.)

Labour welfare Cess 1% 58.13


5,871.01

13.2 1000 Supplying, fitting and placing HYSD bar reinforcement (Fe 415) complete as per
drawings and MORD technical specification Clauses 1000,1200 as per
direction of the Engineer in charge
Unit = t
SUPER STRUCTURE
a) Material
HYSD bars including 5 per cent for laps and wastage t 1.05 45,745.02 48,032.27
Binding wire kg 8.00 216.90 1,735.20
b) Labour for cutting, bending, tying and placing in position
Mate day 0.44 320.00 140.80
Blacksmith day 3.00 370.00 1,110.00
Mazdoor (Unskilled) day 8.00 280.00 2,240.00
c) Overheads @ 15% on (a+b) 7,988.74
Rate per t = a+b+c 61,247.01
Labour welfare Cess 1% 612.47
61,859.48

13.5 800 Providing and laying cement concrete wearing course M 30 grade including
reinforcement complete as per drawing and technical specifications Clauses
800 and 1206.3
Unit = cum
a) Material
Cement t 0.43 5,061.82 2,176.58
Sand cum 0.45 699.53 314.79
20 mm aggregate cum 0.54 1,907.83 1,030.23
10 mm aggregate cum 0.36 1,966.88 708.08
HYSD bar reinforcement (Rate as per item13.2) t 0.075 53,258.27 3,994.37
b) Labour
Mate day 0.08 320.00 25.60
Mason (1st Class) day 0.12 430.00 51.60
Mazdoor (Unskilled) day 1.88 280.00 526.40
Bhisti day 0.27 320.00 86.40
c) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 0.40 153.91 61.56
d) Overheads @ 15% on (a+b+c+d) 1,346.34
e) Royalty
Sand cum 0.45 35.00 15.75
20 mm aggregate cum 0.54 130.00 70.20
10 mm aggregate cum 0.36 130.00 46.80
Rate per cum = a+b+c+d+e 10,454.70
Labour welfare Cess 1% 104.55
10,559.25

13.6 800 Construction of R.C.C. railing of M 25 grade in cast-in-situ with 20 mm nominal


size aggregate, true to line and grade, tolerance of vertical railing post not to
exceed 1 in 500, centre-to-centre spacing between vertical posts not to exceed
2000 mm as per drawing and technical specifications Clauses 800, 900 and
1208.3
Unit = Running m
Taking output = 4x12 m = Span 48m
a) M 25 grade R.C.C.
No. of vertical posts = (6+1) 4 = 28 nos
Cross-sectional area of vertical post = 0.25x0.275 = 0.069 sqm

Concrete in vertical posts = 0.069 x28x1.00 =


1.932 cum
Hand rail in 3 tiers = 3x48 = 144 m
Cross-sectional area = 0.17x0.175 = 0.03 sqm
Concrete in hand rails = 0.03 x 144 = 4.32 cum
Total concrete = 1.932+4.32 = 6.252 cum cum 6.252 6,298.90 39,380.72
b) HYSD bar reinforce. (Rate as per item13.2) t 1.36 61,247.01 83,295.93
Ref. to
Sr. Rate Amount
MORD Description Unit Quantity
No. Spe. (Rs.) (Rs.)

c) Overheads @ 15% on (a+b) 0.00


Cost for 48 m = (a+b+c) 122,676.66
Rate per m = (a+b+c)/48 2,555.76
Labour welfare Cess 1% 25.56
2,581.32

Sub Analysis for Rate of Concrete


a) Material
Cement t 0.40 5,061.82 2,024.73
Coarse sand cum 0.45 699.53 314.79
20 mm aggregate cum 0.54 1,907.83 1,030.23
10 mm aggregate cum 0.36 1,966.88 708.08
b) Labour
Mate day 0.08 320.00 25.60
Mason (1st Class) day 0.12 430.00 51.60
Mazdoor (Unskilled) day 1.73 280.00 484.40
Bhisti day 0.27 320.00 86.40
c) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 0.40 153.91 61.56
d) Formwork @ 12% 574.49
Overheads @ 15% on (a+b) 804.28
e) Royalty
Coarse sand cum 0.45 35.00 15.75
20 mm aggregate cum 0.54 130.00 70.20
10 mm aggregate cum 0.36 130.00 46.80
Total (a+b+c+d+e) 6,298.90
Labour welfare Cess 1% 62.99
6,361.89

13.6 800
R.C.C. of M 25 grade approach slab including reinforcement and framework
complete as per drawing and technical specifications Clauses 800, and 1211
Unit = cum
a) Material
Reinforcement cement concrete M 25 grade
Rate asper item 13.1 II cum 1.00 6,739.34 6,739.34
HYSD reinforcement
Rate asper item 13.2 t 0.05 61,247.01 3,062.35
Rate per cum 9,801.69
Labour welfare Cess 1% 98.02
9,899.71

13.16 1200 Filler Joint


II) Providing and fixing 20 mm thick compressible fibre board in expansion
joint complete as per drawing and technical specifications
Unit = Running m
Taking output = 7.5 m
a) Material
20 mm thick compressible fibre board 7.5 m long and 250 mm deep sqm 1.875 850.14 1,594.01
Area = 7.5 x 0.25 = 1.875 sqm
b) Labour
For carrying, placing and fixing
Mate day 0.01 320.00 3.20
Mazdoor (Unskilled) day 0.10 280.00 28.00
Mazdoor (Skilled) day 0.10 370.00 37.00
c) Overheads @ 15% on (a+b) 249.33
Cost for 7.5 m = a+b+c 1,911.54
Rate per m = (a+b+c)/7.5 254.87
Labour welfare Cess 1% 2.55
257.42
CHAPTER -14
PROTECTION WORKS
Name of the Road Nandighore to Saliajhari
Ref. to
Sr. Rate Amount
MORD Description Unit Quantity
No. Spe. (Rs.) (Rs.)

14.1 & 1300 Providing and laying boulder appron for bed protection & pitching on slopes with
14.5 stone boulders of minimum size and weight as per Table 1300.1, no fragment
weighing less than 25 kg laid dry complete as per drawing and technical
specifications Clause 1301 & 1302
Unit = cum
a) Material
Stone boulder (25 kg minimum) cum 1.00 1,101.08 1,101.08
Stone spalls cum 0.20 1,042.11 208.42
b) Labour
Mate day 0.04 320.00 12.80
Mason 1st Class day 0.35 430.00 150.50
Mazdoor (Unskilled) day 0.75 280.00 210.00
c) Overheads @ 15% on (a+b) 252.42
d) Royalty
Stone boulder (25 kg minimum) cum 1.00 130.00 130.00
Stone spalls cum 0.20 130.00 26.00
Rate per cum = a+b+c+d 2,091.22
Labour welfare Cess 1% 20.91
2,112.13

14.5 1300 Providing and laying pitching with stone boulders on slopes laid over prepared
filter media as per drawing and MORD technical specifications Clause 1300 and
as per direction of the Engineer in charge
I. Stone/Boulder
Unit = cum
a) Material
Stone boulder (25 kg minimum) cum 1.00 1,101.08 1,101.08
Stone spalls of minimum 25 mm size cum 0.20 1,042.11 208.42
b) Labour
Mate day 0.04 320.00 12.80
Mason 1st Class day 0.35 430.00 150.50
Mazdoor (Unskilled) day 0.75 280.00 210.00
c) Overheads @ 15% on (a+b) 252.42
d) Royalty
Stone boulder (25 kg minimum) cum 1.00 130.00 130.00
Stone spalls of minimum 25 mm size cum 0.20 130.00 26.00
Rate per cum = (a+b+c+d) 2,091.22
Labour welfare Cess 1% 20.91
2,112.13

14.6 1300 Providing and laying filter material underneath pitching in slopes complete as per
drawing and technical specifications Clause 1302 and as per the direction of the
Engineer-in-charge.
Unit = cum
a) Material
Aggregate- Crushable type such as moorum or Gravel cum 1.20 195.38 234.46
for Grading III
b) Labour
Mate day 0.05 320.00 16.00
Mazdoor (Skilled) day 0.25 370.00 92.50
Mazdoor (Unskilled) day 1.02 280.00 285.60
c) Overheads @ 15% on (a+b) 94.28
d) Royalty
Aggregate- Crushable type such as moorum or Gravel cum 1.20 35.00 42.00
for Grading III
Rate per cum = a+b+c+d 764.84
Labour welfare Cess 1% 7.65
772.49
Ref. to
Sr. Rate Amount
MORD Description Unit Quantity
No. Spe. (Rs.) (Rs.)

14.11 1300 Construction of Toe wall For Protection of Slopes as per Drawing and Technical
Specifications Clause 1302.5
I. Random Rubble Masonry in case of stone pitching Laid with Cement
Mortar (1:5)
(iii). In Cement Mortar (1:5)
Unit = cum
a). Material
Stone For RR Masonary cum 1.00 182.00 182.00
Through and Bond Stone
(7nox0.24x0.24mx0.39m=0.16cum) Nos. 7.00 12.00 84.00
b) Labour
Mate day 0.12 320.00 38.40
Mazdo
Mason 1st Class day 1.20 430.00 516.00
Mazdoor (Unskilled) day 1.80 280.00 504.00
Bhisti day 0.08 320.00 25.60
c) Add For Scaffolding @ 5% on (a+b) 67.50
d) Overheads @ 15% on (a+b) 212.63
(e). Royalty
Stone For RR Masonary & Bond Stone cum 1.16 130.00 150.80
Rate per cum = a+b+c+d 1,780.93
Labour welfare Cess 1% 17.81
1,798.74

14.10 1300 Construction of flexible apron 1 m thick comprising of loose stone boulders
weighing not less then 25 kg beyond curtain wall
Unit = cum
a) Material
Stone boulder cum 1.00 1,101.08 1,101.08
Stone spalls cum 0.20 1,042.11 208.42
b) Labour
Mate day 0.05 320.00 16.00
Mason 1st Class day 0.25 430.00 107.50
Mazdoor (Unskilled) day 1.00 280.00 280.00
Add: 1 per cent of cost of (a+b) for trimming and preparation of bed 17.13
c) Overheads @ 15% on (a+b) 259.52

d) Royalty
Stone boulder cum 1.00 130.00 130.00
Stone spalls cum 0.20 130.00 26.00
Rate per cum = a+b+c 2,145.65
Labour welfare Cess 1% 21.46
2,167.11

State Grouting approns & revertments


S/R Grouting approns & revertments 2.3cm deep with (1:3:6) with 40mm down graded
size H.G.metal
C.C (1:3:6) Rate as per item 11.4 cum 0.038 4,851.49 184.36
Mason Spl day 0.050 430.00 21.50
Man mluia day 0.110 280.00 30.80
Woman mluia day 0.110 280.00 30.80
Over head charge 15% 40.12
Sundries & T &P etc. 2% 1.66
Rate per Cum 309.24
Labour welfare Cess 1% 3.09
312.33

Suggestive Providing aggregate plugat on sides of drainage layer in road work using Gr-III
agrregate of required size as per drawing & technical specification clause 5.8 of
SP-20 and clause 401.5 of MORD
Unit - cum
Ref. to
Sr. Rate Amount
MORD Description Unit Quantity
No. Spe. (Rs.) (Rs.)

a). Mate day 0.50 320.00 160.00


Mazdoor (Skilled) day 0.25 370.00 92.50
Mazdoor (Un-Skilled) day 1.02 280.00 285.60
b). Material
Grade-III Stone Agregrate of Required Size Cum 1.20 1604.97 1,925.96
c). Over Hade Charges @ 15% on (a+b) 369.61
d). Royalty
Grade-III Stone Agregrate of Required Size Cum 1.20 130.00 156.00
Rate per cum = a+b+c 2,989.67
Labour welfare Cess 1% 29.90
3,019.57
CHAPTER -15
MAINTENANCE OF ROAD
Name of the Road : Nandighore to Saliajhari
Sr. Ref. to Rate Amount
Description Unit Quantity
No. MORD Spe. (Rs.) (Rs.)

15.1 1900 Restoration of Rain Cuts


i) Restoration of rain cuts with soil, clearing the loose soil, benching for 300mm
width laying fresh material in layers not exceeding 250 mm and compaction

with plate compactor or power rammer to restore the original alignment, level

and slopes as per drawings and MORD technical specifications Clause 1902

by manual means as per direction of the Engineer in charge


A. Manual Means
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.24 320.00 76.80
Mazdoor (Unskilled) day 6.00 280.00 1,680.00
b) Machinery
Plate compactor hour 3.00 92.17 276.51
c) Materials
Compensation for earth Taken from private land cum 7.50 0.00 0.00
d) Overhead charges @ 15% on (a+b) 305.00
e) Royalty
Earth cum 7.50 35.00 262.50
Cost for 10 cum = a+b+c+d+e 2,600.81
Rate per cum = a+b+c+d+e/10 260.08
Labour welfare Cess 1% 2.60
262.68
Note: Only 75% of fresh material has been provided as 25% can be retrieved from site
from earth i.e. flown down the slop in the form of slurry and deposited at the foot
of rain cuts.

15.2 1900 1. Maintenance of Earthen shoulder (filling with fresh selected soil)

Making up loss of material/irregularities on shoulders to the design level by


adding fresh approved selected soil and compacting it with appropriate
equipment at OMC upto a lead of 1000 m as per MORD technical
specification Clause 1903 as per direction of the Engineer in charge
Unit = sqm
Taking output = 100 sqm
Assuming average thickness of filling to be 150 mm
Quality of fresh material = 15 cum
a. Labour
Mate day 0.20 320.00 64.00
Mazdoor (Unskilled) day 5.00 280.00 1,400.00
b. Machinery
Hydraulic Excavator 0.9 cum bucket capacity @ 60 cum per hour hour 0.25 730.43 182.61
Tipper 6.05 cum hour 0.62 506.09 313.78
Add 10% cost of transportation to cover cost of loading and unloading 31.38

Plate compactor @ 25 sqm per hour hour 4.00 92.17 368.68


c. Material
d. Overheads Charges @ 15% on a+b+c 354.07
f. Royalty
Earth 15.00 35.00 525.00
Cost for 100 sqm = a+b+c+d+e 3,239.51
Rate per sqm = (a+b+c+d+e)/100 32.40
Labour welfare Cess 1% 0.32
32.72
Sr. Ref. to Rate Amount
Description Unit Quantity
No. MORD Spe. (Rs.) (Rs.)

15.10 1900 ii Maintenance of RCC Railing


Maintenance and repair of RCC railing to bring it to the original shape
cleaning and repainting as per drawings and technical specification clause
1911 as per direction of Engineer in Charge.
RCC Railing
Unit = running metre
Taking output = 1 metre
It is assumed that damage is to the extent of 10%
a) Labour
Mate day 0.010 320.00 3.20
Mazdoor (Unskilled) day 0.20 280.00 56.00
Mason 1st Class day 0.10 430.00 43.00
b) Materials
M 30 grade cement concrete
Rate as per item Concrete works as above cum 0.10 6,250.37 625.04

Steel bars reinforcement


Rate as per item above t 0.013 45,745.02 594.69
c) Overheads Charges @ 15% on (a) 15.33
Cost for 100 sqm = a+b+c 1,337.25
Labour welfare Cess 1% 13.37
1,350.62

2. Maintenance of Earthen shoulder (stripping of excess soil)


Stripping excess soil from the shoulder surface to achieve the approved level
and compacting with plate compactor at OMC as per drawings and Technical
Specification Clause 1903.
Unit = sqm
Taking output = 100 sqm
Assuming height of stripping as 75 mm
Quantity of earth cutting involved = 7.5 cum
a. Labour
Mate day 0.10 320.00 32.00
Mazdoor (Unskilled) day 2.50 280.00 700.00
b. Machinery
Plate compactor hour 4.00 92.17 368.68
c. Overheads @ 15% on a+b 165.10

Cost for 100 sqm = a+b+c 1,265.78


Rate per sqm = a+b+c/100 12.66
Labour welfare Cess 1% 0.13
12.79

Note: Earth stripped from earthen shoulders to be used as shoulders or dumped on the
side slopes locally for disposal.

15.3 1900 Maintenace of bituminous surface road


iii. Repair to pot holes and removal of loose material, trimming of sides, cleaning
of surface by providing tack coat, 20 mm thick pre-mix carpet and seal coat
type C as per MORD technical specification Clause 503,508,510,1904 as
per direction of the Engineer in charge.
Unit = sqm
Taking output = 200 sqm
a) Labour
Mate day 0.80 320.00 256.00
Mazdoor (Unskilled) day 20.00 280.00 5,600.00
b) Machinery
Air compressor 210 cfm with tractor hour 2.00 179.13 358.26
Bitumen pressure distributor hour 2.00 448.70 897.40
Mixall 6/10t capacity hour 2.00 891.30 1,782.60
Three wheeled 80-100 kN Static Roller hour 4.00 294.78 1,179.12
c) Material
Bitumen for tack coat @ 3kg per 10 sqm 200 x 3 / 10 = 60 kg tonne 0.064 29,010.34 1,856.66

Bitumen for pre-mix carpet @ 14.60 kg per 10 sqm = 200 x 14.6 / 10 = 292 tonne 0.290 31,100.08 9,019.02
kg
Bitumen for seal coat @ 6.8 kg per 10 sqm tonne 0.140 31,100.08 4,354.01
= 200 x 6.8 / 10 = 136 kg
Sr. Ref. to Rate Amount
Description Unit Quantity
No. MORD Spe. (Rs.) (Rs.)
Crushed stone aggregate @ 0.27 cum per 10 sqm cum 5.40 1,933.22 10,439.41
= 200 x 0.27 / 10 = 5.4 cum (Rate =( 9cum13.2+4.5cum 11.2mm)/13.5)
Crushed stone chipping passing 6.70 mm sieve and retained on 180 micron cum 1.20 1,604.37 1,925.24
sieve @ 0.06 cum per 10 sqm
200 x 0.09 / 10 = 1.80 cum
d) Overhead charges @ 15% on a+b+c 5,650.16
e) Roalty
Crushed stone aggregate 0 = 5.4 cum cum 5.40 130.00 702.00
Crushed sand = 1.20 cum cum 1.80 35.00 63.00
Cost for 200 sqm = a+b+c+d+e 44,082.89
Rate per sqm = a+b+c+d+e/200 220.41
Labour welfare Cess 1% 2.20
222.61

15.7 1900 (I) Maintenance of Culverts


Maintenance of Hume pipe Culvert by way of Clearing, Cleaning, Erosion repair,
repairs to cracks, parapet wall and protection work as per drawing and technical
specification Clause 1908 of MORD and as per direction of the Engineer in
charge.
Unit = One No. Hume pipe (1000 mm dia)
Taking output = One No.H.P. Culvert
a) Labour
Mate day 0.10 320.00 32.00
Mazdoor (Unskilled) day 1.00 280.00 280.00
Mason 2nd Class day 1.40 370.00 518.00
b) Material
Cement, Sand, Brick, Boulder etc. L.S 200.00
c) Overhead charges @ 15% on a+b 154.50
Rate per hume pipe Culvert = a+b+c No 144.06
Labour welfare Cess 1% 1.44
145.50

(II) Maintenance of Culverts (Slab type)


Maintenance of Slab type Culverts by way of clearing, Cleaning, Erosion
repair, repairs to cracks, parapet walls and Protection works as per drawing
and technical specification Clasue 1908 of MORD as per direction of the
Engineer in charge.
Unit = One No. Culvert (2 m span)
Taking output = one No. Slab Culvert
a) Labour
Mate day 0.20 320.00 64.00
Mazdoor (Unskilled) day 4.00 280.00 1,120.00
Mason 2nd Class day 1.00 370.00 370.00
b) Material
Cement, Sand, Brick, Boulder etc. L.S 350.00
c) Overhead charges @ 15% on a+b 285.60
Rate per hume pipe Culvert = a+b+c No 2,189.60
Labour welfare Cess 1% 21.90
2,211.50

15.9 1900 Maintenance of Road Signs


Maintenance of road signs by way of cleaning and repainting of mandatory /
requlatory / cautionary / informatory and place identifications sign board as
perdrawings and technical specification Clause 1910 of MORD as per direction of the
Engineer in charge.
Unit = 1 km
Taking output = one km
All types of signs in one Km
a) Labour
Mate day 0.09 320.00 28.80
Mazdoor (Unskilled) day 2.00 280.00 560.00
Painter 1st Class day 0.125 430.00 53.75
b) Material
Synthetic Enamel Paint, Engineering grade tape, welding machine etc. (LS LS 300.00
c) Rs.300)
Overhead charges @ 15% on a+b 141.38
Rate per km = a+b+c 1,083.93
Labour welfare Cess 1% 10.84
1,094.77
Sr. Ref. to Rate Amount
Description Unit Quantity
No. MORD Spe. (Rs.) (Rs.)

15.11 1900 Maintenance of 200 metre and km stones


Maintenance of 200 metre, km stones & 5th Km stones by way of refiting of tilted
stones repairing with cement mortar, cleaning, repairing and lettering on 200 metre
km stone and 5th km stone as per drawing and technical specification Clause 1912
of MORD as per direction of the Engineer in charge.

Unit = 1 km
Assuming 1 km stone, 4 nos 200 metre stone and 1/5th 5km stone
(i) Painting two coats with synthetic enamel paint
200 m stone 4 nos = 0.760 sqm. 6000
One km stone = 0.815 sqm.
5th km stone 1x1/5 = 0.320 sqm.
Total =(1.575+0.320)= 1.895 sqm.
As per item No. 10.5 of chapter 10 sqm 1.895 84.04 159.26

(ii) Printing letters and figures of any shade with synthtic enamel paint of any
approved colour to give an even shade
200 m stone 4 Nos = 40 per cm height per letter
One no km stone = 120 per cm height per letter
5th km stones 1/5th = 60 per cm height per letter
Total =(160+60)= 220 per cm height per letter
Rate as per item no 10.1 of chapter 10 per cm
height per 220.00 0.900 198.00
letter
a) Labour
Mate day 0.024 320.00 7.68
Mazdoor day 0.50 280.00 140.00
Mason 1st Class day 0.10 430.00 43.00
b) Materials
Cement, sand, aggregates etc. LS 100.00
c) Overheads charges @ 15% on (a+b) 43.60
Rate per/km = (i+ii+a+b+c) 691.54
Labour welfare Cess 1% 6.92
698.46

15.12 1900 Cutting of branches of trees shrubs and trimming of grass and
weeds
(i) Cutting of branches of trees from the road way or with in R.O.W including
disposal of wood and leaves to suitable location as per technical specification

Clause 1914 of MORD as per direction of the Engineer in charge.


Unit = one tree
Taking output = 10 trees of 900 mm average girth
a) Labour
Mate day 0.12 320.00 38.40
Mazdoor (Skilled) day 1.00 370.00 370.00
Mazdoor (Unskilled) day 2.00 280.00 560.00
b) Overhead charges @ 15% on (a) 145.26
Cost for 10 trees = (a+b) 1,113.66
Rate per tree = (a+b)/10 111.37
Labour welfare Cess 1% 1.11
112.48

(ii) Cutting of shurb from the road way or with in R.O.W including disposal of wood
and leaves to suitable location as per technical specification Clause 1914 of
MORD as per direction of the Engineer in charge.
Unit=Each
Taking output = 100 nos shrubs

a) Labour
Mate day 0.08 320.00 25.60
Mazdoor (Unskilled) day 2.00 280.00 560.00
b) Overhead charges @ 15% on (a) 87.84
Cost for 100 shurbs = a+b 673.44
Rate per shurb = a+b/100 6.73
Labour welfare Cess 1% 0.07
6.80
Sr. Ref. to Rate Amount
Description Unit Quantity
No. MORD Spe. (Rs.) (Rs.)
iii) Triming of grass and weeds from the shoulder/berms and disposal the same to
suitable location as per technical specification Clause 1914 of MORD as per
direction of the Engineer in charge
Unit = sqm
Taking output = 1500 sqm
a) Labour
Mate day 0.40 320.00 128.00
Mazdoor (Unskilled) day 10.00 280.00 2,800.00
b) Overheads charges @ 15% on a 439.20
Cost for 1500 sqm = a+b 3,367.20
Rate per sqm = a+b/1500 2.24
Labour welfare Cess 1% 0.02
2.26

15.13 1900 White washing of parapet walls of CD work and tree truncks
White washing two coats on parapet walls and tree trunks including preparation of
surface by cleaning scraping etc. as per MORD technical specifications Clause 1915
as per direction of the Engineer in charge.
Unit = sqm
Taking output = 9 sqm
a) Labour
Mate day 0.01 320.00 3.20
Mazdoor (Unskilled) day 0.143 280.00 40.00
White washer day 0.143 370.00 52.86
b) Materials
Lime Qntl. 0.045 1,900.00 85.50
Fevicol adhesive kg 0.10 321.32 32.13
Indigo kg 0.013 59.06 0.77
c) Overhead charges @ 15% on a+b 32.17

Cost for 9 sqm = a+b+c 246.63


Rate per sqm = a+b+c/9 27.40
Labour welfare Cess 1% 0.27
27.67

Junior Engineer Assistant Executive Engineer Executive Enginer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh
TRANSECT WALK REPORT

NAME OF ROAD:- Nandighore to Saliajhari


PACKAGE NO
DIST:- Nayagarh
BLOCK:- Odagaon

REPORT

During coducting compass survey on the road to find out / select the suitable alignment

for construction of road, we interacted with some villagers/ land owners/

Nandighara,Goudap
public representatives of village uta,Bandhasahi,SAL Discussion was made with them &
IAJHARI,Tikarpali

they have agreed for construction of the road on the exsting alignment.Required land

width is available, how ever if required the villagers/land owners agreed to extend their

co-operation to provide the required land.No forest land/deforestation is required for

construction of the road,since entire length of the road is passing through revenue land.

Junior Engineer Assistant Executive Engineer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh

Executive Enginer
R.W.Division, Nayagarh
RANSECT WALK REPORT

REPORT

mpass survey on the road to find out / select the suitable alignment

ad, we interacted with some villagers/ land owners/

Discussion was made with them &

or construction of the road on the exsting alignment.Required land

ow ever if required the villagers/land owners agreed to extend their

vide the required land.No forest land/deforestation is required for

oad,since entire length of the road is passing through revenue land.

Assistant Executive Engineer


R.W.Sub-Division, Nayagarh
LAND AVAILIBILITY CERTIFICATE
NAME OF ROAD:- Nandighore to Saliajhari
PACKAGE NO
DIST:- Nayagarh
BLOCK:- Odagaon

This is to certify that the road from Nandighore to Saliajhari

under PACKAGE NO is a R D Department road which has the

rquired land available for improvement of the road.No forest land or private land

will be involved for construction of the above mentioned road.

Junior Engineer Assistant Executive Engineer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh

Executive Enginer
R.W.Division, Nayagarh
PRADHANMANTRI GRAM SADAK YOJANA (PMGSY)
COST ESTIMATE FOR CONSTRUCTION OF CROSS DRAINAGE WORKS.
Name of the road: Nandighore to Saliajhari
Type of cross Drainage Work: Hume Pipe Culvert (1000mm dia Double row) PACKAGE NO

Total Nos. of Culvert : 0 Nos. At RD-,,,,, District :


Type of soil : All kinds of soil Block :
Sl. Ht / Th
Description of item Nos. Length Width Unit Quantity Rate in Rs.
No in M
1 2 3 4 5 6 7 8 9
1 Earthwork in excavation for foundation of
structures in all types of soil as per drawing and
technical specification Clause 305 and 1104 of
MoRD includding setting out, construction of
shoring and bracing, removal of stumps and
other deleterious material and disposal upto all
lead & lift, dressing of sides and bottom and
back filling with excavated suitable material
upto 3mt. as per direction of Engineer-in-
Charge.

Head wall 2 × 6.70 × 1.50 × 1.00 Cum 20.10


Pipe portion 1 × 4.65 × 3.70 × 0.900 Cum 15.48
U/S appron 1 × 6.70 × 1.50 × 0.30 Cum 1.58
D/S appron 1 × 6.70 × 2.00 × 0.30 Cum 2.43
D/S toe wall 4 × 3.00 × 1.00 × 1.00 Cum 12.00
Total 51.59
For 0 no culverts 51.59 x 0 Cum 0 @ 272.07
2 Filling Sand in foundation in trenches as per
drawing and technical specification clause
305.3.9.

Below Head Wall 2 × 6.70 × 1.50 × 0.15 Cum 3.02


Around pipe 1 x 5.00 x 3.70 x 1.20 Cum 22.20
D/S toe wall 4 × 3.00 × 1.00 × 0.15 Cum 1.80
Total 27.02
Deduct for pipe 2 × 4.65 × 0.785 × (1.20)2 Cum 10.51
Total 16.51
For 0 no culverts 16.51 x 0 Cum 0.00 @ 1125.35
3 Providing M15 concrete for plain / reinforced
concrete in open foundation complete as per
drawing and MORD technical specification
Clause 800,1100,1200 and as per direction of
Engineer-in-Charge.

Head wall 2 × 6.70 × 1.50 × 0.15 Cum 3.02


Toe Wall 4 × 3.00 × 1.00 × 0.150 Cum 1.80
Total 4.82
For 0 no culverts 4.82 x 0 Cum 0 @ 4696.88

4 Providing and laying of Type-B(first class)


bedding for laying of Hume Pipe on well
compacted moorum or approved granular
material as per MORD Technical Specification
clause 1105(ii) and as per direction of the
engineer-in-charge.

Below Pipe 1 × 4.65 × 3.70 × 0.150 Cum 2.58


For 0 no culverts 2.58 x 0 Cum 0 @ 471.32
5 Providing and laying reinforced cement
concrete NP3 Double Row pipe for culverts
jointing with cement mortar 1:2 but excluding
excavation, protection works, backfilling,
concrete and masonry works in head walls and
parapets as per Clause 1100 of MoRD & as per
direction of Engineer-in-Charge.

2
Sl. Ht / Th
Description of item Nos. Length Width Unit Quantity Rate in Rs.
No in M
1 2 3 4 5 6 7 8 9
1000 mm dia Double row 1 × 7.50 RM 7.50
For 0 no culverts 7.50 x 0 RM 0.00 @ 10329.62
6 Plain/reinforced cement concrete in sub-
structure complete as per drawings and MORD
technical specification Clauses 800,1200 and
as per direction of the Engineer in charge

Parapet 2 × 6.70 × 0.875 × 2.50 Cum 23.12


Parapet 2 × 0.40 × 0.400 × 0.40 Cum 0.13
Collar Joint 2 × 0.20 × 3.70 × 1.40 Cum 2.07
Toe Wall 4 x 3.00 x (0.9+0.4)/2 x 1.20 Cum 9.36
Total 34.68
Deduction in Pipe joint 4 × 0.20 × 0.785 × (1.20)2 um (-) 0.90
Deduct for Pipe 4 × 0.865 × 0.785 × (1.20) 2
um (-) 3.91
Total 29.87
For 0 no culverts 29.87 x 0 Cum 0 @ 4960.82

0 Nos. of Hume Pipe Culverts Total Cost Rs.

Junior Engineer Assistant Executive Engineer Executive Enginer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh

2
Format-F-7

NO

Nayagarh
Odagaon
Amount in
Rs.
10

0.00

0.00

0.00

0.00

2
Amount in
Rs.
10

0.00

0.00

0.00

ve Enginer
on, Nayagarh

2
PRADHANMANTRI GRAM SADAK YOJANA (PMGSY) Format-F-7

COST ESTIMATE FOR CONSTRUCTION OF CROSS DRAINAGE WORKS.

Name of the road: Nandighore to Saliajhari


Type of cross Drainage Work: Hume Pipe Culvert (600mm dia Double row) PACKAGE NO
Total Nos. of Culvert : 0 Nos. At RD-,,,,,,, District : Nayagarh

Type of soil : All kinds of soil Block : Odagaon


Sl. Ht / Th in Quantit Amount in
Description of item Nos. Length Width Unit Rate in Rs.
No M y Rs.
1 2 3 4 5 6 7 8 9 10
1. Earthwork in excavation for foundation of structures in all types
of soil as per drawing and technical specification Clause 305
and 1104 of MoRD includding setting out, construction of
shoring and bracing, removal of stumps and other deleterious
material and disposal upto all lead & lift, dressing of sides and
bottom and back filling with excavated suitable material upto
3mt. as per direction of Engineer-in-Charge.

Head wall 2 × 5.00 × 1.40 × 1.05 Cum 14.70


Pipe bed 1 × 4.65 × 2.37 × 0.90 Cum 9.92
U/S appron 1 × 4.65 × 1.50 × 0.30 Cum 2.09
D/S appron 1 × 4.85 × 2.00 × 0.30 Cum 2.91
toe wall 4 × 4.85 × 1.00 × 1.00 Cum 19.40
Total 49.02
For 0 no culverts 49.02 x 0 Cum 0.00 @ 272.07 0.00
2 Filling Sand in foundation in trenches as per drawing and
technical specification clause 305.3.9.

Below Pipe bed 1 × 4.65 × 2.37 × 0.15 Cum 1.65


Around pipe 1 x 4.65 x 2.37 x 0.76 Cum 8.38
Below H.W. 2 × 5.00 × 1.400 × 0.15 Cum 2.10
Toe Wall 4 x 5.00 x 1.000 x 0.15 Cum 3.00
Total 15.13
Deduct for pipe 2 × 5.55 × 0.785 × (0.76)2 Cum 5.03
Total 10.10
For 0 no culverts 10.10 x 0 Cum 0.00 @ 1125.35 0.00
3 Providing M15 concrete for plain / reinforced concrete in open
foundation complete as per drawing and MORD technical
specification Clause 800,1100,1200 and as per direction of
Engineer-in-Charge.

Head wall bed 2 × 5.00 × 1.400 × 0.15 Cum 2.10


Below pipe 1 × 4.65 × 2.37 × 0.15 Cum 1.65
Toe Wall 4 x 5.00 x 1.00 x 0.15 Cum 3.00
6.75
For 0 no culverts 6.75 x 0 Cum 0.00 @ 4629.17 0.00
5 Providing and laying reinforced cement concrete NP3 Double
Row pipe for culverts jointing with cement mortar 1:2 but
excluding excavation, protection works, backfilling, concrete
and masonry works in head walls and parapets as per Clause
1100 of MoRD & as per direction of Engineer-in-Charge.

600 mm dia Double row 0 × 7.50 RM 0.00 @ 4768.08 0.00

7 Plain/reinforced cement concrete in sub-structure complete as


per drawings and MORD technical specification Clauses
800,1200 and as per direction of the Engineer in charge

Head wall 2 × 5.00 × 0.825 × 2.10 Cum 12.60


Collar Joint 2 × 0.20 × 2.70 × 1.00 Cum 1.08
Parapet 2 × 0.40 × 0.40 × 0.40 Cum 0.13
Toe Wall 4 x 5.00 x (0.9+0.4)/2 x 1.20 Cum 15.60
Total 29.41
Deduction in Pipe joint 4 × 0.2 × p/4 × (0.76)2 Cum (-) 0.36
Sl. Ht / Th in Quantit Amount in
Description of item Nos. Length Width Unit Rate in Rs.
No M y Rs.
1 2 3 4 5 6 7 8 9 10
Deduct for Pipe 4 × 0.660 × 0.785 × (0.76)2 Cum (-) 1.20
27.85
For 0 no culverts 27.85 x 0 Cum 0.00 @ 5074.82 0.00
8 Providing and laying filter material underneath pitching in
slopes complete as per drawing and technical specifications
Clause 1302 and as per the direction of the Engineer-in-charge.

U/S appron 0 × 3.18 × 1.50 × 0.15 Cum 0.00


D/S appron 0 × 3.18 × 2.00 × 0.15 Cum 0.00
U/S D/S revetment 0 ×0.785×1.35× 1.45 × 0.15 Cum 0.00
Total Cum 0.00
For 0 no culverts 0.00 x 0 Cum 0.00 @ 772.49 0.00
9 Providing and laying pitching with stone boulders on slopes laid
over prepared filter media as per drawing and MORD technical
specifications Clause 1300 and as per direction of the Engineer
in charge

U/S appron 1 × 4.65 × 1.50 × 0.30 Cum 2.09


D/S appron 1 × 4.65 × 2.00 × 0.30 Cum 2.79
Deduct 1/6 th voids Cum -0.81
Total Cum 4.07
For 0 no culverts 4.07 x 0 Cum 0.00 @ 2112.13 0.00

0 Nos. of Hume Pipe Culverts Total Cost 0.00

Junior Engineer Assistant Executive Engineer Executive Enginer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh
PRADHANMANTRI GRAM SADAK YOJANA (PMGSY) Format-F-7

COST ESTIMATE FOR CONSTRUCTION OF CROSS DRAINAGE WORKS.

Name of the road: Nandighore to Saliajhari


Type of cross Drainage Work: Hume Pipe Culvert (1000mm dia Three row) PACKAGE NO

Total Nos. of Culvert : 0 Nos. At RD-,,,,, District : Nayagarh

Type of soil : All kinds of soil Block : Odagaon


Ht / Th
Sl. No Description of item Nos. Length Width Unit Quantity Rate in Rs. Amount in Rs.
in M
1 2 3 4 5 6 7 8 9
1 Earthwork in excavation for foundation of
structures in all types of soil as per drawing and
technical specification Clause 305 and 1104 of
MoRD includding setting out, construction of
shoring and bracing, removal of stumps and
other deleterious material and disposal upto all
lead & lift, dressing of sides and bottom and
back filling with excavated suitable material
upto 3mt. as per direction of Engineer-in-
Charge.

Head wall 2 × 8.20 × 1.50 × 0.95 Cum 23.37


Pipe bed 1 × 4.65 × 5.60 × 0.65 Cum 16.93
U/S appron 1 × 6.40 × 1.50 × 0.30 Cum 2.88
D/S appron 1 × 6.40 × 2.00 × 0.30 Cum 3.84
D/S toe wall 1 × 8.05 × 0.60 × 0.40 Cum 1.93
Total 65.54
For 0 no culverts 65.54 x 0 Cum 0 @ 272.07 0.00
2 Filling Sand in foundation in trenches as per
drawing and technical specification clause
305.3.9.

Below Pipe bed 0 × 5.10 × 5.60 × 0.15 Cum 0.00


Around pipe 1 x 5.35 x 5.60 x 1.20 Cum 35.95
Below H.W. 2 × 8.20 × 1.50 × 0.15 Cum 3.69
Total 39.64
Deduct for pipe 4 × 5.65 × 0.785 × (1.20)2 Cum 25.55
Total 14.09
For 0 no culverts 14.09 x 0 Cum 0.00 @ 1125.35 0.00
4 Providing M15 concrete for plain / reinforced
concrete in open foundation complete as per
drawing and MORD technical specification
Clause 800,1100,1200 and as per direction of
Engineer-in-Charge.

Head wall 2 × 8.20 × 1.70 × 0.15 Cum 4.18


Below Pipe bed 1 x 5.10 x 5.60 x 0.15 Cum 4.28
For 0 no culverts 8.46 x 0 Cum 0 @ 4629.17 0.00
5 Providing and laying reinforced cement concrete
NP3 pipe for culverts jointing with cement mortar
1:2 but excluding excavation, protection works,
backfilling, concrete and masonry works in head
walls and parapets as per Clause 1100 of MoRD
& as per direction of Engineer-in-Charge.

1000 mm dia Three Row 0 × 7.50 RM 0.00


0.00 @ 6453.77 0.00

7 Plain/reinforced cement concrete in sub-


structure complete as per drawings and MORD
technical specification Clauses 800,1200 and
as per direction of the Engineer in charge

Pipe joint 2 × 7.05 × 1.40 × 0.20 Cum 3.95


Head wall 2 × 8.05 × 0.950 × 2.45 Cum 37.47
Parapet 2 × 5.60 × 0.40 × 0.40 Cum 1.79
Total 51.28
Ht / Th
Sl. No Description of item Nos. Length Width Unit Quantity Rate in Rs. Amount in Rs.
in M
1 2 3 4 5 6 7 8 9
Deduction in Pipe joint 4 × 0.20 × 0.785 × (1.20)2 Cum (-) 0.90
Deduct for Pipe in head wall 4 × 0.950 × 0.785 × (1.20)2 Cum (-) 4.30
Total 46.08
For 0 no culverts 46.08 x 0 Cum 0 @ 5074.82 0.00

8 Providing and laying filter material underneath


pitching in slopes complete as per drawing and
technical specifications Clause 1302 and as per
the direction of the Engineer-in-charge.

U/S appron 1 × 6.40 × 1.50 × 0.15 Cum 1.44


D/S appron 1 × 6.40 × 2.00 × 0.15 Cum 1.92
U/S D/S revetment 4 ×0.785×1.86× 2.00 × 0.15 Cum 1.75
Total 5.11
For 0 no culverts 5.11 x 0 Cum 0.00 @ 772.49 0.00
9 Providing and laying pitching with stone
boulders on slopes laid over prepared filter
media as per drawing and MORD technical
specifications Clause 1300 and as per direction
of the Engineer in charge

U/S appron 1 × 6.40 × 1.50 × 0.30 Cum 2.88


D/S appron 1 × 6.40 × 2.00 × 0.30 Cum 3.84
U/S D/S revetment 4 ×0.785×1.86× 2.00 × 0.30 Cum 3.50
D/S toe wall 1 × 8.05 × 0.60 × 0.40 Cum 1.93
Total Cum 12.15
For 0 no culverts 12.15 x 0 Cum 0.00 @ 2112.13 0.00
0 Nos. of Hume Pipe Culverts Total Cost Rs. 0.00

Junior Engineer Assistant Executive Engineer Executive Enginer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh
PRADHANMANTRI GRAM SADAK YOJANA (PMGSY) Format-F-7
COST ESTIMATE FOR CONSTRUCTION OF CROSS DRAINAGE WORKS.
Name of the road: Nandighore to Saliajhari
Type of cross Drainage Work: Hume Pipe Culvert (300mm dia Single row) PACKAGE NO
Total Nos. of Culvert : 0 Nos. At RD-,,,,,,, District : Nayagarh
Type of soil : All kinds of soil Block : Odagaon
Sl. Ht / Th
Description of item Nos. Length Width Unit Quantity Rate in Rs. Amount in Rs.
No in M
1 2 3 4 5 6 7 8 9
1. Earthwork in excavation for foundation of
structures upto 3 mtr depth as per drawing
and technical specification clause 1104
including setting out construction of shoring
and bracing, removal of stumps and other
deleterious matter, dressing sides and
bottom and back filling with approved
materials

Head wall 0 × 1.00 × 0.60 × 0.45 Cum 0.00


Pipe bed 1 × 10.00 × 0.80 × 0.65 Cum 5.20
Total 5.20
For 0 no culverts 5.20 x 0 Cum 0.00 @ 272.07 0.00
11.2 Backfilling in foundation trenches as per
drawing and technical clause 1108 (Sand
filling)

Around pipe 1 x 9.00 x 0.80 x 0.76 Cum 5.47


Below H.W. 0 × 1.00 × 0.60 × 0.10 Cum 0.00
Total 5.47
Deduct for pipe 1 × 5.55 × 0.785 × (0..45)2 Cum 0.88
Total 4.59
For 0 no culverts 4.59 x 0 Cum 0.00 @ 1125.35 0.00
11.4 Plain cement concrete M-10 (1:3:6) Nominal
mix in levelling coarse below open
foundation of head walls as per drawing and
technical clause 1109

Pipe bed 1 × 10.00 × 0.80 × 0.10 Cum 0.80


For 0 no culverts 0.80 x 0 Cum 0.00 @ 4900.00 0.00
9.3 Providing and laying reinforced cement
concrete pipe for culverts inlcuding fixing
collar with cement mortar (1:2) but excluding
excavation, protection works, backfilling,
concrete and masonry works in head wall
and parapets clause 1106

350 mm dia Single row 0 × 10.00 RM 0.00 @ 1018.64 0.00


12.5 Plain cement concrete in sub-structure
complete as per drawing and technical
specification clauses 802,804, 805, 806, 807,
1202 & 1204 of MORD with P.C.C. M-15
grade nominal mix (1:2.5:5)

Pipe joint 3 × 0.80 × 0.80 × 0.20 Cum 0.38


Head wall 0 × 1.00 × 0.50 × 0.90 Cum 0.00
Total 0.38
Deduction in Pipe joint 3 × 0.2 × p/4 × (0.45)2 Cum (-) 0.10
Deduct for Pipe in head wall 0 × 0.50 × p/4 × (0.45)2 Cum (-) 0.00
0.28
For 0 no culverts 0.28 x 0 Cum 0.00 @ 5074.82 0.00

0 Nos. of Hume Pipe Culverts Total Cost Rs. 0.00

Junior Engineer Assistant Enggineer Executive Engineer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh
PRADHANMANTRI GRAM SADAK YOJANA (PMGSY)
COST ESTIMATE FOR CONSTRUCTION OF R.C.C. SLAB CULVERT
Name of the road: Nandighore to Saliajhari PACKAGE NO
Type of cross Drainage Work: 1 Span R.C.C. Slab Culvert of
( 4.000 x 3.000 m) At RD-,,
Nos. of Culvert : 0 Nos
Sl. Description of item Nos. Length Width Ht / Th Unit Quantity Rate in Rs. Amount in
No in M Rs.
1 2 3 4 5 6 7 8 9 10
1 Earthwork in excavation for foundation of structures in all types of
soil as per drawing and technical specification Clause 305 and 1104
of MoRD includding setting out, construction of shoring and bracing,
removal of stumps and other deleterious material and disposal upto
all lead & lift, dressing of sides and bottom and back filling with
excavated suitable material upto 3mt. as per direction of Engineer-
in-Charge.
Foundation
Abutments 2 × 7.40 × 3.20 × 1.50 Cum 71.04
Piers 0 × 7.40 × 2.00 × 1.50 Cum 0.00
Cut off U/S 1 × 8.00 × 1.00 × 1.20 Cum 9.60
Cut off D/S 1 × 9.00 × 1.00 × 1.50 Cum 13.50
D/S Bed 1 × 3.00 × 2.20 × 0.60 Cum 3.96
U/S Bed 1 × 3.00 × 1.70 × 0.60 Cum 3.06
CD Bed 1 × 6.00 × 4.40 × 0.60 Cum 15.84
Wing walls 4 × 1.65 × 2.52 × 1.50 Cum 24.95
Total Cum 0.00 @ 299.20 0.00
2 Filling Sand in foundation in trenches as per drawing and technical
specification clause 305.3.9.

Foundation
Abutments 2 × 7.40 × 3.20 × 0.20 Cum 9.47
Piers 0 × 7.40 × 2.00 × 0.20 Cum 0.00
Cut off U/S 1 × 8.00 × 1.00 × 0.20 Cum 1.60
Cut off D/S 1 × 9.00 × 1.00 × 0.20 Cum 1.80
Wing walls 4 × 1.65 × 2.52 × 0.20 Cum 3.33
D/S Bed 1 × 3.00 × 2.40 × 0.20 Cum 1.44
U/S Bed 1 × 3.00 × 1.90 × 0.20 Cum 1.14
CD Bed 1 × 6.00 × 3.50 × 0.20 Cum 4.20
Total Cum 0.00 @ 1125.35 0.00
3 Providing concrete for plain / reinforced concrete in open foundation
complete as per drawing and MORD technical specification Clause
800,1100,1200 and as per direction of Engineer-in-Charge.

With Dewatering in Foundation


Abutments 1st Step 2 × 7.40 × 3.20 × 0.20 Cum 9.47
Pier 1st Step 0 × 7.40 × 2.00 × 0.40 Cum 0.00
Cut off D/S 1st step 1 × 9.00 × 1.00 × 0.30 Cum 2.7
Cut off D/S 2nd step 1 × 9.00 × 0.60 × 1.00 Cum 5.40
Cut off U/S 1st step 1 × 8.00 × 1.00 × 0.30 Cum 2.4
Cut off U/S 2nd step 1 × 8.00 × 0.60 × 0.70 Cum 3.36
Wing 1st Step 4 × 1.65 × 2.52 × 0.40 Cum 6.65
CD Bed 1 × 6.00 × 3.50 × 0.15 Cum 3.15
U/S Bed 1 × 3.00 × 1.90 × 0.15 Cum 0.86
D/S Bed 1 × 3.00 × 2.40 × 0.15 Cum 1.08
Toe wall 4 × 15.00 × 0.60 × 1.20 Cum 43.20
Total Cum 0.00 @ 4,900.00 0.00
4 Plain/reinforced cement concrete in sub-structure complete as per
drawings and MORD technical specification Clauses 800,1200 and
as per direction of the Engineer in charge

A. With dewatering in Sub-structure


Abutments 2nd Step 2 × 7.00 × 2.80 × 0.20 Cum 7.84
Pier 2nd Step 0 × 7.00 × 1.60 × 0.40 Cum 0.00
Cum 0.00 @ 5,018.99 0.00
B. With shuttering in sub-structure
Abutments 3rd step 2 × 6.60 × 2.40 × 0.40 Cum 12.67
4th Step 2 x 6.6+5.6 x 2.4+2.0 x 0.40 Cum 10.91
2 2
Above G.L. 2 × 5.4+6.0 × 1.6+0.7 × 3.10 Cum 40.64
2 2
Pier 3rd Step 0 × 6.60 × 1.20 × 0.40 Cum 0.00
Above G.L. 0 × 6.20 × .77+0.7 × 3.10 Cum 0.00
2
Sl. Description of item Nos. Length Width Ht / Th Unit Quantity Rate in Rs. Amount in
No in M Rs.
1 2 3 4 5 6 7 8 9 10
Wing 4 × 1.85 × 2.12 × 0.40 Cum 6.28
4 × 2.05 × 1.92 × 0.40 Cum 6.3
4 × 3.0+2.05 × 1.72+.4 × 3.42 Cum 36.61
2 2
Total Cum 0@ 5,074.82 0.00
5 Providing and laying reinforced cement concrete in superstructure as
per drawing and technical specifications Clauses 800, 1205.4 and
1205.5
(a) Deck Slab 1 × 4.80 × 6.00 × 0.345 Cum 0@ 7438.74 0.00

(b) Abutment Cap 2 × 6.00 × 0.45 × 0.150 Cum 0.81


Pier Cap 0 × 6.20 × 0.80 × 0.150 Cum 0.00
Parapet 2 × 4.80 × 0.40 × 0.400 Cum 1.54
Dirt wall 2 × 6.00 × 0.30 × 0.570 Cum 2.05
Cum 0.00 @ 6806.73 0.00
6 Providing and laying cement concrete wearing course M 30 grade
including reinforcement complete as per drawing and technical
specifications Clauses 800 and 1206.3

Wearing Coat 2 × 4.80 × 6.00 × 0.075 Cum 0.00 @ 10,559.25 0.00

6 Supplying, fitting and placing HYSD bar reinforcement (Fe 415)


complete as per drawings and MORD technical specification
Clauses 1000,1200 as per direction of the Engineer in charge
a - Deck Slab - R.C.C 0.00 Cum @ 1.00 Qntl. 0.000
b- Cap & Dirt wall 0.00 Cum @ 1.00 Qntl. 0.000
c.- Abutments Piers 36.61 Cum @ 0.08 Qntl. 2.929
Total Qntl. 0.000 @ 6,185.95 0.00
7 Providing weepholes in brick masonry/stone masonry,
plain/reinforced concrete abutment, wing wall, return wall with 100
mm dia AC pipe extending through the full width of the structures
with slope of 1(V):20(H) towards drawing face complete as per
drawing and MORD technical specification Clauses 614, 709, 1204
and as per direction of the Engineer in charge

Abutment 2 × 11 Nos. Nos. 22


Wing wall 4 × 8 Nos. Nos. 32
Nos. 0.00 @ 155.57 0.00
8 Providing and laying boulder appron for bed protection & pitching on
slopes with stone boulders of minimum size and weight as per Table
1300.1, no fragment weighing less than 25 kg laid dry complete as
per drawing and technical specifications Clause 1301 & 1302

U/S & D/S River Bed 1 × 6.00 × 2.50 × 0.60 Cum 16.85
1 × 6.00 × 3.00 × 0.60 Cum 23.33
Cum 0@ 2112.13 0.00

9 Providing and laying filter media with granular crushed aggregates


as per specification to a thickness of not less than 600 mm with
smaller size towards the soil and bigger size towards the wall and
providing over the entire surface behind abutment, wing wall, return
wall to the full height, compacted to firm condition complete as per
drawing and MORD technical specification Clause 1204.3.8 and as
per direction of the Engineer in charge

In between Wing wall and Abutment


Behind Abutments 2 × 6.00 × 3.00 × 0.60 Cum 21.60
Behind Wing wall 4 × 2.53 × 3.42 × 0.60 Cum 20.73
Cum 0.00 @ 2463.69 0.00

Total 0.00
For
0 Nos. of slab culvert Rs. 0.00

Junior Engineer Assistant Executive Engineer Executive Enginer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh
PRADHANMANTRI GRAM SADAK YOJANA (PMGSY)
COST ESTIMATE FOR CONSTRUCTION OF R.C.C. BOX-CELL CULVERT

Name of the road: Nandighore to Saliajhari PACKAGE NO


Type of cross Drainage Work: 1 Span Box-cell Culvert ( 4.00 m x 4.00 m) size
Total Nos. of Culvert : 0 Nos At RD-,,,
Type of soil : All kinds of soil
Sl. Ht / Th Amount in
Description of item Nos. Length Width Unit Quantity Rate in Rs.
No in M Rs.
1 2 3 4 5 6 7 8 9 10
1 Earthwork in excavation for foundation of structures in all types of
soil as per drawing and technical specification Clause 305 and
1104 of MoRD includding setting out, construction of shoring and
bracing, removal of stumps and other deleterious material and
disposal upto all lead & lift, dressing of sides and bottom and back
filling with excavated suitable material upto 3mt. as per direction
of Engineer-in-Charge.

Cut off U/S(with side cut off) 1 × 17.90 × 1.00 × 2.00 Cum 35.80
Cut off D/S 1 × 18.90 × 1.00 × 2.50 Cum 47.25
Bridge proper and appron 1 × 9.90 × 4.90 × 0.80 Cum 38.81
Flexible appron U/S 1 × 6.10 × 2.50 × 1.00 Cum 15.25
Flexible appron D/S 1 × 6.10 × 3.00 × 1.00 Cum 18.30
Wing walls 4 × 2.20 × 2.52 × 2.00 Cum 44.35
199.76
No of culverts=2 Cum 0.00 @ 272.07 0
2 Filling Sand in foundation in trenches as per drawing and technical
specification clause 305.3.9.

Below raft 1 × 10.30 × 5.30 × 0.20 Cum 10.92


Cut off wall U/S 1 × 17.90 × 1.00 × 0.20 Cum 3.58
Cut off wall D/S 1 × 18.90 × 1.00 × 0.20 Cum 3.78
Wing walls 4 × 2.20 × 2.52 × 0.20 Cum 4.44
22.72
No of culverts=2 Total Cum 0.00 @ 1125.35 0
3 Providing concrete for plain / reinforced concrete in open
foundation complete as per drawing and MORD technical
specification Clause 800,1100,1200 and as per direction of
Engineer-in-Charge.

PCC M 10

Below bed level


Below raft 1 × 10.30 × 5.30 × 0.15 Cum 8.19
Wing walls 4 × 2.20 × 2.52 × 0.40 Cum 8.87
Cut off D/S 1st step 1 × 17.90 × 1.00 × 0.50 Cum 8.95
Cut off U/S 1st step 1 × 18.90 × 1.00 × 0.50 Cum 9.45
Cut off D/S 2nd step 1 × 17.90 × 0.60 × 1.00 Cum 10.74
Cut off U/S 2nd step 1 × 18.90 × 0.60 × 1.50 Cum 17.01
63.21
No of culverts=2 0.00 @ 4,696.88 0
4 Plain/reinforced cement concrete in sub-structure complete as per
drawings and MORD technical specification Clauses 800,1200
and as per direction of the Engineer in charge

P.C.C grade M 15(Nominal mix)


( Below bed)
Rigid Appron U/S 1 × 6.50 × 2.50 × 0.30 Cum 4.88
D/S 1 × 6.50 × 3.00 × 0.30 Cum 5.85
Wing 4 × 2.20 × 1.96 × 0.40 Cum 6.90
Wing walls 4 × 2.20 × 1.84 × 0.40 Cum 6.48
4 × 3.00 × 1.06 × 3.60 Cum 45.79
69.90
No of culverts=2 Total Cum 0.00 @ 4,960.82 0
5 Providing and laying reinforced cement concrete of M-25 grade in
foundation complete as per drawings and technical specifications
Clause 800 & 1200 of MoRD and as per the direction of the
Engineer-in-charge
Sl. Ht / Th Amount in
Description of item Nos. Length Width Unit Quantity Rate in Rs.
No in M Rs.
1 2 3 4 5 6 7 8 9 10
RCC M 25

(a) Raft 1 × 6.00 × 4.90 × 0.35 Cum 10.29


No of culverts=2 0.00 @ 5740.92 0
Providing and laying reinforced cement concrete of M-25 grade in
Super structure complete as per drawings and technical
specifications Clause 800 & 1200 of MoRD and as per the direction
of the Engineer-in-charge

(b) Deck Slab 1 × 6.00 × 4.90 × 0.35 Cum 10.29


No of culverts=2 0.00 @ 6806.73 0
Providing and laying reinforced cement concrete of M-25 grade in
Sub-structure complete as per drawings and technical
specifications Clause 800 & 1200 of MoRD and as per the direction
of the Engineer-in-charge

c) Rib 2 x 6.00 × 0.45 × 4.00 Cum 21.60


Hunch 4 x 6.00 × 0.15/2 × 0.15 Cum 0.27
21.87
No of culverts=2 Cum 0.00 @ 6,276.55 0
d) Construction of R.C.C. railing of M 25 grade in cast-in-situ with 20
mm nominal size aggregate, true to line and grade, tolerance of
vertical railing post not to exceed 1 in 500, centre-to-centre spacing
between vertical posts not to exceed 2000 mm as per drawing and
technical specifications Clauses 800, 900 and 1208.3

2 × 4.90 Rm 9.80
No of culverts=2 0.00 @ 2,581.32 0
6 Providing and laying cement concrete wearing course M 30 grade
including reinforcement complete as per drawing and technical
specifications Clauses 800 and 1206.3

1 × 6.00 × 4.90 × 0.075 Cum 2.21


No of culverts=2 0.00 @ 10,559.25 0
7 Supplying, fitting and placing HYSD bar reinforcement (Fe 415)
complete as per drawings and MORD technical specification
Clauses 1000,1200 as per direction of the Engineer in charge

In super structure
a - Deck Slab 0.00 Cum @ 1.00 Qntl. 0
No of culverts=2 0@ 6,185.95 0
In foundation
c.- Raft 0.00 Cum @ 1.00 Qntl. 0
No of culverts=2 0@ 5852.53 0
In sub structure
d-Rib & Hunch 0.00 Cum @ 0.80 Qntl. 0.000
e-Wing wall 45.79 Cum @ 0.075 Qntl. 3.434
No of culverts=2 Qntl. 0.000 @ 6,040.09 0
8 Providing weepholes in brick masonry/stone masonry,
plain/reinforced concrete abutment, wing wall, return wall with 100
mm dia AC pipe extending through the full width of the structures
with slope of 1(V):20(H) towards drawing face complete as per
drawing and MORD technical specification Clauses 614, 709,
1204 and as per direction of the Engineer in charge

Abutment 2 × 10 Nos. Nos. 20


Wing wall 4 × 8 Nos. Nos. 32
52
No of culverts=2 Nos. 0@ 155.57 0
9 Providing and laying filter media with granular crushed aggregates
as per specification to a thickness of not less than 600 mm with
smaller size towards the soil and bigger size towards the wall and
providing over the entire surface behind abutment, wing wall,
return wall to the full height, compacted to firm condition complete
as per drawing and MORD technical specification Clause 1204.3.8
and as per direction of the Engineer in charge

In between Wing wall and Abutment


Behind Abutment Ribs 2 × 3.88 × 3.70 × 0.60 Cum 17.23
Behind Wing wall 4 × 3.00 × 3.70 × 0.60 Cum 26.64
43.87
No of culverts=2 Cum 0.00 @ 2,463.69 0
Total 0.00

Rs. 0.00

Junior Engineer Assistant Executive Engineer Executive Enginer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh
PRADHANMANTRI GRAM SADAK YOJANA (PMGSY)
COST ESTIMATE FOR CONSTRUCTION OF R.C.C. BOX-CELL CULVERT

Name of the road: Nandighore to Saliajhari PACKAGE NO


Type of cross Drainage Work: 2 Span Box-cell Culvert ( 4.00 m x 4.00 m) size
Total Nos. of Culvert : 0 Nos At RD-,,
Type of soil : All kinds of soil
Sl. Ht / Th Amount in
Description of item Nos. Length Width Unit Quantity Rate in Rs.
No in M Rs.
1 2 3 4 5 6 7 8 9 10
1 Earthwork in excavation for foundation of structures in all types of soil as per
drawing and technical specification Clause 305 and 1104 of MoRD includding
setting out, construction of shoring and bracing, removal of stumps and other
deleterious material and disposal upto all lead & lift, dressing of sides and
bottom and back filling with excavated suitable material upto 3mt. as per
direction of Engineer-in-Charge.

Cut off U/S(with side cut off) 1 × 22.70 × 1.00 × 2.00 Cum 45.40
Cut off D/S 1 × 23.70 × 1.00 × 2.50 Cum 59.25
Bridge proper and appron 1 × 9.90 × 9.70 × 0.80 Cum 76.82
Flexible appron U/S 1 × 10.90 × 2.50 × 1.00 Cum 27.25
Flexible appron D/S 1 × 10.90 × 3.00 × 1.00 Cum 32.70
Wing walls 4 × 2.20 × 2.52 × 2.00 Cum 44.35
Total Cum 0.00 @ 272.07 0
2 Filling Sand in foundation in trenches as per drawing and technical specification
clause 305.3.9.

Below raft 1 × 10.30 × 10.10 × 0.20 Cum 20.81


Cut off wall U/S 1 × 22.70 × 1.00 × 0.20 Cum 4.54
Cut off wall D/S 1 × 23.70 × 1.00 × 0.20 Cum 4.74
Wing walls 4 × 2.20 × 2.52 × 0.20 Cum 4.44
Total Cum 0.00 @ 1125.35 0
3 Providing concrete for plain / reinforced concrete in open foundation complete as
per drawing and MORD technical specification Clause 800,1100,1200 and as
per direction of Engineer-in-Charge.
PCC M 10

Below bed level


Below raft 1 × 10.30 × 10.10 × 0.15 Cum 15.60
Wing walls 4 × 2.20 × 2.52 × 0.40 Cum 8.87
Cut off D/S 1st step 1 × 22.70 × 1.00 × 0.50 Cum 11.35
Cut off U/S 1st step 1 × 23.70 × 1.00 × 0.50 Cum 11.85
Cut off D/S 2nd step 1 × 22.70 × 0.60 × 1.00 Cum 13.62
Cut off U/S 2nd step 1 × 23.70 × 0.60 × 1.50 Cum 21.33
0.00 @ 4,696.88 0
4 Plain/reinforced cement concrete in sub-structure complete as per drawings and
MORD technical specification Clauses 800,1200 and as per direction of the
Engineer in charge

P.C.C grade M 15(Nominal mix)

( Below bed)
Rigid Appron U/S 1 × 11.30 × 2.50 × 0.30 Cum 8.48
D/S 1 × 11.30 × 3.00 × 0.30 Cum 10.17
Wing 4 × 2.20 × 2.12 × 0.40 Cum 7.46
Wing walls 4 × 2.20 × 1.92 × 0.40 Cum 6.76
4 × 3.00 × 1.06 × 3.60 Cum 45.79
Total Cum 0.00 @ 4,960.82 0
Sl. Ht / Th Amount in
Description of item Nos. Length Width Unit Quantity Rate in Rs.
No in M Rs.
1 2 3 4 5 6 7 8 9 10
5 Providing and laying reinforced cement concrete of M-25 grade in foundation
complete as per drawings and technical specifications Clause 800 & 1200 of
MoRD and as per the direction of the Engineer-in-charge

RCC M 25
(a) Raft 1 × 6.00 × 9.70 × 0.50 Cum 0.00 @ 5740.92 0
Providing and laying reinforced cement concrete of M-25 grade in Super
structure complete as per drawings and technical specifications Clause 800 &
1200 of MoRD and as per the direction of the Engineer-in-charge

(b) Deck Slab 1 × 6.00 × 9.70 × 0.50 Cum 0.00 @ 6806.73 0


Providing and laying reinforced cement concrete of M-25 grade in Sub-structure
complete as per drawings and technical specifications Clause 800 & 1200 of
MoRD and as per the direction of the Engineer-in-charge

c) Rib 2 x 6.00 × 0.60 × 4.00 Cum 28.80


Pier Rib 1 x 6.00 × 0.50 × 4.00 Cum 12.00
Hunch 8 x 6.00 × 0.15/2 × 0.15 Cum 0.54
Cum 0.00 @ 6,276.55 0
d) Construction of R.C.C. railing of M 25 grade in cast-in-situ with 20 mm nominal
size aggregate, true to line and grade, tolerance of vertical railing post not to
exceed 1 in 500, centre-to-centre spacing between vertical posts not to exceed
2000 mm as per drawing and technical specifications Clauses 800, 900 and
1208.3

2 × 9.70 Rm 0.00 @ 2,581.32 0


6 Providing and laying cement concrete wearing course M 30 grade including
reinforcement complete as per drawing and technical specifications Clauses 800
and 1206.3

1 × 6.00 × 9.70 × 0.075 Cum 0.00 @ 10,559.25 0


7 Supplying, fitting and placing HYSD bar reinforcement (Fe 415) complete as per
drawings and MORD technical specification Clauses 1000,1200 as per direction
of the Engineer in charge

In super structure
a - Deck Slab 0.00 Cum @ 1.00 Qntl. 0@ 6,185.95 0
In foundation
c.- Raft 0.00 Cum @ 1.00 Qntl. 0@ 5852.53 0
In sub structure
d-Rib & Hunch 0.00 Cum @ 0.80 Qntl. 0.000
e-Wing wall 45.79 Cum @ 0.075 Qntl. 3.434
Total Qntl. 0@ 6,040.09 0
8 Providing weepholes in brick masonry/stone masonry, plain/reinforced concrete
abutment, wing wall, return wall with 100 mm dia AC pipe extending through the
full width of the structures with slope of 1(V):20(H) towards drawing face
complete as per drawing and MORD technical specification Clauses 614, 709,
1204 and as per direction of the Engineer in charge

Abutment 2 × 10 Nos. Nos. 20


Wing wall 4 × 8 Nos. Nos. 32
Nos. 0@ 155.57 0
9 Providing and laying filter media with granular crushed aggregates as per
specification to a thickness of not less than 600 mm with smaller size towards
the soil and bigger size towards the wall and providing over the entire surface
behind abutment, wing wall, return wall to the full height, compacted to firm
condition complete as per drawing and MORD technical specification Clause
1204.3.8 and as per direction of the Engineer in charge

In between Wing wall and Abutment


Behind Abutment Ribs 2 × 3.88 × 3.70 × 0.60 Cum 17.23
Behind Wing wall 4 × 3.00 × 3.70 × 0.60 Cum 26.64
Cum 0.00 @ 2,463.69 0
Total 0.00

Rs. 0.00

Junior Engineer Assistant Executive Engineer Executive Enginer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh
PRADHANMANTRI GRAM SADAK YOJANA (PMGSY)
COST ESTIMATE FOR CONSTRUCTION OF R.C.C. BOX-CELL CULVERT

Name of the road: Nandighore to Saliajhari PACKAGE NO


Type of cross Drainage Work: 4 Span Box-cell Culvert ( 4.00 m x 4.00 m) size
Total Nos. of Culvert : 0 Nos At RD-,,
Type of soil : All kinds of soil
Sl. Ht / Th Amount in
Description of item Nos. Length Width Unit Quantity Rate in Rs.
No in M Rs.
1 2 3 4 5 6 7 8 9 10
1 Earthwork in excavation for foundation of structures in all types of soil as per
drawing and technical specification Clause 305 and 1104 of MoRD includding
setting out, construction of shoring and bracing, removal of stumps and other
deleterious material and disposal upto all lead & lift, dressing of sides and
bottom and back filling with excavated suitable material upto 3mt. as per
direction of Engineer-in-Charge.
Cut off U/S(with side cut off) 1 × 31.50 × 1.00 × 2.00 Cum 63.00
Cut off D/S 1 × 32.50 × 1.00 × 2.50 Cum 81.25
Bridge proper and appron 1 × 9.90 × 17.50 × 0.80 Cum 138.60
Flexible appron U/S 1 × 19.70 × 2.50 × 1.00 Cum 49.25
Flexible appron D/S 1 × 19.70 × 3.00 × 1.00 Cum 59.10
Wing walls 4 × 2.20 × 2.52 × 2.00 Cum 44.35
Total Cum 0.00 @ 272.07 0
2 Filling Sand in foundation in trenches as per drawing and technical
specification clause 305.3.9.

Below raft 1 × 10.30 × 17.90 × 0.20 Cum 36.87


Cut off wall U/S 1 × 31.50 × 1.00 × 0.20 Cum 6.30
Cut off wall D/S 1 × 32.50 × 1.00 × 0.20 Cum 6.50
Wing walls 4 × 2.20 × 2.52 × 0.20 Cum 4.44
Total Cum 0.00 @ 1125.35 0
3 Providing concrete for plain / reinforced concrete in open foundation complete
as per drawing and MORD technical specification Clause 800,1100,1200
and as per direction of Engineer-in-Charge.

Below bed level


Below raft 1 × 10.30 × 17.90 × 0.15 Cum 27.66
Wing walls 4 × 2.20 × 2.52 × 0.40 Cum 8.87
Cut off D/S 1st step 1 × 31.50 × 1.00 × 0.50 Cum 15.75
Cut off U/S 1st step 1 × 32.50 × 1.00 × 0.50 Cum 16.25
Cut off D/S 2nd step 1 × 31.50 × 0.60 × 1.00 Cum 18.90
Cut off U/S 2nd step 1 × 32.50 × 0.60 × 1.50 Cum 29.25
0.00 @ 4,696.88 0
4 Plain/reinforced cement concrete in sub-structure complete as per drawings
and MORD technical specification Clauses 800,1200 and as per direction of
the Engineer in charge
P.C.C grade M 15(Nominal mix)
( Below bed)
Rigid Appron U/S 1 × 20.10 × 2.50 × 0.30 Cum 15.08
D/S 1 × 20.10 × 3.00 × 0.30 Cum 18.09
Wing 4 × 2.20 × 2.12 × 0.40 Cum 7.46

Wing walls 4 × 2.20 × 1.92 × 0.40 Cum 6.76


4 × 3.00 × 1.06 × 3.60 Cum 45.79
Total Cum 0.00 @ 4,960.82 0
5 Providing and laying reinforced cement concrete of M-25 grade in foundation
complete as per drawings and technical specifications Clause 800 & 1200 of
MoRD and as per the direction of the Engineer-in-charge

RCC M 25
(a) Raft 1 × 6.00 × 18.50 × 0.60 Cum 0.00 @ 5740.92 0
Sl. Ht / Th Amount in
Description of item Nos. Length Width Unit Quantity Rate in Rs.
No in M Rs.
1 2 3 4 5 6 7 8 9 10
Providing and laying reinforced cement concrete of M-25 grade in Super
structure complete as per drawings and technical specifications Clause 800 &
1200 of MoRD and as per the direction of the Engineer-in-charge

(b) Deck Slab 1 × 6.00 × 18.50 × 0.60 Cum 0.00 @ 6806.73 0


Providing and laying reinforced cement concrete of M-25 grade in Sub-
structure complete as per drawings and technical specifications Clause 800 &
1200 of MoRD and as per the direction of the Engineer-in-charge

c) Rib 2 x 6.00 × 0.50 × 4.00 Cum 24.00


Pier Rib 3 x 6.00 × 0.50 × 4.00 Cum 36.00
Hunch 16 x 6.00 × 0.15/2 × 0.15 Cum 1.08
Cum 0.00 @ 6,276.55 0
d) Construction of R.C.C. railing of M 25 grade in cast-in-situ with 20 mm
nominal size aggregate, true to line and grade, tolerance of vertical railing
post not to exceed 1 in 500, centre-to-centre spacing between vertical posts
not to exceed 2000 mm as per drawing and technical specifications Clauses
800, 900 and 1208.3

2 × 18.50 Rm 0.00 @ 2,581.32 0


6 Providing and laying cement concrete wearing course M 30 grade including
reinforcement complete as per drawing and technical specifications Clauses
800 and 1206.3

1 × 6.00 × 18.50 × 0.075 Cum 0.00 @ 10,559.25 0


7 Supplying, fitting and placing HYSD bar reinforcement (Fe 415) complete as
per drawings and MORD technical specification Clauses 1000,1200 as per
direction of the Engineer in charge

In super structure
a - Deck Slab 0.00 Cum @ 1.00 Qntl. 0@ 6,185.95 0
In foundation
c.- Raft 0.00 Cum @ 1.00 Qntl. 0@ 5852.53 0
In sub structure
d-Rib & Hunch 0.00 Cum @ 0.80 Qntl. 0.000
e-Wing wall 45.79 Cum @ 0.075 Qntl. 3.434
Total Qntl. 0@ 6,040.09 0
8 Providing weepholes in brick masonry/stone masonry, plain/reinforced
concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending
through the full width of the structures with slope of 1(V):20(H) towards
drawing face complete as per drawing and MORD technical specification
Clauses 614, 709, 1204 and as per direction of the Engineer in charge

Abutment 2 × 10 Nos. Nos. 20


Wing wall 4 × 8 Nos. Nos. 32
Nos. 0@ 155.57 0
9 Providing and laying filter media with granular crushed aggregates as per
specification to a thickness of not less than 600 mm with smaller size towards
the soil and bigger size towards the wall and providing over the entire surface
behind abutment, wing wall, return wall to the full height, compacted to firm
condition complete as per drawing and MORD technical specification Clause
1204.3.8 and as per direction of the Engineer in charge

In between Wing wall and Abutment


Behind Abutment Ribs 2 × 3.88 × 3.70 × 0.60 Cum 17.23
Behind Wing wall 4 × 3.00 × 3.70 × 0.60 Cum 26.64
Cum 0.00 @ 2,463.69 0
Total 0.00

Rs. 0.00

Junior Engineer Assistant Executive Engineer Executive Enginer


Sl. Ht / Th Amount in
Description of item Nos. Length Width Unit Quantity Rate in Rs.
No in M Rs.
1 2 3 4 5 6 7 8 9 10
R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh
PRADHANMANTRI GRAM SADAK YOJANA (PMGSY)
COST ESTIMATE FOR CONSTRUCTION OF R.C.C. BOX-CELL CULVERT

Name of the road: Nandighore to Saliajhari PACKAGE NO


Type of cross Drainage Work: 1 Span Box-cell Culvert ( 4.00 m x 4.00 m) size
Total Nos. of Culvert : 0 Nos At RD-,,
Type of soil : All kinds of soil
Sl. Ht / Th
Description of item Nos. Length Width Unit Quantity Rate in Rs. Amount in Rs.
No in M
1 2 3 4 5 6 7 8 9 10
1 Earthwork in excavation for foundation of structures in all types of soil as per
drawing and technical specification Clause 305 and 1104 of MoRD includding
setting out, construction of shoring and bracing, removal of stumps and other
deleterious material and disposal upto all lead & lift, dressing of sides and bottom
and back filling with excavated suitable material upto 3mt. as per direction of
Engineer-in-Charge.

Cut off U/S(with side cut off) 1 × 15.40 × 1.00 × 2.00 Cum 30.80
Cut off D/S 1 × 16.40 × 1.00 × 2.50 Cum 41.00
Bridge proper and appron 1 × 7.40 × 4.90 × 0.80 Cum 29.01
Flexible appron U/S 1 × 6.10 × 2.50 × 1.00 Cum 15.25
Flexible appron D/S 1 × 6.10 × 3.00 × 1.00 Cum 18.30
Wing walls 4 × 2.20 × 2.52 × 2.00 Cum 44.35
Total Cum 0.00 @ 272.07 0
2 Filling Sand in foundation in trenches as per drawing and technical specification
clause 305.3.9.

Below raft 1 × 7.80 × 5.30 × 0.20 Cum 8.27


Cut off wall U/S 1 × 15.40 × 1.00 × 0.20 Cum 3.08
Cut off wall D/S 1 × 16.40 × 1.00 × 0.20 Cum 3.28
Wing walls 4 × 2.20 × 2.52 × 0.20 Cum 4.44
Total Cum 0.00 @ 1125.35 0
3 Providing concrete for plain / reinforced concrete in open foundation complete as
per drawing and MORD technical specification Clause 800,1100,1200 and as per
direction of Engineer-in-Charge.

Below bed level


Below raft 1 × 7.80 × 5.30 × 0.15 Cum 6.20
Wing walls 4 × 2.20 × 2.52 × 0.40 Cum 8.87
Cut off D/S 1st step 1 × 15.40 × 1.00 × 0.50 Cum 7.70
Cut off U/S 1st step 1 × 16.40 × 1.00 × 0.50 Cum 8.20
Cut off D/S 2nd step 1 × 15.40 × 0.60 × 1.00 Cum 9.24
Cut off U/S 2nd step 1 × 16.40 × 0.60 × 1.50 Cum 14.76
0.00 @ 4,696.88 0
4 Plain/reinforced cement concrete in sub-structure complete as per drawings and
MORD technical specification Clauses 800,1200 and as per direction of the
Engineer in charge

P.C.C grade M 15(Nominal mix)

( Below bed)
Rigid Appron U/S 1 × 6.50 × 2.50 × 0.30 Cum 4.88
D/S 1 × 6.50 × 3.00 × 0.30 Cum 5.85
Wing 4 × 2.20 × 2.12 × 0.40 Cum 7.46

Wing walls 4 × 2.20 × 1.92 × 0.40 Cum 6.76


4 × 3.00 × 1.06 × 3.60 Cum 45.79
Total Cum 0.00 @ 4,960.82 0
Sl. Ht / Th
Description of item Nos. Length Width Unit Quantity Rate in Rs. Amount in Rs.
No in M
1 2 3 4 5 6 7 8 9 10
5 Providing and laying reinforced cement concrete of M-25 grade in foundation
complete as per drawings and technical specifications Clause 800 & 1200 of MoRD
and as per the direction of the Engineer-in-charge

RCC M 25

(a) Raft 1 × 3.50 × 4.90 × 0.35 Cum 0.00 @ 5740.92 0


Providing and laying reinforced cement concrete of M-25 grade in Super structure
complete as per drawings and technical specifications Clause 800 & 1200 of MoRD
and as per the direction of the Engineer-in-charge

(b) Deck Slab 1 × 3.50 × 4.90 × 0.35 Cum 0.00 @ 6806.73 0


Providing and laying reinforced cement concrete of M-25 grade in Sub-structure
complete as per drawings and technical specifications Clause 800 & 1200 of MoRD
and as per the direction of the Engineer-in-charge

c) Rib 2 x 3.50 × 0.45 × 4.00 Cum 12.60


Pier Rib 0 x 3.50 × 0.00 × 4.00 Cum 0.00
Hunch 4 x 3.50 × 0.15/2 × 0.15 Cum 0.16
Cum 0.00 @ 6,276.55 0
d) Construction of R.C.C. railing of M 25 grade in cast-in-situ with 20 mm nominal size
aggregate, true to line and grade, tolerance of vertical railing post not to exceed 1
in 500, centre-to-centre spacing between vertical posts not to exceed 2000 mm as
per drawing and technical specifications Clauses 800, 900 and 1208.3

2 × 4.90 Rm 0.00 @ 2,581.32 0


6 Providing and laying cement concrete wearing course M 30 grade including
reinforcement complete as per drawing and technical specifications Clauses 800
and 1206.3

1 × 3.50 × 4.90 × 0.075 Cum 0.00 @ 10,559.25 0


7 Supplying, fitting and placing HYSD bar reinforcement (Fe 415) complete as per
drawings and MORD technical specification Clauses 1000,1200 as per direction of
the Engineer in charge

In super structure
a - Deck Slab 0.00 Cum @ 1.00 Qntl. 0@ 6,185.95 0
In foundation
c.- Raft 0.00 Cum @ 1.00 Qntl. 0@ 5852.53 0
In sub structure
d-Rib & Hunch 0.00 Cum @ 0.80 Qntl. 0.000
e-Wing wall 45.79 Cum @ 0.075 Qntl. 3.434
Total Qntl. 0@ 6,040.09 0
8 Providing weepholes in brick masonry/stone masonry, plain/reinforced concrete
abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full
width of the structures with slope of 1(V):20(H) towards drawing face complete as
per drawing and MORD technical specification Clauses 614, 709, 1204 and as
per direction of the Engineer in charge

Abutment 2 × 10 Nos. Nos. 20


Wing wall 4 × 8 Nos. Nos. 32
Nos. 0@ 155.57 0
9 Providing and laying filter media with granular crushed aggregates as per
specification to a thickness of not less than 600 mm with smaller size towards the
soil and bigger size towards the wall and providing over the entire surface behind
abutment, wing wall, return wall to the full height, compacted to firm condition
complete as per drawing and MORD technical specification Clause 1204.3.8 and
as per direction of the Engineer in charge
In between Wing wall and Abutment
Behind Abutment Ribs 2 × 1.38 × 3.70 × 0.60 Cum 6.13
Behind Wing wall 4 × 3.00 × 3.70 × 0.60 Cum 26.64
Cum 0.00 @ 2,463.69 0
Total 0.00

0.00
Sl. Ht / Th
Description of item Nos. Length Width Unit Quantity Rate in Rs. Amount in Rs.
No in M
1 2 3 4 5 6 7 8 9 10
Junior Engineer Assistant Executive Engineer Executive Enginer
R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh
PRADHANMANTRI GRAM SADAK YOJANA (PMGSY) Format-F-7

COST ESTIMATE FOR R.R MASONARY

Name of the road: Nandighore to Saliajhari PACKAGE NO


Total length of Protection work : 0 Mtr 0 District : Nayagarh
Type of soil : All kinds of soil Block : Odagaon
Sl. Length in Debth in Amount in
Description of item Nos. Base in m Unit Quantity Rate in Rs.
No m M Rs.
1 2 3 4 5 6 7 8 9 10
1. Construction of Toe wall For Protection of Slopes as
per Drawing and Technical Specifications Clause
1302.5

1 × 0 × 1.200 × 0.900 Cum 0.00

1 × 0 × 0.900 × 0.900 Cum 0.00


Total 0.00 @ 1798.74 0.00

Junior Engineer Assistant Executive Engineer Executive Enginer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh
PRADHANMANTRI GRAM SADAK YOJANA (PMGSY)
COST ESTIMATE FOR PROTECTION WORK WITH RETANING WALL

Name of the road: Nandighore to Saliajhari PACKAGE NO


Total length of Protection work : 0 Mtr 0 District :
Type of soil : All kinds of soil Block :
Sl. Length in Debth in
Description of item Nos. Base in m Unit Quantity Rate in Rs.
No m M
1 2 3 4 5 6 7 8 9
1. Earthwork in excavation for foundation of structures in
all types of soil as per drawing and technical
specification Clause 305 and 1104 of MoRD includding
setting out, construction of shoring and bracing,
removal of stumps and other deleterious material and
disposal upto all lead & lift, dressing of sides and
bottom and back filling with excavated suitable
material upto 3mt. as per direction of Engineer-in-
Charge.

Quantity 1 × 0 × 1.100 × 0.800 Cum 0.00


Total 0.00 @ 272.07
2. Filling Sand in foundation in trenches as per drawing
and technical specification clause 305.3.9.

SAND Filling
Retaning Wall 1 × 0 × 1.100 × 0.150 Cum 0.00
Total 0.00 @ 1125.35
3. Providing M15 concrete for plain / reinforced concrete
in open foundation complete as per drawing and
MORD technical specification Clause 800,1100,1200
and as per direction of Engineer-in-Charge.

Retaning Wall BASE 1 × 0 × 1.100 × 0.150 Cum 0.00


Total 0.00 @ 4696.88

4. M15 Plain/reinforced cement concrete in sub-structure


complete as per drawings and MORD technical
specification Clauses 800,1200 and as per direction of
the Engineer in charge

Retaning Wall 1 × 0 × 0.400+1.0 × 1.35 Cum 0.00


2
Total 0.00 @ 4911.70
5. Providing weepholes in brick masonry/stone masonry,
plain/reinforced concrete abutment, wing wall, return
wall with 100 mm dia AC pipe extending through the
full width of the structures with slope of 1(V):20(H)
towards drawing face complete as per drawing and
MORD technical specification Clauses 614, 709, 1204
and as per direction of the Engineer in charge

Nos. 0 @ 155.57
Total Rs.
Junior Engineer Assistant Executive Engineer Executive Enginer
R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh
Format-F-7

PACKAGE NO
Nayagarh
Odagaon
Amount in
Rs.
10

0.00

0.00

0.00

0.00

0.00
0.00
Executive Enginer
W.Division, Nayagarh
PRADHANMANTRI GRAM SADAK YOJANA (PMGSY) Format-F-7

COST ESTIMATE FOR CONSTRUCTION OF CROSS DRAINAGE WORKS.

Name of the road: Nandighore to Saliajhari


Type of cross Drainage Work: Hume Pipe Culvert (1000mm dia Four row) PACKAGE NO

Total Nos. of Culvert : 0 Nos. At RD-,,,,, District : Nayagarh


Type of soil : All kinds of soil Block : Odagaon
Ht / Th Quantit
Sl. No Description of item Nos. Length Width Unit Rate in Rs. Amount in Rs.
in M y
1 2 3 4 5 6 7 8 9
1 Earthwork in excavation for foundation of structures in all
types of soil as per drawing and technical specification
Clause 305 and 1104 of MoRD includding setting out,
construction of shoring and bracing, removal of stumps
and other deleterious material and disposal upto all lead &
lift, dressing of sides and bottom and back filling with
excavated suitable material upto 3mt. as per direction of
Engineer-in-Charge.

Head wall 2 × 9.90 × 1.50 × 0.95 Cum 28.22


Pipe bed 1 × 4.25 × 7.05 × 0.65 Cum 19.48
U/S appron 1 × 8.10 × 1.50 × 0.30 Cum 3.65
D/S appron 1 × 8.10 × 2.00 × 0.30 Cum 4.86
D/S toe wall 1 × 9.90 × 0.60 × 0.40 Cum 2.38
Total 65.54
For 0 no culverts 65.54 x 0 Cum 0 @ 272.07 0.00
2 Filling Sand in foundation in trenches as per drawing and
technical specification clause 305.3.9.

Below Pipe bed 0 × 5.10 × 7.05 × 0.15 Cum 0.00


Around pipe 1 x 5.35 x 7.30 x 1.20 Cum 46.87
Below H.W. 2 × 9.90 × 1.50 × 0.15 Cum 4.46
Total 51.33
Deduct for pipe 4 × 5.65 × 0.785 × (1.20)2 Cum 25.55
Total 25.78
For 0 no culverts 25.78 x 0 Cum 0.00 @ 1125.35 0.00
4 Providing M15 concrete for plain / reinforced concrete in
open foundation complete as per drawing and MORD
technical specification Clause 800,1100,1200 and as per
direction of Engineer-in-Charge.

Head wall 2 × 9.90 × 1.70 × 0.15 Cum 5.05


Below Pipe Bed 1 x 4.90 x 7.05 x 0.15 Cum 5.18
For 0 no culverts 10.23 x 0 Cum 0 @ 4629.17 0.00
5 Providing and laying reinforced cement concrete NP3 pipe
for culverts jointing with cement mortar 1:2 but excluding
excavation, protection works, backfilling, concrete and
masonry works in head walls and parapets as per Clause
1100 of MoRD & as per direction of Engineer-in-Charge.

1000 mm dia Four Row 0 × 7.50 RM 0.00


0.00 @ 6453.77 0.00

7 Plain/reinforced cement concrete in sub-structure


complete as per drawings and MORD technical
specification Clauses 800,1200 and as per direction of the
Engineer in charge

Pipe joint 2 × 7.30 × 1.40 × 0.20 Cum 4.09


Head wall 2 × 9.75 × 0.950 × 2.45 Cum 45.39
Parapet 2 × 7.30 × 0.40 × 0.40 Cum 2.34
Total 51.28
Deduction in Pipe joint 4 × 0.20 × 0.785 × (1.20)2 um (-) 0.90
Deduct for Pipe in head wall 4 × 0.950 × 0.785 × (1.20)2 um (-) 4.30
Total 46.08
For 0 no culverts 46.08 x 0 Cum 0 @ 5074.82 0.00
Ht / Th Quantit
Sl. No Description of item Nos. Length Width Unit Rate in Rs. Amount in Rs.
in M y
1 2 3 4 5 6 7 8 9

8 Providing and laying filter material underneath pitching in


slopes complete as per drawing and technical
specifications Clause 1302 and as per the direction of the
Engineer-in-charge.

U/S appron 1 × 8.10 × 1.50 × 0.15 Cum 1.82


D/S appron 1 × 8.10 × 2.00 × 0.15 Cum 2.43
U/S D/S revetment 4 × 0.785×1.86 × 2.00 × 0.15 Cum 1.75
Total 6.00
For 0 no culverts 6.00 x 0 Cum 0.00 @ 772.49 0.00
9 Providing and laying pitching with stone boulders on
slopes laid over prepared filter media as per drawing and
MORD technical specifications Clause 1300 and as per
direction of the Engineer in charge

U/S appron 1 × 8.10 × 1.50 × 0.30 Cum 3.65


D/S appron 1 × 8.10 × 2.00 × 0.30 Cum 4.86
U/S D/S revetment 4 × 0.785×1.86 × 2.00 × 0.30 Cum 3.50
D/S toe wall 1 × 9.90 × 0.60 × 0.40 Cum 2.38
Total Cum 14.39
For 0 no culverts 14.39 x 0 Cum 0.00 @ 2112.13 0.00
0 Nos. of Hume Pipe Culverts Total Cost Rs. 0.00

Junior Engineer Assistant Executive Engineer Executive Enginer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh
PRADHANMANTRI GRAM SADAK YOJANA (PMGSY) Format-F-7

COST ESTIMATE FOR CONSTRUCTION OF CROSS DRAINAGE WORKS.

Name of the road: Nandighore to Saliajhari


Type of cross Drainage Work: Hume Pipe Culvert (600mm dia Triple row) PACKAGE NO

Total Nos. of Culvert : 0 Nos. At RD-,,,,,,, District : Nayagarh

Type of soil : All kinds of soil Block : Odagaon


Ht / Th Amount in
Sl. No Description of item Nos. Length Width Unit Quantity Rate in Rs.
in M Rs.
1 2 3 4 5 6 7 8 9
1. Earthwork in excavation for foundation of structures in all
types of soil as per drawing and technical specification
Clause 305 and 1104 of MoRD includding setting out,
construction of shoring and bracing, removal of stumps and
other deleterious material and disposal upto all lead & lift,
dressing of sides and bottom and back filling with excavated
suitable material upto 3mt. as per direction of Engineer-in-
Charge.

Head wall 2 × 5.75 × 1.40 × 0.80 Cum 12.88


Pipe bed 1 × 4.85 × 3.48 × 0.65 Cum 10.97
U/S appron 1 × 4.24 × 1.50 × 0.30 Cum 1.91
D/S appron 1 × 4.24 × 2.00 × 0.30 Cum 2.54
D/S toe wall 1 × 5.45 × 0.60 × 0.40 Cum 1.31
Total 29.61
For 0 no culverts 29.61 x 0 Cum 0.00 @ 272.07 0.00
2 Filling Sand in foundation in trenches as per drawing and
technical specification clause 305.3.9.

Below Pipe bed 1 × 5.34 × 3.48 × 0.15 Cum 2.79


Around pipe 1 x 5.55 x 3.48 x 0.76 Cum 14.68
Below H.W. 2 × 5.75 × 1.40 × 0.15 Cum 2.42
Total 19.89
Deduct for pipe 2 × 5.55 × 0.785 × (0.76)2 Cum 5.03
Total 14.86
For 0 no culverts 14.86 x 0 Cum 0.00 @ 1125.35 0.00
4 Providing concrete for plain / reinforced concrete in open
foundation complete as per drawing and MORD technical
specification Clause 800,1100,1200 and as per direction of
Engineer-in-Charge.

Head wall bed 2 × 5.75 × 1.40 × 0.15 Cum 2.42


Below pipe 1 x 5.50 x 3.48 x 0.15 Cum 2.87
For 0 no culverts 5.29 x 0 Cum 0.00 @ 4629.17 0.00
5 Providing and laying reinforced cement concrete NP3 pipe for
culverts jointing with cement mortar 1:2 but excluding
excavation, protection works, backfilling, concrete and
masonry works in head walls and parapets as per Clause
1100 of MoRD & as per direction of Engineer-in-Charge.

600 mm dia Three row 0 × 7.50 RM 0.00 @ 2384.25 0.00

7 Plain/reinforced cement concrete in sub-structure complete


as per drawings and MORD technical specification Clauses
800,1200 and as per direction of the Engineer in charge

Below pipe 1 × 5.50 × 3.48 × 0.15 Cum 2.87


Pipe joint 2 × 3.48 × 1.26 × 0.20 Cum 1.75
Head wall 2 × 5.60 × 0.825 × 2.01 Cum 18.57
Parapet 0 × 5.60 × 0.40 × 0.40 Cum 0.00
Ht / Th Amount in
Sl. No Description of item Nos. Length Width Unit Quantity Rate in Rs.
in M Rs.
1 2 3 4 5 6 7 8 9
Total 23.19
Deduction in Pipe joint 4 × 0.3 × p/4 × (0.76)2 Cum (-) 0.54
Deduct for Pipe 4 × 0.823 × p/4 × (0.76)2 Cum (-) 1.49
21.16
For 0 no culverts 22.95 x 0 Cum 0.00 @ 5074.82 0.00
8 Providing and laying filter material underneath pitching in
slopes complete as per drawing and technical specifications
Clause 1302 and as per the direction of the Engineer-in-
charge.

U/S appron 1 × 4.24 × 1.50 × 0.15 Cum 0.95


D/S appron 1 × 4.24 × 2.00 × 0.15 Cum 1.27
U/S D/S revetment 4 ×0.785×1.35× 1.45 × 0.15 Cum 0.92
Total Cum 3.14
For 0 no culverts 3.14 x 0 Cum 0.00 @ 772.49 0.00
9 Providing and laying pitching with stone boulders on slopes
laid over prepared filter media as per drawing and MORD
technical specifications Clause 1300 and as per direction of
the Engineer in charge

U/S appron 1 × 4.24 × 1.35 × 0.30 Cum 1.72


D/S appron 1 × 4.24 × 3.00 × 0.30 Cum 3.82
U/S D/S revetment 4 × p/4 × 1.35×1.4 × 0.30 Cum 1.85
D/S toe wall 1 × 4.45 × 0.60 × 0.30 Cum 0.80
Total Cum 8.19
For 0 no culverts 8.19 x 0 Cum 0.00 @ 2112.13 0.00

0 Nos. of Hume Pipe Culverts Total Cost 0.00

Junior Engineer Assistant Executive Engineer Executive Enginer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh
BILL OF QUANTITY

PACKAGE NO
Name of the Road :- Nandighore to Saliajhari

(Rate & Amount are in Rs.)


Sl. Estimated Rate
No. Items Quantity Unit
Figure Words
B.T Road
1 #NAME?

#NAME? #NAME? Nos. #NAME?


#NAME? #NAME? Nos. #NAME?
1 Scarifying Existing Bituminous Surface to a Depth of 150 mm by Mechanical Means and
disposal of scarified material with a lift upto 3 m and lead upto 1000 m as per Technical
Specification Clause 301.4.
Considering 60% area 5334.00 Sqm 6.70
2 Reworking or Rerolling the scarified bituminous surface suitably after supplementing the
base materials with quarry dust and compacting finished surface. #NAME? Cum #NAME?
2

Clearing grass and remocval of rubbish up to a distance of 30m outside the periphry of the
24000.00 Cum 1.36
area as per technical specification

2.
#NAME? #NAME? Sqm #NAME?

3
Dismantling of existing structures like culverts, bridges, retaining walls and other sturcture
comprising of masonry, cement concrete wood work, steel work, including T&P and
scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable 6.75 Sqm 390.48
materials and stacking the serviceable materials with all lifts and lead of 1000m as per
Technical Specification Clause 202
3. Construction of embankment with approved material obtained from borrow pits with all lead
and lift, transporting to site, spreading, grading to required slope and compacting to meet
requirement as per MoRD Rural roads Specification Clause 301as per the direction of
Engineer in charge by manual means.

(A). Within initial lead and lift 0.00 Cum 225.90


(B). With mechanical lead upto 1000m 12389.31 Cum 192.04
4. Excavation in Hard Rock (blasting prohibited by mechanical means) as per technical
0.00 Cum 217.36
specificaation clause 302
Excavation in ordinary rockusing hydraullic ecavator of 0.9cum bucket capacity including
Cutting and loading in tippers,transporting to embankment embnankment site with a lead 0.00 Cum 55.39
upto 1000m. , Trimming buttom nd side slopes in accordance with requirements of lines,
grades and cross-sections as[er technical specification clause302.3.5.
5. Cuting in Disintegrated rocks not requiring blasting to be removed by picked axes and crow
bars and depositing materials with 50m. Initial lead and 1.5m initial lift including rock 0.00 Cum 354.49
dressing as per direction and specification of thhe department including stacking the usefull
materials separately as order .
Construction of embankment with approved materials deposited at site from roadway
cutting and excavation from drain and foundation of other structures graded and compacted
to meet requirement as per MORD technical Specification Clause 301 and direction of the 1110.42 Cum 28.44
Engineer in Charge (excluding cost of excavation and transportation to site).

7. Construction of Gravel/soil Aggregate Sub Base/Base by providing well graded material of


nominal maximum size grading 20 mm as per Table 2.3 of IRCSP 77-2008 spreading in
uniform layers with tractor mount appropriate grading arrangements on prepared surface,
1428.56 Cum 680.34
mixing by place in method at OMC with tractor mount appropriate rotavator attachment &
compaction with 3 wheel 80-100 KNstatic roller capacity to achieve the desired density
complete as per specification contained in para 2.2,3.6&of IRCSP 77-2008.

Providing, laying, spreading and compacting stone aggregates of specific sizes to water
bound macadam specification including spreading in uniform thickness, hand packing,
rolling with three wheel 80-100 kN static roller in stages to proper grade and camber,
145.74 Cum 2917.56
applying and brooming, crushable screening(morum and sand admixture) to fill-up the
interstices of coarse aggregate, watering and compacting to the required density as per
Technical Specification Clause 405 of MoRD & as per direction of Engineer-in-Charge.
8.
Grading No. -III (53-22.4 mm size) with crusable screening 764.39 Cum 2844.90
9. 9715.50 30.23
Providing and applying primer coat with bitumen emulsion (SS-1) on prepared surface of
granular base including cleaning of road surface and spraying primer at the rate of 0.70-1.0
Cum
kg/sqm using mechanical means as per MORD Technical Specification Clause 502 for low
porosity surface and as per direction of Engineer-in-Charge.
a. Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor
at the rate of 0.25 to 0.30 kg per sqm on the prepared granular surfaces treated with primer &
cleaned with Hydraulic broom as per Technical Specification Clause 503 of MoRD & as per 9715.50 Cum 10.50
direction of Engineer-in-Charge.
b. Providing and laying surface dressing as wearing course consisting of a layer of bitumen
Binder(-65) laid on the prepared surface,followed by a cover of crushed stone chippings of
9.5 mm nominal Precoat Chips with1% bitumen by weight of chips crushed stone chipping
9.5mm size and rolling with Three wheel 80-100KN Static roller including cleaning the road
surface as per Technical specification clause 506.(Second coat surface dressing) 0.00 Cum 76.36

11. Fine dressing and turfing including transportation by mechanical means with all lead and lift
and placing of turf in position and ramming with thapies and including watering and cost of
0.00 Sqm 17.83
all labour, materials etc. complete as per Clause 309 of MORD Specification and as per
direction of the Engineer in Charge.

TOTAL B.T COST

C.C ROAD
14.
Providing concrete for plain / reinforced concrete in open foundation complete as per
drawing and MORD technical specification Clause 800,1100,1200 and as per direction of
Engineer-in-Charge.M15

233.55 Cum 4629.17

15. Providing, laying, spreading and compacting stone aggregates of specific sizes to water
bound macadam specification including spreading in uniform thickness, hand packing,
rolling with three wheel 80-100 kN static roller in stages to proper grade and camber,
applying and brooming, crushable screening(morum and sand admixture) to fill-up the
interstices of coarse aggregate, watering and compacting to the required density as per
Technical Specification Clause 405 of MoRD & as per direction of Engineer-in-Charge.

WBM Gr.-II 0.00 Cum 499.99


Construction of un-reinforced, plain cement Panelled(0.75mx.75m) concrete pavement of 207.60 Cum 5749.95
100mm thickn as per design, over a prepared sub-base, with 43 grade cement or any other
type as per Clause 1501.2.2, M30 (grade) coarse and fine aggregates conforming to IS:383,
maximum size of coarse aggregate not exceeding 25mm mixed in a concrete mixer of not
less than 0.2 cum capacity and appropriate weigh batcher using approved mix design, laid in
approved fixed side formwork (steel channel, laying and fixing of 125 micron thick
polythene film, wedges, steel plates including levelling the form work as per drawing),
spreading the concrete with shovels, rakes, compacted using needle, screed and plate
vibrators and finished in continuous operation including provision of contraction and
expansion, construction joints, applying debonding strips, primer, sealant near approaches to
bridges and culverts (expansion joints), admixtures as approved, curing of concrete slabs for
14 days, curing compound and water finishing to lines and grade as per drawing and
Technical Specification Clause 1501.Panels are to be made by cutting grooves of 3 to 5mm
thick and 25 to 30mm deep in CC slab.The grooves are to be filled with VG-30 Bitumen
with a spray of fine sand at top.
16.
TOTAL C.C COST

PROTECTION WALL & DRAIN


Earthwork in excavation for foundation of structures in all types of soil as per drawing and
technical specification Clause 305 and 1104 of MoRD includding setting out, construction of
shoring and bracing, removal of stumps and other deleterious material and disposal upto all
lead & lift, dressing of sides and bottom and back filling with excavated suitable material 386.40 Cum 272.07
upto 3mt. as per direction of Engineer-in-Charge.

Filling Sand in foundation in trenches as per drawing and technical specification clause
305.3.9. 72.45 Cum 1125.35

17. Providing M15 concrete for plain / reinforced concrete in open foundation complete as per
drawing and MORD technical specification Clause 800,1100,1200 and as per direction of
Engineer-in-Charge. 72.45 Cum 4629.17
M15 Plain/reinforced cement concrete in sub-structure complete as per drawings and
MORD technical specification Clauses 800,1200 and as per direction of the Engineer in
414.00 Cum 4889.19
charge

Providing and laying pitching with stone boulders on slopes laid over prepared filter media
as per drawing and MORD technical specifications Clause 1300 and as per direction of the
Engineer in charge 0.00 Cum 2112.13

Providing and laying filter material underneath pitching in slopes complete as per drawing
and technical specifications Clause 1302 and as per the direction of the Engineer-in-charge. 0.00 Cum 772.49

Grouting approns & revertments 2.3cm deep with (1:3:6) with 40mm down graded size
H.G.metal 0.00 Cum 312.33

16 Providing weepholes in brick masonry/stone masonry, plain/reinforced concrete abutment,


wing wall, return wall with 100 mm dia AC pipe extending through the full width of the
structures with slope of 1(V):20(H) towards drawing face complete as per drawing and
184.00 Rm 135.02
MORD technical specification Clauses 614, 709, 1204 and as per direction of the Engineer
in charge

18.
TOTAL COST OF PROTECTION WALL

19.
HUME PIPE CULVERT
Earthwork in excavation for foundation of structures in all types of soil as per drawing and
technical specification Clause 305 and 1104 of MoRD includding setting out, construction of
shoring and bracing, removal of stumps and other deleterious material and disposal upto all Cum
lead & lift, dressing of sides and bottom and back filling with excavated suitable material
upto 3mt. as per direction of Engineer-in-Charge.
65.56 272.07
Filling Sand in foundation in trenches as per drawing and technical specification clause
305.3.9. 37.04 Cum 1125.35
20. Providing M15 concrete for plain / reinforced concrete in open foundation complete as per
drawing and MORD technical specification Clause 800,1100,1200 and as per direction of 4.20 Cum 4629.17
Engineer-in-Charge.

21. Plain/reinforced cement concrete M-15 in sub-structure complete as per drawings and
MORD technical specification Clauses 800,1200 and as per direction of the Engineer in 35.94 Rm 5074.82
charge M-15

22. Providing and laying reinforced cement concrete NP3 Double Row pipe for culverts jointing
with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and
masonry works in head walls and parapets as per Clause 1100 of MoRD & as per direction
of Engineer-in-Charge.

a. 600 mm dia Single row 0.00 Rmt 2384.25


b. 600 mm dia Double row 0.00 Rmt 4768.08
c. 1000 mm dia Single row 15.00 Rmt 6453.77
d. 1000 mm dia Double row 0.00 Rmt 10329.62
Providing and laying pitching with stone boulders on slopes laid over prepared filter media
23. as per drawing and MORD technical specifications Clause 1300 and as per direction of the
Engineer in charge
0.00 Cum 2112.13

TOTAL COST OF HUME PIPE CULVERT

25.
SLAB & BOXCELL CULVERT
Earthwork in excavation for foundation of structures in all types of soil as per drawing and
technical specification Clause 305 and 1104 of MoRD includding setting out, construction of
shoring and bracing, removal of stumps and other deleterious material and disposal upto all
lead & lift, dressing of sides and bottom and back filling with excavated suitable material 0.00 Cum 272.07
upto 3mt. as per direction of Engineer-in-Charge.

Filling Sand in foundation in trenches as per drawing and technical specification clause
305.3.9. 0.00 Cum 1125.35
26. Providing concrete for plain / reinforced concrete in open foundation complete as per
drawing and MORD technical specification Clause 800,1100,1200 and as per direction of 0.00 Cum 4696.88
Engineer-in-Charge.
24
Plain/reinforced cement concrete in sub-structure complete as per drawings and MORD
technical specification Clauses 800,1200 and as per direction of the Engineer in charge

With Shuttering 0.00 Cum 4960.82


27. With Dewatering 0.00 Cum 4960.82
Providing and laying reinforced cement concrete of M-25 grade in Super structure complete
as per drawings and technical specifications Clause 800 & 1200 of MoRD and as per the
direction of the Engineer-in-charge.
Deck Slab 22.83 Sqm 6806.73
Abutment Cap,Dirt wall,Pier cap 0.00 Nos. 6276.55
Raft 10.29 Nos. 5740.92
28. Hunch,Rib 0.00 No 6276.55
29. Providing and laying cement concrete wearing course M 30 grade including reinforcement
complete as per drawing and technical specifications Clauses 800 and 1206.3 5.63 No 10559.25

30. Construction of R.C.C. railing of M 25 grade in cast-in-situ with 20 mm nominal size


aggregate, true to line and grade, tolerance of vertical railing post not to exceed 1 in 500,
centre-to-centre spacing between vertical posts not to exceed 2000 mm as per drawing and 9.80 No 2581.32
technical specifications Clauses 800, 900 and 1208.3

31. Supplying, fitting and placing HYSD bar reinforcement (Fe 415) complete as per drawings
and MORD technical specification Clauses 1000,1200 as per direction of the Engineer in
charge

32. Superstructure 0.00 No 6185.95


33. Substructure 0.00 6040.09
a). Providing weepholes in brick masonry/stone masonry, plain/reinforced concrete abutment, 0.00 155.57
wing wall, return wall with 100 mm dia AC pipe extending through the full width of the
structures with slope of 1(V):20(H) towards drawing face complete as per drawing and
MORD technical specification Clauses 614, 709, 1204 and as per direction of the Engineer No
in charge

b). Providing and laying boulder appron for bed protection & pitching on slopes with stone
boulders of minimum size and weight as per Table 1300.1, no fragment weighing less than 0.00 No 2112.13
25 kg laid dry complete as per drawing and technical specifications Clause 1301 & 1302
c). Providing and laying filter media with granular crushed aggregates as per specification to a
thickness of not less than 600 mm with smaller size towards the soil and bigger size towards
the wall and providing over the entire surface behind abutment, wing wall, return wall to the
full height, compacted to firm condition complete as per drawing and MORD technical 0.00 No 2463.69
specification Clause 1204.3.8 and as per direction of the Engineer in charge

TOTAL COST

Providing and fixing of typical OMBADC informatory sign board with Logo as per MORD
specifications and drawing. Three MS Plates of 1.6 mm thick, top and middle plate duly
welded with MS flat iron 25mm x 5m size on back on edges. The lower plate will be welded
with MS angle iron frame of 25mm x 25mm x 5mm. The angle iron frame of the lower most
plate and flat iron frame of middle plate will be welded to 2 nos. 75mm x 75 mm of 12 SWG
sheet tubes posts duly embedded in cement concrete M-15 grade blocks of 450mm x 450mm
x 600mm, 600mm below ground level. The top most diamond plate will be welded to
middle plate by 47mm x 47mm of 12 SWG steel plate tube. All M.S. will be stove enameled
2.00 8656.90
on both sides. Lettering and printing arrows, border etc. will be painted with ready mixed
synthetic enamel paint of superior quality in required shade and colour. All sections of
framed posts and steel tube will be painted with primer and two coats of epoxy paint as per
drawing Clause Annexure 300,800,1700 of MORD as per direction of the Engineer in
charge
Providing and fixing of typical OMBADC citizen information board as per MORD
specifications and drawing. Three MS Plates of 50x5mm mm thick, back plate duly welded
with 75mm dia steel tubes back on edges as per drawings. The upper & lower plate will be
welded with MS flat iron frame of 50mmx5mm. The steel tubes duly embedded in cement
concrete M-15 grade blocks of 600mm x 600mm x 750mm below ground level.All M.S. will
be stove enameled on both sides. Lettering and printing arrows, border etc. will be painted 3.00 12777.33
with ready mixed synthetic enamel paint of superior quality in required shade and colour.
All sections of framed posts and steel tube will be painted with primer and two coats of
epoxy paint as per drawing Clause 1701 and Annexture 1700.1.

Providing and fixing of semi reflective cautionary, mandatory and informatory sign board as
per IRC:67 made of 1.5 mm thick MS Sheet duly stove white colour in front and gray colour
on back with red reflective border of 65 mm width and required letters and figures with
reflective tape engineering grade as per Clause 1701.3.9 of MORD for Rural Roads of
required shade and colour supported and welded on 47mm x 47 mm x 12 SWG sheet tube 2.00 1968.58
firmly fixed to the ground by mean of properly designed foundations with M-15 grade
cement concrete 450x450x600 mm, 600 mm below ground level as per approved drawing
Clause 300,800,1700 as per direction of the Engineer in charge.(600 mm square)

Reinforced cement concrete M15 grade kilometre stone of standard design as per IRC:8
fixing in position including painting and printing, etc as per drawing and MORD technical
Specification Clause 1703 as per direction of the Engineer in charge

Fixing of 5th KM stone


1.00 3156.85

Fixing of Ordinary KM stone


7.00 1932.77

Fixing of 200mtr stone


24.00 526.87
Providing and erecting direction and place identifications of semi reflective sign boards of
size upto 0.90 Sqm. as per IRC:67 made of 2 mm thick M.S. Sheet duly stove enameled
paint in white colour in front and grey colour on back with red reflective border of 70 mm
width and required message, letters, figures with reflective engineering grade tape as per
MORD specifications of required shade and colour. Supported and welded on 47 mm x
47mm of 12 SWG Square tube of 3050 mm height duly strengthened by 25 mm x 5 mm M/s
flat iron on edges on back firmly fixed to the ground by means of properly designed 0.00 1968.58
foundations with M-15 grade cement concrete 450 mm x 450 mm x 600 mm, 600 mm below
ground level as per approved drawing and MORD technical Specification Clause
300,800,1700 as per direction of the Engineer in charge (Inter mediate Board)

#NAME? #NAME? #NAME?

34. Guide post 130.00 628.74


TOTAL COST
MAINTAINANACE
Routine Maintenance after completion of construction work.

1st Year 6.00 Km/Yr 43069.86


2nd Year 6.00 Km/Yr 51683.84
3rd Year 6.00 Km/Yr 60297.81
4th Year 6.00 Km/Yr 68911.78
5th Year 6.00 Km/Yr 77525.75
Total Maintainance Cost
Total BOQ Amount:-
Executive Enginer
R.W.Division, Nayagarh
Rate & Amount are in Rs.)
Amount

#NAME?
#NAME?

35737.80

#NAME?
32640.00

#NAME?

2635.74

0.00
2379243.09

0.00

0.00

0.00
31580.34

971906.51

425205.19

2174613.11

293699.57

102012.75
0.00

0.00

#NAME?

1081142.65

0.00
1193689.62

2839241.18

105127.85

81531.61

335383.37
2024124.66

0.00

0.00

0.00

24843.68

2571011.17

17836.91

41682.96
19442.51

182389.03

0.00
0.00
96806.55
0.00

0.00

358157.96

0.00

0.00
0.00

0.00
0.00

155397.65
0.00
59074.07
0.00

59448.58

25296.94

0.00
0.00
0.00

0.00

0.00

299217.24

17313.80
38331.99

3937.16

3156.85

13529.39

12644.88
0.00

#NAME?

81736.2
#NAME?

258419.16
310103.04
361786.86
413470.68
465154.50
1808934.24
#NAME?
Executive Enginer
R.W.Division, Nayagarh
PRADHANMANTRI GRAM SADAK YOJANA (PMGSY)
COST ESTIMATE FOR CONSTRUCTION OF R.C.C. BOX-CELL CULVERT

Name of the road: Nandighore to Saliajhari PACKAGE NO


Type of cross Drainage Work: 3 Span Box-cell Culvert ( 5.00 m x 4.00 m) size
Total Nos. of Culvert : 0 Nos At RD-,,
Type of soil : All kinds of soil
Sl. Ht / Th
Description of item Nos. Length Width Unit Quantity Rate in Rs. Amount in Rs.
No in M
1 2 3 4 5 6 7 8 9 10
1 Earthwork in excavation for foundation of structures in all types of soil as per
drawing and technical specification Clause 305 and 1104 of MoRD includding
setting out, construction of shoring and bracing, removal of stumps and other
deleterious material and disposal upto all lead & lift, dressing of sides and
bottom and back filling with excavated suitable material upto 3mt. as per
direction of Engineer-in-Charge.
Cut off U/S(with side cut off) 1 × 30.80 × 1.00 × 2.00 Cum 61.60
Cut off D/S 1 × 32.80 × 1.00 × 2.50 Cum 82.00
Bridge proper and appron 1 × 11.40 × 16.40 × 0.80 Cum 149.57
Flexible appron U/S 1 × 18.00 × 3.00 × 1.00 Cum 54.00
Flexible appron D/S 1 × 18.00 × 4.00 × 1.00 Cum 72.00
Wing walls 4 × 2.20 × 2.52 × 2.00 Cum 44.35
Total Cum 0.00 @ 272.07 0
2 Filling Sand in foundation in trenches as per drawing and technical specification
clause 305.3.9.

Below raft 1 × 11.80 × 16.80 × 0.20 Cum 39.65


Cut off wall U/S 1 × 30.80 × 1.00 × 0.20 Cum 6.16
Cut off wall D/S 1 × 32.80 × 1.00 × 0.20 Cum 6.56
Wing walls 4 × 2.20 × 2.52 × 0.20 Cum 4.44
Total Cum 0.00 @ 1125.35 0
3 Providing concrete for plain / reinforced concrete in open foundation complete
as per drawing and MORD technical specification Clause 800,1100,1200 and
as per direction of Engineer-in-Charge.

Below bed level


Below raft 1 × 11.80 × 16.80 × 0.15 Cum 29.74
Wing walls 4 × 2.20 × 2.52 × 0.40 Cum 8.87
Cut off D/S 1st step 1 × 30.80 × 1.00 × 0.50 Cum 15.40
Cut off U/S 1st step 1 × 32.80 × 1.00 × 0.50 Cum 16.40
Toe wall 4 × 15.00 × 0.60 × 1.20 Cum 43.20
Cut off D/S 2nd step 1 × 30.80 × 0.60 × 1.00 Cum 18.48
Cut off U/S 2nd step 1 × 32.80 × 0.60 × 1.50 Cum 29.52
0.00 @ 4,696.88 0
4 Plain/reinforced cement concrete in sub-structure complete as per drawings and
MORD technical specification Clauses 800,1200 and as per direction of the
Engineer in charge

DEWATERING ( Below bed)


Rigid Appron U/S 1 × 18.40 × 3.00 × 0.30 Cum 16.56
D/S 1 × 18.40 × 4.00 × 0.30 Cum 22.08
Wing 4 × 2.20 × 2.12 × 0.40 Cum 7.46
Cum 0.00 @ 4,960.82 0
SHUTTERING(above bed)
Wing walls 4 × 2.20 × 1.92 × 0.40 Cum 6.76
4 × 3.00 × 1.06 × 3.60 Cum 45.79
Total Cum 0.00 @ 4,960.82 0
Sl. Ht / Th
Description of item Nos. Length Width Unit Quantity Rate in Rs. Amount in Rs.
No in M
1 2 3 4 5 6 7 8 9 10
5 Providing and laying reinforced cement concrete in superstructure as per
drawing and technical specifications Clauses 800, 1205.4 and 1205.5

(a) Raft 1 × 6.00 × 16.80 × 0.40 Cum 0.00 @ 5740.92 0


(b) Deck Slab 1 × 6.00 × 16.80 × 0.40 Cum 0.00 @ 6806.73 0
c) Rib 2 x 6.00 × 0.50 × 4.00 Cum 24.00
Pier Rib 2 x 6.00 × 0.40 × 4.00 Cum 19.20
Hunch 12 x 6.00 × 0.15/2 × 0.15 Cum 0.81
Cum 0.00 @ 6,276.55 0
d) Construction of R.C.C. railing of M 25 grade in cast-in-situ with 20 mm nominal
size aggregate, true to line and grade, tolerance of vertical railing post not to
exceed 1 in 500, centre-to-centre spacing between vertical posts not to exceed
2000 mm as per drawing and technical specifications Clauses 800, 900 and
1208.3

2 × 16.80 Rm 0.00 @ 2,581.32 0


6 Providing and laying cement concrete wearing course M 30 grade including
reinforcement complete as per drawing and technical specifications Clauses 800
and 1206.3

1 × 6.00 × 16.80 × 0.075 Cum 0.00 @ 10,559.25 0


7 Supplying, fitting and placing HYSD bar reinforcement (Fe 415) complete as per
drawings and MORD technical specification Clauses 1000,1200 as per direction
of the Engineer in charge

a - Deck Slab 0.00 Cum @ 1.00 Qntl. 0@ 6,185.95 0


c.- Raft 0.00 Cum @ 1.00 Qntl. 0
d-Rib & Hunch 0.00 Cum @ 0.80 Qntl. 0.000
e-Wing wall 45.79 Cum @ 0.075 Qntl. 3.434
Total Qntl. 0@ 6,040.09 0
8 Providing weepholes in brick masonry/stone masonry, plain/reinforced concrete
abutment, wing wall, return wall with 100 mm dia AC pipe extending through the
full width of the structures with slope of 1(V):20(H) towards drawing face
complete as per drawing and MORD technical specification Clauses 614, 709,
1204 and as per direction of the Engineer in charge

Abutment 2 × 10 Nos. Nos. 20


Wing wall 4 × 8 Nos. Nos. 32
Nos. 0@ 155.57 0
9 Providing and laying boulder appron for bed protection & pitching on slopes with
stone boulders of minimum size and weight as per Table 1300.1, no fragment
weighing less than 25 kg laid dry complete as per drawing and technical
specifications Clause 1301 & 1302

U/S Appron 1 × 18.40 × 3.00 × 0.6 Cum 33.12


D/S Appron 2 × 18.40 × 4.00 × 0.6 Cum 88.32
Revertment 4 × 3.00 × 4.00 × 0.3 Cum 14.40
Cum 0.00 @ 2112.13 0
10 Providing and laying filter media with granular crushed aggregates as per
specification to a thickness of not less than 600 mm with smaller size towards
the soil and bigger size towards the wall and providing over the entire surface
behind abutment, wing wall, return wall to the full height, compacted to firm
condition complete as per drawing and MORD technical specification Clause
1204.3.8 and as per direction of the Engineer in charge

In between Wing wall and Abutment


Behind Abutment Ribs 2 × 3.88 × 3.70 × 0.60 Cum 17.23
Behind Wing wall 4 × 3.00 × 3.70 × 0.60 Cum 26.64
Cum 0.00 @ 2,463.69 0
Total 0.00

Rs. 0.00

Junior Engineer Assistant Executive Engineer Executive Enginer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh
PRADHANMANTRI GRAM SADAK YOJANA (PMGSY)
COST ESTIMATE FOR CONSTRUCTION OF R.C.C. BOX-CELL CULVERT

Name of the road: Nandighore to Saliajhari PACKAGE NO


Type of cross Drainage Work: 1 Span Box-cell Culvert ( 2.00 m x 2.00 m) size
Total Nos. of Culvert : 0 Nos At RD-,,
Type of soil : All kinds of soil
Sl. Ht / Th
Description of item Nos. Length Width Unit Quantity Rate in Rs. Amount in Rs.
No in M
1 2 3 4 5 6 7 8 9 10
1 Earthwork in excavation for foundation of structures in all types of
soil as per drawing and technical specification Clause 305 and
1104 of MoRD includding setting out, construction of shoring and
bracing, removal of stumps and other deleterious material and
disposal upto all lead & lift, dressing of sides and bottom and back
filling with excavated suitable material upto 3mt. as per direction
of
CutEngineer-in-Charge.
off U/S(with side cut off) 1 × 13.50 × 1.00 × 2.00 Cum 27.00
Cut off D/S 1 × 14.50 × 1.00 × 2.50 Cum 36.25
Bridge proper and appron 1 × 7.90 × 2.50 × 0.80 Cum 15.80
Flexible appron U/S 1 × 3.70 × 1.50 × 1.00 Cum 5.55
Flexible appron D/S 1 × 3.70 × 2.00 × 1.00 Cum 7.40
Wing walls 4 × 2.20 × 2.52 × 2.00 Cum 44.35
Total Cum 0.00 @ 272.07 0
2 Filling Sand in foundation in trenches as per drawing and technical
specification clause 305.3.9.

Below raft 1 × 8.30 × 2.90 × 0.20 Cum 4.81


Cut off wall U/S 1 × 13.50 × 1.00 × 0.20 Cum 2.70
Cut off wall D/S 1 × 14.50 × 1.00 × 0.20 Cum 2.90
Wing walls 4 × 2.20 × 2.52 × 0.20 Cum 4.44
Total Cum 0.00 @ 1125.35 0
3 Providing concrete for plain / reinforced concrete in open
foundation complete as per drawing and MORD technical
specification Clause 800,1100,1200 and as per direction of
Engineer-in-Charge.
Below bed level
Below raft 1 × 8.30 × 2.90 × 0.15 Cum 3.61
Wing walls 4 × 2.20 × 2.52 × 0.40 Cum 8.87
Cut off D/S 1st step 1 × 13.50 × 1.00 × 0.50 Cum 6.75
Cut off U/S 1st step 1 × 14.50 × 1.00 × 0.50 Cum 7.25
Toe wall 4 × 15.00 × 0.60 × 1.20 Cum 43.20
Cut off D/S 2nd step 1 × 13.50 × 0.60 × 1.00 Cum 8.10
Cut off U/S 2nd step 1 × 14.50 × 0.60 × 1.50 Cum 13.05
0.00 @ 4,696.88 0
4 Plain/reinforced cement concrete in sub-structure complete as per
drawings and MORD technical specification Clauses 800,1200
and as per direction of the Engineer in charge

DEWATERING ( Below bed)


Rigid Appron U/S 1 × 4.10 × 1.50 × 0.30 Cum 1.85
D/S 1 × 4.10 × 2.00 × 0.30 Cum 2.46
Wing 4 × 2.20 × 2.12 × 0.40 Cum 7.46
Cum 0.00 @ 4,960.82 0
SHUTTERING(above bed)
Wing walls 4 × 2.20 × 1.92 × 0.40 Cum 6.76
4 × 3.00 × 1.06 × 3.60 Cum 45.79
Total Cum 0.00 @ 4,960.82 0
5 Providing and laying reinforced cement concrete in superstructure
as per drawing and technical specifications Clauses 800, 1205.4
and 1205.5

(a) Raft 1 × 6.00 × 2.50 × 0.25 Cum 0.00 @ 5740.92 0


(b) Deck Slab 1 × 6.00 × 2.50 × 0.25 Cum 0.00 @ 6806.73 0
c) Rib 2 x 6.00 × 0.25 × 2.00 Cum 6.00
Pier Rib 0 x 6.00 × 0.00 × 2.00 Cum 0.00
Hunch 4 x 6.00 × 0.15/2 × 0.15 Cum 0.27
Cum 0.00 @ 6,276.55 0
d) Construction of R.C.C. railing of M 25 grade in cast-in-situ with 20
mm nominal size aggregate, true to line and grade, tolerance of
vertical railing post not to exceed 1 in 500, centre-to-centre
spacing between vertical posts not to exceed 2000 mm as per
drawing and technical specifications Clauses 800, 900 and 1208.3

2 × 2.50 Rm 0.00 @ 2,581.32 0


6 Providing and laying cement concrete wearing course M 30 grade
including reinforcement complete as per drawing and technical
specifications Clauses 800 and 1206.3

1 × 6.00 × 2.50 × 0.075 Cum 0.00 @ 10,559.25 0


7 Supplying, fitting and placing HYSD bar reinforcement (Fe 415)
complete as per drawings and MORD technical specification
Clauses 1000,1200 as per direction of the Engineer in charge

a - Deck Slab 0.00 Cum @ 1.00 Qntl. 0@ 6,185.95 0


c.- Raft 0.00 Cum @ 1.00 Qntl. 0
d-Rib & Hunch 0.00 Cum @ 0.80 Qntl. 0.000
e-Wing wall 45.79 Cum @ 0.075 Qntl. 3.434
Total Qntl. 0@ 6,040.09 0
8 Providing weepholes in brick masonry/stone masonry,
plain/reinforced concrete abutment, wing wall, return wall with 100
mm dia AC pipe extending through the full width of the structures
with slope of 1(V):20(H) towards drawing face complete as per
drawing and MORD technical specification Clauses 614, 709,
1204 and as per direction of the Engineer in charge

Abutment 2 × 10 Nos. Nos. 20


Wing wall 4 × 8 Nos. Nos. 32
Nos. 0@ 155.57 0
9 Providing and laying boulder appron for bed protection & pitching
on slopes with stone boulders of minimum size and weight as per
Table 1300.1, no fragment weighing less than 25 kg laid dry
complete as per drawing and technical specifications Clause 1301
& 1302

U/S Appron 1 × 4.10 × 1.50 × 0.6 Cum 3.69


D/S Appron 2 × 4.10 × 2.00 × 0.6 Cum 9.84
Revertment 4 × 3.00 × 4.00 × 0.3 Cum 14.40
Cum 0.00 @ 2112.13 0
10 Providing and laying filter media with granular crushed aggregates
as per specification to a thickness of not less than 600 mm with
smaller size towards the soil and bigger size towards the wall and
providing over the entire surface behind abutment, wing wall,
return wall to the full height, compacted to firm condition complete
as per drawing and MORD technical specification Clause
1204.3.8 and as per direction of the Engineer in charge

In between Wing wall and Abutment


Behind Abutment Ribs 2 × 3.88 × 1.70 × 0.60 Cum 7.92
Behind Wing wall 4 × 3.00 × 1.70 × 0.60 Cum 12.24
Cum 0.00 @ 2,463.69 0
Total 0.00
Rs. 0.00

Junior Engineer Assistant Executive Engineer Executive Enginer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh
PRADHANMANTRI GRAM SADAK YOJANA Format-F-7
COST ESTIMATE FOR REFERENCE PILLAR
Name of the road:- Nandighore to Saliajhari 0.00
Total length of Protection work :- 120 Nos. District : Nayagarh
Block : Odagaon
Type of soil :- All kinds of soil
Sl. Debth Amount in
Description of item Nos. Length in m Base in m Unit Quantity Rate in Rs.
No in M Rs.
1 2 3 4 5 6 7 8 9 10
1. Earthwork in excavation for foundation of structures in all
types of soil as per drawing and technical specification
Clause 305 and 1104 of MoRD includding setting out,
construction of shoring and bracing, removal of stumps
and other deleterious material

Quantity 1 × 0.400 × 0.400 × 0.600 Cum 0.10 @ 272.07 27.21

2. Providing concrete for plain / reinforced concrete in open


foundation complete as per drawing and MORD
technical specification Clause 800,1100,1200 and as per
direction of Engineer-in-Charge.

PCC (1:3:6 Nominal Mix) Foundation Bed


1 x 0.400 x 0.400 ###0.150 Cum 0.02 @ 4900.00 117.60

3. Plain/reinforced cement concrete in sub-structure


complete as per drawings and MORD technical
specification Clauses 800,1200 and as per direction of
the Engineer in charge

(1:2:4) Nominal Mix M-20 1 x 0.150 x 0.150 ###1.200 Cum 0.03 @ 5520.55 149.05

4. Supplying, fitting and placing HYSD bar reinforcement


(Fe 415) complete as per drawings and MORD technical
specification Clauses 1000,1200 as per direction of the
Engineer in charge

0.05 0.15 % x Ton 0.000075 @ 60400.87 4.53


Total Rs. 298.39
The Cost for Reference Pillar 298.39 x 120 Rs. 35806.80

Junior Engineer Assistant Executive Engineer Executive Enginer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh

204/218 - REFERENCE PILLAR of 480488552.xlsx


PRADHANMANTRI GRAM SADAK YOJANA Format-F-7
COST ESTIMATE FOR TBM PILLAR
Name of the road:- Nandighore to Saliajhari 0.00
Total length of Protection work :- 24 Nos. District : Nayagarh
Block : Odagaon
Type of soil :- All kinds of soil
Sl. Debth Quantit Amount in
Description of item Nos. Length in m Base in m Unit Rate in Rs.
No in M y Rs.
1 2 3 4 5 6 7 8 9 10
1. Earthwork in excavation for foundation of structures in all
types of soil as per drawing and technical specification
Clause 305 and 1104 of MoRD includding setting out,
construction of shoring and bracing, removal of stumps
and other deleterious material

Quantity 1 × 0.600 × 0.600 × 0.300 Cum 0.11 @ 272.07 29.93

2. Providing concrete for plain / reinforced concrete in open


foundation complete as per drawing and MORD
technical specification Clause 800,1100,1200 and as per
direction of Engineer-in-Charge.

PCC (1:3:6 Nominal Mix) Foundation Bed


1 x 0.600 x 0.600 ###0.150 Cum 0.05 @ 4900.00 264.60

3. Plain/reinforced cement concrete in sub-structure


complete as per drawings and MORD technical
specification Clauses 800,1200 and as per direction of
the Engineer in charge

(1:2.5:5) Nominal Mix M-15 Wall 1 x 0.450 x 0.450 ###0.300 Cum 0.06 @ 4960.82 301.37
Total Rs. 595.90
The Cost for TBM Pillar 595.90 x 24 Rs. 14301.60

Junior Engineer Assistant Executive Engineer Executive Enginer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh

205/218 - TBM PILLAR of 480488552.xlsx


PRADHANMANTRI GRAM SADAK YOJANA (PMGSY) Format-F-7
COST ESTIMATE FOR CONSTRUCTION OF R.C.C. SLAB CULVERT
Name of the road: Nandighore to Saliajhari
Type of cross Drainage Work: Extn. Of exsting R.C.C. Slab Culvert on canal PACKAGE NO
Total Nos. of Culvert : 0 Nos. 0 District : Nayagarh
Type of soil : All kinds of soil Block : Odagaon

Sl. Ht / Th Quant
Description of item Nos. Length Width Unit Rate in Rs. Amount in Rs.
No in M ity

1 2 3 4 5 6 7 8 9
1 Earthwork in excavation for foundation of
structures upto 3 mtr debth as per
drawing and technical specification
clause 1104 including setting out
construction of shoring and bracing,
removal of stumps and other deleterious
matter, dressing sides and bottom and
back filling with approved materials.

Abutment 2 × 3.20 × 1.50 × 1.00 9.60 Cum


Bed 1 × 3.20 × 1.30 × 0.35 1.46 Cum
D/S cut off 1 × 2.50 × 0.60 × 0.60 0.90 Cum
D/S appron 1 × 2.50 × 1.50 × 0.30 1.13 Cum
Total 13.09 Cum @ 49.50 648.00
11.2 Backfilling in foundation trenches as per
drawing and technical clause 1108 (Sand
filling).
Abutment 2 × 3.20 × 1.50 × 0.20 1.92 Cum
Bed 1 × 3.20 × 1.30 × 0.20 0.83 Cum
D/S cut off 1 × 2.50 × 0.60 × 0.10 0.15 Cum
D/S appron 1 × 2.50 × 1.50 × 0.10 0.38 Cum
Total 3.28 Cum @ 222.12 729.00
11.4 Plain cement concrete M-10 (1:3:6)
Nominal mix in levelling coarse below
open foundation of head walls as per
drawing and technical clause 1109.

Abutment 2 × 3.20 × 1.50 × 0.20 1.92 Cum


Bed 1 × 3.20 × 1.50 × 0.15 0.72 Cum
D/S cut off 1 × 2.50 × 0.60 × 0.50 0.75 Cum
D/S appron 1 × 2.50 × 1.50 × 0.15 0.56 Cum
Total 2.03 Cum @ 2007.18 4075.00
12.5(a)P.C.C. M-20Grade in foundation using
12mm to 20mm size chips with side
shuttering, dewatering etc. complete as
per drawing and technical specification.
Abutment 2 × 3.10 × 0.88 × 1.45 7.87 Cum
Bed 1 × 3.10 × 1.50 × 0.075 0.35 Cum
D/S appron 1 × 2.50 × 1.50 × 0.075 0.28 Cum
Total 14.20 Cum @ 2271.06 32249.00
13.1.IIR.C.C. M-20 in super structure using
12mm size chips including centrering
centering shuttering cost, conveyance,
royalty, taxes etc. of all materials
complete.

(a) Deck slab 1 × 3.10 × 2.40 × 0.220 1.64 Cum @ 3760.65 6167.00
(b) Abutment cap 2 × 3.10 × 0.50 × 0.150 0.47 Cum @ 3010.28 1415.00
(c) Wearing Coat(M-25)
1 × 3.10 × 2.40 × 0.075 0.56 Cum @ 3034.82 1699.00
(D) Parapet 2 × 3.10 × 0.40 × 0.400 0.99 Cum @ 3010.28 2980.00

13.2 Supplying, fitting and palcing HYSD bar


reinforcement (Fe-415) complete as per
drawing and technical specification
Cluses 1002, 1005, 1010 & 1202.

Deck slab 1.64 × 1.25 qntl 2.05 Qntl.


Abutment cap 0.47 × 1.00 qntl 0.47 Qntl.
Wearing coat 0.56 × 0.60 qntl 0.34 Qntl.
Parapets 0.99 × 0.80 qntl 0.79 Qntl.
3.650 Qntl. @ 3334.30 12170.00

12.9 Providing weep holes in plain or


reinforced concrete abutment, wingwall,
retunn wall with 100mm dia AC pipe
extending through the full width of the
structures with slope of 1(V):20H towards
drawing face complete as per drawing
and technical specification as per sectin
600, 700 & 1200 of MORD.

Abutment 6 × 1.00 6.00 Rm


6.00 Rm @ 121.84 731.00
12 Providing and laying filter media with
granular crushed aggregates as per
specification to a thickness of not less
than 600 mm with smaller size towards
the soil and bigger size towards the wall
and providing over the entire surface
behind abutment, wing wall, return wall to
the full height, compacted to firm
condition complete as per drawing and
technical specification Clause 1204.3.8.

Behind Abutments 2 × 3.10 × 0.60 × 1.50 5.58 Cum


5.58 Cum @ 727.79 4061.00
14.1 Providing and laying boulder revertment
for slope protection with stone boulders of
minimum size & weight as per table
1300.1, no fragment weighing less than
25 kg. laid dry complete as per drawing
and technical specification clause 1301.

CANAL SLOPE 4 × 3.00 × 1.40 × 0.300 5.04 Cum @ 516.99 2606.00


14.6 Providng and laying filter material
underneath pitching and slopes complete
as per drawing and technical specification
Clause 1302.

CANAL SLOPE
4 × 3.00 × 1.40 × 0.150 2.52 Cum @ 322.95 814.00
Total cost Rs 70344.00

For 0.00 No culvert Rs 0.00


Junior Engineer Assistant Enggineer Executive Engineer
R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh
PRADHANMANTRI GRAM SADAK YOJANA (PMGSY) Format-F-7
COST ESTIMATE FOR CONSTRUCTION OF R.C.C. SLAB CULVERT
Name of the road: Nandighore to Saliajhari
Type of cross Drainage Work: 2 Span R.C.C. Slab Culvert (5.00m × 2.00m) PACKAGE NO
Total Nos. of Culvert : 1 Nos. District : Nayagarh
Type of soil : All kinds of soil Block : Odagaon
Sl. Ht / Th
Description of item Nos. Length Width Unit Quantity Rate in Rs. Amount in Rs.
No in M
1 2 3 4 5 6 7 8 9
1 Earthwork in excavation for foundation of structures upto 3 mtr debth as per
drawing and technical specification clause 1104 including setting out
construction of shoring and bracing, removal of stumps and other deleterious
matter, dressing sides and bottom and back filling with approved materials

Foundation
Abutments 2× 8.20 × 2.20 × 1.70 Cum 61.34
Pier 1× 8.20 × 1.60 × 1.70 Cum 22.3
Cut off U/S 1× 14.10 × 0.60 × 1.40 Cum 11.84
Cut off D/S 1× 16.80 × 0.60 × 1.70 Cum 17.14
Bed
D/S Bed 1× 10.60 × 2.50 × 0.75 Cum 19.88
U/S Bed 1× 10.60 × 1.50 × 0.75 Cum 11.93
CD Bed 2× 7.50 × 4.10 × 0.75 Cum 46.13
Foundation
Wing walls 4× 3.40 × 1.65 × 1.40 Cum 31.42
Total Cum 223.98 @ 296.24 66351.84
2 Backfilling in foundation trenches as per drawing and technical clause 1108
(Sand filling)

Foundation
Abutments 2× 8.20 × 2.20 × 0.20 Cum 7.22
Pier 1× 8.20 × 1.60 × 0.20 Cum 2.62
Cut off U/S 1× 14.10 × 0.60 × 0.20 Cum 1.69
Cut off D/S 1× 16.80 × 0.60 × 0.20 Cum 2.02
Wing walls 4× 3.40 × 1.65 × 0.20 Cum 4.49
Bed
D/S Bed 1× 10.80 × 3.60 × 0.20 Cum 7.78
U/S Bed 1× 10.80 × 2.60 × 0.20 Cum 5.62
CD Bed 2× 7.50 × 4.40 × 0.20 Cum 13.2
Total Cum 46.64 @ 1114.21 51966.75
3 Plain cement concrete M-10 (1:3:6) Nominal mix in levelling coarse below
open foundation of head walls as per drawing and technical clause 1109

Cut off D/S


1st Step 1× 16.80 × 0.60 × 0.30 Cum 3.02
2nd Step 1× 16.10 × 0.40 × 1.20 Cum 7.73
Cut off U/S
1st Step 1× 14.10 × 0.60 × 0.30 Cum 2.54
2nd Step 1× 14.10 × 0.40 × 0.90 Cum 5.08
CD Bed 2× 7.50 × 4.40 × 0.15 Cum 9.90
U/S Bed 1× 10.80 × 2.60 × 0.15 Cum 4.21
D/S Bed 1× 10.80 × 3.60 × 0.15 Cum 5.83
Total 2.60 Cum 40.31 @ 4,909.09 197885.42
B. DEWATERING AND SHUTERING
Abutments 1st Step 2× 8.20 × 2.20 × 0.30 Cum 10.82
2nd Step 2× 8.40 × 1.90 × 0.90 Cum 28.73
Pier 1st Step 2× 9.20 × 1.60 × 0.30 Cum 8.83
2nd Step 2× 8.40 × 1.30 × 0.90 Cum 19.66
Wing 1st Step 4× 3.40 × 1.65 × 0.30 Cum 6.73
2nd Step 4× 3.40 × 1.35 × 0.90 Cum 16.52
CD Bed 2× 7.50 × 4.60 × 0.10 Cum 6.9
U/S Bed 1× 10.80 × 2.60 × 0.10 Cum 2.81
D/S Bed 1× 10.80 × 3.60 × 0.10 Cum 3.89
Cum 106.89 @ 4,911.70 525011.61
R.C.C. M-20 in super structure using 12mm size chips including centrering
centering shuttering cost, conveyance, royalty, taxes etc. of all materials
complete

B. SHUTTERING
Abutments 8.0+7.5 0+0.9 2.00 Cum 13.95
2 X x x
2 2
1st Step 2× 7.5 × 0.3 × 2.00 Cum 9
2nd Step 2× 7.5 × 0.3 × 2.00 Cum 9
Pier 1× 7.5 × 0.90+0.50 × 2.00 Cum 10.5
2
Wing 4× 4.5 × 0.3 × 2.00 Cum 5.4
2
4 × 4.5+3.6 × 0+0.65 × 2.00 Cum 10.53
2 2
Total Cum 58.38 @ 5,578.77 325688.30
5 R.C.C. M-25 in super structure using 12mm size chips including centrering
centering shuttering cost, conveyance, royalty, taxes etc. of all materials
complete

(a) Deck Slab 2× 5.60 × 7.50 × 0.43 Cum 36.12 @ 6739.34 243424.96

(b) Abutment Cap 2× 7.60 × 0.40 × 0.30 Cum 1.82


Pier Cap 1× 7.60 × 0.80 × 0.30 Cum 1.82
Cum 3.64 @ 6739.34 24531.20
6 Providing and laying cement concrete wearing course M 30 grade including
reinforcement complete as per drawing and technical specifications Clauses
800 and 1206.3

(a) Wearing Coat 2× 5.60 × 7.50 × 0.075 Cum 6.30


Cum 6.30 @ 10,454.70 65864.61
6 Supplying, fitting and palcing HYSD bar reinforcement (Fe-415) complete as
per drawing and technical specification Cluses 1002, 1005, 1010 & 1202

a - Deck Slab - R.C.C 36.12 Cum @ 1.25 Qntl. 45.15


d.- Abutments Piers 3.64 Cum @ 0.6 Qntl. 2.18
Total Qntl. 47.33 @ 6,124.70 289882.10
7 Providing weep holes in plain or reinforced concrete abutment, wingwall,
retunn wall with 100mm dia AC pipe extending through the full width of the
structures with slope of 1(V):20H towards drawing face complete as per
drawing and technical specification as per sectin 600, 700 & 1200 of MORD

Abutment 2× 11 Nos. Nos. 22


Wing wall 4× 8 Nos. Nos. 32
Nos. 54 @ 154.03 8317.62
8 Providing and laying boulder appron for bed protection with stone boulders of
minimum size & weight as per table 1300.1, no fragment weighing less than
25 kg. laid dry complete as per drawing and technical specification clause
1301

U/S & D/S River Bed 1× 10.8 × 2.6 × 0.6 Cum 16.85
1× 10.8 × 3.6 × 0.6 Cum 23.33
Cum 40.18 @ 2,091.22 84025.22
9 Providing and Fixing 25mm dia anchor bars in abutments & piers as per
approved design for holding down deck slab with abutment & piers etc.
complete.

Free end
Abutment & Pier = 8 Nos. @ Rs. 250.00 2000.00
Fixed end
Abutment & Pier = 8 Nos. @ Rs. 61.60 492.80
10 Providing and laying filter media with granular crushed aggregates as per
specification to a thickness of not less than 600 mm with smaller size towards
the soil and bigger size towards the wall and providing over the entire surface
behind abutment, wing wall, return wall to the full height, compacted to firm
condition complete as per drawing and technical specification Clause
1204.3.8

In between Wing wall and Abutment


Behind Abutments 2× 7.50 × 3.00 × 0.60 Cum 27.00
Behind Wing wall 4× 11.30 × 2.05 × 0.60 Cum 55.60
Cum 82.60 @ 2,439.30 201486.18
11 Providing and fixing 20 mm thick compressible fibre board in expansion joint
complete as per drawing and technical specifications

In between Wing wall and Abutment 2× 7.50 RM 15


In between abutment and pier 1× 7.50 RM 7.5
RM 22.5 @ 254.87 5734.58

Total 2092663.19
For
1 Nos. of slab culvert 1x 2092663.19 Rs. 2092663.19

Junior Engineer Assistant Enggineer Executive Engineer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh
PRADHANMANTRI GRAM SADAK YOJANA (PMGSY)
COST ESTIMATE FOR CONSTRUCTION OF R.C.C. SLAB CULVERT
Name of the road: Nandighore to Saliajhari
Type of cross Drainage Work: 1 Span R.C.C. Slab Culvert (3.00m × 1.50m) PACKAGE NO
Total Nos. of Culvert : 0 No. District :
Type of soil : All kinds of soil Block :
Sl. No Ht / Th
Description of item Length Width Unit Quantity Rate in Rs.
No s. in M
1 2 3 4 5 6 7 8 9
1 Earthwork in excavation for foundation of structures upto 3 mtr debth as per
drawing and technical specification clause 1104 including setting out
construction of shoring and bracing, removal of stumps and other
deleterious matter, dressing sides and bottom and back filling with approved
materials

Abutment 1× 9.2 × 2.5 × 1.2 Cum 55.2


U/S cut off 1× 2.5 × 1.05 × 1.5 Cum 3.94
D/S cut off 1× 2.5 × 1.05 × 1.5 Cum 3.94
Bed 1× 6.3 × 1.9 × 0.3 Cum 3.59
Wing wall 4× 0.75 × 2× 1.2 Cum 7.2
U/S appron 1× 5.5 × 2× 0.6 Cum 6.6
D/S appron 1× 5.5 × 3× 0.6 Cum 9.9
Total Cum 90.37 @ 49.5
11.2 Backfilling in foundation trenches as per drawing and technical clause 1108
(Sand filling)
Abutment 2× 9.2 × 2.5 × 0.2 Cum 9.2
U/S cut off 1× 2.5 × 1.05 × 0.1 Cum 0.26
D/S cut off 1× 2.5 × 1.05 × 0.1 Cum 0.26
Bed 1× 6.6 × 2.4 × 0.1 Cum 1.58
Wing wall 4× 0.75 × 2× 0.2 Cum 1.2
Total Cum 12.5 @ 157.32
11.4 Plain cement concrete M-10 (1:3:6) Nominal mix in levelling coarse below
open foundation of head walls as per drawing and technical clause 1109

Abutment 2× 9.2 × 2.5 × 0.3 Cum 13.8


1st Footing U/S & D/S cut off 2× 2.5 × 1.05 × 0.2 Cum 1.05
2nd Footing U/S & D/S cut off 2× 2.5 × 0.525(av) × 1.2 Cum 3.15
Bed 1× 6.6 × 2.4 × 0.15 Cum 2.38
Wing wall 4× 0.75 × 2× 0.3 Cum 1.8
Total Cum 22.18 @ 1888.83
12.5 P.C.C. M-20Grade in foundation using 12mm to 20mm size chips with side
(a) shuttering, dewatering etc. complete as per drawing and technical
specification.

(a) Dewatering & Shuttering


Below bed
Abutment 1st step 2× 8.9 × 2.2 × 0.3 Cum 11.75
Wing 4× 0.75 × 1.7 × 0.3 Cum 1.53
Bed wearing coat 1× 7.5 × 2.4 × 0.05 Cum 0.9

Total Cum 14.18 @ 2354.67


(b) Shuttering (Above bed)
Abutment 2nd step 2× 8.1+7.5 × 2.2+1.64 × 0.4 Cum 11.98
2× 7.5 × 1.64+0.6 × 1.8 Cum 30.24
(c) Wing 2nd Step 4× 1.65+1.82 × 1.7+1.12× 0.4 Cum 3.91
4× (1.82+2.56)× 1.14+0.4 × 1.8 Cum 12.14
(d) Parapet 2x 3.6 x 0.4 x 0.4 1.15
Cum 59.43 @ 2570.2

13.1 R.C.C. M-20 in super structure using 12mm size chips including centrering
.II centering shuttering cost, conveyance, royalty, taxes etc. of all materials
complete

(a) Deck slab 1× 3.6 × 7.5 × 0.305 Cum 8.24


(b) Abutment cap 2× 7.6 × 0.35 × 0.225 Cum 1.2
Cum 9.44 @ 3627.58
( c) Dirt wall 2x 7.6 x 0.3 x 0.305 1.39
(d) Parapets 2× 4.2 × 0.4 × 0.4 Cum 1.34
Cum 2.73 @ 2976.23
R.C.C. M-25 in super structure using 12mm size chips including centrering
centering shuttering cost, conveyance, royalty, taxes etc. of all materials
complete

(c) Wearing Coat 1× 7.5 × 3.6 × 0.075 Cum 2.03


Cum 26.37 @ 2899.15

13.2 Supplying, fitting and palcing HYSD bar reinforcement (Fe-415) complete as
per drawing and technical specification Cluses 1002, 1005, 1010 & 1202

Deck slab 8.24 × 1.25 qntl Qntl. 10.3


Abutment cap 1.2 × 1 qntl Qntl. 1.2
Wearing coat 2.03 × 0.6 qntl Qntl. 1.22
Parapets 7 Dirt wall 2.73 × 0.8 qntl Qntl. 2.18
Abutments 53.97 × 0.08 qntl Qntl. 4.32
Wigwalls 17.59 × 0.08 qntl Qntl. 1.41
Qntl. 20.63
t 2.063 @ 33300.45
12.9 Providing weep holes in plain or reinforced concrete abutment, wingwall,
retunn wall with 100mm dia AC pipe extending through the full width of the
structures with slope of 1(V):20H towards drawing face complete as per
drawing and technical specification as per sectin 600, 700 & 1200 of MORD

(d) Abutment 2× 5 No 10
Wing wall 4× 2 No 8
No 18 @ 121.84
12 Providing and laying filter media with granular crushed aggregates as per
specification to a thickness of not less than 600 mm with smaller size
towards the soil and bigger size towards the wall and providing over the
entire surface behind abutment, wing wall, return wall to the full height,
compacted to firm condition complete as per drawing and technical
specification Clause 1204.3.8

Behind Abutments 2× 6× 0.6 × 1.5 Cum 10.8


Behind Wingwalls 4× 1.6 × 0.6 × 1.5 Cum 5.76
Cum 16.56 @ 630.59
13 Providing and fixing 20 mm thick compressible fibre board in expansion joint
complete as per drawing and technical specifications
2x 7.5 RM 15 @ 236.25

14.1 Providing and laying boulder appron for bed protection with stone boulders
of minimum size & weight as per table 1300.1, no fragment weighing less
than 25 kg. laid dry complete as per drawing and technical specification
clause 1301

U/S Appron 1× 5.5 × 2× 0.6 Cum 6.6


D/S Appron 1× 5.5 × 3× 0.6 Cum 9.9
Cum 16.5 @ 429.81
14.1 Providing and laying boulder revertment for slope protection with stone
boulders of minimum size & weight as per table 1300.1, no fragment
weighing less than 25 kg. laid dry complete as per drawing and technical
specification clause 1301

ROAD SLOPE 4× 3× 2.4 × 0.3 Cum 8.64 @ 429.81


14.6 Providng and laying filter material underneath pitching and slopes complete
as per drawing and technical specification Clause 1302
ROAD SLOPE 4× 3× 2.4 × 0.15 Cum 4.32 @ 274.35

1x 450151 Rs.

Junior Engineer Assistant Enggineer Executive Engineer


R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh
Format-F-7

PACKAGE NO
Nayagarh
Odagaon

Amount in Rs.

4473.00

1967.00

41894.00

33389.00

152738.00

34244.00

8125.00
76451.00

68699.00

2193.00

10443.00

3544.00

7092.00

3714.00

1185.00
450151.00

450151.00

Executive Engineer
W.Division, Nayagarh
PRADHANMANTRI GRAM SADAK YOJANA (PMGSY) Format-F-7
COST ESTIMATE FOR REPAIR TO EXISTING CD WORK
Name of the road: Nandighore to Saliajhari PACKAGE NO
0 no District : Nayagarh
Type of soil : All kinds of soil Block : Odagaon
Ht / Th
Sl. No Description of item Nos. Length Width Unit Quantity Rate in Rs. Amount in Rs.
in M
1 2 3 4 5 6 7 8 9
1 Dismantling of existing structures like
culverts, bridges, retaining walls and
other sturcture comprising of masonry,
cement concrete wood work, steel work,
including T&P and scaffolding wherever
necessary, sorting the dismantled
material, disposal of unserviceable
materials and stacking the serviceable
materials with all lifts and lead of 1000m
as per Technical Specification Clause
202

HPC culverts 6no 0 × 3.50 × 0.50 × 1.500 Cum 0.00


Cum 0.00 @ 394.10 0.00
Backfilling in foundation trenches as per
drawing and technical clause 1108 (Sand
filling)

0 × 3.50 × 1.40 × 0.150 Cum 0.00 @ 1125.35 0.00


Plain cement concrete M-10 (1:3:6)
Nominal mix in levelling coarse below
open foundation of head walls as per
drawing and technical clause 1109

0 × 3.50 × 1.40 × 0.150 Cum 0.00 @ 4696.88 0.00


Plain cement concrete in sub-structure
complete as per drawing and technical
specification clauses 802,804, 805, 806,
807, 1202 & 1204 of MORD with P.C.C.
M-15 grade nominal mix (1:2.5:5)

Head wall 0 × 3.35 × 0.825 × 2.01 Cum 0.00


Parapet 0 × 3.35 × 0.40 × 0.40 Cum 0.00
Deduct for Pipe in head wall 0 × 0.823 × p/4 × (0.76)2 Cum (-) 0.00
Cum 0.00 @ 4960.82 0.00

Providing and laying filter material


underneath pitching in slopes complete
as per drawing and technical specifi-
cations Clause 1302

0.785 ×
U/S D/S revetment 0 × 1.35 × 1.45 × 0.15 Cum 0.00 @ 772.49 0.00

Providing and laying boulder appron for


bed protection with stone boulders of
minimum size & weight as per table
1300.1, no fragment weighing less than
25 kg. laid dry complete as per drawing
and technical specification clause 1301

0.785 ×
U/S D/S revetment 0 × 1.35 × 1.45 × 0.30 Cum 0.00 @ 2112.13 0.00

Total Rs. 0.00


Junior Engineer Assistant Engineer Executive Engineer
R. W. Section ,Odagaon R.W.Sub-Division, Nayagarh R.W.Division, Nayagarh