Sunteți pe pagina 1din 4

SUBMITTAL FOR APPROVAL OF DOCUMENT

Project Name : GULF CHLORINE-CHLOR ALKALI Doc # : GC-10-ATC-S13-011


AT MIC
Contract# : ME1500017 Rev # : 01
Client : Gulf Chlorine Date : 07 September 2015
Contractor : FATA Copies : 4 sets hard copy + CD
Designer : Qatar Design Consortium From : ATC
Contractor : Al Alia Trading & Contracting Co. To : FATA

TO : CONTRACTOR
We request your approval on the following Document(s) : “ERECTION ITP FOR BLDG-15 UTILITY BUILDING”
Document Type : A4 Hard Copy Discipline : Steel (Structural)
Area of Application : PEB Steel structure system BOQ Ref. No : GC-00-QDC-X11-011 page 2/5/2
Drawing Ref. : Project IFC Drawings Standards : QCS 2010
Specification : As Per BOQ Other : N/A
Enclosure : N/A Document No. : GC-10-ATC-S13-011
We certify that the above submitted documents have been reviewed in detail and are correct and in strict conformity with the
contract drawings specification except as otherwise stated.
FOR : THE SUB-CONTRACTOR
Name SOUMEN (QA/AC) 3081-8276 07 September 2015
Name Signature Date

CONTRACTOR 'S COMMENTS :

ACTION CODE
A Approved As Submitted B Approved – Approved as Noted C Revise – Resubmit
D Rejected – Resubmit E Receipt acknowledged

TO : THE SUB-CONTRACTOR
We return hereby this actioned Submittal for Approval of Documents. The approval shall not releive the Contractor of its obligations and liabilities
under the Contract or constitute authorization of any change to Contract Documents, and therefore,shall not imply any recognition whatsoever of
additional time or cost to the contract.
FOR : CONTRACTOR

Name Signature Date

Receiving by Sub-Contractor…
Name Signature Date
FATA GULF

PROJECT / CONTRACT REF.: ME1500017

CONTRACT TITLE: - Gulf Chlorine Plant at MIC

DOCUMENT TITLE :

Erection ITP for Utility Building.


Doc No-GC-10-ATC-S13-011_01

Al ALIA TRADING & CONTRACTING WLL

P
1
1
INSPECTION AND TEST (ITP) PLAN
Discipline ITP Code Insert the Subcontractor
Subcontractor Name ITP Description (see UC-00-FAT-X03-001) (see UC-00-FAT-X03-001)
Logo
STRUCTURAL STEEL INSTALLATION
Al Alia Trading & Contracting WLL (Utility Building) S GC-10-ATC-S13-011

Main Identification Information


System Subsystem Document Revision Status Type of Inspection
00 03
CP Code MCP Code Plan Rev/
Date 00M 01M 02M 03M H= HOLD Point - Representative of indicated party to attend (mandatory)
008,013,009,014,015,016 001
Project Phase Subcontractor WITNESS Point - Representative of indicated party to be notified.
(Manufacturing/Construction/ C Issuing 25-Aug-15 6-Sep-15 W=
Commissioning) If not attending at specified time, inspection may proceed.
Subcontractor Premise of Inspections At Gulf Chlorine Contractor REVIEW Point - Representative of indicated party to review submitted documents,
or Site Work Area Coordinates Approval … R=
Job Site result of test etc.
Activity No:

Actual Date and


Acceptance Criteria (Controlling Subcontractor Contractor Owner Approving Signatures of Specific Quality Report
Description of Inspection and Test Activity Drawing N° of reference Procedure, Specifications, Punchlist item N°
Inspection and Test Code (if any)
Standards, etc)
Activity
H W R H W R H W R
1 MATERIAL INSPECTION
Material Inspection Material receipt at
Conformance with
1.1 site Inspection for damages, deformation GC-10-ATC-S52-001 to 007 H W R
reference documents
and Erection Mark.
Conformance with
1.2 Inspection of all Fasteners. GC-10-ATC-S52-001 to 007 H W R
reference documents

Inspection of Anchor Bolt Level and Conformance with


1.3 GC-10-ATC-S52-001 to 007 H W R
Position. reference documents

2 ERECTION (Frame Work)

Alignments Check for Base Plate, Twin


GC-10-ATC-S52-001 to 007 Conformance with
2.1 Column, Top side Column, Connection H W R
,AISC & MBMA reference documents
Beam, and Cross members.

Inspection of above items Bolt


GC-10-ATC-S52-001 to 007 Conformance with
2.2 Tightening and Overall Inspection of H W R
,AISC & MBMA reference documents
structure for conformity with drawings.

Page 1 of 2
INSPECTION AND TEST (ITP) PLAN
Discipline ITP Code Insert the Subcontractor
Subcontractor Name ITP Description (see UC-00-FAT-X03-001) (see UC-00-FAT-X03-001)
Logo
STRUCTURAL STEEL INSTALLATION
Al Alia Trading & Contracting WLL (Utility Building) S GC-10-ATC-S13-011

Main Identification Information


System Subsystem Document Revision Status Type of Inspection
00 03
CP Code MCP Code Plan Rev/
Date 00M 01M 02M 03M H= HOLD Point - Representative of indicated party to attend (mandatory)
008,013,009,014,015,016 001
Project Phase Subcontractor WITNESS Point - Representative of indicated party to be notified.
(Manufacturing/Construction/ C Issuing 25-Aug-15 6-Sep-15 W=
Commissioning) If not attending at specified time, inspection may proceed.
Subcontractor Premise of Inspections At Gulf Chlorine Contractor REVIEW Point - Representative of indicated party to review submitted documents,
or Site Work Area Coordinates Approval … R=
Job Site result of test etc.
Activity No:

Actual Date and


Acceptance Criteria (Controlling Subcontractor Contractor Owner Approving Signatures of Specific Quality Report
Description of Inspection and Test Activity Drawing N° of reference Procedure, Specifications, Punchlist item N°
Inspection and Test Code (if any)
Standards, etc)
Activity
H W R H W R H W R
3 INSTALLATION (Roofing & Wall Cladding)

Conformance with
3.1 Material Verification GC-10-ATC-S52-010 to 014 H W R
reference documents

Conformance with
3.2 Cladding Installation GC-10-ATC-S52-010 to 014 H W R
reference documents

4 PAINT (Touch Up)

Touch Up for above said all Erected As per paint Manufacture Conformance with
4.1 H W R
Areas recommendations reference documents

5 HANDING OVER

Conformance with
5.1 Handing Over As Per Contract H W R
reference documents

Page 2 of 2