The document outlines 26 activities for construction of a building with their quantities, units, and productivity rates. The activities include clearing and grubbing, excavation for footings and a septic tank, fabrication and installation of reinforcement bars and formworks for footings, grade beams, columns, slabs, and roof beams. Other activities are laying concrete blocks and plastering for a septic tank, laying concrete blocks and plastering walls, truss and roof fabrication and installation, and installation of purlins, roofing, ceilings, doors, windows, partitions, floor tiles, and paint works. The productivity rates are given in units like m2/day, MH/m3, and MH/kg for
The document outlines 26 activities for construction of a building with their quantities, units, and productivity rates. The activities include clearing and grubbing, excavation for footings and a septic tank, fabrication and installation of reinforcement bars and formworks for footings, grade beams, columns, slabs, and roof beams. Other activities are laying concrete blocks and plastering for a septic tank, laying concrete blocks and plastering walls, truss and roof fabrication and installation, and installation of purlins, roofing, ceilings, doors, windows, partitions, floor tiles, and paint works. The productivity rates are given in units like m2/day, MH/m3, and MH/kg for
The document outlines 26 activities for construction of a building with their quantities, units, and productivity rates. The activities include clearing and grubbing, excavation for footings and a septic tank, fabrication and installation of reinforcement bars and formworks for footings, grade beams, columns, slabs, and roof beams. Other activities are laying concrete blocks and plastering for a septic tank, laying concrete blocks and plastering walls, truss and roof fabrication and installation, and installation of purlins, roofing, ceilings, doors, windows, partitions, floor tiles, and paint works. The productivity rates are given in units like m2/day, MH/m3, and MH/kg for
Designation Activity Quantity Units Productivity Rates Duration (days)
A Clearing & Grubbing 200 m² 0.03 MH/m² (manual clearing)
B Footing excavation 30.24 m³ 0.5 mh/m³ (machine) C Fabrication of Footing Reinf. 40 pcs (d16) 0.07 MH/kg D Footing concrete pouring 5.04 m³ 4 MH/m³ E Fabrication of Grade Beam Reinf. 52 pcs (d12) 0.1 MH/kg F Installation of Formworks for Grade beam 60.32 m² 0.66 MH/m² G grade beam concrete pouring 5.028 m³ 4 MH/m³ H Disassembling of formworks of Grade beam 66.42 m² 0.23 MH/m² I Fabrication of column Reinf. 85 pcs (d16) 0.1 MH/kg J installation of formworks for column 88.2 m² 0.66 MH/m² K column concrete pouring 5.67 m³ 4 MH/m³ L Disassembling of formworks of column 88.2 m² 0.23 MH/m² M Fabrication of slab rsb 435 pcs (d10) 0.1 MH/kg N concrete pouring on slab 15.2 m³ 4 MH/m³ O Excavation for septic tank 12 m³ 0.5 mh/m³ (machine) P Laying of chb wall (septic tank) 22.8 m² 10 m²/day Q plastering of chb (septic tank) 11.4 m² 10 m²/day R concrete pouring for septic tank top cover 0.75 m³ 4 MH/m³ S Fabrication for Roof beam rsb 36 pcs (d12) 0.1 MH/kg T Installation of formworks for roof beam 66.42 m² 0.66 MH/m² U conrete pouring of roof beam 4.428 m³ 4 MH/m³ V disassembling of formworks 66.42 m² 0.23 MH/m² W laying chb walls 159.34 m² 10 m²/day X palstering of chb walls 299.68 m² 10 m²/day Y truss fabrication 250 bf 0.35 MH/B.F. Z roof installation 250 bf 0.8 MH/B.F. AA purlins & roofing installation 145.2 m² 0.27 MH/m² AB installation of ceilings& framework 121.6 m² 0.36 MH/m² AC installation of doors & windows 14.7 m² 2.37 MH/m² AD installation of wooden partitions 13.14 m² 3.44 MH/m² AE installation of floor tiles 121.6 m² 0.55 MH/m² AF paint works 311.88 m² 0.24 MH/m²