NEW QUESTION 1

You know that PV = 470, AC = 430, EV = 480, EAC = 500, and BAC = 525. What is VAC?

A. 25

B. 30

C. 20

D. 70

Answer: A

NEW QUESTION 2

At which point of the project is the uncertainty the highest and the risk of failing the greatest

A. Final phase of the project

B. Start of the project

C. End of the project

D. Midpoint of the project

Answer: B

NEW QUESTION 3

Co-location can help with:

A. Bringing customers together.

B. Building the team.

C. Decreasing project rental costs.

D. Decreasing project time.

Answer: B

NEW QUESTION 4

You are a project manager for Dutch Harbor Consulting. Your latest project involves the upgrade of an
organization's operating system on 236 servers. You performed this project under contract.

You are in the Closing process and know that product verification is for what purpose?

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

A. To verify that all the work was completed correctly and satisfactorily

B. To evaluate project goals and ensure that the product of the project meets the requirements

C. To verify the goals of the project and ensure that the product of the project is complete

D. To evaluate all the work of the project and compare the results to project scope

Answer: A

NEW QUESTION 5

You have assembled your thoughts into a message. As you pass this information to a second party, you are
giving this person your:

A. Input and Data

B. Feedback

C. Data

D. Output

E. Input

Answer: D

NEW QUESTION 6

Another name for an Ishikawa diagram is:

A. Cause and effect diagram

B. Control Chart

C. Flowchart

D. Histogram

Answer: A

NEW QUESTION 7

Cost baseline is an output of which of the following processes?

A. Cost Control

B. Cost Budgeting

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

C. Cost Estimating

D. Cost Planning

Answer: B

NEW QUESTION 8

How is quality control performed?

A. By identifying quality standards that are relevant to the project and determining how to satisfy them.

B. By monitoring specific project results in compliance with relevant quality standards and determining
corrective actions as needed.

C. By ensuring that the entire project team has been adequately trained in quality assurance processes.

D. By applying Monte Carlo, sampling, Pareto analysis and benchmarking techniques to ensure conformance
to quality standards.

Answer: B

NEW QUESTION 9

Which of the following can be used to track the requirements throughout the project life cycle?

A. Requirements traceability matrix

B. Scope management plan

C. Project charter

D. Work breakdown structure

Answer: A

NEW QUESTION 10

Manage Project Team belongs to which knowledge area?

A. Project Integration Management

B. Project Time Management

C. Project Procurement Management

D. Project Human Resource Management

Answer: D

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

Visit and Download Full Version pmp Exam Dumps

NEW QUESTION 11

What name(s) is (are) associated with the Plan-Do-Check-Act cycle?

A. Pareto

B. Ishikawa

C. Shewart-Deming

D. Delphi

Answer: C

NEW QUESTION 12

Which of the following does NOT assess the value a project brings to an organization?

A. Benefit cost analysis

B. Net present value

C. Value analysis

D. Needs assessment

Answer: C

NEW QUESTION 13

In which type of organization does a project manager have a moderate-to-high resource availability?

A. Functional

B. Weak

C. Balanced

D. Strong

Answer: D

NEW QUESTION 14

Your project team has identified several potential risks on your current project that could have a significant

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

impact if they occurred. The team examined the impact of the risks by keeping all the uncertain elements at
their baseline values. What type of diagram will the team use to display this information?

A. Process flowchart

B. Tornado diagram

C. Influence diagram

D. Fishbone diagram

Answer: B

NEW QUESTION 15

The erection of foundation formwork before the placement of foundation concrete would be an example of a
_____ dependency.

A. Soft logic

B. Subcontracted

C. Mandatory

D. Discretionary

E. External

Answer: C

NEW QUESTION 16

Which of the following is a technique for resolving conflict?

A. Collaborating

B. Issue log

C. Leadership

D. Motivation

Answer: A

NEW QUESTION 17

Management reserves are normally defined as a % of the total budget. As a project progresses, the project
manager wants the $ value of management reserve to _____, whereas the customer wants the management
reserve to _____.

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

A. Increase, increase.

B. Increase, decrease.

C. Remain the same, return to customer.

D. Decrease, increase.

E. Decrease, decrease.

Answer: C

NEW QUESTION 18

A work breakdown structure is most useful for:

A. determining potential delays

B. developing a cost estimate

C. scheduling the start of tasks

D. identifying individual tasks for a project

E. A and C

Answer: E

NEW QUESTION 19

A team member from research and development tells you that her work is too creative to provide you with a
fixed single estimate for the activity. You both decide to use the average labor hours per installation from past
projects to predict the future. This is an example of which of the following?

A. Parametric estimating

B. Three-point estimating

C. Analogous estimating

D. Monte Carlo analysis

Answer: A

NEW QUESTION 20

A(n) _____ is defined as a specified accomplishment in a particular instant in time which does not consume
time or resources.

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

A. Event.

B. Activity

C. Correlation

D. Event constrained within planned effort.

E. Constant

Answer: A

Visit and Download Full Version pmp Exam Dumps

NEW QUESTION 21

Communication plays a major role in:

A. Organizing

B. Controlling

C. All of the other alternatives apply

D. Directing

E. Planning

Answer: C

NEW QUESTION 22

Which tool or technique measures performance of the project as it moves from project initiation through
project closure?

A. Resource leveling

B. Parametric measuring

C. Pareto chart

D. Earned value

Answer: D

NEW QUESTION 23

To accommodate a new project in your department, you need to move resources from one project to another.

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

Because your department is currently working at capacity, moving resources will inevitably delay the project
from which you move the resources. It would cause the LEAST negative impact if you move resources from
which of the following projects?

A. Project A with a benefit cost ratio of 0.8, no project charter, and four resources

B. Project B with a net present value of $60,000, 12 resources, and variable costs between US $1,000 and
$2,000 per month

C. Project C with an opportunity cost of US $300,000, no project control plan, and an internal rate of return of
12 percent

D. Project D with indirect costs of US $20,000 and 13 resources

Answer: A

NEW QUESTION 24

A _____ estimate prepared from layouts, sketches and flowsheets, should be accurate within (-10, +25%).

A. Parametric

B. Bottom up.

C. Budget

D. Top down.

E. Definitive.

Answer: C

NEW QUESTION 25

The resource calendars document is an output of which process?

A. Estimate Activity Resources

B. Acquire Project Team

C. Develop Schedule

D. Develop Project Team

Answer: B

NEW QUESTION 26

Which of the following must not performed in the project initiation process?

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

A. Evaluate historical information

B. List down business need

C. List down stakeholders

D. Create scope statement

Answer: D

NEW QUESTION 27

In crashing a task, you would focus on:

A. Accelerate performance by minimizing cost.

B. As many tasks as possible and accelerate performance by minimizing cost.

C. Non critical tasks.

D. Accelerating performance of tasks on critical path.

E. As many tasks as possible.

Answer: D

NEW QUESTION 28

The most rapid Estimate Costs technique is:

A. Analogous estimating

B. Template estimating

C. Computerized estimating

D. Square foot estimating

Answer: C

NEW QUESTION 29

You are working on a project that was proceeding well until a manufacturing glitch occurred that requires
corrective action. It turns out the glitch was an unintentional enhancement to the product, and the marketing
people are absolutely crazy about its potential. The corrective action is canceled, and you continue to produce
the product with the newly discovered enhancement. As the project manager, you know that a change has
occurred to the project scope. Which of the following statements is true?

A. Performance measurement baselines might be affected by scope changes.

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

B. Project scope change uses workarounds to correct unexpected problems with scope change.

C. Project scope change uses inspection to determine whether change has occurred.

D. Project scope changes do not require CCB approval.

Answer: A

NEW QUESTION 30

An employee approaches you and asks to tell you something in confidence. He advises you that he has been
performing illegal activities within the company for the last year. He is feeling guilty about it and is telling you
in order to receive advice as to what he should do. What should you do?

A. Ask for full details.

B. Confirm that the activity is really illegal.

C. Inform your manager of the illegal activity.

D. Tell the employee to inform his boss.

Answer: C

Visit and Download Full Version pmp Exam Dumps

NEW QUESTION 31

Which is one of the determining factors used to calculate CPI?

A. EV

B. SPI

C. PV

D. ETC

Answer: A

NEW QUESTION 32

You are the project manger for Xylophone Phonics. This company produces children's software programs
that teach basic reading and math skills. You are ready to assign project roles, responsibilities, and reporting
relationships. Which project Planning process are you working on?

A. Human Resource Acquisition

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

B. Acquire Staff

C. Human Resource Planning

D. Resource Planning

Answer: C

NEW QUESTION 33

What quality control tool graphically represents how various elements of a system interrelate?

A. Control chart

B. Flowchart

C. Run chart

D. Pareto chart

Answer: B

NEW QUESTION 34

Trend Analysis is best described as:

A. Examining project performance over time

B. Calculating Earned Value

C. Calculating Cost Variance

D. Analyzing performance of similar projects over time

Answer: A

NEW QUESTION 35

What are the performance measurements for the Schedule Control process?

A. SV (EV - PV) and SPI (EV ?PV)

B. SV (PV - EV) and SPI (PV ?EV)

C. SV (EV - BAC) and SPI (EV ?BAC)

D. SV (EV - AC) and SPI (EV ?AC)

Answer: A

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

NEW QUESTION 36

Which type of analysis is used to develop the communications management plan?

A. Product

B. Cost benefit

C. Stakeholder

D. Research

Answer: C

NEW QUESTION 37

Employee unions would most likely satisfy which level in Maslow's hierarchy of needs?

A. Empowerment

B. Self-actualization

C. Belonging

D. Esteem

E. Safety

Answer: C

NEW QUESTION 38

Many organizations categorize requirements into which of the following two categories?

A. Project and Product

B. Staffing and Budget

C. Stakeholder and Customer

D. Business and Technical

Answer: A

NEW QUESTION 39

Which of the following statements is true regarding schedule variances?

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

A. Schedule variances never impact the schedule.

B. Schedule variances sometimes impact the schedule.

C. Schedule variances impact scope, which impacts the schedule.

D. Schedule variances always impact the schedule.

Answer: B

NEW QUESTION 40

Which of the following is NOT a reason to measure variances from the baseline?

A. To catch deviations early

B. To allow early corrective action

C. To determine if there are any wild fluctuations

D. To create a project control system

Answer: D

Visit and Download Full Version pmp Exam Dumps

NEW QUESTION 41

Your company has just presented its new five-year strategic plan. You have received a new product request
from a customer that is in line with the previous five-year strategic plan, but it does not meet the objectives of
the new plan. The product description seems to have a valid business driver and to be a straightforward
development effort. As project manager, what is the BEST course of action?

A. Do a benefit cost analysis of the project and submit it for management approval.

B. Submit the new product request to the PMO for review and approval before proceeding.

C. Inform the customer of the change in corporate direction and ask him/her to take another look at the
project.

D. Request a project charter from management and begin a WBS.

Answer: B

NEW QUESTION 42

When do stakeholders have the greatest influence?

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

A. At the start of the project

B. At the end of the project

C. During execution

D. Stakeholders have constant influence

Answer: A

NEW QUESTION 43

Which of the following is defined by a project's life cycle and varies by application area?

A. Product

B. Product-oriented processes

C. Project management process groups

D. Project-oriented processes

Answer: B

NEW QUESTION 44

The estimated cost to complete (ETC) is _____.

A. BCWP/ACWP

B. the forecasted and final cost - cost to date

C. None of the other alternatives apply

D. Total estimate - ACWP

E. (ACWP-BCWP)/BCWP * 100

Answer: B

NEW QUESTION 45

Communication always makes use of.

A. words

B. All of the other alternatives apply.

C. language

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

D. gestures

E. symbols

Answer: B

NEW QUESTION 46

Who has the cost risk in a fixed price (FP) contract?

A. The team

B. The buyer

C. The seller

D. Management

Answer: C

NEW QUESTION 47

At the end of the project, what will be the value of SV?

A. Positive

B. Zero

C. Negative

D. Greater than one

Answer: B

NEW QUESTION 48

Using the chart, what is the lowest cost of crashing this project to save four weeks?

A. $18,000

B. $6,000

C. $7,000

D. $9,000

Answer: B

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

NEW QUESTION 49

All of the following are tools and techniques of the Contract Administration process except for which one?

A. Contract change control system, buyer-conducted performance review, and inspections and audits

B. Records management system and information technology

C. Contract performance information gathering and contract reporting systems

D. Performance reporting, payment system, and claims administration

Answer: C

NEW QUESTION 50

If you are the project manager for a new project. You have collected the necessary input information and
delivered the project charter to the stakeholders. What should you do next?

A. Develop the preliminary project scope statement.

B. Get the project charter signed.

C. Start to create project plan

D. Start the initial project planning process.

Answer: B

Visit and Download Full Version pmp Exam Dumps

NEW QUESTION 51

Which of the following is an input to the Direct and Manage Project Execution Process?

A. Approved corrective actions

B. Approved contract documentation

C. Work performance information

D. Rejected change requests

Answer: A

NEW QUESTION 52

You are a project manager for Pizza Direct, which is a retail pizza delivery store. Your company is competing

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

with another retail store for the option of opening two new stores in a foreign country. You know, but have not
yet informed your company, that you are going to go to work for the competitor, which happens to be bidding
for this same opportunity. What is the most appropriate response?

A. You decide to participate in the initial meetings with the foreign business partners because any information
you gain now will help you when you make the move to the new company.

B. You inform the foreign business partners that you're going to be working with a new company and that you
know the deal they'll receive from the competing company is better than the one this company is proposing.

C. You decline to participate in the initial meetings with the foreign business partners because of a conflict of
interest.

D. You've not yet received an official offer from the competing company for your new job opportunity, so you
choose to participate in the initial meetings with the foreign business partners.

Answer: C

NEW QUESTION 53

Risk Event Status is defined as _____ .

A. Both 1) the severity of the consequences, and 2)how likely the event is to occur with risk.

B. (Cost + Benefit + Business Risk) / Insurable Risk.

C. how likely the event is to occur with risk.

D. Risk Probability x Amount At Stake.

E. the severity of the consequences.

Answer: D

NEW QUESTION 54

All the following are needed to create the WBS EXCEPT:

A. Organizational process assets.

B. Quality measurements.

C. Requirements documentation.

D. Project scope statement.

Answer: B

NEW QUESTION 55

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

A new project manager is having difficulty creating a WBS with the team. To alleviate this situation, the
project manager should ask for help from:

A. The sponsor.

B. Other project managers.

C. The project management office.

D. The team.

Answer: C

NEW QUESTION 56

A person is writing a document identifying the business need for a project and is including a description of the
product created by the project. She includes a list of stakeholders and pre assigned resources. What is the
role of this person on the project?

A. The project manager for the project or a company functional manager

B. A member of the project management team working at the direction of the project manager

C. The sponsor or the project manager

D. A manager or executive in the organization who is higher in the corporate hierarchy than theproject
manager

Answer: C

NEW QUESTION 57

You are the project manager for a new website for the local zoo. You need to perform Qualitative Risk
Analysis. When you've completed this process, you'll produce all of the following as part of the risk register
update output except which one?

A. Probability of achieving time and cost estimates

B. Watch list of low-priority risks

C. Priority list of risks

D. Risks grouped by categories

Answer: A

NEW QUESTION 58

Which of the following is an input to Collect Requirements?

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

A. Stakeholder register

B. Requirements documentation

C. Prototypes

D. Organizational process assets

Answer: A

NEW QUESTION 59

A project manager has finished the project. He knows that the project scope has been completed and is
within cost and time objectives set by management. Management, however, says that the project is a failure,
because the original schedule was for 27 weeks and the project was completed in 33 weeks. If the project
baseline was 33 weeks, the project is a success because:

A. It only had six weeks of changes.

B. It was completed within the baseline.

C. There were so few changes.

D. There was good communication control.

Answer: B

NEW QUESTION 60

Your management has decided that all orders will be treated as "projects" and that project managers will be
used to update orders daily, to resolve issues, and to ensure that the customer formally accepts the product
within 30 days of completion. Revenue from the individual orders can vary from US $100 to US $150,000.
The project manager will not be required to perform planning or provide documentation other than daily
status. How would you define this situation?

A. Because each individual order is a "temporary endeavor," each order is a project.

B. This is program management since there are multiple projects involved.

C. This is a recurring process.

D. Orders incurring revenue over $100,000 would be considered projects and would involve project
management.

Answer: C

Visit and Download Full Version pmp Exam Dumps

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

NEW QUESTION 61

Based on the network diagram in the chart, the resource working on activity G is replaced with another
resource with 50 percent of the productivity of the previous resource. How long will this project take?

A. 44

B. 51

C. 52

D. 36

Answer: C

NEW QUESTION 62

You are working with XYZ organization. Your senior manager imposed new delivery date which is earlier
than mentioned project deliverables date in scope statement. To whom you are most accountable?

A. customer

B. team member

C. sponsor

D. senior manager

Answer: A

NEW QUESTION 63

Many companies self insure against some risk. Problems which can arise from self-insurance include:

A. confusion of business risks with insurable risks.

B. Both 1) failure to reserve funds to handle worst case scenarios (low probability events) resulting in severe
financial damage to the company, and 2) confusion of business risks with insurable risks.

C. stiff competition from insurance companies

D. All of the other alternatives apply.

E. failure to reserve funds to handle worst case scenarios (low probability events) resulting in severe financial
damage to the company

Answer: B

NEW QUESTION 64

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

While creating the agenda for a status meeting with the team, a project manager receives input from one
team member that an item should be added. Another team member says the team is not ready to resolve the
item during the meeting. After much discussion, the project manager decides to put the item on the agenda as
an initial discussion item only. Which conflict resolution technique is the project manager using?

A. Compromise

B. Smoothing

C. Forcing

D. Withdrawal

Answer: A

NEW QUESTION 65

How is the process of collecting requirements defined?

A. Defining and documenting project sponsors' needs to meet the project objectives

B. Defining and documenting stakeholders' needs to meet the project objectives

C. Defining and documenting the project teams' needs to meet the project objectives

D. Defining and documenting the project needs to meet the project objectives

Answer: B

NEW QUESTION 66

Decomposition is a tool and technique used in which of the following?

A. Define Scope and Define Activities

B. Collect Requirements and Estimate Activity Resources

C. Create WBS and Define Activities

D. Create WBS and Estimate Activity Duration

Answer: C

NEW QUESTION 67

Generally, when is the BEST time to create a procurement management plan?

A. After the contract is signed

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

B. Preceding the Conduct Procurement process

C. During project initiating

D. When updating the procurement management plan

Answer: B

NEW QUESTION 68

Who must accept the end product for a project to be considered closed?

A. Project team

B. Project manager

C. Project management office

D. Customer or sponsor

Answer: D

NEW QUESTION 69

Approved change requests, approved corrective actions, and updates to organizational process assets are
all outputs of which project management process?

A. Risk response planning

B. Manage stakeholders

C. Scope definition

D. Performance reporting

Answer: B

NEW QUESTION 70

The following reports are normally developed during the project closure phase?

A. None of the other alternatives apply

B. Communications Management Plan and Lessons Learned

C. Records Archive, Closure Report, & Specifications Document

D. Records Archive, Closure Report, lessons learned & Formal Acceptance Report

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

E. Communications Management Plan and Closure report

Answer: D

Visit and Download Full Version pmp Exam Dumps

NEW QUESTION 71

Total funding requirements and periodic funding requirements are derived from:

A. funding limit reconciliation

B. scope baseline

C. activity cost estimates.

D. cost baseline.

Answer: D

NEW QUESTION 72

The project manager notices that project activities being completed by one department are all taking slightly
longer than planned. To date, none of the activities/work packages have been on the critical path, nor have
they affected the critical chain planning that has occurred. The project manager is bothered by the problem,
since four of the next five critical path activities are being completed by this department. After making three
calls, the project manager is finally able to converse with the department manager to determine what is going
on. The conversation is slow, because both speak different native languages and they are trying to converse
in French, a shared language. To make communication easier, the project manager frequently asks the
department manager to repeat back what has been said. The department manager communicates that his
staff is following a company policy that requires two levels of testing. During the conversation, the department
manager also makes a comment that leads the project manager to believe that the policy may include
excessive work. This is the fourth time the project manager has heard such a comment. What is the BEST
thing to do?

A. Create a better communications management plan that requires only one language to be the universal
language on the project and have translators readily available on a moment's notice.

B. Contact someone else in the department who speaks the project manager's native language better to
confirm the department manager's opinion.

C. Find out if the upcoming activities should be re estimated.

D. Work on increasing the effectiveness of the performing organization by recommending continuous


improvement of the policy in question.

Answer: D

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

NEW QUESTION 73

What is the function of a Project Management Office (PMO)?

A. To focus on the coordinated planning, prioritization, and execution of projects and subprojects that are tied
to the parent organizations' or the client's overall business objectives.

B. To coordinate and manage the procurement of projects relevant to the parent organization's business
objectives and to administer the project charters accordingly.

C. To administer performance reviews for the project manager and the project team members and to handle
any personnel and payroll issues.

D. To focus on the specified project objectives and to manage the scope, schedule, cost, and quality of the
work packages.

Answer: A

NEW QUESTION 74

Your company has asked you to be the project manager for the product introduction of its new DeskTop
Rock media system. You recently published the project scope statement. Which of the following is not
contained in the project scope statement?

A. Requested changes

B. Project configuration management requirements

C. Constraints

D. Project specifications

Answer: A

NEW QUESTION 75

The risk of accepting a lot of poor quality, in acceptance sampling, is referred to as:

A. type I error

B. producer's risk

C. consumer's risk

D. buyer's risk

E. consumer's risk and type I error

Answer: C

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

NEW QUESTION 76

You are a project manager for Pizza Direct, which is a retail pizza delivery store. Your company is competing
with another retail store for the option of opening two new stores in a foreign country.

You have been invited to dinner with the prospective foreign business partners and their spouses upon your
arrival. You know that all of the following statements are generally true except for which one?

A. You should respect the cultural differences you'll encounter when working with your prospective foreign
business partners.

B. You should build an atmosphere of mutual trust and cooperation.

C. You should spend time building relationships with your prospective foreign business partners before
getting down to business.

D. You should explain your company's rules, standards, and operating policies at your first meeting with the
prospective foreign business partners.

Answer: D

NEW QUESTION 77

What is a tool to improve team performance?

A. Staffing plan

B. External feedback

C. Performance reports

D. Co-Location

Answer: D

NEW QUESTION 78

Which of the following is an example of a risk symptom?

A. Failure to meet intermediate milestones

B. Force of nature, such as a flood

C. Risk threshold target

D. Crashing front loading or fast tracking

Answer: A

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

NEW QUESTION 79

The project management office is worried about the quality of the company's various projects. They want to
know which projects are having problems and which ones are doing well. If the PMO receives the following
information, which project should they be the MOST concerned about?

A. Project A with a benefit cost ratio of 2.3

B. Project B with a benefit cost ratio of 1.3

C. Project C with a benefit cost ratio of negative 2.3

D. Project D with a benefit cost ratio of negative 1.3

Answer: C

NEW QUESTION 80

As part of a mid-project evaluation, your project sponsor has asked you to provide a forecast of total project
cost. You should calculate the forecast using which of the following methods?

A. BAC

B. EAC

C. ETC

D. WBS

Answer: B

Visit and Download Full Version pmp Exam Dumps

NEW QUESTION 81

Which of the following would be the MOST appropriate thing to do during the monitoring and controlling
process group?

A. Implement recognition and reward systems.

B. Obtain sign-off of the product of the project.

C. Issue performance reports.

D. Keep everyone focused on completing the project to the charter.

Answer: C

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

NEW QUESTION 82

Which of the following consists of the detailed project scope statement and its associated WBS and WBS
dictionary?

A. Scope plan

B. Product scope

C. Scope management plan

D. Scope baseline

Answer: D

NEW QUESTION 83

A project manager has just been assigned to a new project and has been given the approved project charter.
The FIRST thing the project manager must do is:

A. Create a project scope statement.

B. Confirm that all the stakeholders have had input to the scope.

C. Analyze project risk.

D. Begin work on a project management plan.

Answer: B

NEW QUESTION 84

Complete final contract performance reporting and verify product is done in _______ .

A. Conduct Procurements

B. Close Procurements

C. Plan Procurements

D. Administer Procurements

Answer: B

NEW QUESTION 85

Control Charts, Flowcharting, Histograms, Pareto Charts, Scatter Diagrams are tools and techniques of what
process?

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

A. Perform Quality Control

B. Perform Quality Assurance

C. Quality Planning

D. Performance Reporting

Answer: A

NEW QUESTION 86

Information distribution involves making needed information available to project stakeholders in a timely
manner. What is an output from information distribution?

A. Earned value analysis

B. Trend analysis

C. Project records

D. Performance reviews

Answer: C

NEW QUESTION 87

What is a cost of nonconformance?

A. Rework

B. Inspections

C. Training

D. Testing

Answer: A

NEW QUESTION 88

A project manager has limited authority in which type of organizational structure?

A. Weak matrix

B. Functional

C. Balanced matrix

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

D. Projectized

Answer: A

NEW QUESTION 89

The Project Management Body of Knowledge (PMBOK Guide) should be considered as a:

A. guide to project management processes, tools and techniques.

B. methodology for managing projects.

C. guide for project, portfolio and program management.

D. standard for project, portfolio and program management.

Answer: A

NEW QUESTION 90

When managing a project team, what helps to reduce the amount of conflict?

A. Clear role definition

B. Negotiation

C. Risk response planning

D. Team member replacement

Answer: A

Visit and Download Full Version pmp Exam Dumps

NEW QUESTION 91

How is scheduled variance calculated using the earned value technique?

A. EV less AC

B. AC less PV

C. EV less PV

D. AC less EV

Answer: C

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

NEW QUESTION 92

You are the project manager for Lucky Stars nightclubs. They specialize in live country and western band
performances. Your newest project is in the Planning process group. You've published the scope statement
and scope management plan. The document that describes who will receive copies of this information as well
as future project information, how it should be distributed, and who will prepare it is which of the following?

A. Scope management plan

B. Project charter

C. Communications management plan

D. Information distribution plan

Answer: C

NEW QUESTION 93

If a project manager is using observation and conversation to help control the project, she must be involved
in which process?

A. Develop Project Team

B. Distribute Information

C. Manage Stakeholder Expectations

D. Manage Project Team

Answer: D

NEW QUESTION 94

A(n) _____ system is designed to ensure the timely availability of nonhuman resources, and includes the
cost in procurement, shipping/freight, storage and loss.

A. Procurement.

B. All of the other alternatives apply.

C. Inventory control.

D. Materials management.

E. Inventory control and Procurement.

Answer: D

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

NEW QUESTION 95

Which of the following is contained within the communications management plan?

A. An organizational chart

B. Glossary of common terminology

C. Organizational process assets

D. Enterprise environmental factors

Answer: B

NEW QUESTION 96

You are a project manager working on gathering requirements and establishing estimates for the project.
Which process group are you in?

A. Monitoring and Controlling

B. Initiating

C. Executing

D. Planning

Answer: D

NEW QUESTION 97

Which of the following is the definition of a project?

A. Temporary endeavor undertaken to create a temporary business process or product

B. Temporary endeavor undertaken to create a unique product, service, or result

C. Permanent endeavor that produces repetitive outputs

D. Temporary endeavor that produces repetitive outputs

Answer: B

NEW QUESTION 98

Root Cause Analysis related to ________.

A. Process Analysis

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

B. Performance Measurements

C. All of the other alternatives apply

D. Quality Audits

Answer: A

NEW QUESTION 99

You are the project manager on an information technology project on which you and the sponsor have
already approved the scope. An information specialist on your team, after having lunch with a low ranking
customer representative working with him on a software project, learns that a simple alteration in the display
would be a great addition to the project. The information specialist installs the change with no negative effect
on the project schedule and at no additional cost. What action should be taken?

A. The information specialist should be recognized for exceeding customer expectations without affecting
project cost or schedule.

B. The project manager should add an activity to the project management plan with no associated time.

C. The information specialist should be told that his behavior was unacceptable, as it may have negatively
affected the overall project.

D. The project manager should create a change control form and have the customer approve thechange
since the change has already been made.

Answer: C

NEW QUESTION 100

Parametric cost estimating involves

A. using a statistical model to estimate costs

B. calculating the individual estimates of work packages

C. defining the perimeters of the life-cycle

D. using the WBS to do bottom up estimates

E. Both 1) using the WBS to do bottom up estimate, and 2) calculating the individual estimates of work
packages

Answer: A

Visit and Download Full Version pmp Exam Dumps

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

NEW QUESTION 101

Make payment to seller is done in _______ .

A. Plan Procurements

B. Conduct Procurements

C. Administer Procurements

D. Close Procurements

Answer: C

NEW QUESTION 102

You are a project manager working on a software development project. You've developed the risk
management plan, identified risks, and determined risk responses for the risks. One of the risks you identified
occurs, and you implement the response for that risk. Then, another risk occurs as a result of the response
you implemented. What type of risk is this called?

A. Residual risk

B. Mitigated risk

C. Secondary risk

D. Trigger risk

Answer: C

NEW QUESTION 103

Which schedule development tool and technique produces a theoretical early start date and late start date?

A. Critical path method

B. Variance analysis

C. Schedule compression

D. Schedule comparison bar charts

Answer: A

NEW QUESTION 104

What scope definition technique is used to generate different approaches to execute and perform the work of
the project?

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

A. Build vs. buy

B. Expert judgment

C. Alternatives identification

D. Product analysis

Answer: C

NEW QUESTION 105

The most common form of written project communication is

A. Bulletin boards

B. All of the other alternatives apply

C. Publications

D. Letters and memos

E. Reports

Answer: D

NEW QUESTION 106

Resource leveling will often affect the project by making it:

A. Shorter.

B. More responsive to customer needs.

C. Longer and more responsive to customer needs.

D. Shorter and more responsive to customer needs

E. Longer

Answer: E

NEW QUESTION 107

What is the primary benefit of meeting quality requirements?

A. Quality metrics

B. Less rework

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

C. Quality control measurements

D. Benchmarking

Answer: B

NEW QUESTION 108

A project manager arranges for project specific training for the new team members. Under which category
does this cost fall?

A. Appraisal

B. Internal failure

C. External failure

D. Prevention

Answer: D

NEW QUESTION 109

You are a project manager for Cinema Snicker Productions. Your company specializes in producing comedy
films for the big screen. Your latest project has just been completed and accepted. You've been given your
next project, which starts right away. Which of the following statements is true?

A. This project ended due to integration because it was completed and accepted.

B. This project ended due to extinction because it was completed and accepted.

C. This project ended due to integration because it was completed and accepted and the project manager
moved on to a new project.

D. This project ended due to addition because it was completed and accepted and archived into the
company's catalog of available films.

Answer: B

NEW QUESTION 110

The sponsor has informed you that the resources for your project will be cut. The sponsor wants to know how
long the project will take if only nine resources each month are committed to your project. What is this activity
called?

A. Crashing

B. Floating

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

C. Leveling

D. Fast tracking

Answer: C

Visit and Download Full Version pmp Exam Dumps

NEW QUESTION 111

What is a technique used in the performance reporting process?

A. Expert judgment

B. Project management methodology

C. Stakeholder analysis

D. Status review meetings

Answer: D

NEW QUESTION 112

What does a SPI value greater than 1.0 indicate?

A. More work was completed than planned

B. Less work was completed than planned

C. Cost overrun for completed work has occurred

D. Cost underrun for completed work has occurred

Answer: A

NEW QUESTION 113

Your project sponsor has requested a cost estimate for the project on which you're working. This project is
similar in scope to a project you worked on last year. She would like to get the cost estimates as soon as
possible. Accuracy is not her primary concern right now. She needs a ballpark figure by tomorrow. You decide
to use ___________________.

A. parametric modeling techniques

B. analogous estimating techniques

C. bottom-up estimating techniques

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

D. computerized modeling techniques

Answer: B

NEW QUESTION 114

What is the purpose of a decision tree?

A. It demonstrates the path of events in a project.

B. It calculates the probability of an outcome.

C. It determines what events may take place.

D. It takes into account future events for today's choices.

Answer: D

NEW QUESTION 115

You receive 25 new computers from the seller, but were expecting only 20. In looking at the contract, you see
that it says "seller to provide twenty (25) computers." What should you do FIRST?

A. Issue a change order through the contract manager.

B. Return the five extra computers.

C. Make payment for the 25 computers.

D. Call the seller and ask for clarification.

Answer: B

NEW QUESTION 116

Which of the following describes the purpose of the quality control process?

A. To identify quality requirements of the project

B. To identify ineffective processes and eliminate them

C. To assess performance and recommend necessary changes

D. To ensure quality standards are used

Answer: C

NEW QUESTION 117

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

What is included in a control chart?

A. Baseline

B. Planned value

C. Upper specification limit

D. Expenditure

Answer: C

NEW QUESTION 118

Which of the following processes is necessary to ensure that the project employs all processes needed to
meet its requirements?

A. Perform Quality Control

B. Quality Policy

C. Perform Quality Assurance

D. Quality Planning

Answer: C

NEW QUESTION 119

Continually measuring and monitoring the actual cost versus the budget is done to _____.

A. None of the other alternatives apply

B. analyze the reasons for variances

C. establish the variances

D. identify the problems

E. All of the other alternatives apply.

Answer: E

NEW QUESTION 120

Which type of control tool identifies whether or not a process has a predictable performance?

A. Cause and effect diagram

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

B. Control Charts

C. Pareto Chart

D. Histogram

Answer: B

Visit and Download Full Version pmp Exam Dumps

NEW QUESTION 121

Which of the following correctly explains the term "progressive elaboration"?

A. Changing project specifications continuously

B. Elaborate tracking of the project progress

C. Elaborate tracking of the project specifications with a change control system

D. Project specifications becoming more explicit and detailed as the project progresses

Answer: D

NEW QUESTION 122

What is the status of the project whose data is shown in the following S-curve?

A. Under budget and ahead of schedule

B. Over budget and behind schedule

C. Over budget and ahead of schedule

D. Under budget and behind schedule

Answer: B

NEW QUESTION 123

Which process group can be performed outside the project's scope of control?

A. Planning

B. Monitoring and Control

C. Closing

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

D. Initiating

Answer: D

NEW QUESTION 124

In which of the following team development stages does the team begin to work together, develop trust, and
adjust to the work habits and behavior?

A. Norming

B. Forming

C. Storming

D. Performing

Answer: A

NEW QUESTION 125

Which of the following events would result in a baseline update?

A. Your project is behind schedule and you want your baseline to reflect estimated actual completion.

B. Your customer has approved a change request broadening the project scope and increasing the budget.

C. One of the risks identified in the Risk Management Plan occurs resulting in a schedule delay.

D. One of your key project team resources has left your team and no replacement is available.

Answer: B

NEW QUESTION 126

A project manager for a small construction company has a project that was budgeted for US $130,000 over a
six-week period. According to her schedule, the project should have cost US $60,000 to date. However, it has
cost US $90,000 to date. The project is also behind schedule, because the original estimates were not
accurate. Who has the PRIMARY responsibility to solve this problem?

A. Project manager

B. Senior management

C. Project sponsor

D. Manager of the project management office

Answer: A

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

NEW QUESTION 127

Which tools or techniques will the project manager use for developing the project team?

A. Negotiation

B. Roles and responsibilities

C. Recognition and rewards

D. Prizing and promoting

Answer: C

NEW QUESTION 128

Your company, Kick That Ball Sports, has appointed you project manager for its new Cricket product line
introduction. This is a national effort, and all the retail stores across the country need to have the new
products on the shelves before the media advertising blitz begins. The product line involves three new
products, two of which will be introduced together and a third one that will follow within two years. Product
number three will be elaborated in more detail closer to the product's release date, while the first two products
will be elaborated in great detail now. The scope management plan has just been completed. Which of the
following is true? (Choose the best response.)

A. The WBS template from a previous project, a tool and technique of the Create WBS process, was used to
create the WBS for this project. The WBS encompasses the major deliverables for the project.

B. Only the deliverables associated with the work of the project should be listed on the WBS.

Since product number three isn't being released until a later date it should not yet be included on the WBS.

C. The WBS encompasses the full scope of work for the project and the technique in the is called rolling wave
planning.

D. The WBS should be created next, and it encompasses the full scope of work for the project.

Only the work of the project is listed on the WBS.

Answer: C

NEW QUESTION 129

A line manager who is asked to wear two hats and function as a project manager at the same time is likely to
exercise:

A. All of the other alternatives apply]

B. Influence

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

C. Power

D. Authority and Power

E. Authority

Answer: A

NEW QUESTION 130

Which of the following inputs is required for the WBS creation?

A. Project Quality Plan

B. Project Schedule Network

C. Project Management Software

D. Project Scope Management Plan

Answer: D

Visit and Download Full Version pmp Exam Dumps

NEW QUESTION 131

The project manager calculated a schedule performance index of 0.8 and a cost performance index of 1.1 for
the project. What is the actual status of this project?

A. Behind schedule and over budget

B. Behind schedule and under budget

C. Ahead of schedule and under budget

D. Ahead of schedule and over budget

Answer: B

NEW QUESTION 132

Perform quality assurance belongs to which of the following process groups?

A. Planning

B. Executing

C. Monitoring and Control

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

D. Closing

Answer: B

NEW QUESTION 133

A weighting system is a tool for which area of procurement?

A. Plan contracting

B. Request seller responses

C. Select sellers

D. Plan purchase and acquisition

Answer: C

NEW QUESTION 134

Which of the following is an input to direct and manage project execution?

A. Requested changes

B. Approved preventive action

C. Work performance information

D. Implemented defect repair

Answer: B

NEW QUESTION 135

The customer's expectations for quality are shown on a control chart as the:

A. Mean.

B. Specification limits.

C. Rule of seven.

D. Upper and lower control limits.

Answer: B

NEW QUESTION 136

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

Which of the following statements is in agreement with McGregor's concepts concerning Theory X and
Theory Y managers?

A. All of the other alternatives apply

B. Theory X managers tend to be autocratic whereas Theory Y managers are more likely to delegate
responsibility

C. Both 1) Theory X managers view subordinates as being lazy, irresponsible, and resistant to change, and 2)
Theory Y managers view subordinates as being imaginative, creative, and willing to accept responsibility

D. Theory Y managers view subordinates as being imaginative, creative, and willing to accept responsibility

E. Theory X managers view subordinates as being lazy, irresponsible, and resistant to change

Answer: A

NEW QUESTION 137

Which stakeholder is responsible for managing related projects in a coordinated way?

A. Sponsor

B. Portfolio manager

C. Program manager

D. Project manager

Answer: C

NEW QUESTION 138

The project charter:

A. Establishes that organizational structure with the project.

B. Expresses upper management commitment to the project.

C. Provides that authority by which the project will be run.

D. Specifies overall objectives and timeframe of the project.

E. All of the other alternatives apply.

Answer: E

NEW QUESTION 139

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

To-complete performance index (TCPI) is represented by which of the following?

A. BAC - EV/BAC - AC

B. A measure of the value of work completed compared to the actual cost or progress

C. A measure of progress achieved compared to progress planned

D. AC + (BAC - EV)

Answer: A

NEW QUESTION 140

Which of the following is an example of a group creativity technique?

A. Delphi technique

B. Unanimity

C. Observation

D. Presentation technique

Answer: A

Visit and Download Full Version pmp Exam Dumps

NEW QUESTION 141

Which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work?

A. WBS directory

B. Activity list

C. WBS

D. Project schedule

Answer: C

NEW QUESTION 142

The project management processes presented in the PMBOK Guide should:

A. Always be applied uniformly

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

B. Be selected as appropriate by the sponsor

C. Be selected as appropriate by the project team

D. Be applied based on ISO guidelines.

Answer: C

NEW QUESTION 143

A team member is not performing well on the project because she is inexperienced in system development
work. There is no one else available who is better qualified to do the work. What is the BEST solution for the
project manager?

A. Consult with the functional manager to determine project completion incentives for the team member.

B. Obtain a new resource more skilled in development work.

C. Arrange for the team member to get training.

D. Allocate some of the project schedule reserve.

Answer: C

NEW QUESTION 144

A Project with a total funding of $70,000 finished with a BAC value of $60,000.

What term can best describe the difference of $10,000?

A. Management Contingency Reserve

B. Cost Variance

C. Schedule Variance

D. Management Overhead

Answer: A

NEW QUESTION 145

What is the term assigned to products or services having the same functional use but different technical
characteristics?

A. Scope

B. Quality

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

C. Specification

D. Grade

Answer: D

NEW QUESTION 146

Based on the following metrics: EV=$20,000, AC=$22,000 and PV=$28,000, what is the project CV?

A. -$8,000

B. -$2,000

C. $2,000

D. $8,000

Answer: B

NEW QUESTION 147

In which domain of project management would a Pareto chart provide useful information?

A. Scope Management

B. Time Management

C. Communications Management

D. Quality Management

Answer: D

NEW QUESTION 148

How many process groups are there according to the PMBOK Guide?

A. 5

B. 9

C. 10

D. 12

Answer: A

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

NEW QUESTION 149

Which of the following is a KEY output of the Verify Scope process?

A. A more complete scope management plan

B. Customer acceptance of project deliverables

C. Improved schedule estimates

D. An improved project management information system

Answer: B

NEW QUESTION 150

You are negotiating with a seller. Time is of the essence but you have a limited budget, and the seller knows
this. What is your BEST negotiating strategy under these circumstances?

A. Focus the negotiation on seller's profit margin in order to decrease the project cost.

B. Negotiate to get the work done even sooner than necessary in order to add a reserve.

C. Negotiate identified risks.

D. Arrange to reschedule the negotiation until you can acquire information of which the seller is not aware.

Answer: C

Visit and Download Full Version pmp Exam Dumps

NEW QUESTION 151

You are the project manager for a top-secret software project for an agency of the United States government.
Your mission-should you choose to accept it-is to complete the project using internal resources. The reason is
that finding contractors with top-secret clearances takes quite a bit of time, and waiting for clearances would
jeopardize the implementation date. Your programmers are 80 percent of the way through the programming
and testing work when your agency appoints a new executive director. Slowly but surely your programmers
are taken off this project and reassigned to the executive director's hot new project. Which of the following
type of project ending is this?

A. Extinction

B. Starvation

C. Addition

D. Integration

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

Answer: D

NEW QUESTION 152

Which knowledge area employs the processes required to ensure timely and appropriate generation,
collection, distribution, storage, retrieval, and ultimate disposition of project information?

A. Project Risk Management

B. Project Integration Management

C. Project Communications Management

D. Project Quality Management

Answer: C

NEW QUESTION 153

Which of the following equations is used to calculate schedule variance?

A. EV/PV

B. PV/EV

C. EV-PV

D. PV-EV

Answer: C

NEW QUESTION 154

Which involves estimating the cost of individual work items:

A. Analogous estimating

B. Bottom up estimating

C. Computerized

D. Square foot

Answer: B

NEW QUESTION 155

Parametric Estimating is done as a part of which process:

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

A. Estimate Activity Durations

B. Sequence Activities

C. Develop Schedule

D. Estimate Activity Resources

Answer: A

NEW QUESTION 156

A work package has been scheduled to cost $1,000 to complete, and was to be finished today. As of today,
the actual expenditure is $1,200 and approximately half of the work has been completed.

What is the cost variance?

A. -$700

B. -$200

C. +$200

D. +$500

Answer: A

NEW QUESTION 157

Planning activities such that predetermined resource availability pools are not exceeded is called:

A. Manpower planning.

B. Manpower leveling.

C. Resource leveling.

D. Manpower contingency planning.

E. Resource limited planning.

Answer: E

NEW QUESTION 158

What is an objective of the Developing Project Team Process?

A. Feelings of trust and improved cohesiveness

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

B. Ground rules for interaction

C. Enhanced resource availability

D. Functional managers become more involved.

Answer: A

NEW QUESTION 159

You have been assigned to a project that will allow job seekers to fill out applications and submit them via the
company website. You report to the VP of human resources. You are also responsible for screening
applications for the information technology division and setting up interviews. The project coordinator has
asked for the latest version of your changes to the online application page for his review. Which
organizational structure do you work in?

A. Functional organization

B. Balanced matrix organization

C. Weak matrix organization

D. Projectized organization

Answer: C

NEW QUESTION 160

The use of group creativity techniques as a tool and technique is done in which of the following processes?

A. Plan Quality

B. Collect Requirements

C. Define Scope

D. Perform Quality Control

Answer: B

Visit and Download Full Version pmp Exam Dumps

NEW QUESTION 161

How many knowledge areas are there according to PMBOK Guide?

A. 5

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

B. 8

C. 9

D. 12

Answer: C

NEW QUESTION 162

Linear programming is an example of what type of project selection criteria?

A. Constrained optimization

B. Comparative approach

C. Benefit measurement

D. Impact analysis

Answer: A

NEW QUESTION 163

The inputs of the Performance Reporting process include all of the following except for which one?

A. Performance reviews

B. Work performance information

C. Forecasted completion

D. Performance measurements

Answer: A

NEW QUESTION 164

The Communications Management Plan should contain the following:

A. Selection of appropriate media to meet specific needs

B. Communications policy

C. All of the other alternatives apply

D. Communications media

E. Reporting channels

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

Answer: C

NEW QUESTION 165

Parametric estimates are based on variables such as:

A. Project objectives and manpower allocations.

B. Physical characteristics and historical data.

C. Precise measurements and multiple inputs.

D. The WBS and similar projects.

E. Detailed planning and cost restraints.

Answer: B

NEW QUESTION 166

Which of the following would be the MOST appropriate thing to do during the planning process group?

A. Update corporate processes and procedures based on lessons learned.

B. Evaluate the effectiveness of risk responses.

C. Recommend changes and defect repair.

D. Work with the customer to determine acceptance criteria.

Answer: D

NEW QUESTION 167

Most project (and non-project) managers prefer _____ communications.

A. Lateral

B. Oral

C. Downward

D. Written

E. Upward

Answer: B

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

NEW QUESTION 168

A computer tape which contains historical project information is called ____ tape.

A. Database

B. Archive.

C. Lessons learned.

D. Baseline.

E. Life cycle summary.

Answer: B

NEW QUESTION 169

Which of the following tools or techniques is used for Estimate Activity Duration?

A. Critical path

B. Rolling Wave

C. PDM

D. Parametric

Answer: D

NEW QUESTION 170

Which of the following would most likely increase the accuracy of estimating the project cost?

A. Using historical data.

B. Pricing out the work at lower levels in the work breakdown structure.

C. Both 1) Pricing out the work at lower levels in the work breakdown structure, and 2) Talking to people who
have worked on similar projects.

D. Talking to people who have worked on similar projects.

E. 1) Pricing out the work at lower levels in the work breakdown structure, and 2) Talking to people who have
worked on similar projects, and 3) Using historical data.

Answer: E

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

Visit and Download Full Version pmp Exam Dumps

NEW QUESTION 171

As project manager, you wish to impose a standard method by which subordinates calculate project costs.
Which level of communication should be required for this effort?

A. All of the other alternatives apply.

B. Face-to-face

C. Written

D. Non-verbal

E. Telephone

Answer: C

NEW QUESTION 172

A project manager is asked to select a contract type for a new software development project that has
complete, detailed requirements. Which is the BEST contract to choose?

A. Cost reimbursable (CR)

B. Fixed price (FP)

C. Time and material (T&M)

D. Cost plus fixed fee (CPFF)

Answer: B

NEW QUESTION 173

In an activity-on-node diagram, the nodes represent:

A. Work packages.

B. Activities.

C. Dependencies.

D. Discretionaries.

Answer: B

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

NEW QUESTION 174

All of the following statements are true regarding the RBS except for which one?

A. The RBS is similar to the WBS in that the lowest levels of both are easily assigned to a responsible party or
owner.

B. The RBS is contained in the risk management plan.

C. The lowest level of the RBS can be used as a checklist, which is a tool and technique of the Risk
Identification process.

D. It describes risk categories, which are a systematic way to identify risks and provide a foundation for
understanding for everyone involved on the project.

Answer: A

NEW QUESTION 175

Which activity is an input to the select sellers process?

A. Organizational process assets

B. Resource availability

C. Change control process

D. Team performance assessment

Answer: A

NEW QUESTION 176

Which of the following is NOT included in a schedule change control system?

A. Approval levels necessary for authorizing changes

B. Tracking systems

C. Paperwork necessary for making changes

D. Limitations on the scope of changes

Answer: D

NEW QUESTION 177

Which of the following choices is a contract closure tool or technique?

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

A. Contract plan

B. Procurement plan

C. Closure process

D. Procurement audits

Answer: D

NEW QUESTION 178

You are in a meeting with someone who just ate a slice of garlic bread. Your are distracted by his pungent
breath. Which of the following communication barriers describe these distractions?

A. None of the other alternatives apply

B. Selective Perception

C. Sensory Limitations

D. Varying Alertness of Perception

E. Sign Detection

Answer: E

NEW QUESTION 179

Project contracts generally fall into which of the following three broad categories?

A. Fixed-price, cost reimbursable, time and materials

B. Make-or-buy, margin analysis, fixed-price

C. Time and materials, fixed-price, margin analysis

D. Make-or-buy, lump-sum, cost-plus-incentive

Answer: A

NEW QUESTION 180

What is the lowest level in the WBS at which the cost and activity durations for the work can be reliably
estimated and managed?

A. Work product

B. Work package

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

C. Project deliverable

D. Scope baseline

Answer: B

Visit and Download Full Version pmp Exam Dumps

NEW QUESTION 181

Control chart theory is based on the differentiation of the causes of variations in quality. Variations may be
produced by assignable causes. All of the following are examples of assignable causes except:

A. None of the other alternatives apply (all are examples)

B. differences among materials.

C. differences among machines.

D. differences among workers.

E. differences in each of these factors over time.

Answer: A

NEW QUESTION 182

Conflict should be best addressed in which manner?

A. Early, in private, using a direct, collaborative approach

B. Early, in public, using an indirect, collaborative approach

C. Early, in private, using an indirect, cooperative approach

D. As late as possible, in public, using a direct, confrontational approach

Answer: A

NEW QUESTION 183

The sponsor is worried about the seller deriving extra profit on the cost plus fixed fee (CPFF) contract. Each
month the sponsor requires the project manager to submit CPI calculations and an analysis of the cost to
complete. The project manager explains to the sponsor that extra profits should NOT be a worry on this
project because:

A. The team is making sure the seller does not cut scope.

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

B. All costs invoiced are being audited.

C. There can only be a maximum 10 percent increase if there is an unexpected cost overrun.

D. The fee is only received by the seller when the project is completed.

Answer: B

NEW QUESTION 184

A project manager is responsible for managing which of the following at the project level?

A. Methodology

B. Standards

C. Constraints

D. Interdependencies

Answer: C

NEW QUESTION 185

You are the project manager of a project .You have just completed the Collect

Requirements and Define Scope. What should you do next?

A. Control Scope

B. Create WBS

C. Value analysis

D. Verify Scope

Answer: B

NEW QUESTION 186

Monitor and control project work is a process of which of the following knowledge areas?

A. Project risk management

B. Project scope management

C. Project time management

D. Project integration management

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

Answer: D

NEW QUESTION 187

Which schedule compression technique has phases or activities done in parallel that would normally have
been done sequentially?

A. Crashing

B. Fast tracking

C. Leads and lags adjustment

D. Parallel task development

Answer: B

NEW QUESTION 188

A project manager discovers that two team members discussed what was needed to complete a work
package on the project and made many changes to the project scope. The work package is now completed
and the team members are planning to go on to the next work package. In looking at what was done, the
project manager determines that the work does NOT meet the requirements of the project. What is the BEST
course of action for the project manager?

A. Add another work package, formatted with the correct scope, to the project.

B. Refuse the submittal of the work package.

C. Have the team begin the work package again and include the incident in their performance reviews.

D. Ask the team member's manager to assign different people to the work package.

Answer: B

NEW QUESTION 189

The decomposition technique is used to do which of the following?

A. Subdivide the estimated costs of individual activities

B. Subdivide project deliverables and project work into smaller, more manageable components

C. Relate the work packages to the performing organizational units

D. Shorten the project schedule duration and the amount of resources needed

Answer: B

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

NEW QUESTION 190

The most effective team motivator is:

A. understanding the importance of the project

B. the satisfaction of meeting a challenge

C. All of the other alternatives apply.

D. the visibility of the team's contribution

E. the individual's professional challenge

Answer: D

Visit and Download Full Version pmp Exam Dumps

NEW QUESTION 191

Objectives can be described as all of the following except for which one? Choose the least correct answer.

A. The monetary units used to express the cost criteria for the project

B. The functionality and specific conditions that must be met in order to satisfy the project, contract, standard,
or specification

C. The quantifiable results used to measure project success that should include schedule, cost, and quality
criteria

D. The purpose for undertaking the project

Answer: B

NEW QUESTION 192

EAC (estimate at complete) is typically based on actual cost (AC) for work completed plus an ETC (estimate
to complete) the remaining work. Which of the following is a valid formula for calculating EAC?

A. EAC = AC + [(BAC-EV) / (Cumulative CPI * Cumulative SPI)]

B. EAC = BAC - AC

C. EAC = 1 - CPI

D. EAC = EV + [1 - (Cumulative CPI * Cumulative SPI) / BAC]

Answer: A

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

NEW QUESTION 193

Bar charts are most appropriate for:

A. Showing slack time.

B. Comparing actual to planned performance to each activity.

C. All of the other alternatives apply.

D. Showing critical path dependencies.

E. Showing which activities can be rearranged in parallel.

Answer: B

NEW QUESTION 194

In which of the team development stages are the teams interdependent and work through issues smoothly
and effectively?

A. Norming

B. Forming

C. Storming

D. Performing

Answer: D

NEW QUESTION 195

In which type of organization(s) is the project manager's role most likely part-time?

A. Functional

B. Weak Matrix

C. Balanced Matrix

D. Both 1) Functional and 2) Weak Matrix

Answer: D

NEW QUESTION 196

What type of project structure is a hierarchically organized depiction of the resources by type?

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

A. Organizational Breakdown Structure (OBS)

B. Resource Breakdown Structure (RBS)

C. Work Breakdown Structure (WBS)

D. Project Breakdown Structure (PBS)

Answer: B

NEW QUESTION 197

Which of the following are outputs of the Monitor and Control Project Work process?

A. Requested changes, forecasts, recommended corrective actions

B. Forecasts, resources plan, bottom up estimating

C. Recommended corrective actions, cost baseline, forecasts

D. Requested changes, recommended corrective actions, project constraints

Answer: A

NEW QUESTION 198

What is one of the advantages of a functional organization?

A. All employees report to two or more managers, but project team members show loyalty to functional
managers.

B. All employees report to one manager and have a clear chain of command.

C. Teams are co-located.

D. The organization is focused on projects and project work.

Answer: B

NEW QUESTION 199

When working in a matrix environment, all of the following are true regarding the Manage Project Team
process except for which one?

A. Communication methods and issue logs are used to create performance appraisals, provide feedback, and
track issues.

B. Managing project teams in a matrix environment is often a critical success factor for the project.

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

C. Loyalty issues might arise when managing projects in a matrix environment.

D. It's the project manager's responsibility to make certain this dual reporting relationship is managed
effectively.

Answer: A

NEW QUESTION 200

What is an output of Control Scope?

A. Accepted deliverables

B. Work performance measurements

C. Requirements documentation

D. Work performance information

Answer: B

Visit and Download Full Version pmp Exam Dumps

The Leader of IT Certification visit - http://www.certleader.com


Visit and Download Full Version Exam Dumps
http://www.certleader.com/PMP-dumps.html

Thank You for Trying Our Product

* 100% Pass or Money Back


All our products come with a 90-day Money Back Guarantee.
* One year free update
You can enjoy free update one year. 24x7 online support.
* Trusted by Millions
We currently serve more than 30,000,000 customers.
* Shop Securely
All transactions are protected by VeriSign!

100% Pass Your PMP Exam with Our Prep Materials Via below:

http://www.certleader.com/PMP-dumps.html

The Leader of IT Certification visit - http://www.certleader.com


Powered by TCPDF (www.tcpdf.org)

S-ar putea să vă placă și