Daily Report

Project : Gulf MALL AT GHARAFA

Owner : Sheikh/ Nasser Bin Abdulla Al-Thani Date : 09/08 /2012

Consultant : Arab Engineering Bureau (A.E.B) Project No : 672

Sub-Contractor : AL alia Trading & Contracting.co (A.T.C) ref. no.: 566

A. Weather Condition :

Rainy Cloudy Sunny Dusty Temperature: Maximum :43°


Minimum: 33°
29% Humidity windy

B. Manpower ( Main Contractor )

PM Q Survivor Safety officer 1 Welder foreman 1


Engineer 1 Draughtsman Safety helper Electrician erector 20

L
Supervisor land surv. Security W.proof Metalex trading 12

TA
St.foreman land surv.helper Store keeper Equip. driver office boy

TO
Steel fixer secretary S.K.assistant Truck driver &help Painter 10
Carp.foreman P. administrator mason. Foreman Mechanical plaster
Carpenter Time keeper mason Mech helper screed
TOTAL 1 TOTAL 0 TOTAL 1 TOTAL 0 43 45

C. Equipment :

S/No. Description Qty No Description Qty No Description Qty


1- crane 1
2- Forklift 1
3- man lift 0
4-
5-
6-
7-
8-

D. Materials

S/No. Description Unit Ref. No. QTY


1
2
3
4
5
6
7
8
9
Daily Report
E. Work Performed : ref. no.: 566

cinema -6 erection of steel frame chair


sector 17 modification work for cantelever along grid lineT/29:31- start
sector 25&27 installation of sandwich panel along grid line K sandwich panel parapet between sector 25& sector 27-roof area
sector 24&26 installation of Z purlins along grid line 27/H:K- sandwich panel parapet between sector 24& sector 26-roof area-done
sector 26 cement paint @ 7.8m level
sector 26 opening two numbers of additional Openings for MEP,@ 7.8m level
sector 27 cement paint @ 18.6m level - roof cinema area

GENERAL

F.SPECIAL Notes :

Submitted By Contractor: Name ousayd k Position Project Manager Signature / Date

Received By Consultant: Name Position Signature / Date