PROGRESS REPORT FOR QF-off site W/H (J‐435) December 1- 2011

PROJECT PROGRESS STATUS


Client : CDC
Consultant: Gulf eng.
    Site supervision : ASTAD      
are
a Description of Work Progress   REMARKS
 B 3  Erection main frame @ GL 15 & 15G  
B1 Erection column & bracing & side grit @ grid line 1  
 
     
     
     
     
     
Man power and equipment

crane 4
Forman Manthakali
Equipment on site

Erector 19 fork lift 1


Man power

man lift 5

total: 20
B3- erection progress.
B3- erection progress
B1- erection progress @ grid line 1