The progress report summarizes work done from December 1-2011 for Project Corrotech J (436). 11 workers erected the main frame from grid lines 8 to 12 and completed decking and bolt tightening for the mezzanine area. Equipment on site included 1 crane, 1 forklift, and 2 man lifts.
The progress report summarizes work done from December 1-2011 for Project Corrotech J (436). 11 workers erected the main frame from grid lines 8 to 12 and completed decking and bolt tightening for the mezzanine area. Equipment on site included 1 crane, 1 forklift, and 2 man lifts.
The progress report summarizes work done from December 1-2011 for Project Corrotech J (436). 11 workers erected the main frame from grid lines 8 to 12 and completed decking and bolt tightening for the mezzanine area. Equipment on site included 1 crane, 1 forklift, and 2 man lifts.
PROGRESS REPORT FOR Corrotech J (436) December 1- 2011
PROJECT PROGRESS STATUS
are a Description of Work Progress REMARKS A Erection of main frame from grid line 8 to 12 @ grid J to A A Mezzanine area decking sheet & Bolt tightening
Man power and equipment Mito mia crane 1 Forman Equipment on site
Erector 10 fork lift
Man power
man lift 2
total: 11 Main frame erection progress Decking sheet progress Mezzanine area Tightening bolt