ERECTION PROGRESS REPORT for Gulf Mall


Date : 28-08-2012
Job No. QA-1044,QA -1299 Bldg. Size : 29 Sector Total Area of 76695.6m²
Project Name : gulf mall at gharrafa ROOF CLADDING :
Customer Name : Business trading company WALL CLADDING :
Project Info

Location : Gharafah SPECIAL MATERIALS:


No. of Buildings : 29 Sectors SUPPLIER : ATC
Erection by : ATC : Mabani Steel BSI
Cement. Paint By almouayad as sub. EBS LOCAL :
KIRBY OTHERS:
A.B. Shipment Date : RECEIVED NO
ANCHOR BOLT

A.B. Installation Date : YES NO


A.B. Setting / Checking Date : YES NO
Concrete casted /A.B. Final Checking Date: 5-8-2011 YES NO

PEB Date of 1st Delivery / Last Delivery Date : ١٠-‫ديسمبر‬-٠٧ -----


PPA Date of 1st Shipment / Last Shipment Date : ------ ------
PEB Date Erection Started / Expected Completion Date: ١٠-‫ديسمبر‬-١٠ ١٢-‫فبراير‬-٢٠
PEB Erection - ACTUAL Completion Date: ----
PPA Date Erection Started / Completion Date: ---- -----
DURATION

PPA Installation - ACTUAL Completion Date:


Erection Duration (as per the Contract) N/A
Time Elapsed N/A
No. of Weeks Remaining for Completion (as per the contract) N/A
Actual No. of Weeks Remaining for Completion N/A
Current Status ACTIVE ON HOLD
Erection Team Leader Dolaram

MANPOWER
Foreman
Group Leader
Average No. of Erectors /day 11
EQPTS. No. of Crane/s on Site N/A
No. of Boom loader on Site N/A
No. of Man lifts / Sissorlift
No. of Forklifts N/A
From : Supplier ATC Office
PENDING ISSUES

From : Customer Consultant


From : Main Cont Others
From : erection team
Claims Issued to Date

PROJECT PROGRESS SUMMARY for the Period of -28 AUG 2012


Bldg no. PEB STEEL Panel decking Cement. Paint
over all 98.00% 98.00% 95.00%

Date : Description of Work Progress REMARKS


28-Aug-12 sector 26-additional stiffeners fixing along grid line 27/H:J @7.7m level see below picture
28-Aug-12 sector 26-addetional extension for the cantilever beam at curve area @ 7.8m level see below picture
28-Aug-12 sector 27- panel decking fixing for balance head room area-done ready for inspection see below picture
28-Aug-12 sector 26- cement paint @ 18.3m level almoayyed company
28-Aug-12 VIP lounge & cinema 6 - panel decking fixing for cinema 6 metalex trading .co
SITE COMMENTS
PHOTOS

sector 26-additional stiffeners fixing along grid line 27/H:J @7.7m leve VIP & cinema 6 - erection & panel decking progress

sector 26-addetional extension for the cantilever beam at curve area @ 7.8m level
VIP lounge & cinema 6 -erection & panel decking
progress
sector 26- cement paint @ 18.3m level sector 26- cement paint progress
sector 26- cement paint @ 18.3m level area
progress

sector

cement paint progress

sector 27- panel decking fixing for balance head room area-done ready for inspection
S.NO NAME ID NO. JOB NO.
1 Shahadadt Rafique 37 402
2 Dulal Bojendra 39 402
3 Karana Bahadur Raika 50 402
4 Manthakalai Kalamegam 95 402
5 Dola Ram Meghwal 97 402
6 Manickam Rethinam 102 402
7 Gopu Pamdi 240 402
8 Kurme Naganna 298 402
9 Manthai Raja 303 402
10 Megwal Dunfar Mal 314 402
11 Balasubramanian Durairaj 369 402
12 Mohammed Arif 375 402