Project: Power supply to Plot P18 at Zayed

Military City
Project no.: D108337 Substation: SWH38A1
Location: Plot P18, Zayed Military City

Client ADDC Site Ref. 33/11kV PU - 1 / 11kV Switchgear


Contractor Time Electro Feeder No. K01 to K09
Testing Company Alphapower Date of Test 08.06.2020
SITE ACCEPTANCE TEST REPORT FOR HIGH VOLTAGE TEST

HIGH VOLTAGE TEST

Performing the power-frequency voltage test


The transport units are already tested at the factory at rated short-duration power frequency
Withstand voltage. On the customer´s request, the dielectric strength of the switchgear can be tested on site.
This is a repeat test at 80% of the values according to IEC 62271-1.

Preparing the power frequency voltage test

DANGER!
High Voltage! Danger! If the panel feeders are included in the rated short-duration power-frequency
withstand voltage test, the panel connections are live during the test. Keep a minimum distance of 1.5
mtr to the panel connections.

ATTENTION!
 Rack-out the Voltage Transformer in Incoming Feeder.
 Earth and short-circuit all test sockets of the voltage detecting system when the test voltage
goes above rated voltage.
 Short & Earth all CT Circuit.
 For the rated short-duration power-frequency withstand voltage test, Rack-in the Circuit Breaker to
service position & switch Circuit-breaker in the First to Last panel to CLOSED Position.
 Check Capdis by injecting a small amount of voltage i.e. between 10% to 45% of Rated
Line voltage (short capdis with earth).
 Check Capdis Voltage detector is shorted with respect phase to earth when High voltage is injected
above nominal voltage
 Apply the power-frequency test voltage as per test format

TESTED BY CONTRACTOR WITNESSED /APPROVED BY


COMPANY ALPHAPOWER TIME ELECTRO ADDC
NAME JAYAPRAKASH M P

SIGNATURE

DATE 08.06.2020

SAT Report for High Voltage Page 1 of 2


Project: Power supply to Plot P18 at Zayed
Military City
Project no.: D108337 Substation: SWH38A1
Location: Plot P18, Zayed Military City

Client ADDC Site Ref. 33/11kV PU - 1 / 11kV Switchgear


Contractor Time Electro Feeder No. K01 to K09
Testing Company Alphapower Date of Test 08.06.2020
SITE ACCEPTANCE TEST REPORT FOR HIGH VOLTAGE TEST
1. INSULATION RESISTANCE TEST (BEFORE & AFTER TEST)

CONDITION: All the feeders (from K01 to K09) CB CLOSED AND IN SERVICE POSITION.

APPLIED VOLTAGE 5000 V DC, 1 MIN.

MEASURED VALUE MEASURED VALUE


TEST POINT REMARKS
(BEFORE HV TEST) (AFTER HV TEST)
R – (Y+B+E) 72.4 GΩ 86.4 GΩ OK
Y – (R+B+E) 76.9 GΩ 87.8 GΩ OK
B – (Y+R+E) 74.9 GΩ 86.0 GΩ OK

2. HIGH VOLTAGE TEST

APPLIED LEAKAGE
TEST POINT DURATION REMARKS
VOLTAGE CURRENT (mA)
R – (Y+B+E) 22.4 kV 1 min 20 WITHSTOOD
Y – (R+B+E) 22.4 kV 1 min 20 WITHSTOOD
B – (Y+R+E) 22.4 kV 1 min 20 WITHSTOOD

3. REMARKS:

4. TEST EQUIPMENT DETAILS:

Description Make Model Serial No Calibration Due Date


Insulation Tester Megger MIT 515 101365331 11.06.2020
AC High Voltage Test Kit HV Diagnostics PFT Series 1110 28.10.2020

TESTED BY CONTRACTOR WITNESSED /APPROVED BY


COMPANY ALPHAPOWER TIME ELECTRO ADDC
NAME JAYAPRAKASH M P

SIGNATURE

DATE 08.06.2020

SAT Report for High Voltage Page 2 of 2