Sunteți pe pagina 1din 13

Jurnal Ilmiah Media Engineering Vol.3 No.

3, September 2013 (214-226)

CONSIDERING THE INTEGRATED VALUE ENGINEERING AND


RISK MANAGEMENT TECHNIQUES DURING THE DESIGN
PHASE IN CONSTRUCTION PROJECTS – ITS IMPLICATIONS
TO PROJECT OBJECTIVES
(A Case Study on Certain Irrigation Projects, North Sulawesi
Province)
Mohamad Jamin Pedju
Lecturer Post Graduate Civil Engineering University of Sam Ratulangi
(Project Management Institute – PMI - Member)

Emelly Mawu
Irrigation Division of Public Works North Sulawesi Province

ABSTRACT
In encouraging of the success of irrigation projects, the implementation of value engineering
technique as well as managing risks as recognized and as important in management process
has been placed into consideration, and put those two concurrently into a single integrated
process. The integrated approach is considered to assist a clear link to achieve the project’s
objectives in terms of, in this case, time, cost, and quality. The purpose of this study is to
identify and analyze factors in conjunction with risks and value and in association with
optimal approach on the development of construction projects via design solutions during the
design and engineering phase in accordance to the project’s objectives, based on data from
questionnaires, interviews, and projects’ documentations, mostly from the respondents’
responses. Those factors are ranked in term of their effects to project time, cost, and quality.
Four factors that are related to project time, five factors linked to project cost, and two
factors associated with project quality. Other result is factors that affecting simultaneously,
as an overall to the project objectives, consists of two related with Value process and the
other three were linked to Risks. Although the findings were concerned to the implementation
of the integration of those two techniques, in accordance with improvement during the design
phase, some possible limitations are expected to exist, for example, time consuming to the
extended process. In addition, education along with training is needed to the prosperous of
the integrated approach.
Keywords: value engineering, risk management, integrated, construction project, design
phase

INTRODUCTION construction phase. Each project has certain


objectives, mostly established since the
Background beginning. During the design phase, the
Projects within the construction industry requirements of the client are identified
are subject to unique features of construction within the constructive aspects and the
activities, and by definition, “a project is a standards of quality. According to Zou et al.
temporary endeavor undertaken to create a (2008), managing risks in construction
unique product, service, or result” (PMI- projects is important while “Value
PMBOK, 2008). A project has two main methodologies can be applied during any
milestones, a definite beginning and end. stage of a project’s development cycle,
Between those two milestones, specific although the greatest benefit and resource
activities take place in a collection of savings are typically achieved early in
sequential phases in the, so called, Project development during the conceptual stages”
Life Cycle (PLC). Design is on one of those (SAVE International Value Standard, 2007
phases (design phase), prior to the edition).

214
Jurnal Ilmiah Media Engineering Vol.3 No.3, September 2013 (214-226)

It is the intention of the study to the use management during design phase, the
of value and risk management techniques in formulated problems are as follows:
a single integrated process during the design • What are those aspects in Engineering
phase in accordance with project’s Design that influence project’s objectives
performance by reaching the project’s and or performance, and
objectives. • How they relate in term of their
The study has specifically been magnitudes of importance to the project
conducted on certain irrigation projects parameter (limited to: Time, Cost, and
within the Irrigation Division of Public Quality).
Works of North Sulawesi Province and
focused on the process during the design Objective of the Research
phase. In the development of those projects, • To understand the impact of using the
especially during construction, although value and risk management on project
quality aspects were not appeared as performance
problems, by some means, there were • Quantify the relation between value and
changes concerning the design aspects as risk and multi factors model for value and
well as time extensions. In facts, the risk in project to finding the risk related to
Designers (design consultants) were not in to project’s objectives
the position of preparing such services of Many reasons for applying value and risk
value and risk management as the services management but the main reason is that it
were not supported and specifically stated in can provide significant benefits to reach the
their consultancy contracts. If the contracts project’s objectives
supported such services, the problems may
appear on the Designers’ works, as certain
skills are required to do their jobs. LITERATURE REVIEW
The research presents findings regarding
impacts in using value engineering and Comprehensive reviews and the
concurrently with risk management substantive research have been conducted to
techniques during the design phase the appropriate field of the application of
proportionally to their importance to the value and risk management techniques using
project’s objectives. Moreover, it is books and scientific articles prepared by
considered as important techniques to apply professionals.
during the design phase since the project’s
outcome could be properly measured on the PLC (Project Life Cycle) and the Design
next construction phase. Phase
Additional information to be added here Projects typically pass through a series
is that those constructed irrigation projects of phases as they move from client need to
were probably in accordance to plans and project, including engineering design phase
commitments from the client side and end as it is one of those phases. ”The life cycle
users (mostly are farmers) without doing the is the only thing that uniquely distinguishes
integrated value and risk management during projects from non-projects,” Patel and
design phase. As written on the Clients’ Morris, as in Widerman (2004), furthermore
formal reports, productions of paddy fields from the same source, the project life cycle
increases as much as twice in comparison to is the sequence of phases through which the
the production prior to the new constructed project will evolve. For the purpose of the
irrigations’ projects. study, Authors have created “sketches” as
shown below. It shows the anticipation
Problem Formulation (dotted red arrow) on project’s objectives
As in the background, in the light of during the design phase based upon the PLC
achieving the desired result of the project of Widerman (2004).
objectives by integrating Value and Risk

215
Jurnal Ilmiah Media Engineering Vol.3 No.3, September 2013 (214-226)

Figure 1. Overview of PLC and anticipation during Design to Project’s Objectives

In the design phase–design and engi- In general, as on the best authors’


neering process, all the requirements of the practices, design is a multi-step including the
client are identified within the constructive research, conceptualization etc., establishing
aspects along with the standards of quality design requirements, preliminary design,
that are defined through procedures, design development, detailed design or
drawings and technical specifications, Luis working drawings (construction documents),
F. Alarcón et al. (1998). Design is a creative and production. This multi-step is one
process, Oberlander (1993) not a routine one, among other aspects that is used as basic
therefore problems encountered are more factors to observe. Factors concerned during
complex although designing irrigation the design phase that are references to
projects, as a typical civil engineering kind implement value and risk management, for
of process, is not a pure multi-disciplinary example, preparation, methodology etc.
works, for instance, in comparison to
building projects. However, during design Value Engineering and Risk Management
phase, according to Alarcón et al. (1998), – An overview
“this important phase is usually carried out According to Dallas (2004), successful
with little interaction between the projects need value and risk management,
construction and design teams causing many value management deals with maximizing
problems during construction such as: value and risk management fulfills effective
incomplete designs, change orders, rework, project management in managing risk. Risk
construction delays, etc.” Although the is often related to the negative and cannot be
possibility of “little interaction between the controlled as an uncertainty that can cause
construction and design,” mentioned above fatalities in any situation. Risks might occur
will depend on project delivery strategies, for in any situations, as in construction projects,
example, when the delivery is using and in every construction project, most of the
construction management approach–an owners’ requirements are concerned with
overlapped design and construction phases. “time” (as soon as possible) while “cost”
In the projects observed, construction should at the level that they can afford.
activities begin upon the completion of Hence, risks should be managed properly,
design and tender processes. It is important and in accordance with the value, the project
though to provide the standards of the should be in the very best performance at the
expected contractors in the construction minimum cost as well as the shortest time in
documents and bid specifications. line with the project’s objectives.

216
Jurnal Ilmiah Media Engineering Vol.3 No.3, September 2013 (214-226)

Value Engineering (VE) where, V=value, f=function, P=performance,


“Value Engineering and Value C=Cost, t=Time, α=Uncertainty. This
Management are sometimes used equation shows the multiple scenarios for
synonymously and sometimes as though they performance, cost, instead of a single point
are different processes. What actually makes estimate. Moreover, this form is then
them different, however, is usually not inspired this study in combining and
defined” (KPK Research Digest – July 2012 integrating value and risk management as
Issue). However, the essence of Value well as “Value Study is guided by the
Engineering or Value management lie in its function-based Job Plan” (SAVE
concept of value. International Value Standard, 2007 edition).
Value engineering is known to reduce The Job plan, in value engineering
project cost, improve project quality, process, is also called as value engineering
eliminate unnecessary design elements, methodology, consists of orientation,
enforce innovation, and improving information, function analysis, creative,
productivity. VE is a systematic recognized evaluation, development, presentation, and
technique, usually by independent team to implementation. The function analysis is as
identify the function of products or services, significant and important step in the
establish the worth of that function and development of value engineering process.
generates alternatives. VE has the objectives Charles W. Bytheway (1965) at National
in reducing construction time, safety, Conference of the Society of American
operational and environmental commitments, Value Engineers (SAVE) in Boston, USA,
and reduced total costs. It may also suggest introduced classical technique called FAST
the use of innovative technologies to (Function Analysis System Technique).
improve finished quality as well as FAST approach is using three questions
considering long-term life-cycle costs. The (what is it, what does it do, and what must it
process can be broken down into four do) in analyzing each function, although it
components: applicability (when it is can be a difficult and time-consuming effort.
required), the team (who will do it), the job
plan, and reporting recommendations. The Risk Management
job plan is divided into steps, information, Risk can be explained as an uncertain
function analysis, creative (how to event, always in the future, has a cause and
accomplish the required function), evaluation effects and it affects the objectives of a
(select alternatives for development), project. In the construction projects,
development (recommend the selected discussed in the PLC, is a process, and risks
alternative), and presentation (for approval). might occur since there is no risk free during
“Value is defined as a fair return or that process. According to David Hillson, an
equivalent in goods, services, or money expert in risk management, risk management
for something exchanged” intuitively is asking and answering some
(SAVE International Value Standard, 2007 basic questions like “what,” “why” etc.
edition). Value is a function of “Function” These series of questions will be steps in
and “Cost” in an equation as follows: managing risks i.e.: risk identification,
assessment, evaluation or analysis, response,
Value ~ Function/Resources tracking-monitoring-control, and learnt. By
doing this, project can be improved in
However, Stewart et al. (SAVE International meeting its objectives. Risk management
2011 Annual Conference) introduced the may be described as “a systematic way of
“Uncertainty Modeling in Multiple looking at areas of risk and consciously
Dimensions for Value Methodology,” and “it determining how each should be treated. It is
is important to acknowledge the multiple sets a management tool that aims at identifying
of outcomes that may occur by introducing sources of risk and uncertainty, determining
uncertainty.” The value’s expression may their impact, and developing appropriate
look as the form of: management responses” (Uher, 2003, in Zou,
2008). A systematic process of risk
Vf(P,C,t)_total=(∑(P∙α)/(∑[(C∙α)+(t∙α)]), management has been divided into risk
classification, risk identification, risk

217
Jurnal Ilmiah Media Engineering Vol.3 No.3, September 2013 (214-226)

analysis and risk response, where risk techniques have been used separately Feili et
response has been further divided into four al. (2012).
actions, i.e. retention, reduction, transfer and Montanah et al (1998) created a chart of
avoidance (Berkeley et al., 1991; Flanagan “the possible interface” between risk
and Norman, 1993, in Zou, 2005). Zou also management and value management. There
identified twenty major risk factors in are four groups in risk management,
construction projects, and stated that those a. pre-study
risks spread through the whole project life b. this group consists of identification and
cycle. Risks related to designers are as categories, assessment, and preliminary
follows, design variations, variation by the risk mitigation
client, inadequate program schedule, and c. the third group is divided into risk
inadequate or insufficient site information analysis of value management
(soil test and survey report). alternatives, finalize risk, and response
strategy
The Integration of Value and Risk d. post-study
Management – during design phase then value management consists of:
According to Dallas et al (2004), (1) pre-study; (2) information phase; (3)
successful projects need value and risk function analysis; (4) creative; (5)
management, value management deals with evaluation; (6) development; (7) decision;
maximizing value and risk management (h) presentation; and (9) post-study. The
fulfills effective project management in original chart had been re-arranged for the
managing risk, even though, those purpose of simplification as in figure 2, as
follows:

Figure 2. Source: Devadass P. Montanah et al (1998) – Simplified by Authors

218
Jurnal Ilmiah Media Engineering Vol.3 No.3, September 2013 (214-226)

The simplified chart is intended to look two recognized tools can be explained, in a
at the alternatives created in value simple way, in line with the project’s
engineering job-plan steps as an important objectives, is as shown in figure 3.
“output” which is integrated to risk analysis It is also, as a kind of remainder for
in risk management process. In the original project’s team during the design phase, to
chart, the interesting part is that risk analysis keep in mind, that every construction project,
has been applied to the result of value in this case irrigation project, has no risk free
engineering alternatives. and always aware with their results in
Having reviewed all the required designing as the best alternative among all
materials regarding value and risk possible alternatives, to reach project’s
management processes, the authors found, parameter i.e., “time,” “cost,” and “quality.”
theoretically, that the integration between the

Figure 3. Integration of value engineering, risk management, and project objectives.

RESEARCH METHODOLOGY

Past research regarding the integration as in figure 5. Firstly, concerning the value-
of value engineering and risk management engineering techniques in this study, in
has been done as Karim et al (Quantity proportion to the designers’ methodology,
Surveying International Conference, 4-5 the idea is inspired using chart from SAVE
September, 2007 Kuala Lumpur, Malaysia), (2007, edition). It has focused on “value job
explored the research methodology with plan,” and the important assumptions were
procedures and process of value and risk made regarding the “alternative selection”
management used by selected organizations, and “best alternative” that they had actually
analyses the application of potential in the been practicing the value concept although it
implementation of value and risk was not as formal steps in value engineering
management. In this study, methodology method. Therefore, questionnaires were
selected, based on and started by indicating created based on the assumptions that most
the type of work as well as risk indicators or of the respondents aware of choosing “best
factors, as in figure 4. In fact, based on alternative” in any aspects concerned.
formal written documents (reports), most of Secondly, risk management as Hillson
the designers used their design methodology

219
Jurnal Ilmiah Media Engineering Vol.3 No.3, September 2013 (214-226)

(www.who.int/management/.../risk/WhenRis matters because it can affect one or more


k...), objectives.” Therefore, risks involved in this
expert in risk management, “the key is to study are assumed that matters to the
realize that risk can only be defined in project’s objectives, and those are applied to
relation to objectives. The simplest definition the main works in the design and engineering
of risk is “uncertainty that matters”, and it process.

.Figure 4. Overview - type of work and risks factors

Figure 5. Design methodology (Source: Designer/Consultant)

220
Jurnal Ilmiah Media Engineering Vol.3 No.3, September 2013 (214-226)

The research methodology has been methodology/proces, 2) actors/doers, 3)


selected using theoretical framework, and resources, 4) project management, and 5)
questionnaires, interviews, and limited regulation/standards. Function analysis,
projects’ documentations from Irrigation creative process, and evaluation are
Division of Public Works North Sulawesi considered as predictors in term of “value
Province, . The survey data were used concept” whereas each alternative is always
(mostly from the respondents’ responses) satisfied the need and its objectives, with its
and a statistical analysis of those data using wide variety of possible alternative ways to
SPSS-20. As shows on figure 6, as a model, improve the value of the project, since the
type of works consists of four main tasks i.e.: result warrant the time, cost , and quality.
preparation and data collection, preliminary Likert scale is used to measure those
and design development, working drawings, variables and is a five-point scale, 1 is
and preparation of contract documents. considered as the lowest while the highest is
Engineering cost estimate and technical 5. Main factors in risks, from 1 to 5, and the
specifications (specs) are always in touch level of impact, consist of 30 questions, 35
with those tasks. questions, 3 questions, 7 questions, and 3
Variables, independent and dependent, questions, respectively, with the total = 48
are assumed as in the model, even though questions, and the likelihood of occurrence,
there are various variables may exist. in line with value process, in term of time,
There are five main factors in risks i.e.: 1) cost, and quality.

Figure 6. Research methodology concept – theoretical framework

Sample composition degree), as technician = 60.0%, high school


The distribution of respondents consist = 4.4% (graph 1). Work experience
of educational backgroud level and work distribution (in year): 55.6% > 5, and 44.4%
experience, graduate levels = 0.00%, ≤ 5 (graph 2).
undergraduate = 35.6%, between high
school and undergraduate (technological

221
Jurnal Ilmiah Media Engineering Vol.3 No.3, September 2013 (214-226)

Graph 1 Educational background of subjects

Graph 2 Work experience (year) of subjects

RESULTS AND DISCUSSIONS

The purpose of the study is mainly to shown in figure 7, 8, and 9 respectively, and
identify and in measuring the magnitude of table 1, 2, 3…(SPSS outputs) in which
factors in considering the integration of value significance or p-value are mostly less than
and risk management during the design 5%. Although model accuracy (the highgest)
phase in construction projects, and its is in the level of 63% (graph 3), it is
implications to the project objectives, as well considered a “good” model since it is more
as its limitations as it is based upon the than average ~ 50%, thus, it is only about
observed irrigation projects. 37% that model is influenced by other
Those factors are ranked in term of their factors.
effects to project time, cost, and quality, as

222
Jurnal Ilmiah Media Engineering Vol.3 No.3, September 2013 (214-226)

Graph 3 Model accuracy

Figure 7. Factors related to project time

EFFECTs / Target: Y_T

Table 1. Factors related to TIME

223
Jurnal Ilmiah Media Engineering Vol.3 No.3, September 2013 (214-226)

Figure 8. Factors related to project cost

EFFECTs / Target: Y_C

Table 2. Factors related to COST

Figure 9. Factors related to project quality

224
Jurnal Ilmiah Media Engineering Vol.3 No.3, September 2013 (214-226)

EFFECTs / Target: Y_Q

Table 3. Factors related to QUALITY

Other result is, by looking at factors that that, as an overall, those two techniques
affecting simultaneously, as an overall, (value and risk management) are important
which are related to project objectives, when they are applied simultaneously within
shown on figure 10. It can be concluded the single process.

Figure 10. Overall project objectives – coefficients

Table 4. Factors related to Overall Project Objectives – Time_Cost_Quality

225
Jurnal Ilmiah Media Engineering Vol.3 No.3, September 2013 (214-226)

CONCLUSIONS Dallas, M. F., 2004. Value & Risk Mana-


gement – A Guide to Best Practice.
Based upon the survey with sound Blackwell-Pub.
industry practitioners as experience and Feili, H.R, Sina N., Navid A., 2012.
knowledge of construction projects are not in Integrating Risk Management and Value
its preference level, the research were Engineering in the Development of
highlighted the factors and its implications to Renewable Energy Project, 6th SASTech
achieve the desired project objectives. As 2012, Malaysia, Kuala Lumpur. 24-25
well as the integration of value and risk March, 2012. Organized by Khavaran
management to be considered to construction Institute of Higher Education.
projects as an approach during the design
phase. Gould, F. E., 2012. Managing the Construc-
The research endeavoured to identify tion Process: Estimating, Scheduling,
those factors associated with the and Project Control. 4th Edition. New
achievement of project time, cost, and Jersey: Prentice Hall.
quality on irrigation projects. “Functional Lechler, T.G., Barbara H. E., Ting G., 2012.
analysis” as “efforts” was found to have Challenging Classic Project Manage-
significant impact on the three aspects in the ment: Turning Project Uncertainties
project objectives while the further step Into Business Opportunities, December
“creative” rest as the second and last from 2012 Project Management Journal DOI:
those three steps being considered. The three 10.1002/pmj
risks seemed to be at the same level of their
Montanah, D. P., Russel P., Mike J., 1998. A
implications i.e.: risks that associated with
Strategy for Managing Project Risks in
design methodology and process, actors
Value Management, SAVE International
involved, and regulation or local standards,
Conference Proceeding
in line with value engineering process.
Moreover, responses of those risks were not Oberlender, G. D. 1993. Project Manage-
included in the research, as the intention lie ment for Engineering and Construction.
only up to the analysis and evaluation as Singapore: McGraw-Hill.
those two techniques are suggested to be in ®
PMBOK Guide – Fourth Edition, 2008.
consideration during the design phase. Licensed To: Mohamad Jamin Pedju
Responses, in term of actions to be taken, in PMI Member ID:2104990
risk management are actually important not
just its analysis and evaluation. Although the Rasmus, D. W., 2011. Management by
findings were concerned to the implement- Design: Applying Design Principles to
tation of the integration of those two the Work Experience. New Jersey: John
techniques, in accordance with improvement Wiley & Sons
during the design phase, some possible SAVE International Value Standard, 2007
limitations are expected to exist, for edition.
example, time consuming to the extended Wideman, R.M., (updated, 2004) The Role of
process. In addition, education along with the Project Life Cycle (Life Span) in
training is needed to the prosperous of the Project Management, AEW Services,
integrated approach. Vancouver, BC ©2003
Wood, D., G. Lamberson, S. Mokhatab,
REFERENCES 2008. Project execution risk manage-
ment for addressing constructability,
Akintoye, A, Jack, G. and Girma, Z., 2012. Special report – Hydrocarbon
Construction Innovation and Process Processing
Improvement. Wiley-Blackwell. Zou, P. X. W., Guomin, Z. Jia.Y.W., 2008.
Alarcón, L.F., Daniel A.M., 1998. Improving Identifying Key Risks in Construction
The Design-Construction Interface, and Projects: Life Cycle.
Stakeholder Perspectives, Proceedings
IGLC ’98.

226

S-ar putea să vă placă și