NTPC STANDARD CHECKLIST TELANGANA

O&M - COMMISSIONING DEPARTMENT


STATION: NTPC- TELANGANA, STAGE-I, 2X800 MW. UNIT :
SYSTEM : 11&3.3KV BUS DUCTS LOCATION:

RATINGS/DETAILS
EQPT. MANUFACTURER
SR NO. FRAME
DRWG CONTRACT REF
VOLTAGE KW CURRENT HZ
RATING

SPACE HEATERS

GENERAL CHECKS

S.No ACTIVITY STATUS

1. Access to the bus-bar enclosures and surrounding area is satisfactory

2. Permanent and adequate lighting is available.

3. Labelling & identification of phases is correct,easily seen and permanent

4. All insulators are tight and fitted satisfactorily

5. Insulators visually inspected for any damage,surface cracks or abnormalities

6. Check correct clearances are maintained

7. Checking of general cleanliness for bus,insulators and busduct by opening


inspection covers.

8. Check end termination tightness and clearance. Also ensure that bi-metallic
strips are provided if material of bus duct and same of bus bar are different.

9. Ensure that breathers are provided and silica gel color is blue

10. Ensure that no part of bus duct is open and supports are permanent.

11. Ensure that bus duct earthing is done properly.

12. Check all enclosure internals are clean,dry and free from any loose material.

13. Check all busbar joints are bolted &tightness is satisfactory.

14. Check for correct functioning of drain taps/plug (if fitted) for correct
opening & closing. Ensure easy accessing of these plugs.
Signatures with Name& date

CONTRACTOR NTPC Erection Dept: NTPC O&M Dept:


NTPC STANDARD CHECKLIST TELANGANA
O&M - COMMISSIONING DEPARTMENT
STATION: NTPC- TELANGANA, STAGE-I, 2X800 MW. UNIT :
SYSTEM : 11&3.3KV BUS DUCTS LOCATION:

15. Check IR value of Space heater circuit in all phases.

16. Water tightness test for out door portion by fire hose ( As per IS Standard)

17. Air Tightness test for portion of busduct i.e., from Transformer to switchgear
room entry ( As per IS Standard)
18. Ensure duct are palced on permanent supports

19. Sectionalizing of space heater circuit, Ensure power supply extension to various
sections of space heater circuit from different sources.
TESTS :
IR TEST
IR test R Y B
Phase - Phase
Phase -Earth

MILLI-VOLT DROP TEST:


Milli-volt drop test results for bus bar joints(welded joints& bolted joints)

Current Joint No./ mV Micro-ohm Remarks


injected identification

Signatures with Name& date

CONTRACTOR NTPC Erection Dept: NTPC O&M Dept:


NTPC STANDARD CHECKLIST TELANGANA
O&M - COMMISSIONING DEPARTMENT
STATION: NTPC- TELANGANA, STAGE-I, 2X800 MW. UNIT :
SYSTEM : 11&3.3KV BUS DUCTS LOCATION:

AC/DC HI-POT OF BUS-DUCT (to be done in presence of FQA):


Pre HI-POT IR HI-POT HI-POT Time Leakage Post HI-POT IR with 5kV
with 5kV phases Voltage MIN current

R-E R-(B+Y+E) R-E

Y-E Y-(R+B+E) Y-E

B-E B-(R+Y+E) B-E

R-Y R-Y

R-B R-B

B-Y B-Y

EARTH RESISTANCE: Measure and record earth resistance at


enclosure earthing points.
Earth Resistance:

Signatures with Name& date

CONTRACTOR NTPC Erection Dept: NTPC O&M Dept:


NTPC STANDARD CHECKLIST TELANGANA
O&M - COMMISSIONING DEPARTMENT
STATION: NTPC- TELANGANA, STAGE-I, 2X800 MW. UNIT :
SYSTEM : 11&3.3KV BUS DUCTS LOCATION:

DEFECTS/OMMISSIONS

s.no Description Remarks

Signatures with Name& date

CONTRACTOR NTPC Erection Dept: NTPC O&M Dept: