EQPT. MANUFACTURER
SR NO. FRAME
DRWG CONTRACT REF
VOLTAGE KW CURRENT HZ
RATING
SPACE HEATERS
GENERAL CHECKS
8. Check end termination tightness and clearance. Also ensure that bi-metallic
strips are provided if material of bus duct and same of bus bar are different.
9. Ensure that breathers are provided and silica gel color is blue
10. Ensure that no part of bus duct is open and supports are permanent.
12. Check all enclosure internals are clean,dry and free from any loose material.
14. Check for correct functioning of drain taps/plug (if fitted) for correct
opening & closing. Ensure easy accessing of these plugs.
Signatures with Name& date
16. Water tightness test for out door portion by fire hose ( As per IS Standard)
17. Air Tightness test for portion of busduct i.e., from Transformer to switchgear
room entry ( As per IS Standard)
18. Ensure duct are palced on permanent supports
19. Sectionalizing of space heater circuit, Ensure power supply extension to various
sections of space heater circuit from different sources.
TESTS :
IR TEST
IR test R Y B
Phase - Phase
Phase -Earth
R-Y R-Y
R-B R-B
B-Y B-Y
DEFECTS/OMMISSIONS