Province of Quezon
MUNICIPALITY OF JOMALIG
DETAILED ESTIMATES
CONSTRUCTION OF LOCAL CORE ROAD APAD
BRGY. APAD, JOMALIG, QUEZON
` Sub-Total 3,000.00
Profit 10% 300.00
OCM 15% 450.00
VAT 5% 187.50
TOTAL OF ITEM I = 3,937.50
UNIT COST= 3,937.50 /LOT
II.SUBGRADE PREPARATION
Estimated Quantity : AREA= 151.40 SQ.M.
A. MATERIAL EXPENSE
A1. Bill of Materials
Aggregate Base Coarse 151.40 cu.m. 1,600.00 /cu.m. 242,240.00
item 201
Coco-lumber 2x6x12 20.00 pcs 180.00 /pc 3,600.00
CWN 10.00 kls 110.00 /kl 1,100.00
A2. Material Cost 246,940.00
B. LABOR EXPENSE
B1. Manpower Composition
1 Foreman @ Php700.00/day X 12 days = 8,400.00
1 First Aider @ Php500.00/day X 12 days = 6,000.00
1 Carpenter @ Php550.00/day X 12 days = 6,600.00
8 Helper @ Php350.00/day X 12 days = 33,600.00
B2. Labor Cost 54,600.00
Sub-Total 301,540.00
Profit 10% 30,154.00
OCM 15% 45,231.00
VAT 5% 18,846.25
TOTAL OF ITEM III = 395,771.25
UNIT COST= 2,614.08 /SQ.M.
`
IV. CONCRETING
Estimated Quantity : VOLUME = 227.10 CU.M.
A. MATERIAL EXPENSE
A1. Bill of Materials
Portland Cement 1,885 bags 350.00 /bag 659,725.50
Sand 158 cu.m. 800.00 /cu.m. 126,667.30
Gravel G-1 211 cu.m. 2,000.00 /cu.m. 422,224.32
Plastic Drum 210L cap. 2.00 pcs 1,200.00 /pc 2,400.00
Deformed Bar 16mm 10.00 pcs 400.00 /pc 4,000.00
Hacksaw blade 10.00 pcs 80.00 /pc 800.00
A2.Materials Cost 1,215,817.12
B.LABOR EXPENSE
B1.Manpower composition
1 Foreman @ Php700.00/day X 18 days = 12,600.00
1 First Aider @ Php500.00/day X 18 days = 9,000.00
1 Mason @ Php500.00/day X 18 days = 9,000.00
8 Laborer @ Php350.00/day X 18 days = 50,400.00
81,000.00
C.EQUIPMENT EXPENSE
C1.List ofEquipments
1 One-bagger Concrete Mixer @ Php1,500.00/day X 12 days = 27,000.00
1 Water Truck @ Php1,500.00/day X 12 days = 27,000.00
C2. Equipment Cost 54,000.00
Sub-Total 1,350,817.12
Profit 10% 135,081.71
OCM 15% 202,622.57
VAT 5% 84,426.07
TOTAL OF ITEM IV = 1,772,947.46
UNIT COST= 7,806.90 /CU.M.
V. HEALTH AND SAFETY PROGRAM
Estimated Quantity : LUMPSUM
A.MATERIAL EXPENSE
A1. Bill of Materials
Hard Hat 11 pcs. 750.00 /pc 8,250.00
Reflectorized Vest 11 pcs. 150.00 /pc 1,650.00
Rubber Boots 6 pcs. 1,710.00 /pc 10,260.00
Safety Goggles 11 pcs. 160.00 /pc 1,760.00
Safety Gloves 11 pairs 61.30 /pair 674.27
Face Mask 11 pcs. 40.00 /pc 440.00
Caution Tape 4 rolls 160.00 /roll 640.00
A2. Materials Cost 23,674.27
Sub-Total 23,674.27
Profit 10% 2,367.43
OCM 0% -
VAT 5% 1,302.09
TOTAL OF ITEM V = 27,343.79
UNIT COST= 27,343.79 /LOT
BILL OF QUANTITIES
CONSTRUCTION OF LOCAL CORE ROAD APAD
7.92
75.5 X190
8 120 X 120
2 60 X 120
1 60 X 240
54
36
9
0
16.5
IMPLEMENTING OFFICE:_______________________________________________________
NAME OF PROJECT:___________________________________________________________
LOCATION:__________________________________________________________________
APPROVED BUDGET FOR THE CONTRACT
Stations: ________________________________
Length: ________________________________ Contract Duration: ____________________________
ITEM NO. DESCRIPTION QUANTITY UNIT ESTIMATED MARK-UPS IN PERCENT TOTAL MARK-UP VAT TOTAL INDIRECT TOTAL COST UNIT COST
DIRECT COST OCM PROFIT % VALUE COST
1 2 3 4 5 6 7 8 9 10 11 12 13
(5) X (8) 5%((5)+(9)) (9) + (10) (5) + (11) (12)/(3)
Part A Facilities for the Engineer
Total of Part A
Part B Other General Requirements
Total of Part B
Part C Earthworks
Total of Part C
Part D Sub-Base and Base Course
Total of Part D
Part E Surface Courses
Total of Part E
Part F Bridge Construction
Total of Part F
Part G Drainange and Slope Protection Structures
Total of Part G
Part H Miscellaneous Structures
Total of Part H
TOTAL
_____
Republic of the Philippines
MUNICIPALITY OF JOMALIG
Province of Quezon
SCOPE OF WORK
CONSTRUCTION OF LOCAL CORE ROAD FROM POBLACION TO SITIO MOROS
BRGY. TALISOY, JOMALIG, QUEZON
I. Mobilization/Demobilzation - this refer to the mobilization and demobilization of all heavy and/or mi-
nor equipments to be used in the above mentioned project
II. Signs and Identification - this refer to the signage printed in a tarpaulin with wooden frame to be
placed or posted in the project site for project identifications.
III. Subgrade Preparation - works undertaken herein were the clearing and grubbing,earthworks inclu-
ding compactions and other related works pertaining to preparation of subgrade
IV. Aggrregate Subbase Course - works undertaken herein were the laying,spreading, and
compacting of aggregate subbase course
V. Portland Cement Concrete Pavement- this refer to pouring of concrete,including rebarworks and
asphalt filling of the groove in the pavement.
VI.Safety Health Program- this refer to as the provision of comprehensive safety health program
of the contractor as mandated by law (see IRR of R.A. 9184), provisions of PPE's to all
workers, and other related occupational safety and health activities in the project.
VII.Temporary Facilities- this item of work refer to as the provision of the contractor of its field
office including warehouse/storage area and living quarters for their workers.
TOTAL = 378.5
sand gravel
158.33412 211.11216
PPE
PROJECT
QUANTITY RATE PER DAY DURATION Hard Hat Safety Shoes Safety Vest
Safety Officer 1.00 540.00 90.00 450.00 1,200.00 200.00
Nurse/First
Aider 1.00 500.00 90.00 450.00 1,200.00 200.00
Foreman 1.00 700.00 90.00 450.00 1,200.00 200.00
Laborer 15.00 330.00 90.00 450.00 1,200.00 200.00
Mason-
Carpenter 4.00 450.00 90.00 450.00 1,200.00 200.00
Equipment
Operator 2.00 600.00 90.00 450.00 1,200.00 200.00
PPE
First Aid
Safety Globes Goggles Kit TOTAL
50.00 200.00 50,700.00