PROJECT PLAN

Report 5
Successful completion of any project requires careful planning and execution. A large project can be
divided into subtasks, each of the subtasks can be further divided into smaller subtasks. Subtasks can be
executed independently and in parallel, several subtasks are dependent on completion of other subtasks.
Each task must be assigned to specific person(s) in the project team. The time required to complete each
task can vary. A Gantt chart shows parallel/serial tasks, the duration of each task and the person
designated to do the task.

Each task requires resources to complete therefore a tentative budget can be estimated by determining
the resources required for each task. The subtasks will also help identify the resources (components)
required which must be ordered at an appropriate time. An appropriate time margin may be considered in
the plan for any delays which may occur due to late completion of a subtask(s) or acquiring of resources.

Project controls and milestones must be established at different stages of the project plan to ensure the
quality and timely completion of the project and for any revisions in the project plan.

The following major points should be addressed when writing the report and preparing the Project Plan

 Gantt chart should identify all the subtasks, including their estimated execution time and person(s)
deputed for the entire duration of the project (FYP I and FYP II)
 All pre and post project tasks such as literature review and project report must also be shown in the
Gantt chart.
 Appropriate milestones should be identified to ensure timely completion of different stages of the
project.

Intelligent Car Parking and Security


System
Type Project Title

Hamza Ali I130524


Type Name of FYP Group Leader Type Reg. No.

Fall 16
Type Spring/Fall 15/16

Use MS Project or some other appropriate tool to draw the Gantt chart. The Gantt chart should be printed using the landscape orientation and attached as
an annexure

1. Tasks and Subtasks identified in Gantt Chart

Page 2 of 6
TASKS and their respective SUBTASKS:

 Project Proposal and Defense Presentation


 Literature Review
 Tentative Specification
 Block Diagram
 Flow Chart
 Tentative Component Selection and Software Selection
 Final Component Selection
 Project Plan and Budget
 Simulation and Coding (software based)
Car Detection and Transmission of Data
 Testing of Sensor
 Interfacing of Sensor with Microcontroller
 Microcontroller coding and Proteus Simulation
 Xbee Testing
 GUI Code
 Configuration of Keypad with Computer
 Configuration of LCD with Computer
 FYP-1 Final Presentation
 Hardware and Integration of Components
 Testing of Components
 Interfacing of Components with each other
 Power Circuit for controlling *indicator LEDs
 FYP- 2 mid Evaluation
 Final Testing and Practical Implementation

Page 3 of 6
2. Main tasks identified in Gantt Chart:

Main tasks are as follow:


 Simulation and Coding (software based)
o Car Detection and Transmission of DATA
 Sensor Testing
 Interfacing of microcontroller and sensor
 Microcontroller coding and Proteus Simulation
 GUI Coding
 Communication using Xbee
 Interfacing of Keypad and LCD with Computer(GUI)

3. Main Milestones identified in Gantt Chart:


Main tasks are as follow:
 Simulation and Coding (software based)
o Car Detection and Transmission of DATA
 Sensor Testing
 Interfacing of microcontroller and sensor
 Microcontroller coding and Proteus Simulation

Page 4 of 6
 GUI Coding
 Communication using Xbee
 Interfacing of Keypad and LCD with Computer(GUI)
 Power Circuit for controlling *indicator LEDs

*Indicator LEDs are the ones which will be connected above the car lot and which
will indicate the presence and absence of the car.

Page 5 of 6
Task Assigned To Duration Start End %

Final Year Project All Group Members 8/21/16 3/24/17 34

Project Proposal and Defense


1 All Group Members 9 8/21/16 8/29/16 100
Presentation

2 Tentative Specifications All Group Members 7 8/30/16 9/5/16 100

3 Literature Review Hamza & Adil 7 9/15/16 9/21/16 100

4 Tentative Component Selection Bilal & Hamza 16 9/16/16 10/1/16 70

5 Block Diagram Bilal & Hamza 8 9/29/16 10/6/16 100

6 Flow Chart Hamza & Adil 8 10/9/16 10/17/16 100

7 Final Component Selection Bilal & Adil 7 10/13/16 10/20/16 90

Simulation and Coding(Software


8 All Group Members 39 10/23/16 12/1/16 10
Based)

9 Project Plan and Budget Bilal & Hamza 9 11/5/16 11/14/16 100

10 FYP-1 Final Presentation All Group Members 11 11/20/16 12/1/16 0

Hardware and Integration of


11 All Group Members 55 1/15/17 3/10/17 0
components

12 FYP-2 mid evaluation Presentation All Group Members 9 2/19/17 2/28/17 0

Final Testing and Practical


13 All Group Members 14 3/11/17 3/24/17 0
Implementation

Page 6 of 6