1. Objective
Section 9 Quality System Documentation
DOC No SHE-EFCP-09-012
PAGE No 2 of 5
Procedures REV 02
DATE 01/03/201
To ensure that the plant and yard is free of superfluous and unused material and
equipment.
To ensure that everything / article has a place and everything is in its place.
2. Scope
This procedure is applicable to Esor Construction and any subcontractor who wants to
perform work on an Esor Construction premises.
3. References
5. Responsibilities
It is the responsibility of the Manager or 16.2 Appointee to ensure that suitable SHE
standards and procedures are implemented and maintained on site, and to appoint
SHE Co-ordinators with appropriate authority for implementing and maintaining the
requirements of this element.
It is the responsibility of the SHE Co-ordinators to co-ordinate, monitor and control the
various activities pertaining t the implementation and maintenance of SHE-ECP-09-012
– Factory and Yard: Tidy, in accordance with the laid down requirements.
5.4 Supervisor
It is the responsibility of the Supervisor to see that all premises are kept tidy and free
form superfluous materials.
6. Procedure
7. Training
All relevant parties and responsible persons to be trained within the contents of this
procedure. Employees to sign as proof of training and proof of training to be kept on file.
8. Records
All inspection records, registers, documents etc. must be kept on site for
record/document control and audit purposes.
9. Documents
Type of
Date Revised Revision No. Revision Details
Training
Revision #
Title:
Date of training
Duration of training