Sunteți pe pagina 1din 1

Status of Approvals & Manufacturing Clearance for OHE

items in Charkop Depot


Design Vendor Whether Manufacturing Factory Inspection
S.NO. Item Vendor Approved Material Delivery
Completion Approval Clearance provided Test
Galvanised Steel Masts,
1 Approved M/s Rukmani Yes Done Delivered
Boom, DMA, Portal & SPS
M/s OM SAI
2 Messenger Wire (65 sqmm) Approved Yes Done Delivered
UDYOG
M/s OM SAI
3 Contact wire (107 sq.mm. ) Approved Yes Done Delivered
UDYOG
M/s OM SAI
4 Bridle & Dropper Wire Approved Yes Done Delivered
UDYOG
M/s Kumar
5 Dropper assembly Approved Yes FAT call awaited
Fasterners
6 Cantilevers Approved M/s Indus Tubes Yes Done Delivered
Conventional Cantilever M/s Kumar
7 Approved Yes Done
Fittings 100% Fasterners
Automatic tensioning
8 Approved M/s Kamgar Yes Done
device
9 Composite Insulator Approved M/s Deccan Yes FAT call awaited

10 Section Insulator Approved M/s Galland Yes

11 25 kV Circuit Breaker Approved M/s ALIND Yes FAT call awaited


Yes, clarifications on Fuse
Measuring and protection
12 Approved M/s SADTEM rating will be provided by
Equipment
15.01.2020
will be provided by
13 25kV Isolators Approved M/s Elektrolites
15.01.2020

14 25 Kv Cables Approved M/s APAR Yes

Note : 1) Manufacturing Clearances of the rest of the equipments will be given by 15.01.2020.
2) Material Inspection of all the equipments will be completed by 31.01.2020.
3) All the materials for Charkop Depot OHE will be received at site by 15.02.2020.