HEAD OFFICE ELEVATOR PROGESS REPORT OF THE INSURANCE SIDE

ALOCATED
NO WORKS PERCENTAGE
1 CIVIL WORK 35
SCAFFOLDING 4
DEMOLISHING OF DOOR OPENING 10
PIT DEPTH ADJUSTMENT 2
DROPPING PLUMB LINES 2
PAINTING 3
ADJUSTMENT OF DOOR OPENING 4
FLOOR SIGNAL WORKS 3
SUPPLY AND FIX MARBLES 7
2 ERECTING GUIDE RAILS OF CAR AND CWF 16
3 CWF FRAME AND PIT SET INSTALLATION 3
4 OVER SPEED GOVERNOR GBP 2
5 LANDING DOOR INSTALLATION 12
6 CAR INSTALLATION 7
7 MACHINE INSTALLATION 8
ELECTRICAL EQUIPMENT AND SHAFT WIRING
8 INSTALLATION 7
9 COMMISSION AND ADJUSTMENT 6
10 HANDOVER 4
TOTAL COMPLETED % 100
E INSURANCE SIDE
COMPELETED
PERCENTAGE

4
10
2
2
3
4
3
4
16
3
2
12
7
8

7
4
0
91
BALCHA ABA NEFSO ELEVATOR PROGRESS REPORT
FORMAT
ALLOCATED
NO WORK DISCRIPTION PERCENTAGE
1 ERECTING GUIDE RAILS OF CAR AND CWF 26
2 LANDING DOOR INSTALLATION 20
3 ELECTRICAL EQUIPMENT AND SHAFT WIRING INSTALLA 14
4 MACHINE INSTALLATION 10
5 CAR INSTALLATION 8
6 CWF AND PIT SET INSTALLATION 5
7 TESTING AND COMMISSION 12
8 HANDOVER 5
TOTAL COMPLETED % 100
COMPELETED
PERCENTAGE