Sunteți pe pagina 1din 18

National Highways Authority Of India Cost Estimate Page 1 of 18

Summary Of Cost Estimate


Description of Items Estimated Amount
Item No. Unit Rate
Quantity (Rs.)

BILL NO-1 (ROUTINE MAINTENANCE)


1.01 Blading/grading the unpaved shoulder Sqm 50000.000 11.00 550000.00
and slopes using motor grader / power
roller / plate compactor at the required
camber as directed by the Engineer in
charge ,confirming to Technical
Specifications clause no. 3003. The work
also include disposal of surplus material
and addition of suitable confirming to
Technical specification clause No. 305.

1.02 Providing spot reconditioning, Cum 2000.000 508.00 1016000.00


reconstruction and regravelling to repair
specific erosion or other damages for
restoring the eroded area to originally
constructed cross section on cuts and fills
sloped/ shoulders confirming to Technical
Specifications clause no. 3002 same to
the original constructed cross section.
Filled material should confirm to Technical
Specification No. 305 watered and well
compacted with all leads and lifts as
directed by the Engineer (Quantity to
loose fill material shall be measured for
payment)

1.03 Providing repair to grouted stone pitching


with 1:3 cement sand mortar over the
already prepared surface/slopes of guide
bunds, river training works and road
embankments as per MOST section 2500
complete in all respects as directed by the
Engineer

a Using Boulders available at site Cum 500.000 221.00 110500.00


b Using Procured material(Granite) Cum 200.000 1110.00 222000.00
1.04 Clearing, cleaning, deepening and
reshaping of roadside unlined/kaccha
drains and making shallow kaccha lateral
drains on shoulders wherever required,
including removal and disposal of
sediments, extraneous debris and
vegetation growth blocking the free flow
from site outside ROW with all leads and
lifts complete in all respects as directed by
the Engineer in charge as per additional
maintenance standard clause No. 6.12.2
(Frequency of cleaning in urban areas will
be quarterly where as in rural it will be
twice in year).

a a) Drains having depth upto 0.6 meter Rm 45640.000 11.00 502040.00


b b) Drains having depth more than 0.6 Rm 24900.000 17.00 423300.00
meter

Operation Routine Maintenance Section NH-16(New) in the State of Odisha from Sunakhala to Ichapuram(New chainage. 513.624 to km.620.430)
National Highways Authority Of India Cost Estimate Page 2 of 18

Summary Of Cost Estimate


Description of Items Estimated Amount
Item No. Unit Rate
Quantity (Rs.)
1.05 Clearing road side/Median open lined/
pucca drains to bring them to original
shape, drainage capacity incuding
disposal of sediments, extraneous debris
& vegetation growth blocking the free flow
from site outside ROW with all leads and
lifts complete in all respects as directed by
the Engineer in charge.

a Drains having cross sectional area upto Rm 32702.000 10.00 327020.00


0.3 Sqm
b Drains having cross sectional area more Rm 7336.000 40.00 293440.00
than 0.3 Sqm
1.06 Clearing, longitudinal and transverse Rm 3300.000 249.00 821700.00
covered drains and pipe drains including
manholes, gratings, channels and gullies
etc. & bringing them to original drainage
capacity, including disposal of sediments,
extraneous debris & vegetation growth
blocking the free flow from site outside
ROW with all leads & lifts complete in all
respect as directed by the Engineer

1.07 Clearing slab/ box type culverts and pipe


culverts including clearing, cleaning and
reshapping of upstream and down stream
faces of these culverts with in right of
way. The job includes disposal of excess
material recovered from site including
vegetation outside ROW with all leads and
lifts complete in all respect as per
direction of Engineer In-Charge.
(Frequency of cleaning will be one time in
a year i.e. before start of monsoon).

a Slab Type/Box Type Culvert No 396.000 633.00 250668.00


b Pipe Culvert No 264.000 455.00 120120.00

1.08 Carrying out proper cleaning of Rmt. Of the 3600.000 122.00 439200.00
carriageways, footpaths, verges, Bridge
expansion joints (for free movement),
drainage spouts of bridge including
removal and disposal of trash, plastic,
vegetation etc. from site outside ROW
complete as per direction of Engineer
(Frequency of cleaning will be two times
in a year i.e. before and after the
monsoon).
1.09 Loading, unloading, transportation & Cum 2000.000 101.00 202000.00
disposal of surplus material left over by
accidental vehicle or otherwise lying on
road (on carriageway) with all lead & lifts
complete as directed by Engineer in
Charge.

Operation Routine Maintenance Section NH-16(New) in the State of Odisha from Sunakhala to Ichapuram(New chainage. 513.624 to km.620.430)
National Highways Authority Of India Cost Estimate Page 3 of 18

Summary Of Cost Estimate


Description of Items Estimated Amount
Item No. Unit Rate
Quantity (Rs.)
1.10 Carrying out proper cleaning & removal of
dust / silt / thrash / plastic / rubbish /
garbage / waste from the carriageways,
footpaths, verges (excluding the verges of
central median) by mechanical means
and from shoulders up to toe line of the
embankment including side slopes upto
the complete ROW manually and removal
of all debries including disposal of the
waste material at a suitable places outside
ROW as directed by the Engineer and as
per performance standard clause 6.10.
The job includes cleaning of road studs
and delineator also.

a Urban area ( Frequency of cleaning once Per Km 220.000 6964.00 1532080.00


in a month)
b Rural area (Frequency of cleaning will be Per Km 348.000 6964.00 2423472.00
quarterly).
1.11 Removal of rank vegetation/weeds and
undesirable vegetation from shoulders,
embankment slopes upto ROW (both
sides) complete in all respect including
breaking of clods,rough dressing and
disposal of waste material and vegetation
at a place outside ROW as per the
direction of Engineer Incharge and as per
performance standard clause 6.11.

a Shoulders including side slopes of Sqm. 880000.000 4.00 3520000.00


embankment up to toe line on both sides
of the carriageway. (Frequency of
cleaning will be four times in a year
however limited to only areas prone to
growth of rank / undesirable vegetation
and weeds).
b From Toe line of embankment slopes to Sqm. 60000.000 4.00 240000.00
ROW on both sides of the carriageway
(Frequency of cleaning will be two times
in a year however limited to only areas
prone to growth of rank / undesirable
vegetation and weeds).

1.12 Providing localized repair to rutted portion Sqm. 500.000 10.00 5000.00
or bituminous surface at scattered
location by applying tack coat as per
technical specification Clause 503 and
then filling the depression with bituminous
concrete by using paving grade bitumen
conforming to technical specification
clause no. 509, complete in all respect as
directed by the Engineer.

Operation Routine Maintenance Section NH-16(New) in the State of Odisha from Sunakhala to Ichapuram(New chainage. 513.624 to km.620.430)
National Highways Authority Of India Cost Estimate Page 4 of 18

Summary Of Cost Estimate


Description of Items Estimated Amount
Item No. Unit Rate
Quantity (Rs.)
1.13 Providing sealing to closely spreaded Sqm. 500.000 66.00 33000.00
cracks at scattered locations after
sweeping the surface clean and dry,
applying tack coat of emulsified bitumen
@ 0.15 ltr/sqm followed by distributing
slurry evenly in 5mm thickness prepared
by mixing emulsified bitumen 6.0 liter
with clean / dry sand / crusher dust 20
liter and water mixed to such
consistencies that it can be satisfactorily
laid. Proper rolling and compacting after
setting of the slurry sufficeintly, complete
in all respect as directed by Engineer in
Charge. The work is to be carried out as
per the additional maintenance standard
clause No. 6.12.6 and performance
standard 6.8.1.

1.14 Providing and applying low viscosity Sqm. 1000.000 34.00 34000.00
bitumen emulson for sealing cracks less
then 3mm wide or incipient fretting or
disintigration in an exiting bitumenious
surfacing complete as per MORTH
specification section 518 and as per
direction of the engineer in charge (Fog
spray).
1.15 Providing sealing cracks wider than 3mm Rmt 500.000 10.00 5000.00
using slow curing bitumen emulsen @
0.66 kg per 10 mtrs of the cracks and
stone crusher screening @ 0.0004 cum/10
mtrs complete as per direction of the
engineer incharge.

1.16 Providing treatment to bleeding Sqm. 500.000 71.00 35500.00


bituminous surface by uniform spreading
of crusher dust/other fine graded material
@ 2.5 kg per sqm, properly rolled as per
clause 3004.4 of technical specification
complete in all respect and as per
direction of Engineer.

1.17 Providing treatment and repair to pot


holes and patch repairs of all types of
bitumen pavement complete as per
technical specification Clause 3004.2 and
as per the direction of Engineer and as
per additional maintenance standard
6.12.9 and performance standard 6.8.1.
Note: The rate shall cover the
provision of Bitumen in the mix as per
job mix formula. No variation in the
rate for this item will be admissible
on account of quality of Bitumen.

Operation Routine Maintenance Section NH-16(New) in the State of Odisha from Sunakhala to Ichapuram(New chainage. 513.624 to km.620.430)
National Highways Authority Of India Cost Estimate Page 5 of 18

Summary Of Cost Estimate


Description of Items Estimated Amount
Item No. Unit Rate
Quantity (Rs.)
a Carrying out patchrepair with bituminious Sqm 500.000 163.00 81500.00
concrete up to 25 mm thickness after
removal of all failed material trimming of
completed excavation to provide firm
vertyical faces , cleaning surface, painting
of tack coat on the sides & base
excavation as per the clause no. 503 back
filling the patch with hot bituminous
concrete as per clause no. 509.
Compacting trimming and finishing the
surface to from a smooth contineous
surface all as per clause no. 3004.2 of
Technical Specification.

b Carrying out patch repair with sqm 500.000 404.00 202000.00


bitumenous concrete up to 40 mm
thickness after removal of all failed
material, trimming of completed
excavation to provide firm vertical faces,
cleaning of surface, painting of tack coat
on the sides & base of excavation asper
clause no. 503 back filling the patch with
hot bitumenous material as per clause no.
509. Compacting trimming & finishing the
surface to form a smooth continuous
surface all as per clause no. 3004.2 of
Technical Specification.

c Filling pot holes and patch repairs sqm 500.000 858.00 429000.00
beyound 40 mm thickness after removal
of all failed material, trimming of
completed excavation to provide firm
vertical faces, cleaning of surface,
painting of tack coat on the sides & base
of excavation asper clause no. 503 back
filling the patch with hot bitumenous
material as per clause no. 509.
Compacting trimming & finishing the
surface to form a smooth continuous
surface all as per clause no. 3004.2 of
Technical Specification.

1.18 Providing and fixing position HYSD Mt 1.000 59466.00 59466.00


reinforcement in abutment, pier,
superstructure, crash barrier and in other
structure complete as per technical
specification section 1600 and as directed
by the Engineer.
1.19 Earthwork in excavation necessary for Cum 1000.000 127.00 127000.00
construction of roadway / structures
including all laeads and lifts complete as
per Technical Specifications Clause No.
301 and 304 duly watered, rolled and
compacted as per direction of Engineer in
charge (All type of soil).

Operation Routine Maintenance Section NH-16(New) in the State of Odisha from Sunakhala to Ichapuram(New chainage. 513.624 to km.620.430)
National Highways Authority Of India Cost Estimate Page 6 of 18

Summary Of Cost Estimate


Description of Items Estimated Amount
Item No. Unit Rate
Quantity (Rs.)
1.20 Construction of Footpaths/ separators/ Sqm 200.000 900.00 180000.00
traffic Islands by Providing 150 mm thick
compacted GSB as per MORTH Section
401 & 25mm thick cement concrete grade
M-15 base over laid with 25 mm thick M-
20 precast cement concrete chequred tiles
in cement mortar 1:3. The joints of the
tiles to be bonded and finished with neat
cement slurry complete in all respect as
per the direction of Engineer.

Operation Routine Maintenance Section NH-16(New) in the State of Odisha from Sunakhala to Ichapuram(New chainage. 513.624 to km.620.430)
National Highways Authority Of India Cost Estimate Page 7 of 18

Summary Of Cost Estimate


Description of Items Estimated Amount
Item No. Unit Rate
Quantity (Rs.)
1.21 Repair involving removal of old joint RM 3000.000 87.00 261000.00
sealant and sealing with fresh sealant in
cement concrete pavement as per
cl.602.2.8 & 602.11.2 of MOST technical
specification.
1.22 Repairs of cracks by epoxy over PQC RM 1000.000 314.00 314000.00
panels including cutting to size and repair
by applyiing epoxy of approved quality as
per the direction of the Engineer In
Charge.
1.23 Patch repair of damaged PQC slab Sqm 300.000 2655.00 796500.00
including cutting and removing upto 100
mm thickness of existing damaged slab,
laying of aproved quality of epoxy mortar
or Epoxy concrete and relaying upto100
mm thick cement concrete as per
Technical Specification Clause 602 and as
directed by the Engineer.

1.24 Dismantling of the damaged panels of Cum 100.000 6475.00 647500.00


PQC and relaying with aproved quality of
epoxy mortar or Epoxy concrete for Rigid
Pavement as per Technical Specification
Clause 602 and as directed by the
Engineer.
1.25 Providing and applying tack coat with Sqm 4375.000 10.00 43750.00
bitumen emulsion using emulsion
pressure distributor at the rate of 0.20 kg
per sqm on the prepared
bituminous/granular surface cleaned with
mechanical broom(2.0 to 2.5 kg per 10
sqm on bituminous surface).

1.26 Providing renewal coat of 40 mm Cum 300.000 10248.00 3074400.00


thickness with bituminous concrete using
60/70 grade or equivalent grade bitumen
including cleaning of existing bituminous
surface as per Technical Specifications
(Part I / II) Clauses 512 & Section 3000
to the areas of the existing carriageway
as per the directions of the Engineer.

Total of Bill No: 1 19322156

Operation Routine Maintenance Section NH-16(New) in the State of Odisha from Sunakhala to Ichapuram(New chainage. 513.624 to km.620.430)
National Highways Authority Of India Cost Estimate Page 8 of 18

Summary Of Cost Estimate


Description of Items Estimated Amount
Item No. Unit Rate
Quantity (Rs.)
BILL NO-2 (ROAD PROPERTY MANAGEMENT & MAINTENANCE)
2.01 Providing planting healthy well developed Each 27559.000 103.00 2838577.00
saplings of ornaments flowering shurbs of
specified species and varities 1-2 years of
age in 25 c m- 30 cm poly bags or
pots,height and spread 0.60 mt-0.90 mt
above ground,with 3-4 branches,in well
prepared pits of minimum 60 cm dia and
minimum 60 cm deep refilled with good
earth mixed with 1/3rd volume of organic,
farm yard, manure/sludge and antitermite
insecticdes & water conserving
polymergel.Development period for
planting the new plants will be two
months during which
watering,weeding,hoeing,manuring,sprayi
ng of insecticides/fungicide, training and
pruning,replacement of casualties, if any,
will be carried out by the contractor and
the expenditure in this period will be
incidental to the main work of planting
new plants.

2.02 Maintenance of new plantation by basin Each 0.000 19.00 0.00


making weeding- Hoeing, cleaning ,
levelling and dressing of median uprooting
and removal ROW regularly to keep the
median clean and plantation in healthy
and good condition. The job also includes
the following activities of work ( a to e).

a Watering of each plants as and when


required depending upon the climatic
conditionsof the locality / region /
season / strictly as per direction of
engineer in charge. Km.Length of
maintenance will be decided considering
density of existing plants/shrubs in
healthy,good and surviving condition. The
casuality/damage to any plant/shrub
during maintenance period will be the
entire reaponsibility of the contractor shall
replace the dead & damaged
plants/shrubs at his own cost with new
plants of the same species,varieties,age
and size etc.

b Application of FYM or sludge @ 1/2 cuft or


10 Kg/plant two times a yearduring
february / march and October / November
plus 20 grams of NPK(12:32:16) or
Bonemeal per plants two times a year as
detailed above.

c Application of insecticide / pesticide /


fungicide etc for control of insects pests
and diseases as and when required as per
direction of engineer.
d Trimming and pruning of all shurbs /
plants as and when required to give them
required shape , size and spread.

Operation Routine Maintenance Section NH-16(New) in the State of Odisha from Sunakhala to Ichapuram(New chainage. 513.624 to km.620.430)
National Highways Authority Of India Cost Estimate Page 9 of 18

Summary Of Cost Estimate


Description of Items Estimated Amount
Item No. Unit Rate
Quantity (Rs.)
e Replacement of dead , damaged plants
from the median by healthy & well
developed plant of similar species ,
varieties , age and size etc within 10
days of occurrence of casuality as
noticed / reported or as directed by the
engineer.
2.02 Maintenance of median and the new(item Km/Month 1906.740 12369.00 23584467.06
no.2.01) & existing plants in it (with a
density of 666 plants per Km.) by basin
making weeding- holeing then cleaning ,
levelling and dressing of median uprooting
and removal of weeds cutting grass
disposal of all muck outside ROW
regularly. (a to e).

a Watering of each plants as and when


required depending upon the climatic
conditionsof the locality / region /
season / strictly as per direction of
engineer in charge. Km.Length of
maintenance will be decided considering
density of existing plants/shrubs in
healthy,good and surviving condition. The
casuality/damage to any plant/shrub
during maintenance period will be the
entire reaponsibility of the contractor shall
replace the dead & damaged
plants/shrubs at his own cost with new
plants of the same species,varieties,age
and size etc.

b Application of FYM or sludge @ 1/2 cuft or


10 Kg/plant two times a yearduring
february / march and October / November
plus 20 grams of NPK(12:32:16) or
Bonemeal per plants two times a year as
detailed above.

c Application of insecticide / pesticide /


fungicide etc for control of insects pests
and diseases as and when required as per
direction of Engineer.
d Trimming and pruning of all shurbs /
plants as and when required to give them
required shape , size and spread.

e Replacement of dead , damaged plants


from the median by healthy & well
developed plant of similar species ,
varieties , age and size etc within 10
days of occurrence of casuality as
noticed / reported or as directed by the
Engineer.
2.03 Supplying and turfing with live ande Sqm 2000.000 37.00 74000.00
perinnal turforming grass on embankment
slopes, verges medians and other
locations conforming to Technical
Specification clause 307 including
watering and maintaining for entire
contract period with periodical mowing
complete in all respects as directed by the
Engineer in charge.

Operation Routine Maintenance Section NH-16(New) in the State of Odisha from Sunakhala to Ichapuram(New chainage. 513.624 to km.620.430)
National Highways Authority Of India Cost Estimate Page 10 of 18

Summary Of Cost Estimate


Description of Items Estimated Amount
Item No. Unit Rate
Quantity (Rs.)
2.04a White wash/ cement paint/ snowcem in Sqm 500.000 11.00 5500.00
two or more coats to give an even shade
and smooth surface for protection of
exposed concrete/masonary portion of
Bridges/CD works, kerb and wheel guard
including scraping of damage paint from
old surface and repairing of the existing
surface whereever necessary complete as
directed by the Engineer incharge.

2.04b Finishing walls with exterior decorative Sqm 250.000 26.00 6500.00
cement based paint such as snowcern on
old work, two coats to give an even shade
after repairing of defects so as to achieve
smooth and defects free surface.

2.05 Painting with higloss synthetic enemal Sqm 14256.000 50.00 712800.00
paint two coats to give an even and
smooth surface for protection of exposed
concrete/masonary portion of Bridges/CD
works/ parapet, kerb painting and
repairing wherever necessary, complete
as per approval of Engineer in charge.

2.06 Cleaning, removing, clearing of dust and Rm 30000.000 3.00 90000.00


dirt from the existing metal crash barrier
and pedestrian guard rail by washing with
water & detergent etc. complete as
directed by Engineer.
2.07 Carrying out routine maintenance to all
types of road signs complete as directed
by the Engineer and as per Additional
Maintenance Standard clause 6.12.3.
Cleaning, removing, clearing of dust and
dirt from the existing Sign boards by
washing with water & detergent etc.
complete as directed by Engineer.

a Road sign boards mounted on single post. No 436.000 22.00 9592.00

b Road sign boards mounted on double No 563.000 33.00 18579.00


post.
c Overhead gantry road sign boards No 28.000 560.00 15680.00

2.08 Carrying out routine maintenance to all


types of road signs complete as directed
by the Engineer and as per additional
maintenance standard clause 6.12.3

a) Road sign Boards mounted onsingle No 170.000 369.00 62730.00


post
b) Road Sign Boards Mounted on double No 162.000 611.00 98982.00
post
2.09 Painting two coats on old surface after
minor repairs to give an even and smooth
surface and printing letters and figures
with 1st quality synthetic enamel paint of
approved brand and manufacture
complete in all respect conforming to
respective IRC specification.

A) Hectometer Stones Sqm 600.000 18.00 10800.00


B) Kilometer Stones Sqm 268.000 41.00 10988.00
C)5th Kilometer stones Sqm 152.000 84.00 12768.00
Operation Routine Maintenance Section NH-16(New) in the State of Odisha from Sunakhala to Ichapuram(New chainage. 513.624 to km.620.430)
National Highways Authority Of India Cost Estimate Page 11 of 18

Summary Of Cost Estimate


Description of Items Estimated Amount
Item No. Unit Rate
Quantity (Rs.)
D) Boundary Stones Sqm 1052.000 20.00 21040.00
2.10 Providing and fixing reinforced cement
concrete M-15 grade and 5th kilometer
stones and hectometer stones of standard
desing as per IRC -8-1980 & MORTH
specification clause 804 including two coat
painting with synthetic enamel paint after
applying approved.

A) Hectometer Stones No 200.000 436.00 87200.00


B) Kilometer Stones No 50.000 1644.00 82200.00
C)5th Kilometer stones No 10.000 2750.00 27500.00
D) Boundary Stones No 200.000 450.00 90000.00
2.11 Painting two coats with first quality No 656.000 7.00 4592.00
enamel paint of approved make & quality
to give an even shade including writing ,
letter & figure etc.complete in all respect
as per IRC standard specification (Printing
letters of Cross Drainage Nos.).

2.12 Replacement of damaged single faced W-


Beam metal crash barrier made out of the
following members. Job includes taking
out old damged member and neatly
refixing the new member (with cement
concrete foundation in M-20 for post
complete in all respects as per MoST
Clause 810 and as directed by Engineer in
Charge including Fasterners and fixing etc
complete in all respect.

a Beam made out of cold rolled steel strip W Rm 500.000 589.00 294500.00
profile of 3 mm thick having a minimum
yield strength of 2400 kg/sqcm having
width of 313 mm and depth of corrugation
as 83 mm hot dip galvanized of zinc
coating @ 550 gm/sqm.

Operation Routine Maintenance Section NH-16(New) in the State of Odisha from Sunakhala to Ichapuram(New chainage. 513.624 to km.620.430)
National Highways Authority Of India Cost Estimate Page 12 of 18

Summary Of Cost Estimate


Description of Items Estimated Amount
Item No. Unit Rate
Quantity (Rs.)
b Post consisting of cold rolled channel 150 No 300.000 1744.00 523200.00
x 75 x 5 mm having minimum yield
strength of 2400 kg/sqcm.The total length
of post shall be 1900 mm and minimum
height of post above M 20 concrete
foundation shall be 800 mm hot dip
galvanized of zinc coating @550 gm /sqm.
The post shall be fixed in M-20 Grade of
cement concrete in a pit of size
350x350x1200 mm as per drawing and
instruction of Engineer. No separate
payment would be made for concreting.

c Space channels or brackets made out of No 300.000 419.00 125700.00


CRP steel channel section 150 x 75 x 5
mm having an yield strength of 2400
kg/sqcm.The length of spacer channel
shall be 330 mm and hot dip galvanized
having zinc coating @ 550 gm/sqm.

d Fasteners button head bolts 16 x 40 mm No 6500.000 16.00 104000.00


long , with nut and washer hot dipped
galvanized.
2.13 Replacing damaged / broken railing with
new precast / cast in situ, concrete railing
to match with existing design and
pattern , made out of cement concrete of
appropriate grade and required
reinforcement including proper curing,
painting and complete in respects as per
MoST Clause 810 and as directed by
Engineer in Charge including Fasterners
and fixing etc complete in all respect.

a) New Bridges and Old Bridges in RCC M- Rm 200.000 1825.00 365000.00


30
Total of Bill No: 2 29276895

Operation Routine Maintenance Section NH-16(New) in the State of Odisha from Sunakhala to Ichapuram(New chainage. 513.624 to km.620.430)
National Highways Authority Of India Cost Estimate Page 13 of 18

Summary Of Cost Estimate


Description of Items Estimated Amount
Item No. Unit Rate
Quantity (Rs.)
BILL NO-3 (ENGINEERING IMPROVEMENT)
3.01 Replacement of stolen/missing retro-
reflectorised traffic sign boards by
providing and fixing new retro-
reflectorised cautionary, mandatory and
informatory sign as per ASTM D 4956-04
made of high intensity grade
Microprismatic sheeting Type-IV, fixed
over aluminium sheeting 2.0 mm thick
supported on aluminum composite panels
with durable PVDF(Fluororesin) resin as a
composite structure of
40mm*40mm*4mm.This frame is
75mm*75mm*6mm size, 3.5 mts high
vertical post complete as per drawing and
as per the directions of the Engineer.

a (i) Advance direction, Destination , No 38.000 28486.00 1082468.00


Reassurance and place identification sign
(size 2100mm x 1700mm),Help line
boards, as per drawing with two vertical
posts embeded in M15 Cement concrete
details as per description given above and
as per drawing.

(ii) Facility Information sign 800mm x No 40.000 5187.00 207480.00


600 mm.
b (i) Supplying and fixing sign boards No 100.000 4603.00 460300.00
complete as per Technical Specifications
Clause 801 and as directed by Engineer,
including the cost of posts, fitting & fixing.
Sheeting shall be retro reflective type of
high intensively grade and messages
/borders- Cautionary/Warning signs,
triangular of side 900 mm

c (i) Mandatory/Regulatory signs(STOP), No 50.000 6430.00 321500.00


Octagon of side 900 mm

(ii) Mandatory/Regulatory signs, Circular No 40.000 3899.00 155960.00


600 mm
d Supplying and fixing sign boards complete
as per Technical Specifications Clause 801
and as directed by Engineer, including the
cost of posts, fitting & fixing. Sheeting
shall be retro reflective type of high
intensively grade and messages /borders.

(i) Direction/ place identification sign No 20.000 6380.00 127600.00


(1200 mm x 700 mm).
(ii) Advance direction/Destination/ No 20.000 11051.00 221020.00
Reassurance/Place Identification sign-
(1500mm x 900 mm)
(iii) Route marker signs (450mm x No 100.000 3546.00 354600.00
600mm) & Chevron boards of size
450mmx600mm.
(iv) Hazard Marker sign (Size.300mm x No 544.000 2999.00 1631456.00
900mm)

Operation Routine Maintenance Section NH-16(New) in the State of Odisha from Sunakhala to Ichapuram(New chainage. 513.624 to km.620.430)
National Highways Authority Of India Cost Estimate Page 14 of 18

Summary Of Cost Estimate


Description of Items Estimated Amount
Item No. Unit Rate
Quantity (Rs.)
3.02 Supplying and installation of delineators Each 880.000 1117.00 982960.00
(Road way indicators) 95 cm high above
ground level of total length 135 cm
painted black and white in 15 cm wide
strips, fitted with 3 nos. rectangular
microprismatic reflective sheeting fixed on
2 mm thick alluminium sheet of size 80
mm x 100 mm one in each black strip
duly riveted in the rectangular tubular
section facing direction of traffic.
Rectangular tubular section of size 100
mm x 50 mm x 3 mm (Thickness) the
tubular section of the delineator is
encased all around with steel weided wire
mesh of thickness 2.5 mm, in size 120 x
70 mm x 760 mm as shown in the
drawing. The welded wiremesh is painted
with two coats synthetic enamel white
paint after applying two coats synthetic
enamel white paint after applying two
coat red oxide primer. The delineator is
embeded in M-15 cement concrete in pit
size 300 mm x 300 mm x 450 mm. the
ate quoted is further complete job.

3.03 P/F Cats Eye / Pavement Marker (NMC No 20420.000 232.00 4737440.00
nail less):- Made out of Acryliv-strene-
Acrylonitril or Hi-impact polystyrene fitted
with Moulded of Methacrylate (NMC)
reflector cube corner reflector design;
Filled with tightly adhering potting
compound as per ASTM.

3.04 Providing and fixing retro-reflective No 25000.000 12.00 300000.00


stickers (Engineering grade) of size 10cm
X 5cm on structures and where necessary
at site as per MoST Cl No. 801 and as per
approval of Engineer in charge.

3.05 Providing and marking of hot applied Sqm 14674.000 564.15 8278337.10
thermoplastic compound 2.5 mm thick
including reflectorising glass beads @ 250
gms/ sqm area, thickness of 2.5 mm is
exclusive of surface applied glass beads
as per IRC 35. The finished surface to be
level, uniform and free from streaks and
holes complete in all respect. The jobe
includes marking of centre line, shoulder
line then edge line, zebra crossing
marking, arrows and dashes marking at
the junctions as per the technical
specification clause No. 803.4 complete in
all respect and as per approval of
Engineer in Charge.

3.06 Construction and laying Cast in situ Rm 400.000 394.00 157600.00


cement concrete kerb in M 20 grade and
matching with the existing kerb section
complete including dismantling and
disposal of existing damaged broken
kerbs as per technical Specifications
Clause 408 for kerbs (M-20 Grade).

Operation Routine Maintenance Section NH-16(New) in the State of Odisha from Sunakhala to Ichapuram(New chainage. 513.624 to km.620.430)
National Highways Authority Of India Cost Estimate Page 15 of 18

Summary Of Cost Estimate


Description of Items Estimated Amount
Item No. Unit Rate
Quantity (Rs.)
3.07 Repairing of damaged kerb after Rm 2000.000 141.00 282000.00
dismantling of the kerb upto minimum of
100mm and making good the section with
M-20 concrete to match with the existing
section including form work , curing ,
painting with two coats of first quality
synthetic enamel paint etc. complete in
all respect conforming to relevant MOST
clauses and as per the direction of
Engineer.
3.08 Providing and fixing 1.8 metres high GI Rm 400.000 276.00 110400.00
barbed wire fencing with 2.4m angle iron
posts 50mm x 50mm x 6mm placed every
3 metres center to center founded in M15
grade cement concrete,in pit size of 225
mmx225 mmx600 mm below ground
level, every 15th post, last but one end
post and corner post shall be strutted on
both sides and end post one side only and
provided with 12 horizontal lines wires,
fixed with GI staples,turn buckles etc.
complete as per drawings and technical
specifications clause no.807.

3.09 Providing and fixing single faced W-Beam Rm 1000.000 3196.00 3196000.00
metal crash barrier (W-Profile safety
guard rails) made out of the following
members. Job includes erection complete
in all respect as per MOST clause 810 and
using M-20 grade cement concrete
wherever required.

Beam made out of cold rolled steel strip W


profile double of 3 mm thick having a
minimum yield strength of 2400 kg / sq
cm having width of 313 mm and depth of
corrugation as 83 mm hot dip galvanized
of zinc coating @ 550 gm / sqm.

Post consisting of cold rolled channel 150


x 75 x 5 mm and spaced 2 mtr centre to
centre having minimum yield strength of
2400 kg/sqcm. The length of post shall
be 1900 mm and minimum height of post
above concrete foundation shall be 800
mm, hot dip galvanized of zinc coating
@550 gm / sqm. The post shall be fixed
in M20 grade of cement concrete in a pit
of size 350 x 350 x 1200 mm as per
drawing and instruction of the Engineer.
No separate payment would be made for
concreting. Minimum height of the post
above concrete foundation shall be 800
mm.

Spacer channels or brackets made out of


CRP Steel Channel Section 150 x 75 x 5
mm having an yield strength of 2400 kg /
sq. Cm. The length of spacer channel
shall be 330 mm and hot dip galvanized
having zinc coating @550 gm / sqm.

Operation Routine Maintenance Section NH-16(New) in the State of Odisha from Sunakhala to Ichapuram(New chainage. 513.624 to km.620.430)
National Highways Authority Of India Cost Estimate Page 16 of 18

Summary Of Cost Estimate


Description of Items Estimated Amount
Item No. Unit Rate
Quantity (Rs.)
Fasteners, Button head bolts 16 x 40 mm
long and 20 x 40 mm Hex. Bolt, nut and
washer, hot dipped galvanized inlcuding
tack welding to the bolt.
3.10 Removal of encroachment of ROW Sqm 10000.000 82.00 820000.00
including cost of dismantaling,liasioning
with local authorities,transportation of
debries etc complete as per the dirctions
of the Engineer in charge.
3.11 Supplying and fixing overhead signs No 7.000 392840.00 2749880.00
complete as per Drawings and Technical
Specifications Section 800 including cost
of posts, truss, erection, fitting and
foundations. Sheeting shall be retro
reflective type of high intensity grade and
messages/borders shall be screen-printed.
Simply supported overhead sign
complete:
a Supplying and fixing of Aluminum Sqm 156.170 5505.00 859715.85
sheeting complete as per Drawings and
Technical Specifications Section 800 .
Sheeting shall be retro reflective type of
high intensity grade and
messages/borders shall be screen-
printed(Including all miscellaneous costs).

b Supplying and fixing overhead signs Kgs 589.000 80.00 47120.00


complete as per Drawings and Technical
Specifications Section 800, for beam truss
erection on Simply supported overhead
sign complete (Including all miscellaneous
costs).
3.12 Fixing of Solar LED Blinker light at Median No
cut comprises 12" dia LED Yellow blinker
(Cost including excavation, concreting,
fixing and all other miscellaneous charges
and taxes) and as directed by the
Engineer.

3.13 Providing and fixing new MS railing / pipe Rmt 200.000 3018.00 603600.00
railing for medians / horizontal curves
including foundation concrete 9.45 cm x
45 cm x 75 cm x in M-15) and two coat
painting with first quality synthetic
enamel paint after applying two coat
metallic primer of approved quality. The
job includes dismantling of existing
damaged railing and the rate quoted
should be inclusive of the salvage value of
dismantled material, if any, complete as
per technical specification 300, 1500,
1700 and 1900 drawing and direction of
Engineer.

Total of Bill No: 3 27687437

Operation Routine Maintenance Section NH-16(New) in the State of Odisha from Sunakhala to Ichapuram(New chainage. 513.624 to km.620.430)
National Highways Authority Of India Cost Estimate Page 17 of 18

Summary Of Cost Estimate


Description of Items Estimated Amount
Item No. Unit Rate
Quantity (Rs.)
BILL NO-4 (INCIDENT MANAGEMENT)
4.01 Removing all types of broken Per month 48.000 76000.00 3648000.00
down/vehicles which have met with
accidents from the carriageway and toeing
the same to proper locations i.e. nearest
Police Stations or some suitable location
by using 15 tonne or of more capacity
pick and carry crane, as per the
requirement of the incident and as per
Clause 6.4 of Scope of Work and as per
Clause 6.8 'Performance Standard' of
scope of work. The crane shall be
equipped with precise Vehicle Tracking
System (VTS) (of reputed ISO 9001
company) based on Global Positioning
System (GPS) and GSM/GPRMS
technology. The system shall include
micro, live, real time tracking web based
software through which use of GIS maps
and transit, stoppage idle, over speed
reports of vehicle shall be obtained. 2
Vehicles.

4.02 Patrolling by route petrol vehicle as per Per month 48.000 156906.00 7531488.00
Clause 6.4 of scope of work and as per
Clause 6.8 and 6.8.3 of performance
Standard of scope of work. The route
patrol vehicle shall be equipped with
precise vehicle tracking system (VTS) and
facility of GPS and GSM/GPRMS
technology on each vehicle of reputed ISO
9001 company. The system shall include
micro,live,real time tracking web based
software through which use of GIS maps
and transit, stoppage idle, over speed
reports of vehicle shall be obtained.
2Vehicles

4.03 Provision of Ambulance as per Claseu 6.4 Per month 48.000 140000.00 6720000.00
of Scope of Work and as per Clause 6.8
and Clause 6.8.3 'Performance Standard'
of Scope of Work. The ambulance shall be
equipped with precise vehicle tracking
system (VTS) and facility of GPS and
GSM/GPRMS technology on each vehicle
of reputed ISO 9001 company. The
system shall include micro,live,real time
tracking web based software through
which use of GIS maps and transit,
stoppage idle, over speed reports of
vehicle shall be obtained. 2Vehicles

Operation Routine Maintenance Section NH-16(New) in the State of Odisha from Sunakhala to Ichapuram(New chainage. 513.624 to km.620.430)
National Highways Authority Of India Cost Estimate Page 18 of 18

Summary Of Cost Estimate


Description of Items Estimated Amount
Item No. Unit Rate
Quantity (Rs.)
4.04 Removing the Dead Animals lying on the Per month 48.000 24699.00 1185552.00
Highway and burying them at proper safe
locations outside RoW complete in all
respect with all lead and lifts as per
Clause 6.8 'Performance Standard' of
scope of work and as per direction of the
Engineer.

4.05 Supply of colour photographs in three Per set 24.000 300.00 7200.00
copies and two CDs complete as per
Technical specification clause 125
4.06 Supply of Vedio Cassette (CD) in three Per set 3.000 2000.00 6000.00
copies including videography of complete
stretch at three stages in O&M period
complete as per Technical specification
clause 126
4.07 Providing and supply of following
manpower for misc. work as and when
required basis as per instruction of
Engineer.
(a) Unskilled Per Day 1440.000 150.00 216000.00
(b) Semi Skilled Per Day 1440.000 170.00 244800.00
(c) Skilled Per Day 480.000 190.00 91200.00
Total of Bill No: 4 19650240
BILL NO 5-( MISCELLANEOUS ITEMS)
5.01 Providing Vehicle for the Month 0.000 0.00 0.00
Employer(Passenger car type, like Innova
model).
5.01 Providing Following equipments in running
condition on hire basis including running
and maintenance charges as per
instructions of the Engineer including
P.O.L. complete as per specification.

a Tipper 5 Cum Capacity Per Hour 1500.000 582.00 873000.00


b JCB Per Hour 2200.000 840.00 1848000.00
c Tractor with trolly Per Hour 1000.000 395.00 395000.00
5.02 Providing and placing in proper position No 8000.000 20.00 160000.00
empty cement bags filled with local earth
to control erosion / damage of the side of
the road or bank of the river / nallha at
required locations including cost of
material, labour equipment transporation
etc.
Total of bill no: 5 3276000
Total of bill no: 1 to 5 (Rs) 99,212,728
Name of Firm with Address

Quoted per centage above / below the overall contract


amount applicable for all items of work in the contract
in words
Quoted per centage above / below the overall contract
amount applicable for all items of work in the contract
in figures
Contract Value calculated after quoted percentage
above / below in words

Contract Value calculated after quoted percentage


above / below in figures

Operation Routine Maintenance Section NH-16(New) in the State of Odisha from Sunakhala to Ichapuram(New chainage. 513.624 to km.620.430)