Documente Academic
Documente Profesional
Documente Cultură
Overhead % 8%
Profit % 10%
VAT & Tax: % 6.00%
Cement bag 450.00
Bricks Nos 8.50
Re Bar MT 54,000.00
Binding wire Kg 120.00
MS Angle, channel, plates MT 55,000.00
Filing Sand cum 706.00
Sand(F.M 1.2) cum 1,235.00
Sand(F.M 2.5) cum 2,047.00
Stone Chips cum 5,649.00
Brick Chips cum 2,824.00
Breaking Charge of Khoa cum 353.00
Ordinary labor/General labour Each 400.00
Skilled labor Each 450.00
Head Mason Each 550.00
Mason Each 550.00
Equipment charge Each 2,500.00
Hire Charge of Vibrator Each 1,500.00
Cost of wood, bamboo props etc cum 19,420.00
Cost of Form work sqm 5,912.00
White Cement Kg 30.00
Wall Tiles-(BSRM Supply) sqm 645.00
Floor Tiles-(BSRM Supply) sqm 645.00
3mm glass panes sqm 490.00
Enamel Paint sqm 140.00
CGI Sheet kg 95.00
Page 1 of 41
Item
1 Excavation ( very soft/ saturated/organic type soil)
No
Tk, 220.50
Overhead 8% Tk, 17.64
Tk, 238.14
Add Profit 10% Tk, 22.05
Tk, 260.19
VAT & Tax 6.00% Tk, 16.61
Tk, 276.80
Item
1.2 Backfilling
No
By excavated earth
Ordinry Labor for filling including local carriage 0.2830 Nos @ Tk, 400.00 Each Tk, 113.20
Skilled Labor for dressing 0.0710 Nos @ Tk, 450.00 Each Tk, 31.95
Sundries, Tools & Equipments etc LS Tk, 3.00
Tk, 148.15
Overhead 8% Tk, 11.85
Tk, 160.00
Add Profit 10% Tk, 14.82
Tk, 174.82
VAT & Tax 6.00% Tk, 11.16
185.98
By filling sand
Sand (considering 30% compaction) 1.3000 cum @ Tk, 706.00 Per cum Tk, 917.80
Head Mason 0.0440 Nos @ Tk, 550.00 Each Tk, 24.20
Ordinary Labor for leveling & others 0.2360 Nos @ Tk, 400.00 Each Tk, 94.40
Sundries and other accessories LS Tk, 10.00
Page 2 of 41
Tk, 1,046.40
Overhead 8% Tk, 83.71
Tk, 1,130.11
Add Profit 10% Tk, 104.64
Tk, 1,234.75
VAT & Tax 6.00% Tk, 78.81
Tk, 1,313.57
Note: Whenever material is provided by client, profit will be calculated excluding cost of materials for any type of item.
Item
1.4 Khoa Sand Compaction
No
(2:1; Loose volume 1.35 cum)
Cost of Materials:
Sand 0.4500 Cum @ Tk, 706.00 Per cum Tk, 317.70
Bricks-(BSRM Supply) 270.3200 Nos @ Tk, 8.50 Per Nos Tk, 2,297.72
Cost of Labors:
Breaking charge of Khoa 0.9000 Cum @ Tk, 353.00 Per cum Tk, 317.70
Mason 0.2650 Nos @ Tk, 550.00 Each Tk, 145.75
Skilled Labor 0.7100 Nos @ Tk, 450.00 Each Tk, 319.50
Ordinary Labor 0.7100 Nos @ Tk, 400.00 Each Tk, 284.00
Equipment, fuel & compaction LS Tk, 20.00
Tk, 3,702.37
Overhead 8% Tk, 296.19
3,998.56
Less cost of materials supplied by BSRM Tk, 2,297.72
1,700.84
Add Profit 10% Tk, 170.08
1,870.92
VAT & Tax Tk, -
Total cost including VAT & Tax Tk, 1,870.92
Add cost of materials supplied by BSRM Tk, 2,297.72
Tk, 4,168.64
Item
1.4 Khoa Sand Compaction
No
(1:1; Loose volume 1.35 cum)
Cost of Materials:
Sand 0.6750 Cum @ Tk, 706.00 Per cum Tk, 476.55
Bricks-(BSRM Supply) 202.7400 Nos @ Tk, 8.50 Per Nos Tk, 1,723.29
Page 3 of 41
Cost of Labors:
Breaking charge of Khoa 0.6750 Cum @ Tk, 353.00 Per cum Tk, 238.28
Mason 0.2650 Nos @ Tk, 550.00 Each Tk, 145.75
Skilled Labor 0.7100 Nos @ Tk, 450.00 Each Tk, 319.50
Ordinary Labor 0.7100 Nos @ Tk, 400.00 Each Tk, 284.00
Equipment, fuel & compaction LS Tk, 20.00
Tk, 3,207.37
Overhead 8% Tk, 256.59
3,463.95
Less cost of materials supplied by BSRM Tk, 1,723.29
1,740.66
Add Profit 10% Tk, 174.07
1,914.73
VAT & Tax 6.00% Tk, 122.22
Total cost including VAT & Tax Tk, 2,036.95
Add cost of materials supplied by BSRM Tk, 1,723.29
Tk, 3,760.24
Note: Whenever material is provided by client, profit will be calculated excluding cost of materials for any type of item.
Item
2.1 Brick Flat Soling
No
Cost of Materials:
Bricks-(BSRM Supply) 32.3000 Nos @ 8.50 Each Tk, 274.55
Sand (F.M 1.2) 0.0152 Cum @ Tk, 1,235.00 Per cum Tk, 18.77
Cost of Labors:
Mason 0.0270 Nos @ Tk, 550.00 Each Tk, 14.85
Skilled Labor 0.1070 Nos @ Tk, 450.00 Each Tk, 48.15
Local carriage, sundries, T & P etc. LS Tk, 4.00
Tk, 360.32
Overhead 8% Tk, 28.83
389.15
Less cost of materials supplied by BSRM Tk, 274.55
114.60
Add Profit 10% Tk, 11.46
126.06
VAT & Tax 6.00% Tk, 8.05
Total cost including VAT & Tax Tk, 134.10
Add cost of materials supplied by BSRM Tk, 274.55
Tk, 408.65
Page 4 of 41
Item
2.6 Plain Cement Concrete work
No
i) PCC (1:4:8)
Cost of Materials:
Sand(F.M 1.2) 0.4620 Cum @ Tk, 1,235.00 Per cum Tk, 570.57
Stone Chips 0.9200 Cum @ Tk, 5,649.00 Per cum Tk, 5,197.08
Cement-(BSRM Supply) 3.3000 bag @ Tk, 450.00 Per bag Tk, 1,485.00
Hire Charge of Mixture Machine 0.0350 nos @ Tk, 2,500.00 Per day Tk, 87.50
Hire Charge of Vibrator 0.0350 nos @ Tk, 1,500.00 Per day Tk, 52.50
Fuel & Lubricant for mixture machine & vibrator Ls Tk, 60.00
Cost of Labors:
Head Mason 0.0350 Nos @ Tk, 550.00 Each Tk, 19.25
Mason 0.0700 Nos @ Tk, 550.00 Each Tk, 38.50
Skilled Labor 0.1750 Nos @ Tk, 450.00 Each Tk, 78.75
Ordinary Labor 1.0950 Nos @ Tk, 400.00 Each Tk, 438.00
Extra Mason for floor finish 0.3530 Nos @ Tk, 550.00 Each Tk, 194.15
Curing for 7 days LS 30.00
Local carriage, Sundries LS 100.00
Tk, 8,351.30
Overhead 2.5% Tk, 208.78
8,560.08
Less cost of materials supplied by BSRM Tk,
8,560.08
Add Profit 10% Tk, 856.01
9,416.09
VAT & Tax 6.00% Tk, 601.03
Total cost including VAT & Tax Tk, 10,017.12
Add cost of materials supplied by BSRM Tk, -
Tk, 10,017.12
Note: Whenever material is provided by client, profit will be calculated excluding cost of materials for any type of item.
Item
2.6 Plain Cement Concrete work
No
ii) PCC (1:3:6)
Cost of Materials:
Sand(F.M 1.2) 0.4500 Cum @ Tk, 1,235.00 Per cum Tk, 555.75
Stone Chips 0.9000 Cum @ Tk, 5,649.00 Per cum Tk, 5,084.10
Cement -(BSRM Supply) 4.3000 bag @ Tk, 450.00 Per bag Tk, 1,935.00
Hire Charge of Mixture Machine 0.0350 Nos @ Tk, 2,500.00 Per day Tk, 87.50
Hire Charge of Vibrator 0.0350 Nos @ Tk, 1,500.00 Per day Tk, 52.50
Page 5 of 41
Fuel & Lubricant for mixture machine & vibrator Tk, 60.00
Cost of Labors:
Head Mason 0.0350 Nos @ Tk, 550.00 Each Tk, 19.25
Mason 0.0700 Nos @ Tk, 550.00 Each Tk, 38.50
Skilled Labor 0.1750 Nos @ Tk, 450.00 Each Tk, 78.75
Ordinary Labor 1.0950 Nos @ Tk, 400.00 Each Tk, 438.00
Extra Mason for floor finish 0.3530 Nos @ Tk, 550.00 Each Tk, 194.15
Curing for 7 days LS 30.00
Local carriage, Sundries LS 100.00
Tk, 8,673.50
Overhead 8.0% Tk, 693.88
9,367.38
Less cost of materials supplied by BSRM Tk, 1,935.00
7,432.38
Add Profit 10% Tk, 936.74
8,369.12
VAT & Tax 6.00% Tk, 534.20
Total cost including VAT & Tax Tk, 8,903.32
Add cost of materials supplied by BSRM Tk, 1,935.00
Tk, 10,838.32
Note: Whenever material is provided by client, profit will be calculated excluding cost of materials for any type of item.
Item
2.6 Plain Cement Concrete work
No
iii) PCC (1:2:4)
Cost of Materials:
Sand(F.M 1.2) 0.4290 Cum @ Tk, 1,235.00 Per cum Tk, 529.82
Stone Chips 0.8600 Cum @ Tk, 5,649.00 Per cum Tk, 4,858.14
Cement -(BSRM Supply) 6.0000 bag @ Tk, 450.00 Per bag Tk, 2,700.00
Hire Charge of Mixture Machine 0.0350 @ Tk, 2,500.00 Per day Tk, 87.50
Hire Charge of Vibrator 0.0350 @ Tk, 1,500.00 Per day Tk, 52.50
Fuel & Lubricant for mixture machine & vibrator Tk, 60.00
Cost of Labors:
Head Mason 0.0350 Nos @ Tk, 550.00 Each Tk, 19.25
Mason 0.0700 Nos @ Tk, 550.00 Each Tk, 38.50
Skilled Labor 0.1750 Nos @ Tk, 450.00 Each Tk, 78.75
Ordinary Labor 1.0950 Nos @ Tk, 400.00 Each Tk, 438.00
Curing for 7 days LS 50.00
Tk, 8,912.46
Page 6 of 41
Overhead 8.0% Tk, 713.00
9,625.45
Less cost of materials supplied by BSRM Tk, 2,700.00
6,925.45
Add Profit 10% Tk, 692.55
7,618.00
VAT & Tax 6.00% Tk, 486.26
Total cost including VAT & Tax Tk, 8,104.25
Add cost of materials supplied by BSRM Tk, 2,700.00
Tk, 10,804.25
Note: Whenever material is provided by client, profit will be calculated excluding cost of materials for any type of item.
Item
3.1 Reinforced Cement Concrete Work
No
i) RCC (1:1.5:3)
Cost of Materials:
20mm downgraded crushed stone chips 0.8300 Cum @ Tk, 3,200.00 Per cum Tk, 2,656.00
Sand (F.M 2.5) 0.4150 Cum @ Tk, 2,047.00 Per cum Tk, 849.51
Cement-(BSRM Supply) 7.7000 bag @ Tk, 450.00 Per bag Tk, 3,465.00
Hire Charge of Mixture Machine 0.0350 @ Tk, 2,500.00 Per day Tk, 87.50
Hire Charge of Vibrator 0.0350 @ Tk, 1,500.00 Per day Tk, 52.50
Fuel & Lubricant for mixture machine & vibrator Tk, 50.00
Cost of Labors:
Head Mason 0.0700 Nos @ Tk, 550.00 Each Tk, 38.50
Mason 0.1400 Nos @ Tk, 550.00 Each Tk, 77.00
Skilled Labor 0.3500 Nos @ Tk, 400.00 Each Tk, 140.00
Ordinary Labor 2.1900 Nos @ Tk, 400.00 Each Tk, 876.00
Local carriage, Sundries LS 100.00
Tk, 8,392.01
Overhead 4% Tk, 293.72
8,685.73
Less cost of materials supplied by BSRM Tk, 3,465.00
5,220.73
Add Profit 10% Tk, 522.07
5,742.80
VAT & Tax Tk, -
Total cost including VAT & Tax Tk, 5,742.80
Add cost of materials supplied by BSRM Tk, 3,465.00
Tk, 9,207.80
Note: Whenever material is provided by client, profit will be calculated excluding cost of materials for any type of item.
Page 7 of 41
Cost of Materials:
20mm downgraded crushed stone chips 0.8300 Cum @ Tk, 5,297.25 Per cum Tk, 4,396.72
Sand (F.M 2.5) 0.4150 Cum @ Tk, 1,412.60 Per cum Tk, 586.23
Cement-(BSRM Supply) 6.0000 bag @ Tk, 430.00 Per bag Tk, 2,580.00
Hire Charge of Mixture Machine 0.0350 nos @ Tk, 2,500.00 Per day Tk,
Hire Charge of Vibrator 0.0350 nos @ Tk, 1,500.00 Per day Tk,
Fuel & Lubricant for mixture machine & vibrator Tk, 50.00
Cost of Labors:
Head Mason 0.0700 Nos @ Tk, 550.00 Each Tk,
Mason 0.2000 Nos @ Tk, 550.00 Each Tk,
Skilled Labor 0.5000 Nos @ Tk, 450.00 Each Tk,
Ordinary Labor 2.5000 Nos @ Tk, 400.00 Each Tk,
Local carriage, Sundries LS 882.00
Tk, 8,494.95
882.0 Overhead 3.50% Tk, 297.32
8,792.27
Less cost of materials supplied by BSRM Tk,
8,792.27
Add Profit 10% Tk, 879.23
9,671.50
Cost of Materials:
20mm downgraded crushed stone chips 0.9000 Cum @ 5,649.00 Per cum Tk, 5,084.10
Sand (F.M 2.5) 0.4500 Cum @ Tk, 2,047.00 Per cum Tk, 921.15
Cement-(BSRM Supply) 6.1000 bag @ Tk, 450.00 Per bag Tk, 2,745.00
Hire Charge of Mixture Machine 0.0350 @ Tk, 2,500.00 Per day Tk, 87.50
Hire Charge of Vibrator 0.0350 @ Tk, 1,500.00 Per day Tk, 52.50
Fuel & Lubricant for mixture machine & vibrator Tk, 50.00
Cost of Labors:
Head Mason 0.0700 Nos @ Tk, 550.00 Each Tk, 38.50
Page 8 of 41
Mason 0.1400 Nos @ Tk, 550.00 Each Tk, 77.00
Skilled Labor 0.3500 Nos @ Tk, 450.00 Each Tk, 157.50
Ordinary Labor 2.1900 Nos @ Tk, 400.00 Each Tk, 876.00
Local carriage, Sundries LS Tk. 100.00
Tk, 10,189.25
Overhead 8.0% Tk, 815.14
11,004.39
Less cost of materials supplied by BSRM Tk, 2,745.00
8,259.39
Add Profit 10% Tk, 825.94
9,085.33
VAT & Tax 6.00% Tk, 579.91
Total cost including VAT & Tax Tk, 9,665.24
Add cost of materials supplied by BSRM Tk, 2,745.00
Tk, 12,410.24
Cost of Materials:
20mm downgraded crushed stone chips 0.9000 Cum @ Tk, 5,649.00 Per cum Tk, 5,084.10
Sand (F.M 2.5) 0.4500 Cum @ Tk, 2,047.00 Per cum Tk, 921.15
Cement-(BSRM Supply) 6.1000 bag @ Tk, 450.00 Per bag Tk, 2,745.00
Hire Charge of Mixture Machine 0.0350 nos @ Tk, 2,500.00 Per day Tk, 87.50
Hire Charge of Vibrator 0.0350 nos @ Tk, 1,500.00 Per day Tk, 52.50
Fuel & Lubricant for mixture machine & vibrator Tk, 50.00
Cost of Labors:
Head Mason 0.0700 Nos @ Tk, 550.00 Each Tk, 38.50
Mason 0.2000 Nos @ Tk, 550.00 Each Tk, 110.00
Skilled Labor 0.5000 Nos @ Tk, 450.00 Each Tk, 225.00
Ordinary Labor 2.5000 Nos @ Tk, 400.00 Each Tk, 1,000.00
Local carriage, Sundries LS Tk. 100.00
Tk, 10,413.75
Overhead 8.0% Tk, 833.10
11,246.85
Less cost of materials supplied by BSRM Tk, 2,745.00
8,501.85
Add Profit 10% Tk, 850.19
9,352.04
Page 9 of 41
Item
3.4 Reinforcement Works
No
Unit For 1.00 MT
Cost of Materials:
Cost of Rebar-(BSRM Supply) 1.0000 MT @ 54,000.00 Per MT Tk, 54,000.00
Binding wire 10.0000 kg @ 120.00 Per kg Tk, 1,200.00
Cost of Labors:
Rod binding Mason 2.0000 Nos @ Tk, 550.00 Each Tk, 1,100.00
Ordinary Labor/Helper 3.0000 Nos @ Tk, 400.00 Each Tk, 1,200.00
Local carriage, T & P 500.00
Tk, 58,000.00
Overhead 8% Tk, 4,640.00
62,640.00
Less cost of materials supplied by BSRM Tk, 54,000.00
8,640.00
Add Profit 10% Tk, 864.00
9,504.00
VAT & Tax 6.00% Tk, 606.64
Total cost including VAT & Tax Tk, 10,110.64
Add cost of materials supplied by BSRM Tk, 54,000.00
Tk, 64,110.64
Note: Whenever material is provided by client, profit will be calculated excluding cost of materials for any type of item.
Cost of Materials:
Cost of Rebar-(BSRM Supply) 1.0000 MT @ 54,000.00 Per MT Tk, 54,000.00
Binding wire 10.0000 kg @ 120.00 Per kg Tk, 1,200.00
Cost of Labors:
Rod binding Mason 2.0000 Nos @ Tk, 550.00 Each Tk, 1,100.00
Ordinary Labor/Helper 3.5000 Nos @ Tk, 400.00 Each Tk, 1,400.00
Local carriage, T & P 330.00
Tk, 58,030.00
Overhead 8% Tk, 4,642.40
62,672.40
Less cost of materials supplied by BSRM Tk, 54,000.00
8,672.40
Add Profit 10% Tk, 867.24
9,539.64
Page 10 of 41
VAT & Tax 6.00% Tk, 608.91
Total cost including VAT & Tax Tk, 10,148.55
Add cost of materials supplied by BSRM Tk, 54,000.00
Tk, 64,148.55
Item
4.1 Shuttering
No
i) Rough Shuttering
Cost of Materials:
Cost of wood, bamboo props etc 0.0550 cum @ 19,420.00 Per cum Tk, 1,068.10
(Considering 6 times use) Tk, 178.02
Hardware/Materials LS Tk, 80.00
Labor LS Tk, 75.00
Tk, 333.02
Overhead 8% Tk, 26.64
Tk, 359.66
Add Profit 10% Tk, 33.30
Tk, 392.96
VAT & Tax 6.00% Tk, 23.58
Tk, 416.54
Cost of Materials:
Cost of wood, bamboo props etc 0.0550 cum @ 19,420.00 Per cum Tk, 1,068.10
(Considering 6 times use) Tk, 178.02
Hardware/Materials LS Tk, 80.00
Labor LS Tk, 100.00
Tk, 358.02
Overhead 8% Tk, 28.64
Tk, 386.66
Add Profit 10% Tk, 35.80
Tk, 422.46
VAT & Tax 6.00% Tk, 25.35
Tk, 447.81
Page 11 of 41
iii) Rough Shuttering(Over level 5.5m from FFL)
Cost of Materials:
Cost of wood, bamboo props etc 0.0550 cum @ 19,420.00 Per cum Tk, 1,068.10
(Considering 6 times use) Tk, 178.02
Hardware/Materials LS Tk, 90.00
Labor LS Tk, 100.00
Tk, 368.02
Overhead 8% Tk, 29.44
Tk, 397.46
Add Profit 10% Tk, 36.80
Tk, 434.26
VAT & Tax 6.00% Tk, 26.06
Tk, 460.32
Item
4.1 Shuttering
No
ii) Fair face Shuttering
Cost of Materials:
Cost of Form work 1.0000 Sqm @ Tk, 5,912.00 Per sqm Tk, 5,912.00
(Considering 16 times use) Tk, 369.50
Hardware/Materials LS Tk, 100.00
Labour cost LS Tk, 120.00
Tk, 589.50
Overhead 8% Tk, 47.16
Tk, 636.66
Add Profit 10% Tk, 63.67
Tk, 700.33
VAT & Tax 6.00% Tk, 44.70
Tk, 745.03
Note: Whenever material is provided by client, profit will be calculated excluding cost of materials for any type of item.
Page 12 of 41
Item
4.2 Brick work
No
i) 250mm thick brick work(1:6)
Cost of Materials:
Bricks-(BSRM Supply) 388.6900 Nos @ Tk, 8.50 Each Tk, 3,303.87
Sand (F.M 1.2) 0.3600 Cum @ Tk, 1,235.00 Per cum Tk, 444.60
Cement-(BSRM Supply) 1.4100 bag @ Tk, 450.00 Per bag Tk, 634.50
Cost of Labors:
Head Mason 0.0350 Nos @ Tk, 550.00 Each Tk, 19.25
Mason 0.3530 Nos @ Tk, 550.00 Each Tk, 194.15
Skilled Labor 0.3530 Nos @ Tk, 450.00 Each Tk, 158.85
Ordinary Labor 0.5300 Nos @ Tk, 400.00 Each Tk, 212.00
Local carriage, Sundries LS Tk. 75.00
Tk, 5,042.22
Overhead 8% Tk, 403.38
5,445.59
Less cost of materials supplied by BSRM Tk,
5,445.59
Add Profit 10% Tk, 544.56
5,990.15
VAT & Tax 6.00% Tk, 382.35
Total cost including VAT & Tax Tk, 6,372.50
Add cost of materials supplied by BSRM Tk,
Tk, 6,372.50
Note: Whenever material is provided by client, profit will be calculated excluding cost of materials for any type of item.
Cost of Materials:
Bricks-(BSRM Supply) 388.6900 Nos @ 8.50 Each Tk, 3,303.87
Sand (F.M 1.2) 0.3000 Cum @ Tk, 1,235.00 Per cum Tk, 370.50
Cement-(BSRM Supply) 1.4100 bag @ Tk, 450.00 Per bag Tk, 634.50
Cost of Labors:
Head Mason 0.0350 Nos @ Tk, 550.00 Each Tk, 19.25
Page 13 of 41
Mason 0.3530 Nos @ Tk, 550.00 Each Tk, 194.15
Skilled Labor 0.3530 Nos @ Tk, 450.00 Each Tk, 158.85
Ordinary Labor 0.6000 Nos @ Tk, 400.00 Each Tk, 240.00
Local carriage, Sundries LS Tk. 90.00
Tk, 5,011.12
Overhead 8% Tk, 400.89
5,412.00
Less cost of materials supplied by BSRM Tk, 3,938.37
1,473.64
Add Profit 10% Tk, 147.36
1,621.00
VAT & Tax 6.00% Tk, 103.47
Total cost including VAT & Tax Tk, 1,724.47
Add cost of materials supplied by BSRM Tk, 3,938.37
Tk, 5,662.84
Item
5.1 Plastering work
No
i) 20 mm thick (1:4) plastering work
Cost of Materials:
Cement-(BSRM Supply) 0.1700 bag @ Tk, 450.00 Per bag Tk, 76.50
Sand 0.0250 Cum @ Tk, 1,235.00 Per cum Tk, 30.88
Cost of Labors:
Head Mason 0.0270 Nos @ Tk, 550.00 Each Tk, 14.85
Mason 0.1100 Nos @ Tk, 550.00 Each Tk, 60.50
Ordinary Labor 0.1100 Nos @ Tk, 400.00 Each Tk, 44.00
Curing & Local carriage sundries LS Tk, 20.00
Tk, 246.73
Overhead 8% Tk, 19.74
266.46
Less cost of materials supplied by BSRM Tk, 76.50
189.96
Add Profit 10% Tk, 19.00
208.96
VAT & Tax 6.00% Tk, 13.34
Total cost including VAT & Tax Tk, 222.30
Page 14 of 41
Add cost of materials supplied by BSRM Tk, 107.38
Tk, 329.67
Note: Whenever material is provided by client, profit will be calculated excluding cost of materials for any type of item.
Cost of Materials:
Cement-(BSRM Supply) 0.1270 bag @ Tk, 450.00 Per bag Tk, 57.15
Sand 0.0180 Cum @ Tk, 1,235.00 Per cum Tk, 22.23
Cost of Labors:
Head Mason 0.0270 Nos @ Tk, 550.00 Each Tk, 14.85
Mason 0.1100 Nos @ Tk, 550.00 Each Tk, 60.50
Ordinary Labor 0.1500 Nos @ Tk, 400.00 Each Tk, 60.00
Curing & Local carriage sundries LS Tk, 25.00
Tk, 239.73
Overhead 8% Tk, 19.18
258.91
Less cost of materials supplied by BSRM Tk, 57.15
201.76
Add Profit 10% Tk, 20.18
221.93
VAT & Tax 6.00% Tk, 14.17
Total cost including VAT & Tax Tk, 236.10
Add cost of materials supplied by BSRM Tk, 57.15
Tk, 293.25
Item
5.1 Plastering work
No
iv) 8mm thick (1:4) plastering work
Cost of Materials:
Cement-(BSRM Supply) 0.0700 bag @ 450.00 Per bag Tk, 31.50
Sand 0.0080 Cum @ Tk, 1,235.00 Per cum Tk, 9.88
Cost of Labors: Tk,
Head Mason 0.0270 Nos @ Tk, 550.00 Each Tk, 14.85
Mason/Skillled Labor 0.1100 Nos @ Tk, 450.00 Each Tk, 49.50
Page 15 of 41
Ordinary Labor 0.1610 Nos @ Tk, 400.00 Each Tk, 64.40
Curing & Local carriage sundries LS Tk, 20.00
Tk, 190.13
Overhead 8% Tk, 15.21
205.34
Less cost of materials supplied by BSRM Tk, 31.50
173.84
Add Profit 10% Tk, 17.38
191.22
VAT & Tax 6.00% Tk, 12.21
Total cost including VAT & Tax Tk, 203.43
Add cost of materials supplied by BSRM Tk, 31.50
Tk, 234.93
Page 16 of 41
Item
6.1 MS plate inserts, curb angle, joist etc.
No
Cost of Materials:
Cost of MS plate,curb angle etc-(BSRM Supply) 1.0000 MT @ Tk, 55,000.00 Per MT Tk, 55,000.00
Cost of Labors:
Labour cost for fabrication & erection 1.0000 MT @ Tk, Per MT Tk, 11,000.00
Tk, 66,000.00
Overhead 8% Tk, 5,280.00
71,280.00
Less cost of materials supplied by BSRM Tk, 55,000.00
16,280.00
Add Profit 10% Tk, 1,628.00
17,908.00
VAT & Tax 6.00% Tk, 1,143.06
Total cost including VAT & Tax Tk, 19,051.06
Add cost of materials supplied by BSRM Tk, 55,000.00
Tk, 74,051.06
Item
7.1 Wall Tiles
No
Cost of Materials:
Sand (FM 1.2) 0.0210 cum @ Tk, 1,235.00 Per cum Tk, 25.94
Cement-(BSRM Supply) 0.2000 bag @ Tk, 450.00 Per bag Tk, 90.00
White Cement 0.3900 Kg @ Tk, 30.00 Per Kg Tk, 11.70
Wall Tiles-(BSRM Supply) 1.0000 sqm @ Tk, 645.00 Per sqm Tk, 645.00
Cost of Labors:
Head Mason 0.2200 Nos @ Tk, 550.00 Each Tk, 121.00
Mason 0.2200 Nos @ Tk, 550.00 Each Tk, 121.00
Skilled Labor 0.3230 Nos @ Tk, 450.00 Each Tk, 145.35
Ordinary Labor 0.3230 Nos @ Tk, 400.00 Each Tk, 129.20
Tk, 1,289.19
Overhead 8% Tk, 103.13
1,392.32
Less cost of materials supplied by BSRM Tk, 735.00
657.32
Page 17 of 41
Add Profit 10% Tk, 65.73
723.05
VAT & Tax 6.00% Tk, 43.38
Tk, 766.43
Add cost of materials supplied by BSRM Tk, 735.00
Tk, 1,501.43
Note: Whenever material is provided by client, profit will be calculated excluding cost of materials for any type of item.
Item
7.2 Floor Tiles
No
Cost of Materials:
Sand (FM 1.2) 0.0220 cum @ Tk, 1,235.00 Per cum Tk, 27.17
Cement-(BSRM Supply) 0.1610 bag @ Tk, 450.00 Per bag Tk, 72.45
White Cement 0.3900 Kg @ Tk, 30.00 Per Kg Tk, 11.70
Floor Tiles-(BSRM Supply) 1.0000 sqm @ Tk, 645.00 Per sqm Tk, 645.00
Cost of Labors:
Head Mason 0.2200 Nos @ Tk, 550.00 Each Tk, 121.00
Mason 0.2200 Nos @ Tk, 550.00 Each Tk, 121.00
Skilled Labor 0.3230 Nos @ Tk, 450.00 Each Tk, 145.35
Ordinary Labor 0.3230 Nos @ Tk, 400.00 Each Tk, 129.20
Tk, 1,272.87
Overhead 8% Tk, 101.83
1,374.70
Less cost of materials supplied by BSRM Tk, 717.45
657.25
Add Profit 10% Tk, 65.72
722.97
VAT & Tax 6.00% Tk, 46.15
Tk, 769.12
Add cost of materials supplied by BSRM Tk, 717.45
Tk, 1,486.57
Item
7.5 38 mm Pantent Stone Flooring (1:2:4)
No
Cost of Materials:
Sand(F.M 1.2) 0.0170 Cum @ Tk, 1,235.00 Per cum Tk, 21.00
Brick-(BSRM Supply) 10.2000 nos @ Tk, 8.50 Each Tk, 86.70
Cement-(BSRM Supply) 0.2400 bag @ Tk, 450.00 Per bag Tk, 108.00
Extra cement for finishing-(BSRM Supply) 0.0060 bag @ Tk, 450.00 Per bag Tk, 2.70
Page 18 of 41
Cost of Labors:
Breaking charge of khoa 0.0340 cum @ Tk. 353.00 Per cum Tk, 12.00
Head Mason 0.0020 Nos @ Tk, 550.00 Each Tk, 1.10
Mason 0.0100 Nos @ Tk, 550.00 Each Tk, 5.50
Skillled Labor 0.0130 Nos @ Tk, 450.00 Each Tk, 5.85
Ordinary Labor 0.0130 Nos @ Tk, 400.00 Each Tk, 5.20
Lacal carriage, sundries LS Tk, 15.00
Tk, 263.05
Overhead 8% Tk, 21.04
284.09
Less cost of materials supplied by BSRM Tk, 197.40
86.69
Add Profit 10% Tk, 8.67
95.36
VAT & Tax 6.00% Tk, 6.09
Total cost including VAT & Tax Tk, 101.45
Add cost of materials supplied by BSRM Tk, 197.40
Tk, 298.85
Note: Whenever material is provided by client, profit will be calculated excluding cost of materials for any type of item.
Item
8.7 Window Shutter (steel)
No
Cost of Materials:
MS Angle, Flat bar(BSRM Supply) 0.0220 MT @ Tk, 55,000.00 Per MT Tk, 1,210.00
3mm glass panes 1.0000 sqm @ Tk, 490.00 Per sqm Tk, 490.00
Fabrication charge/labor 1.2000 Nos @ Tk, 400.00 Per Nos Tk, 480.00
Enamel Paint 1.0000 sqm @ Tk, 140.00 Per sqm Tk, 140.00
Hardwares & all other accessories LS @ Tk, Tk, 100.00
Cost of Labors:
Page 19 of 41
Add cost of materials supplied by BSRM Tk, 1,210.00
Tk, 3,198.80
Note: Whenever material is provided by client, profit will be calculated excluding cost of materials for any type of item.
Item
8.7 Door Shutter (steel)
No
Cost of Materials:
MS Angle, Flat bar(BSRM Supply) 0.0270 MT @ Tk, 55,000.00 Per kg Tk, 1,485.00
CGI Sheet 10.0000 kg @ Tk, 95.00 Per kg Tk, 950.00
Fabrication charge/labor 2.0000 Nos @ Tk, 400.00 Per Sqm Tk, 800.00
Enamel Paint 1.0000 sqm @ Tk, 140.00 Per sqm Tk, 140.00
Hardwares & all other accessories LS @ Tk, Tk, 160.00
Cost of Labors:
Item
10.3 Rolling Shutter
No
Unit For 1.00 Sqm
Cost of Materials:
Page 20 of 41
CC, Hardwares, Electrodes & all other accessories LS 250.00
Cost of Labors:
Item
17 RCC Pipe Laying:
No
Page 21 of 41
Item
18 Removing Sludge/Semi Liquid clay from the bottom of any type of Marshy land/Lake/Ditch/Pond in/c mixing fine local sand of F.M. 0.8 .
No
Considering 1000 cft of Work:
Fine Sand(F.M 0.8) 2.8400 Cum @ Tk. 706.00 Per Cum = 2,005.04
Labour for mixing sand & cutting
loose sludge in/c spreading and
stacking 12.0000 nos @ Tk. 400.00 Per Nos = 4,800.00
Labour cutting dried sludge in/c
loading, unloading & truck/cart etc.
7.0000 nos @ Tk. 400.00 Per Nos = 2,800.00
Hire charge of truck 7.0000 Trip @ Tk. 900.00 Per Trip = 6,300.00
Tools and plant,sundries, incidental
etc. LS = 50.00
Total = 15,955.04
Overhead 8% = 1,276.40
Total = 17,231.44
Add Profit 10% = 1,595.50
Total = 18,826.95
Vat & Tax 6.00% = 1,129.62
Total = 19,956.56
Item
25 Grouting Work (Labor Rate in/c shuttering):
No
Considering 1 cum of work
1. Grout Materials 1.0000 cum @ Tk. 155,000.00 Per Cum = 155,000.00
1. Shuttering in/c materials 4.0000 Sqm @ Tk. 450.00 Per Sqm = 1,800.00
2. Mason 1.5000 Nos @ Tk. 550.00 Per nos = 825.00
3. Ordinary Labour 2.0000 Nos @ Tk. 400.00 Per nos = 800.00
Total = 158,425.00
Overhead 8% = 12,674.00
Total = 171,099.00
Add Profit 10% = 17,109.90
Total = 188,208.90
Vat & Tax 6.00% = 11,292.53
Total = 199,501.43
Page 22 of 41
BILL OF QUANTITIES No. 1
Bill of Quantities related to GIS Substation Building
1.0. EXCAVATION
1.1. Excavation in ordinary soil upto a depth of 3 M from
existing surface in both dry & wet conditions including
shoring & strutting where necessary dewatering sub-soil &
rainwater to keep the excavation dry by bailing, dressing the
bottom of the excavation to correct level, slope & 3,500.00 M3 276.80 968,792.55
dimension, deposit in heaps upto a distance of 30 M
including dressing of the heap by breaking of lumps.
2.0. BACKFILLING -
Backfilling in plinth, sides of excavation, trenches, etc. with
selected materials obtained from within a lead of 100 M in
layers not exceeding 300 mm depth and consolidation of 1,700.00 M3 185.98 316,158.40
each deposited layers by ramming & watering, dressing the
top surface to correct level as required.
Page 23 of 41
Item No. Description
Qty. Unit Rate (BDT) Amount (BDT)
6.1. Straightening & decoiling wherever necessary, cutting &
bending, hooking & fixing in position with approved
annealed tying wire, all reinfor-cement in foundations, floor
& roof slabs, lintels, beams, columns, overhead & under-
ground tanks, etc. including the cost of supply-ing & fixing
cover blocks, all materials & labour complete (Authorised
laps, chairs & separators will be measured and paid under
this item):
7.0. SHUTTERING
7.1. Providing, erecting, fixing & removing shuttering as
specified for all concrete work as shown in drawing
including all chamfers, splays, keys, wedged props, nails,
bracings, brackets, cutting holes, etc. and applying one coat
of waste oil on all shuttering faces in contact with concrete,
all materials & labour complete.
a) Rough Shuttering -
To straight sides of all foundations & pits in contact with
earth at all depths below G.L. 2,000.00 M2 416.54 833,074.49
b) Fairfaced Shuttering
To straight vertical & horizontal surfaces of lintels, beams,
walls, equipment foundations, pits, underground tanks,
columns, slabs, chajjas, etc.:
i) From G.L. upto a height of 5 M above G.L. 2,000.00 M2 745.03 1,490,055.32
ii) Exceeding 5 M but not exceeding 10 M above G.L. 1,700.00 M2 745.03 1,266,547.02
iii) Exceeding 10 M but not exceeding 20 M above G.L. 3,750.00 M2 745.03 2,793,853.72
-
7.2. Providing, fixing, removing & cleaning, shuttering as
specified for core holes & pockets as shown in drawing
including all temporary form work & applying one coat of 100.00 M2 750.00 75,000.00
waste oil on all shuttering faces in contact with concrete, all
materials & labour complete.
b) Superstructure above plinth level to a height not exceeding 4 50.00 M3 6,372.50 318,625.08
M
c) -do- exceeding 4 M but not exceeding 8 M 120 M3 5,662.84 679,540.37
d) -do- exceeding 8 M but not exceeding 12 M 120 M3 5,662.84 679,540.37
e) -do- exceeding 12 M but not exceeding 20 M 150 M3 5,662.84 849,425.46
Page 24 of 41
Item No. Description
Qty. Unit Rate (BDT) Amount (BDT)
Page 25 of 41
Item No. Description
Qty. Unit Rate (BDT) Amount (BDT)
11.2. Providing two coats of SUPER SNOWCEM or approved
cement based paint of different shades and as specified by
manufacturer to all external plastered surfaces at all heights
& depths, above & below plinth level after preparing the bed 3,000.00 M2 185.66 556,985.11
including scraping the surface thoroughly, scaffolding,
watering, all materials & labour complete.
12.4. Supplying, fitting & fixing in position at and all depths &
heights, above & below plinth level approved Hand
Operated M.S. Rolling Shutter fabricated from 18 gauge
steel sheets with all accessories, side guides, hood cover,
locking arrangement, etc. complete in all respects with one
shop coat of red oxide zinc chromate paint, all materials & 12.00 M2 5,326.56 63,918.67
labour complete. (Measurement of rolling shutter shall be
same as that of clean opening of brickwall).
-
13.0. PAINTING & VARNISHING -
Page 26 of 41
Item No. Description
Qty. Unit Rate (BDT) Amount (BDT)
13.1. Providing two coats of ready mixed approved flat oil paint
as specified at all heights & lengths, above & below plinth
level on Glazed Steel Doors, Windows & Ventilators
including cleaning, sanding, putty filling, etc. and 200.00 M2 219.48 43,895.53
scaffolding, all materials & labour complete.
Page 27 of 41
Item No. Description
Qty. Unit Rate (BDT) Amount (BDT)
The consumption of cement is 9 Kg/Sq.m. These holes shall
be spaced at 1 M C/C for a depth into the concrete leaving
50 mm from the bottom surface of the slab section. The
Nozzle top shall be opened and fixed to the grouting pump.
A grout slurry of cement, water, expanding grout admixture
of approved make is to be applied till refusal of the injected
grout material from the adjacent nozzle or refusal of intake
(till grout pump exerts back pressure after this the nozzle is
to be plugged by cap. The quantity of the grouting admixture
will be as per manufacturer’s specification. However, in
-
case of any seepage in Raft/Retaining Wall in any points the
same is to be treated by grouting. The specification of
treatment will be same as mentioned earlier (10 Year
Guarantee Bond to be submitted by authorised agency).
Page 28 of 41
Item No. Description
Qty. Unit Rate (BDT) Amount (BDT)
The whole terrace so finished shall be flooded with water for
a minimum period of two (2) weeks for curing and for final
test. All the above operations to be done in order & directed -
and specified by Engineer-in-Charge.
-
14.3. Providing & fixing Rebars by Chemical Anchoring to
develop full tension with appropriate embedment of
“HILTI” or “BOSCH” or similar approved make for the -
following dia:
i) 8 mm Nos. 1200 -
ii) 10 mm Nos. 1200 -
iii) 12 mm Nos. 1200 -
iv) 16 mm Nos. 1500 -
v) 20 mm Nos. 2500 -
vi) 25 mm Nos. 2500 -
vii) 28 mm Nos. 3200 -
viii) 32 mm Nos. 3200 -
-
15.0. MISCELLANEOUS ITEMS -
15.1. Providing & filling with Local Sand consolidated by
watering & ramming to the optimum moisture content with
plate compactor to the satisfaction of the Engineer, in layers
not exceeding 200 mm in depth properly to the level,
watering, all materials & labour complete (Sand used shall 25.00 M3 1,487.79 37,194.83
not contain particles finer than 75 micron more than 5%).
-
2.0. BACKFILLING -
Backfilling in plinth, sides of excavation, trenches, etc. with
selected materials obtained from within a lead of 100 M in
layers not exceeding 300 mm depth and consolidation of 410.00 M3 185.98 76,249.97
each deposited layers by ramming & watering, dressing the
top surface to correct level as required.
Page 29 of 41
Item No. Description
Qty. Unit Rate (BDT) Amount (BDT)
5.1. Mixing & laying machine mixed plain cement concrete
mechanically vibrated excluding shuttering but including
curing, all materials & labour complete. M7.5 Nominal mix 25.00 M3 10,017.12 250,427.95
1:4:8 with 40 mm down aggregate between 3.0 M & 6.0 M
below G.L.
6.0. REINFORCEMENT -
Straightening & decoiling wherever necessary, cutting &
bending, hooking & fixing in position deformed steel bars of
60 grade with approved annealed tying wire, all
reinforcement in foundations, floor & roof slabs, lintels,
beams, columns, overhead & under-ground tanks, etc. 62.00 T 64,110.64 3,974,859.57
including the cost of supplying & fixing cover blocks, all
materials & labour complete (Authorised laps, chairs &
separators will be measured and paid under this item)
7.0. SHUTTERING -
Providing, erecting, fixing & removing shuttering as
specified for all concrete work as shown in drawing
including all chamfers, splays, keys, wedged props, nails,
bracings, brackets, cutting holes, etc. and applying one coat 1,575.00 M2 416.54 656,046.16
of waste oil on all shuttering faces in contact with concrete,
all materials & labour complete.
8.0. BRICKWORK -
8.1. Laying brickwork 250 mm thick as specified in cement
mortar (1:6) including fair cutting, waste, bonding,
plumbing, lining, levelling, finishing flush, raking joints, 107.00 M3 6,372.50 681,857.66
scaffolding & curing in foundations, walls, piers, columns,
etc., all materials & labour complete.
8.2. Supplying & laying brickwork 125 thick at all heights above
plinth level in (1:4) cement mortar and H.B. wire netting in
every third course, half brick thick including fair cutting,
waste, bonding, plumbing, lining, levelling, finishing flush, 110.00 M2 932.04 102,524.82
raking joints, scaffolding & curing, all materials & labour
complete.
9.0. PLASTERING -
Providing cement plaster to all internal & external walls and
ceiling, pillars, columns, parapets, lintel sides, drains,
column projections, narrow bands and widths etc. including -
chipping of concrete surfaces, raking joints, scaffolding,
cleaning, curing, all materials & labour complete.
9.1. 20 mm plaster (in two operation) in cement mortar (1:6) 770.00 M2 329.67 253,847.54
9.2. [outside
15 surface]
mm plaster (in one operation) in cement mortar (1:6) 860.00 M2 329.67 283,518.03
10.0. [inside
FLOORINGsurface] -
Page 30 of 41
Item No. Description
Qty. Unit Rate (BDT) Amount (BDT)
10.1. Providing & laying 30 mm thick polished grey artificial
stone flooring as specified in floors with necessary falls &
cross falls at and all heights & depths, above & below plinth
level with (1:2:4) mix in grey cement without colouring
pigment but with 2 mm thick glass dividers upto the depth of 430.00 M2 298.85 128,504.05
the I.P.S. at max. 2 M centres in both directions including
curing, polishing, all materials & labour complete.
Page 31 of 41
Item No. Description
Qty. Unit Rate (BDT) Amount (BDT)
12.3.
Providing, fitting & fixing commercial quality solid core,
block board flush Door Shutters 38mm thk. or approved
quality lipping with Garjan or similar wood Vineer using hot
pressed phenol formaldehyde as glue, etc. with all hinges, 10.00 M2 6,254.00 62,540.00
fittings, fixing cleats, bolts, handles, stays, all complete as
per design or as directed by the Engineer with one coat of
approved primer, all materials & labour complete.
Page 32 of 41
Item No. Description
Qty. Unit Rate (BDT) Amount (BDT)
Providing & laying ACRYLIC POLMER MODIFIED
CEMENTITIOUS Water Proofing Membrane in two layers
of approved quality by the BSRM Engineer after thoroughly
chipping & cleaning the roof top surface as per
manufacturer’s specification, curing all complete including 446.00 M2 4,244.10 1,892,868.91
treating similarly the adjoining walls upto 300 mm height
including rounding of junctions of walls & slabs to the
satisfaction of the BSRM Engineer.
Page 33 of 41
Item No. Description
Qty. Unit Rate (BDT) Amount (BDT)
3.2. Mixing & placing machine mixed and Mechanically
vibrated reinforced cement concrete in foundation, lintels,
beams, slabs, columns, side walls, curved surfaces, machine
foundations, etc. as shown in drawings excluding shuttering
& reinforcement but including curing, all materials & labour 450.00 M3 9,207.80 4,143,508.96
complete. M25 with 20 mm down aggregate upto 3 M below
G.L
4.0. SHUTTERING -
Providing, erecting, fixing & removing Rough Shuttering as
specified for all concrete work as shown in drawing
including all chamfers, splays, keys, wedged props, nails,
bracings, brackets, cutting holes, etc. and applying one coat
of waste oil on all shuttering faces in contact with concrete 2,000.00 M2 416.54 833,074.49
at all depths below G.L., all materials & labour complete.
5.0. REINFORCEMENT -
Straightening & decoiling wherever necessary, cutting &
bending, hooking & fixing in position with approved
annealed tying wire, all reinfor-cement in foundations, floor
& roof slabs, lintels, beams, columns, overhead &
underground tanks, etc. including the cost of supplying &
fixing cover blocks, all materials & labour complete 70.00 T 64,110.64 4,487,744.68
(Authorised laps, chairs & separators will be measured and
paid under this item): Deformed steel bars of 60 Grade
Page 34 of 41
Item No. Description
Qty. Unit Rate (BDT) Amount (BDT)
Backfilling in plinth, sides of excavation, trenches, etc. with
selected materials obtained from within a lead of 100 M in
layers not exceeding 300 mm depth and consolidation of 232.00 M3 185.98 43,146.32
each deposited layers by ramming & watering, dressing the
top surface to correct level as required.
a) M25 with 20 mm down aggregate upto 3 M below G.L 112.00 M3 9,207.80 1,031,273.34
b) M25 with 20 mm down aggregate between 3 M & 6 M 83.00 M3 9,207.80 764,247.21
c) below G.L.20 mm down aggregate upto 2 M above G.L.
M25 with 42.00 M3 9,207.80 386,727.50
6.0. SHUTTERING
Providing, erecting, fixing & removing shuttering as
specified for all concrete work as shown in drawing
including all chamfers, splays, keys, wedged props, nails,
bracings, brackets, cutting holes, etc. and applying one coat
of waste oil on all shuttering faces in contact with concrete,
a) Rough Shuttering
all materials & labour complete.
To straight sides of all foundations & pits in contact with
earth uoto 6.0 M below G.L. 270.00 M2 416.54 112,465.06
b) Fairfaced Shuttering
To straight vertical & horizontal surfaces of inside walls,
ceiling of top slab, beams, column sides, etc. from 4.0 M
below GL to 2.0 M above GL M2 745.03
Page 35 of 41
Item No. Description
Qty. Unit Rate (BDT) Amount (BDT)
5.0. SHUTTERING -
Providing, erecting, fixing & removing Rough Shuttering as
specified for all concrete work as shown in drawing including all
chamfers, splays, keys, wedged props, nails, bracings, brackets,
cutting holes, etc. and applying one coat of waste oil on all
shuttering faces in contact with concrete, all materials & labour 140.00 M2 416.53724666667 58,315.21
complete. To straight sides of all foundations in contact with
earth at all depths below G.L.
Page 36 of 41
Item No. Description
Qty. Unit Rate (BDT) Amount (BDT)
6.2. Fabricating, erecting & fixing in position at all depths above &
below G.L. foundation bolts, anchor plates, M.S. plate inserts,
curved angles, M.S. or galvanised steel pipes, etc. as shown in
drawing or as directed by the Engineer, all materials & labour 2.00 T 74,051.06 148,102.13
complete.
a) M25 with 20 mm down aggregate upto 3 M below G.L 27.00 M3 9,207.80 248,610.54
b) M25 with 20 mm down aggregate upto 2 M above G.L 2.00 M3 9,207.80 18,415.60
4.3. Non-shrink Cementitious Grout -
Supplying & providing non-shrink Cementitious Grout
“SHRINKOMP” of ACC Ltd. or approved equivalent underside
of machine base, anchor bolt holes, foundation bolt holes,
1.80 M3 199,501.43 359,102.58
pockets, etc., as per manufacturer’s specification.
5.0. SHUTTERING
Page 37 of 41
Item No. Description
Qty. Unit Rate (BDT) Amount (BDT)
Providing, erecting, fixing & removing Rough Shuttering as
specified for all concrete work as shown in drawing including all
chamfers, splays, keys, wedged props, nails, bracings, brackets,
cutting holes, etc. and applying one coat of waste oil on all
shuttering faces in contact with concrete, all materials & labour 230.00 M2 416.53724666667 95,803.57
complete. To straight sides of all foundations in contact with
earth at all depths below G.L.
6.2. Embedments -
Fabricating, erecting & fixing in position at all depths above &
below G.L. foundation bolts, anchor plates, M.S. plate inserts,
curved angles, M.S. or galvanised steel pipes, etc. as shown in
drawing or as directed by the Engineer, all materials & labour
1.10 T 74,051.06 81,456.17
complete.
Page 38 of 41
Item No. Description
Qty. Unit Rate (BDT) Amount (BDT)
Supplying, laying & hand packing 300 mm (approx. finished
thickness) Base Course Soling and ramming down small
pieces in the interstices including rolling by a 10 T power
roller and preparing the bed to proper level & camber and
ultimate filling of voids with moorum or sand including cost 4,750.00 M2 2,200.00 10,450,000.00
of all materials & labour.
Page 39 of 41
Item No.07 Wearing Course(50mm Thk.)
Ratio (1:1.5:3)
Concrete Class-25
Unit For 1.00 Cum
Cost of Materials:
20mm downgraded crushed stone chips 0.8300 Cum @ Tk, 6,356.00 Per cum Tk, 5,275.48
Sand (F.M 2.5) 0.4150 Cum @ Tk, 1,765.00 Per cum Tk, 732.48
Cement- 7.7000 bag @ Tk, 500.00 Per bag Tk, 3,850.00
Hire Charge of Mixture Machine 0.0350 day @ Tk, 600.00 Per day Tk, 21.00
Hire Charge of Vibrator 0.0350 day @ Tk, 300.00 Per day Tk, 10.50
Fuel & Lubricant for mixture machine & vibrator Tk, 20.00
Cost of Labors:
Head Mason 0.0700 Nos @ Tk, 550.00 Each Tk, 38.50
Mason 0.1400 Nos @ Tk, 500.00 Each Tk, 70.00
Skilled Labor 0.3500 Nos @ Tk, 400.00 Each Tk, 140.00
Ordinary Labor 2.1900 Nos @ Tk, 400.00 Each Tk, 876.00
Local carriage, Sundries LS 10.00
Tk, 11,043.96
Overhead 3.5%Tk, 386.54
11,430.49
Add Profit 10%Tk, 1,143.05
12,573.54
VAT & Tax Tk, -
12,573.54
Item No.07 Wearing Course(50mm Thk.)
Ratio (1:1.5:3)
Concrete Class-25
Unit For 1.00 Cum
Cost of Materials:
20mm downgraded crushed stone chips 0.8300 Cum @ Tk, 6,356.00 Per cum Tk, 5,275.48
Sand (F.M 2.5) 0.4150 Cum @ Tk, 1,765.00 Per cum Tk, 732.48
Cement- 7.7000 bag @ Tk, 500.00 Per bag Tk, 3,850.00
Hire Charge of Mixture Machine 0.0350 day @ Tk, 600.00 Per day Tk, 21.00
Hire Charge of Vibrator 0.0350 day @ Tk, 300.00 Per day Tk, 10.50
Fuel & Lubricant for mixture machine & vibrator Tk, 20.00
Cost of Labors:
Head Mason 0.0700 Nos @ Tk, 550.00 Each Tk, 38.50
Mason 0.1400 Nos @ Tk, 500.00 Each Tk, 70.00
Skilled Labor 0.3500 Nos @ Tk, 400.00 Each Tk, 140.00
Ordinary Labor 2.1900 Nos @ Tk, 400.00 Each Tk, 876.00
Local carriage, Sundries LS 10.00
Tk, 11,043.96
Overhead 3.5%Tk, 386.54
11,430.49
Add Profit 10%Tk, 1,143.05
12,573.54
VAT & Tax Tk, -
12,573.54