Documente Academic
Documente Profesional
Documente Cultură
PROJECT MANAGEMENT
BY HUZAIFA BIN HASHIM
KIX2004
DK2/BLOCK U/8.00- DK2/BLOCK U/8.00-
11.00am/Group 2/KIB-KIA 11.00am/Group 2/KIB-KIA DK2/BLOCK U/8.00- DK2/BLOCK U/8.00- DK2/BLOCK U/8.00- DK2/BLOCK U/8.00-
11.00am/Group 2/KIB-KIA 11.00am/Group 2/KIB-KIA 11.00am/Group 2/KIB-KIA 11.00am/Group 2/KIB-KIA
HH HH HH T T T
WEEK 1 WEEK 2 WEEK 3 WEEK 4 WEEK 5 WEEK 6
DK2/BLOCK U/8.00- DK2/BLOCK U/8.00- DK2/BLOCK U/8.00- DK2/BLOCK U/8.00- DK2/BLOCK U/8.00- DK2/BLOCK U/8.00-
11.00am/Group 2/KIB-KIA 11.00am/Group 2/KIB-KIA 11.00am/Group 2/KIB-KIA 11.00am/Group 2/KIB-KIA 11.00am/Group 2/KIB-KIA 11.00am/Group 2/KIB-KIA
HH HA Br HA HA HA
WEEK 7 WEEK 8 WEEK 9 WEEK 10 WEEK 11 WEEK 12
Pr
KIX2004 Pr Pr aS Sw F
WEEK 13 WEEK 14 WEEK 15 WEEK 16 WEEK 17 – WEEK 19 WEEK 20
CONTENT
1.1 DEFINITION
1.1.1 Project
1.1.2 Project Management
1.2 BENEFITS OF PROJECT MANAGEMENT
1.3 ROLE OF PROJECT MANAGEMENT
1.4 PROJECT MANAGEMENT SKILLS
Ch
1.5 TERMS PROJECT MANAGERS USE
1.6 TIPS ON HOW TO START PROJECT MANAGEMENT
1
CONTENT 2.1 HISTORY OF PROJECT MANAGEMENT
It’s only once the discipline had been codified that we could start to look back
and identify key points in time that contributed to its development, such as the
creation of the Gantt chart and the Agile Manifesto.
Let’s start at the beginning and sketch out the rich history of project
management.
But know that, though historic, project management isn’t a dusty relic of the
past. It continues to grow and influence the way people do almost anything that
has a start and a finish.
2.2 The Modern History of Project Management
It wasn’t until the 1900s that project management as we know it began to take
form.
Due to the nature of projects being unique undertakings, they involve a degree of
uncertainty.
Organizations performing projects will usually divide each project into several
project phases to improve management control and provide for links to the
ongoing operations of the performing organization.
Collectively, the project phases are known as the project life cycle.
2.4.1 Characteristics of Project Phases
The deliverables, and hence the phases, are part of a generally sequential logic
designed to ensure proper definition of the product of the project.
a) determine if the project should continue into its next phase and
b) detect and correct errors cost effectively. These phase-end reviews are
often called phase exits, stage gates, or kill points.
Each project phase normally includes a set of defined deliverables designed to
establish the desired level of management control.
The majority of these items are related to the primary phase deliverable, and the
phases typically take their names from these items: requirements, design, build,
test, startup, turnover, and others, as appropriate.
2.4.2 Characteristics of the Project Life Cycle
The project life cycle serves to define the beginning and the end of a project.
The project life-cycle definition will determine whether the feasibility study is
treated as the first project phase or as a separate, standalone project.
The project life-cycle definition will also determine which transitional actions at
the beginning and the end of the project are included and which are not.
In this manner, the project life-cycle definition can be used to link the project to
the ongoing operations of the performing organization.
The phase sequence defined by most project life cycles generally involves some
form of technology transfer or handoff such as requirements to design,
construction to operations, or design to manufacturing.
Deliverables from the preceding phase are usually approved before work starts
on the next phase. However, a sub- sequent phase is sometimes begun prior to
approval of the previous phase deliverables when the risks involved are
deemed acceptable.
1. What technical work should be done in each phase (e.g., is the work of the
architect part of the definition phase or part of the execution phase?).
Highly detailed descriptions may have numerous forms, charts, and checklists
to provide structure and consistency.
1. Cost and staffing levels are low at the start, higher toward the end, and drop
rapidly as the project draws to a conclusion.
Most have four or five phases, but some have nine or more.
Even within a single application area, there can be significant variations - one
organization’s software development life cycle may have a single design phase
while another’s has separate phases for functional and detail design.
Subprojects within projects may also have distinct project life cycles.
For example, an architectural firm hired to design a new office building is first
involved in the owner’s definition phase when doing the design, and in the
owner’s implementation phase when supporting the construction effort.
The architect’s design project, however, will have its own series of phases from
conceptual development through definition and implementation to closure.
The architect may even treat designing the facility and supporting the
construction as separate projects with their own distinct phases.
2.4.3 Characteristics of the Project Life Cycle
The following project life cycles have been chosen to illustrate the diversity of
approaches in use.
The examples shown are typical; they are neither recommended nor preferred.
In each case, the phase names and major deliverables are those described by
the author for each of the figures.
A. A Defense Acquisition
B. Construction
C. Pharmaceuticals
D. Software development
A. Defense acquisition
Representative Construction
Project Life Cycle, per Morris
1. Feasibility - project formulation, feasibility studies, and strategy design and
approval. A go/no-go decision is made at the end of this phase.
2. Planning and design - base design, cost and schedule, contract terms and
conditions, and detailed planning. Major contracts are let at the end of this
phase.
4. Turnover and startup - final testing and maintenance. The facility is in full
operation at the end of this phase.
C. Pharmaceuticals
There are a number of software life-cycle models in use such as the waterfall
model. Muench, describe a spiral model for software development with four
cycles and four quadrants, as illustrated in Figure 2-4..
Figure 2-5
Representative Software
Development Life Cycle,
per Muench
1. Proof-of-concept cycle - capture business requirements, define goals for
proof of concept, produce conceptual system design and logic design, and
construct the proof of concept, produce acceptance test plans, conduct risk
analysis, and make recommendations.
2. First-build cycle - derive system requirements, define goals for first build,
pro- duce logical system design, design and construct the first build, produce
system test plans, evaluate the first build, and make recommendations.
4. Final cycle - complete unit requirements and final design, construct final
build, and perform unit, subsystem, system, and acceptance tests.
2.5 Feasibility Study
There can be many reasons for this, including requiring too many resources,
which not only prevents those resources from performing other tasks but also
may cost more than an organization would earn back by taking on a project that
isn’t profitable.
A well-designed study should offer a historical background of the business or
project, such as a description of the product or service, accounting statements,
details of operations and management, marketing research and policies,
financial data, legal requirements, and tax obligations.
There are five types of feasibility study - separate areas that a feasibility study
examines, described below.
1. Technical Feasibility
2. Economic Feasibility
3. Legal Feasibility
4. Operational Feasibility
5. Scheduling Feasibility
1. TECHNICAL FEASIBILITY
A feasibility study might reveal the organization’s ideal location isn’t zoned for
that type of business.
That organization has just saved considerable time and effort by learning that
their project was not feasible right from the beginning.
4. OPERATIONAL FEASIBILITY
Operational feasibility studies also examine how a project plan satisfies the
requirements identified in the requirements analysis phase of system
development.
5. SCHEDULING FEASIBILITY
This assessment is the most important for project success; after all, a project
will fail if not completed on time.
A feasibility study might uncover new ideas that could completely change a
project’s scope.
It’s best to make these determinations in advance, rather than to jump in and to
learn that the project won’t work.