CONCRETE
1 Concrete C-7 Cement = 1.82 qts/m3
Mechanical Mix Sand = 0.50m3/m3
Mix ratio = 1:2:5:6 Gravel = 0.85/m3
2 Concrete C-15 Cement = 2.75 qts/m3
Mechanical Mix Sand = 0.53m3/m3
Mix ratio = 1:2:5:3.5 Gravel = 0.75/m3
3 Concrete C-20 Cement = 3.18 qts/m3
Mechanical Mix Sand = 0.50m3/m3
Mix ratio = 1:2:3 Gravel = 0.75/m3
4 Concrete C-15 Cement = 2.94qts/m3
Hand Mix Sand = 0.46m3/m3
Mix ratio = 1:2:3.5 Gravel = 0.80/m3
5 Concrete C-20 Cement = 3.47qts/m3
Hand Mix Sand = 0.41m3/m3
Mix ratio = 1:1.5:3 Gravel = 0.82/m3
6 Concrete C-30 Cement = 3.82 qts/m3
Mix ratio = 1:1.5:2:5 Sand = 0.45m3/m3
Gravel = 0.75/m3
7 Concrete C-15 Cement = 2.40 qts/m3
Total Agg. = 1850 kg Sand = 35.50%
Gravel =
8 Concrete C-15 Cement = 2.80 qts/m3
Total Agg. = 1800 kg Sand = 35.50%
Gravel = X
9 Concrete C-15 Cement = 3.20 qts/m3
Total Agg. = 1800 kg Sand = 30.40%
Gravel = X
10 Concrete C-30 Cement = 4.0 qts/m3
Total Agg. = 1700 kg Sand = 30.40%
Gravel = X
11 Steel Reinforcement (with 5% wastage)
12 Concrete C-25 Cement = 3.6 qts/m3
Total Agg. = 1750 kg Gravel = X
Item Type Of Work Quantity
1 Form Work for sides of the walls:
(Usages for boards)
a) 2.5 cm thick board ( with 5% wastage) 0.53m2/m2
b) 50x75mm battens (with 5% wastage) ( 5 Usages) 0.84m/m2
c) Beam 50x125mm (with 5% wastage) (10 Usages) 0.10m/m2
d) Strut (# 60cm eucalyptus) (10 Usages) 0.10kg/m2
e) Nails 0.2kg/m2
f) Mould oil 0.06 lit/m2
2 Soffit form work for slab,props height not exceeding/300mm
a) 2.5 cm thick board ( with 5% wastage)( 4 Usages) 0.27m2/m2
b) 30x100mm battens ( 10 Usages)4.0m/m2 0.42m/m2
c) 75x125mm beams (10 Usages) 1.0m/m2 0.15m/m2
d) 20x100mm bracings ( 20 Usages) 2m/m2 0.10m/m2
e) Nails 0.20kg/m2
g) Mould oil 0.06 lit/m2
3 Form work for edges of the slab width not exceeding 200mm
a) 2.5mm thick boards (4 Usages) 0.053m/m2
b) 50x50mm battens (8 Usages)2m/m 0.25 m/m2
c) Nails 0.05m/m2
4 Form work for face of the steps & edges of the slab width over
200mm not exceeding 250mm
a) 25x250 mm boards (5 Usages) 0.21m/m
b) 50x50mm battens (10 Usages)1.0m/m 0.11 m/m
c) Nails 0.05kg/m
d) Mould oil 0.015 lit/m
5 Form work for sides of the footing depth, not exceeding 250mm
a) 25mm thick boards (4 Usages) 0.07m/m2
b) 50x50mm battens (10 Usages) 0.32m/m2
c) Nails 0.05kg/m
d) Mould oil 0.015 lit/m
6 Ditto, but depth over 250mm but not exceeding 350mm
a) 25mm thick boards (4 Usages) 0.10m/m2
b) 50x50mm battens (10 Usages) 3.5m/m 0.38m/m2
c) Nails 0.07kg/m
d) Mould oil 0.021 lit/m
7 Form work for sides of the ground beams & footing width over 450mm
a) 25mm thick boards (4 Usages) 0.27m/m2
b) 50x50mm battens (10 Usages) 3.0m/m2 0.32m/m2
c) Struts # 60mm (10 Usages) 2.0m/m2 0.21m/m2
d) Nails 0.20kg/m2
e) Mould oil 0.21 lit/m
Item Type Of Work Quantity
8 Form work for sides of the foundation wall
a) 25mm thick boards (4 Usages) 0.27m/m2
b) 50x75mm battens ( 10 Usages) 4.5m/m2 0.47m/m2
c) 50x125mm beams (10 Usages) 1.05m/m2 0.11m/m2
d) Strut # 60cm eucalyptus (10 Usages)1.0m/m2 0.10m/m2
e) Nails 0.25kg/m2
f) Mould oil 0.06 lit/m2
9 Form work for sides of the foundation columns
a) 25mm thick boards (4 Usages) 0.27m/m2
b) 50x100mm battens ( 10 Usages) 4.6m/m2 0.27m/m2
c) 50x125mm beams (10 Usages) 1.05m/m2 0.10m/m2
d) Nails 0.20kg/m2
e) Mould oil 0.06 lit/m2
10 Form work for sides of the columns
a) 25mm thick boards (4 Usages) 0.27m/m2
b) 50x75mm battens ( 10 Usages) 4.6m/m2 0.46m/m2
c) Struts # 60mm (10 Usages) 2.0m/m2 0.20m/m2
d) Nails 0.30kg/m2
e) Mould oil 0.06 lit/m2
11 Form work for sides of the beam
a) 25mm thick boards (1 Usages) 0.27m/m2
b) 50x75mm battens ( 10 Usages) 4.2m/m2 0.46m/m2
c) Beam 50x100mm (10 Usages)2.1m/m2 0.20m/m2
d) Nails 0.30kg/m2
e) Mould oil 0.06 lit/m2
12 Form Work for sides of the walls:
a) 25mm thick boards (4 Usages) 0.27m/m2
b) 50x75mm battens ( 10 Usages) 4.2m/m2 0.42m/m2
c) 50x125mm beams (10 Usages) 1.05m/m2 0.105m/m2
d) Struts # 6mm eucalyptus (10 Usages) 1m/m2 0.10m/m2
e) Nails 0.30kg/m2
f) Mould oil 0.06 lit/m2
Item Type Of Work Quantity
Concrete Block For Foundation
1 150mm thick concrete hollow block foundation wall bedded in
cement mortar 1:4
a) Concrete hollow block 12.5pcs/m2
b) Mortar (10m joints + 5% waste) 0.0138m3/m2
c) Cement 0.01m3/m2
d) Sand 0.01m3/m2
e) Hollows filled with concrete mortar 1;5 0.08m3/m2
f) Cement 0.19qts/m2
g) Sand 0.07m3/m2
2 Ditto, but 200mm thick
a) Concrete hollow block 12.5pcs/m2
b) Mortar 0.0184m2/m2
c) Cement 0.05qts/m2
d) Sand 0.01m3/m2
e) Hollows filled with concrete mortar 1;5 0.11m3/m2
f) Cement 0.26qts/m2
g) Sand 0.09m3/m2
3 Ditto, but 250mm thick
a) Concrete hollow block 12.5pcs/m2
b) Mortar 0.023m2/m2
c) Cement 0.06qts/m2
d) Sand 0.02m3/m2
e) Hollows filled with concrete mortar 1;5 0.14m3/m2
f) Cement 0.33qts/m2
g) Sand 0.12m3/m2
4 Natural Stone masonry Foundation:-
400mm thick hard basaltic stone measonry foudation:-
Wall bedded in cement mortar 1:4 in full joints
a) Basaltic Stone 1.25m3/m3 x 0.40 m3 x 1.05 waste 0.53m3/m2
b) Mortar 0.34m3/m3 x 0.40mm x 0.40 1.05 waste 0.14m3/m2
c) Cement 0.392qts/m2
d) Sand 0.112m3/m2
5 Ditto but one side roughly dressed & left for pointing:
a) Basaltic Stone 1.34m3/m3 x 0.40 m3 x 1.05 waste 0.56m3/m2
b) Mortar 0.34m3/m3 x 0.40mm x 0.40 1.05 waste 0.14m3/m2
c) Cement 0.392qts/m2
d) Sand 0.112m3/m2
Item Type Of Work Quantity
Burnt brick walls for super structures:
6 120mm thick burnt brick wall bedded in cement lime mortar
1:2:9 both side left for plastering.
a) Brick 57.7pcs/m2
b) Mortar (with 5% waste) 0.026m3/m2
c) Cement 0.031qts/m2
d) lime 0.048qts/m2
e) Sand 0.02m3/m2
7 Ditto, but 250mm thick
a) Brick 115.4pcs/m2
b) Mortar (with 5% waste) 0.062m3/m2
c) Cement 0.07qts/m2
d) lime 0.11qts/m2
e) Sand
8 Ditto, but 150mm thick
a) Hollow concrete block 12.5pcs/m2
b) Mortar (with 5% waste) 0.0138m3/m2
c) Cement 0.16qts/m2
d) lime 0.02qts/m2
e) Sand 0.01m3/m2
9 Ditto, but 200mm thick
a) Hollow concrete block 12.5pcs/m2
b) Mortar (with 15% waste) 0.0184m3/m2
c) Cement 0.021qts/m2
d) lime 0.34qts/m2
e) Sand 0.014m3/m2
10 Ditto, but 250mm thick
a) Hollow concrete block 12.5pcs/m2
b) Mortar (with 15% waste) 0.023m3/m2
c) Cement 0.027qts/m2
d) lime 0.042qts/m2
e) Sand 0.017m3/m2
Natural Stone masonry for super structure:-
11 350mm thick trachytic stone wall bedded in cement mortar 1:4
one side left for plastering & one side dressed & left for pointing
a) Trachytic Stone 1.33m3/m3 x 0.65 m3 x 1.05m waste 0.9m3/m3
b) Cement Mortar 0.264m3/m3 x 0.35mm x 1.05 waste 0.1m3/m2
c) Cement 0.28qts/m3
d) Sand 0.80m3/m3
Item Descrption
E. Form Work
24 Form work for footing 1.52h/m2(carpenter)
1.5h/m2( carpenter)
0.77h/m2(labourer)
25 Ditto but sides of columns 2.25h/m3(carpenter)
2.25h/m2( carpenter)
1.4h/m2(labourer)
26 Ditto but for flat slabs 1.31h/m2(carp.)+31h
m2(ass.Carp.)+65m(lab.)
27 Ditto but for edgesof slabs(average 20cm high) 0.41/m(carpenter)
0.41h/m(ass.Carp.)
0.13h/m(laboburer)
F.Masonry Stone
28 Constructing 50cm thick stone foundation wall 8.25h/m3(mason)+10.35hm3
29 Ditto but above ground level with one side roughly dressed 10.98h/m3(mason)+11.25h/m3
30 40cm thick stone wall one side left for plastering & the other for
pointing 9.86h/m3(mason)+12.30h/m3
31 Ditto but both sides dressed & laft for pointing 10.76h/m3(mason)+13.5h/m3
G. Block Work
32 12cm thick wall both side left for plastering 1.73h/m2+(mason)+1.73h/m3
33 Ditto but one side left for plastering the other for pointing 1.92h/m2(mason)+1.92h/m2
34 Ditto but 25cm thick brick wall both sides left for pointing 2.89h/m2(mason)+
2.89h/m2(labourer)
35 Ditto but one side left for plastering the other for pointing 3.15h/m2(mason)+3.15h/m2
36 10cm thick H.C.B wall both sides left for plastering 1.18h/m2(mason)+1.18h/m2
37 Ditto but one side left plastering & the other for pointing 1.28h/m2(mason)+1.28h/m2
38 Ditto but 15cm H.C.B wall both sides left for plastering 1.23h/m3 (labourer)
39 Ditte but one side left for plastaring the other for pointing 1.34h/m3 (massone) +1
40 Ditto but 20 cm C.H.B. wall both sides left for plastering 1.28h/m2(mason)+1.28h/m2
41 Ditto but one side left for plastering the other for pointing 1.41h/m2(masson)+1,41h/m2
H. Plastering
42 Plastering in first coat 0.18h/m2(Plaster)+0,18h/m2
43 Ditto but in second coat 0.54h/m2(labourer)
44 Ditto but in finishing coat 0.18h/m2(Plasterer)+0.18 H/m2 (Plasterar)
45 Tyrolen rendering 0.63h/m2(plasterer)+0.63h/m2(plasterer)
0.63h/m2(labourer)
I. Pointing
46 Pointing to brick wall 1.41h/m2(plasterer)m2(labourer)
47 Ditto but H.C.B wall 0.69h/m2(plasterer)+1.041/m2(labourer)
48 Ditto but to stone wall 1.13h/m2(plasterer)+1.7h/m2
Item Descrption
J.Morter & Screeding
49 Mixing cemp-morter manually 12h/m3(labourer)
50 Ditto but cement mortar of 1:2 13.8h/m3(labourer)
51 Cement screeding (3.5cm thick) 1h/m2(prvier)+1.19h/m2(labourer)
52 5x10cm tid joint on ground floor 0.11h/m(carpenter)+0.11h/m
53 2.5x15cm zigba for trussing 0.25h/m(carpenter)+0.11h/m(labourer)
54 5x10cm zigba diagonal & vertical for trussing 0.38h/m(carpenter)+0.3h
55 5x10cm zigba rafter intruss 0.19h/m(carpenter)+0.19h/m
56 5x10cm zigba purlin 0.14h/m(carpenter)+0.19h/m
57 5x50cm zigba for surpension of ceiling 0.14h/m(carpenter)+0.14h/m
58 8cm eucalyptus for lower & upper cord in truss 0.38h/m(carpenter)+0.38h/m
59 6cm eucalptus for diagonal & vertical in truss 0.22h/m(carpenter)+0.2h/m
60 Tid wood flooring 1.32h/m2(carpenter)+0.59h/m2
L. Flooring
61 Glazed ceramic wall tile of size 15x15x0.6cm & 1.8x1.8x0.04cm
mostick tiles 3.51h/m2(tiler)+3.54h/m2
62 Terazzo tiles of size 20x20x2cm 1.67h/m2(tiler)+2.24h/m2
63 100x30x2cm marble slate paving 1.8h/m(mason)+1.98h/m2
64 Flooring in plastic tiles of 20x20x.02cm 0.99h/m(teller)+1.11h/m2
65 25cm thick hard-core 1.47h/m2(labour)
M. Painting
66 Painting in 3 coat of plastic paint 1.08h/m2(painter)
67 Ditto but in oil paint 0.75h/m2(painter)
N. Water Proofing
68 Bituminous roofing 1 coat of primer & one play of glass fiber
behberane 2.64h/m2(roofer)+2.64h/m2(labourer)
69 Ditto but glass fiber memberance in two plies 3.63h/m2(roofer)+3.63h/m2(;abourer)
O. Concrete pipe Laying
70 Laying 15cm cement pipe 0.6h/m(mason)+1.34h/m(labour)
71 Ditto but 50cm pipes 0.22h/m(mason)+2.43h/m(labour)
72 Ditto but 20cm pipes 0.71h/m(mason)+1.55h/m(labour)
73 Ditto but 40cm pipes 0.07h/m(mason)+2.27h/m(labour)
74 Bitumen P-pavement 1 coat of primer one surface dressing coat
two layers of chippeings 0.32h/m2/m(sparayer)+0.12h/m2(labour)
75 Ditto but with two surface dressing coats & 3 layers of chipping (Driver)+1.53h/m2(labourer)
76 Complaction of sub-bars to 10cm consolidated thickness 0.04h/m3(rolver driver)+0.11h/m2
Q. Glazing
77 Glazing with putty in 3mm thick clear glass 2.07h/m2(glazier)+2.07h/m2
78 Ditto but in 4mm clear glass 2.58h/m2(glazier)+2.58h/m2
79 Ditto but in 5mm clear glass 2.58h/m2(glazier)
80 Ditto but in 6mm clear glass 2.94h/m2(glazier)
Item Descrption
R. Doors & Windows
81 Fixing flush door of size 90x210cm 2.10h/pc(carpenter)+2.1h/pc(labourer)
82 Fixing wooden window of size 100x100cm 2.13h/pc(carpenter)+2.13h/pc(labourer)
S. Sanitary Line & Installation
83 Installing 50mm PVC pipe under ground bedded with sand 0.2h/m(plumber)+0.73h/m(labour)
84 Ditto but in 75mm 0.26h/m(plumber)+0.92h/m(labour)
85 Ditto but in 110mm 0.26h/m(plumber)+0.92h/m(labour)
86 Installing 1/2" glavanzed steel pipe in walls 0.42h/m(plumber)+1.98h/m)
(plasterer)+0.53h/m(labourer)
87 Ditto but in 3/4" pipe 0.74h/m(plumber)+1.98h/m)
(plasterer)+0.53h/m(labourer)
88 Installing 12 glavanized steel pipe increnahes(excluding)excavation
89 Ditto but 2" galvanized steel pipe 0.36h/m(plumber)+0.5h/m(labourer)
90 Installing wash basing 3.75/m(plumber)+0.5h/m(labourer)
91 Ditto But both tub 5.31h/pc(labourer)+3.31h/pc
92 Ditto but W.C 4.73h/pc(labourer)+4.73h/pc
93 Ditto but water heater(No lit) 4.2h/pc(labourer)+1.5h/pc
(electrician )+1.5h/pc
94 Installing electrical outer or socket outlet 2.32h/outlet(electrician)+2.32h/outlet
(asst electrician)
GENERAL FORMULA
A. Assumed Concrete mix ratio =1:2:4
Volume of concrete = XM3
a. Cement =1/6xXm3x1400 kg/m3x1.05wastage
b. Sand =2/6xXm3x1.30shrinkage x 1.15wastage
c. Gravel =4/6xXm3x1.30shrinkage x 1.15wastage
B. Mix Ratio =1:1
Volume of lime morter = YM3
a. Lime = 1/4xYm3x1.20shrinkage x1100kg/m3x1.05wastage
b. Sand =2/7xYm3x1.20shrinkage x 1.20wastage
C. Mix Ratio =1:2:9
Volume of cement lime mortar =Zm3
a. Cement =1/12xZm3x1.20shrinkage x 1400 kg/m3x1.05wastage
b. Sand =2/12xZm3x1.20shrinkage x 1100kg/m3x1.05wastage
c. Gravel =9/12xZm3x1.20shrinkage x 1.2wastage
D. Mix Ratio = 1:3
Volume of cement mortar =Ym3
a. Cement =1/4xYm3x1.20shrinkage x 1400 kg/m3xwastage
b. Sand =1/4xYm3x1.20shrinkage x 1.2wastage
E. Maximum amount of water that is needed to mix & place either
R.C or plane concrete is =500wt.
a) For concrete =500liters or 0.5m3/m3
b) For Mortar =400 liters or 0.4m3/m3
Type of work
HARDCORING
20cm thick basaltic stone hard coring :
a. Basaltic stone0.20mx1.15 decrease & waste 0.23m3/m2
Coarse gravel filling for hard core to a finished thickness of 15cm
a. Coarse gravel 0.15mx x1.15decrease & waste 0.17m3/m2
Roof Work
28 gauge roofing sheet
a. Fixers with plastic washers + 5% waste 1.25m2/m2
4.2pcs/m2
400mm wide roof valley covers in 28 gauge
a. Sheet + 5% waste 0.57m2/ml
b. Fixers + 5% waste 4.3pcs/ml
500mm wide roof valley covers in 28 gauge
a. Sheet + 5% waste 0.57m2/ml
b. Fixers + 5% waste 4.3pcs/ml
Eaves gutter 100x100m (girth not exceeding room)
a. 0.5mm gal. steel sheet + 5% waste(0.42m2/mlx4.12kg/m2) 1.73kg/ml
b. 3.20mm L-400mm steel brackets + 5% waste 0.2kg/ml
c Fixers 0.02kg/ml
1 The absolute volume of material, is the minimum volume of the material with all voids
removed, is given by the equations.
Absolute volumes wight of material in kilogrammes
specific gravity x weight of 1m3 of water
wt of material in kgs
S.B x 100kg
1 Nails Pcs kilogramme
1cm 950 1
2cm 815 1
4cm 546 1
6cm 275 1
7cm 180 1
8cm 127 1
10cm 63 1
12cm 44 1
15cm 29 1
Assumption
a. Roofing Work:
- Roofing nails = 14pcs/G.I.S
- Purlin = 8cm nails
- Truss = 10 or 12 cm nails 20-35 pcs per truss
b. Ceiling Work
- Bateens = 8cm nails -16per m2
- Chipwood = 4cm nails - 80 pcs per chipwood
or 25 pcs per m2
c. Beams:
- 6cm nails = 60pcs 1ml
- 12cm nails = 6-8pcs 1ml(stiffening)
ason)+10.35hm3
mason)+11.25h/m3
ason)+12.30h/m3
mason)+13.5h/m3
mason)+1.73h/m3
ason)+1.92h/m2
ason)+3.15h/m2
ason)+1.18h/m2
ason)+1.28h/m2
.34h/m2 (labourer)
ason)+1.28h/m2
asson)+1,41h/m2
aster)+0,18h/m2
asterer)m2(labourer)
asterer)+1.041/m2(labourer)
asterer)+1.7h/m2
r)+1.19h/m2(labourer)
penter)+0.11h/m
penter)+0.11h/m(labourer)
penter)+0.3h
penter)+0.19h/m
penter)+0.19h/m
penter)+0.14h/m
penter)+0.38h/m
penter)+0.2h/m
rpenter)+0.59h/m2
er)+3.54h/m2
er)+2.24h/m2
on)+1.98h/m2
er)+1.11h/m2
ofer)+2.64h/m2(labourer)
ofer)+3.63h/m2(;abourer)
on)+1.34h/m(labour)
son)+2.43h/m(labour)
son)+1.55h/m(labour)
son)+2.27h/m(labour)
(sparayer)+0.12h/m2(labour)
3h/m2(labourer)
lver driver)+0.11h/m2
azier)+2.07h/m2
azier)+2.58h/m2
penter)+2.1h/pc(labourer)
penter)+2.13h/pc(labourer)
mber)+0.73h/m(labour)
mber)+0.92h/m(labour)
mber)+0.92h/m(labour)
mber)+1.98h/m)
.53h/m(labourer)
mber)+1.98h/m)
.53h/m(labourer)
mber)+0.5h/m(labourer)
mber)+0.5h/m(labourer)
ourer)+3.31h/pc
ourer)+4.73h/pc
urer)+1.5h/pc
electrician)+2.32h/outlet
GENERAL FORMULA
A. Assumed concrete mix ratio = 1:2:4
Volume of concrete = xm3
a) Cement = 1/7xXm3x1400kg/m3x1.30 shrinkage x1.05 wastage
b) Sand = 2/7xXm3x1.30 shrinkagex1.15 wastage
c) Gravel = 4/7xXm3x1.30 shrinkagex1.15 wastage
B. Mix ratio = 1:2
Volume of lime mortar = Ym3
a) lime = 1/3xYm3x1.20 shrinkage x700/m3x1.05 wastage
b) Sand = 2/3xYm3x1.20 shrinkage x1.20 wastage
C. Mix ratio = 1:2:9
Volume of cement lime mortar = Zm3
a) Cement = 1/12xZm3x 1.20 shrinkage x 1400 kg/m3 x1.05 wastage
b) Lime = 2/12 xZm3 x1.20 shrinkage x 700/m3 x1.05 wastage
c) Sand = 9/12 xZm3 x1.20 shrinkage x 1.20wastage
D. Mix ratio = 1:3
Volume of cement mortar = Ym3
a) Cement = 1/4x Ym3 x1.20 shrinkage x 1400kg/m3 x1.05 wastage
b) Sand = 3/4x Ym3 x1.20 shrinkage x 1.20 wastage
UNIT WEIGHT
- Measured unit weight of fresh concrete = 2300 kg/m3
- Measured unit weight of R.C = 2400 kg/m3
- Measured unit weight of cement = 1400 kg/m3
- Measured unit weight of lime = 700 kg/m3
- Measured unit weight of sand = 1350 kg/m3
- Measured unit weight of gravel = 1300 kg/m3
- Measured unit weight of steel = 7850 kg/m3
WORK ACTUAL WORK
ITEM DESCRIPTION GANG TIME EXCCUTED TO BE EXECUTED
1 Excavation 1 dylb 1 day 0.5-0.75m3 0.75-1m3
2 Back fill(loose volume) 1 dylb 1 day 1.2m3 1.5-3m3
3 Cartaway 1 dylb 1 day 1.5-3m3 3-5m2
4 Hard Coreing imas+2L 1 day 6-10m 12-15m2
5 Masonry (B.G.L) imas+2L 1 day 0.5-1m3 1.2-3m3
6 Masonry (A.G.L) 1mas+2L 1 day 0.5-0.75 1.00-2.3m3
7 Form Work
1. Beam B.G.L 1 cap-2L 1 day 5-8m2 10-20m2
2. Footing 1 cap-2L 1 day 5-8m2 10-20m2
3. Beam A.G.L 1 cap-2L 1 day 5-8m2 10-25m2
8 Reinforcement
1. Bending & Cutting 21-2L 1 day 1 qt-15qt 11qt-3qt
2. Erecting 21-10L 1 day 10 qt-20qt 15qt-25qt
9 Concrete Work
Beam B.G.L 1 day
Slab ( Ground Floor) 1 day
Tie beam above 2m 1 day
Column up to 2m 1 day
Column above 2m 1 day
10 Bricks
Double Wall 1m+2L 1 day 1.5-3m2 2.5m2-4m2
Single Wall 1m+2L 1 day 3m2-6m2 5m2-8m2
11 Hollow Block
Double Wall 1m=2L 1 day 2-3.5 2-5m2
Single Wall 1m=2L 1 day 3-6m2 5-8m2
12 Plastering
1st Coat 1p+2L 1 day 1.0-15m2 16-24m2
2nd Coat 1p+2L 1 day 2-4m2 3-6m2
3rd Coat 1p+2L 1 day 5-7m2 8-10m2
13 Roofing
1. Truss (ground) 1cap+2L 1 day 2.3 truss 4-6trusses
2. Truss erecting 2cap+81 1 day 8-10truss 15-20trusses
3. Purlin 2cap+4L 1 day 50-100ml 200-300ml
4. Corr-iron sheet 1cap+2L 1 day 10-15sheds 20-35sheds
5. Asbestos 1cap+2L 1 day 10-15sheds
14 Fascia board 1cap+2L 1 day 10-15ml 20-35ml
15 Gutter aground work 1plumber+2L 1 day 20-30ml
Gutter (fixing) 1plumber+2L 1 day 50-70ml
WORK ACTUAL WORK
ITEM DESCRIPTION GANG TIME EXCCUTED TO BE EXECUTED
16 Flooring
Cement screed 1mas+2L 1 day 5-10m2 15-20m2
Plastic tiles 1mas+2L 1 day 15-20m2 25-30m2
Ceramic tiles parque 1mas+2L 1 day 5-10m2 15-25m2
17 Wall tileing 1 day 7.5-9m2 10-20m2
18 Window oil:-
Precast window cill (marble etc) 1mas+2L 1 day 5-10ml 8-15ml
Un precast window cill 1mas+2L 1 day 3-5ml 3-35ml
19 Door & Window
Metal door 1skiled+2L 1-2pcs 2-3pcs
Metal Window 1skiled+2L 1-2pcs 2-3pcs
Wood door 1skiled+2L 2-4pcs 3-5pcs
Wood Window 1skiled+2L 1-3pcs 2-4pcs
Door list 1car+11 25-39ml 40-55ml
Door keys 1car+11 1 day 5-10pcs 8-15ml
Window handle 1car+2L 1 day 8-13pcs 8-15ml
20 Glazing
Cutting 2cap+2L 1 day 50-100m2
Fixing 1 cap+1L 1 day 15-20m2
21 Pointing
H.B.C pointing 1p=2l 1 day
Brick pointing 1pl+2L 1 day
Masonary pointing 1pl+2L 1 day
Masonary dressed stone 1pl+2L 1 day
22 Painting
Plastic painting
1. Ceiling (adujdid) 1pt+1L 1 day 10-15G 10-20g
2. Ceiling (concrete) 1pt+1L 1 day 15-20G 15-20g
3. Wall 1pt+1L 1 day 15-20G 25-40g
4. Oil painting wall 1pt+1L 1 day 10-20G 20-20g
5. Oil painting door 1pt+1L 1 day 10-15G 20-30m
23 Sanitary Installation
G.I. pipe around 1plum-2L 1 day 10-15ml 20-30ml
Fixtures(W.C wash basin)bidit Lpc+20 1 day 1-2ptc 1-4qty
24 Electrical Installation
Fixing conduites Lec+2L 1 day 10-75ml 50-100ml
Pulling wires Lec+2L 1 day 30-50ml 50-75ml
Fixing sockets,switch 1E+1L 1 day 10pcs-30pcs 35pcs-65pcs
Fixing fittings 1E+1L 1 day 3-8pcs 15pcs-30pcs
Distribution board
WORK ACTUAL WORK
ITEM DESCRIPTION GANG TIME EXCCUTED TO BE EXECUTED
25 Cement copping
(40-50 wide) 1E+1L 1 day 3-5ml 5-10ml
Curb stone 1m+2L 1 day 5-10ml 8-20ml
Pavement 1m+2L 1 day 3-5m2 5-10m2
Rate of Production perAmount
crew of work done/breigade
Labour needed in Work No to crew Work
Item Type Of Activity a single crem Done/Day Per brigage Done/Day Remark
1 Mobilization a) Engineering aid - 1 -
b) Skilled labour 6
c) Labourer 14
d) Assistant 6
2 Excavation D7-Dozer 100m3 1 100m3
3 Masonry a) 1 Mason 1m3 23 23m3
b) 1 Asst/Mason
c) 2 Labourers
4 Form Work a) Carpenter 3m2 29 87m2
b) 1 Asst/Carpenter
c) 2 Labourers
5 Concrete a) 4 Skilled 35m3 1 35m3
b) 23 Labourers
6 Reinforcement a) 2 Skilled 75 14 1050kg
b) 2 Assistant
c) 4 Labourers
7 H.C.B & Brick a) 1 Mason 4m2 35 140m2
b) 3 Labourers
8 Pavior a) 1 Mason 15m2 23 345m2
b) 1 Assistant
c) 3 Labourers
9 Plaster a) Plasterer 4m2 20 80m2
b) 1 Asst/Plasterer
c) 2 Labourers
10 Sanitary a) Plumber 2pcs 4 8m2
b) 1 Asst/Plumber
c) 2 Labourers
11 Carpentry a) 1 Carpenter 2pcs 9 58pcs Fixing doors
b) 1 Asst/Carpenter & Windows
12 Painter a) 1 Painter 25m2 10 250m2
b) 2 Labourer
13 Glazier a) 1 Glazier 40m2 1 40m2
b) 2 Labourer
14 Roofer a) 1 Carpenter 4m2 29 116m
b) 1 Asst/Electrician
c) 4 Labourers
15 Electrical a) 1 Electrician
b) 1 Asst/Electrician
c) 2 Labourers
16 Misclianeous