ID Task Task Name Duration Start Finish 31 May '20 14 Jun '20 28 Jun '20 12 Jul '20 26 Jul

on Start Finish 31 May '20 14 Jun '20 28 Jun '20 12 Jul '20 26 Jul '20 9 Aug '20
Mode W S T M F T S W S T M F T S W S T M F
1 Supply, Installation, Testing & Commissioning of Cold Water Piping System at 60 days Fri 5/6/20 Mon 3/8/20
Pantai Hospital Ampang
2 Civil and Structural Works 57 days Fri 5/6/20 Fri 31/7/20
3 Demolishing Works 3 days Fri 5/6/20 Sun 7/6/20
4 Domestic Tank Concrete Plinth (Rooftop) 15 days Mon 8/6/20 Mon 22/6/20
5 I-Beam Installation 10 days Sun 28/6/20 Tue 7/7/20
6 Waterproofing 7 days Sat 25/7/20 Fri 31/7/20
7 Mechanical & Electrical Works 56 days Fri 5/6/20 Thu 30/7/20
8 Pipe, Valve & Fittings 56 days Fri 5/6/20 Thu 30/7/20
9 Installation at Ward A3 21 days Fri 5/6/20 Thu 25/6/20
10 Installation at Common Area, Corridor, Riser 30 days Mon 15/6/20 Tue 14/7/20
11 Installation at ward B3 21 days Thu 25/6/20 Wed 15/7/20
12 Installation at Ward A4 3 days Wed 15/7/20 Fri 17/7/20
13 Installation at Ward B2 & A2 21 days Fri 10/7/20 Thu 30/7/20
14 Water Tank 16 days Thu 25/6/20 Fri 10/7/20
15 Installation of Suction Tank at Lower Ground Floor 7 days Thu 25/6/20 Wed 1/7/20
16 Installation of Domestic Tank at Rooftop 7 days Wed 1/7/20 Tue 7/7/20
17 Switch Board & Control Panel 10 days Wed 1/7/20 Fri 10/7/20
18 Cable Installation complete with conduit, cable tray & switchboard panel10 days Wed 1/7/20 Fri 10/7/20
19 Building Automation System 10 days Tue 7/7/20 Thu 16/7/20
20 Installation of BAS, wiring & controller 10 days Tue 7/7/20 Thu 16/7/20
21 Water Pump 14 days Tue 7/7/20 Mon 20/7/20
22 Water Pump Installation 14 days Tue 7/7/20 Mon 20/7/20
23 Handover Stage 8 days Mon 27/7/20 Mon 3/8/20
24 Final Inspection 3 days Mon 27/7/20 Wed 29/7/20
25 Testing & Commissioning 3 days Wed 29/7/20 Fri 31/7/20
26 Handover 2 days Sat 1/8/20 Sun 2/8/20
27 Demobilization 2 days Sun 2/8/20 Mon 3/8/20

Task Project Summary Manual Task Start-only Deadline


TECHFIDENT SDN. BHD. Split Inactive Task Duration-only Finish-only Progress
Project: PHA COLD WATER PIPING
Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress
Date: Tue 2/6/20
Summary Inactive Summary Manual Summary External Milestone

Page 1