on Start Finish 31 May '20 14 Jun '20 28 Jun '20 12 Jul '20 26 Jul '20 9 Aug '20
Mode W S T M F T S W S T M F T S W S T M F
1 Supply, Installation, Testing & Commissioning of Cold Water Piping System at 60 days Fri 5/6/20 Mon 3/8/20
Pantai Hospital Ampang
2 Civil and Structural Works 57 days Fri 5/6/20 Fri 31/7/20
3 Demolishing Works 3 days Fri 5/6/20 Sun 7/6/20
4 Domestic Tank Concrete Plinth (Rooftop) 15 days Mon 8/6/20 Mon 22/6/20
5 I-Beam Installation 10 days Sun 28/6/20 Tue 7/7/20
6 Waterproofing 7 days Sat 25/7/20 Fri 31/7/20
7 Mechanical & Electrical Works 56 days Fri 5/6/20 Thu 30/7/20
8 Pipe, Valve & Fittings 56 days Fri 5/6/20 Thu 30/7/20
9 Installation at Ward A3 21 days Fri 5/6/20 Thu 25/6/20
10 Installation at Common Area, Corridor, Riser 30 days Mon 15/6/20 Tue 14/7/20
11 Installation at ward B3 21 days Thu 25/6/20 Wed 15/7/20
12 Installation at Ward A4 3 days Wed 15/7/20 Fri 17/7/20
13 Installation at Ward B2 & A2 21 days Fri 10/7/20 Thu 30/7/20
14 Water Tank 16 days Thu 25/6/20 Fri 10/7/20
15 Installation of Suction Tank at Lower Ground Floor 7 days Thu 25/6/20 Wed 1/7/20
16 Installation of Domestic Tank at Rooftop 7 days Wed 1/7/20 Tue 7/7/20
17 Switch Board & Control Panel 10 days Wed 1/7/20 Fri 10/7/20
18 Cable Installation complete with conduit, cable tray & switchboard panel10 days Wed 1/7/20 Fri 10/7/20
19 Building Automation System 10 days Tue 7/7/20 Thu 16/7/20
20 Installation of BAS, wiring & controller 10 days Tue 7/7/20 Thu 16/7/20
21 Water Pump 14 days Tue 7/7/20 Mon 20/7/20
22 Water Pump Installation 14 days Tue 7/7/20 Mon 20/7/20
23 Handover Stage 8 days Mon 27/7/20 Mon 3/8/20
24 Final Inspection 3 days Mon 27/7/20 Wed 29/7/20
25 Testing & Commissioning 3 days Wed 29/7/20 Fri 31/7/20
26 Handover 2 days Sat 1/8/20 Sun 2/8/20
27 Demobilization 2 days Sun 2/8/20 Mon 3/8/20