METHOD STATEMENT Revision : 0
Issued : Nov 2002
UE Construction Sdn Bhd UEC/MS/KGTB/GI/005

Electrified Double Track Project Between Rawang And Ipoh

CONTROLLED COPY NO:

METHOD STATEMENT FOR GROUND


IMPROVEMENT (REMOVAL & REPLACEMENT)
AT APPROACH OF VBC KG. TITI BESI
(CH 232.457)

(PACKAGE KAMPAR TO BIDOR)

Prepared by Date Reviewed by Date Approved by Date

Sheikh Faizal 18/11/02 Mohd Fauzi 18/11/02 B.T Tee 19/11/02

IMPORTANT:

The information contained herein is proprietary property of UE CONSRUCTION


SDN BHD.

The holder agrees to the following:


1. Not to reproduce; copy; reveal; publish; or, distribute in a whole or any
portion of in without authorisation; and,
Page No. : 2 of 7
METHOD STATEMENT Revision : 0
Issued : Nov 2002
UE Construction Sdn Bhd UEC/MS/KGTB/GI/005

Electrified Double Track Project Between Rawang And Ipoh

2. To maintain this document in confidence.

CONTENTS

1.0 SCOPE

2.0 MATERIALS

3.0 EQUIPMENT & RESOURCES

4.0 METHOD

5.0 QUALITY CONTROL PROCEDURE

6.0 HEALTH, SAFETY AND ENVIRONMENT

7.0 TRACK POSSESSION

8.0 SUMMARY OF FORMS

9.0 DOCUMENTATION
Page No. : 3 of 7
METHOD STATEMENT Revision : 0
Issued : Nov 2002
UE Construction Sdn Bhd UEC/MS/KGTB/GI/005

Electrified Double Track Project Between Rawang And Ipoh

1.0 SCOPE

This method statement specifically describes the procedure involved


in construction of ground improvement work at the approach of
Vehicular Box Culvert near Kg. Titi Besi to ensure that the works is
completed in accordance with the specification and applicable
Standard Codes of Practice and that the activities are documented.

The scope of work shall include :

a) Joint inspection with SE on the proposed removal and


replacement area.

b) Carry out of relevant pre-treatment and post treatment tests


specified in the Drawings.

c) Carry out of removal of unsuitable material and replacement


with approved suitable fill material at location specified in the
Drawings.

d) Installation of all necessary geotechnical instrumentation for


monitoring purposes as specified in the Drawings.

e) Obtaining the relevant approval from local authorities, if


required.

f) Installation of all necessary local traffic management, if


required.

2.0 MATERIALS

Materials to be used will be :

2.1 Suitable Fill Material

Suitable material shall comprise all materials that meet the specific
requirements, physically and chemically, for incorporation in the
works as indicated in the contract. The material shall be capable
for being compacted to a degree specified in the drawings and
relevant Specification, regardless of whether it is obtained from
within or outside the Site. Materials that are soft or unsuitable
merely because they are too wet or too dry for effective compaction
are not to be classified as unsuitable, unless otherwise classified by
the S.E.

Suitable materials are defined as follows:


Page No. : 4 of 7
METHOD STATEMENT Revision : 0
Issued : Nov 2002
UE Construction Sdn Bhd UEC/MS/KGTB/GI/005

Electrified Double Track Project Between Rawang And Ipoh

‘Cohesive soil’ includes clay with up to 20% of gravel or rock having


moisture content 3% of Optimum Moisture Content (OMC)
determined in accordance with BS 1377 : Part 4 : 1990 clause 3.5.
‘Well graded granular and dry cohesive soils’ including clay
containing more than 20% of gravel or rock and/or having moisture
content 3% of OMC determined in accordance with BS 1377 : Part
4 : 1990 clause 3.5, well graded sands and gravel with a uniformity
coefficient exceeding 10.
‘Uniformly graded material’ includes sands and gravel with a
uniformity coefficient of 10 or less and all silts. Any soil containing
80% or more of material in the particle size range 0.06 to 0.002
mm will be regarded as silt for this purpose.

2.2 Geotextile filter fabric.

3.0 EQUIPMENT & RESOURCES

3.1 Machinery/Equipment

The basic equipment to be used is as follows:

a) Back pusher
b) 10 wheel lorry
c) Hydraulic excavator
d) Roller compactor
e) 1 ton plate compactor

3.2 Manpower

Manpower involved :

a) Supervisor
b) Back pusher operator
c) Excavator operator
d) Compactor operator
e) Lorry driver

4.0 CONSTRUCTION METHOD

4.1 The location and depth for removal of unsuitable materials shall be
determined by reviewing the soil investigation reports or by
carrying out Mackintosh Probe tests. Details shall be recorded in the
form DRB-F-E011 and the works will proceed with the instructions
of SE.
Page No. : 5 of 7
METHOD STATEMENT Revision : 0
Issued : Nov 2002
UE Construction Sdn Bhd UEC/MS/KGTB/GI/005

Electrified Double Track Project Between Rawang And Ipoh

4.2 Trial pits up to a depth not less than 1 m below the estimated depth
of removal of unsuitable material, Mackintosh probings or other test
as directed by S.E shall be carried out at 30 m interval to decide
the actual depth of removal as well as the depth of ground water
table.

4.3 The depth of ground water table shall be measured by pumping out
water from the pit up to the bottom level of pit and allowing the
water level to stabilize for 24 hours.

4.4 A joint survey will be carried out with SE to inspect and set out the
location in accordance with Ground Improvement Work
(Removal/Replacement of Unsuitable Material) drawings.

4.5 The unsuitable material shall be excavated and removed. The depth
and extent should be given by SE based from Mackintosh Probe
Report. Cross sections showing the extend and depth of removal of
unsuitable material will be submitted later.

4.6 Level of excavation shall be constantly monitored using dumpy


level.

4.7 Geotextile filter fabric will be placed above base of excavation when
directed by SE.

4.8 The area will be filled with suitable fill or granular material
complying with table 2.1 of Technical Specification up to existing
ground level based on Ground Improvement Work
(Removal/Replacement of Unsuitable Material) drawings or as
instructed by SE.

4.9 If ground water table is encountered, granular material complying


with table 2.1 of Technical Specification shall be used as
replacement material from the base of excavation up to a height of
300mm above ground water table.

4.10 All necessary geotechnical instruments for settlement monitoring


records will be installed according to Geotechnical Instrumentation
drawings. Actual locations and depths of instrumentation will be
decided by S.E at site.

5.0 QUALITY CONTROL PROCEDURE


Page No. : 6 of 7
METHOD STATEMENT Revision : 0
Issued : Nov 2002
UE Construction Sdn Bhd UEC/MS/KGTB/GI/005

Electrified Double Track Project Between Rawang And Ipoh

On site quality control shall be carried out in accordance with the


Inspection and test plan as attached in the Appendix B to ensure
that the job is carried out to the client satisfaction.

Materials test must be conducted to ensure their conformance with


the specification requirement.

6.0 HEALTH, SAFETY AND ENVIRONMENT

6.1 The work to be carried out in accordance with the Project Safety
Plan. Particular activities requiring attention are highlighted in the
Appendix C.

6.2 All machinery engaged are subject to the standard colour coding
system as required in the Site Safety Manual and all other relevant
requirements.

6.3 All the works shall comply with DRB-HICOM Environmental


management Plan.

6.4 Toolbox meeting will be carried out on construction area at regular


intervals to ensure compliance with the Safety Plan and familiarity
with accident and emergency procedures.

6.5 Conduct safety induction course to workers before commencement


of work.

6.6 Provide PPE to all workers including safety helmet, safety shoe,
vest, ear protector, etc.

6.7 Provide signboards to warn workers and public of dangers


associated with construction works.

6.8 Inspect all machinery at site and ensure that it has competent
certificate and is safe to operate.

7.0 TRACK POSSESSION

Not applicable.

8.0 SUMMARY OF FORMS


Page No. : 7 of 7
METHOD STATEMENT Revision : 0
Issued : Nov 2002
UE Construction Sdn Bhd UEC/MS/KGTB/GI/005

Electrified Double Track Project Between Rawang And Ipoh

Forms which shall be used for the works are:

8.1 Soil Compaction Test (Form No: DRB-F-E007).

8.2 Field Density Test (Form No: DRB-F-E009).

8.3 Mackintosh Probe (Form No: DRB-F-E011).

All the forms are attached in Appendix D.

9.0 DOCUMENTATION

9.1 Appendix A: Site Organisation Chart

9.2 Appendix B: Inspection and Test Plan

9.3 Appendix C: Safety, Health and Environment

9.4 Appendix D: Related Forms