Approved By: HSE Manager Date : 1st November, 2015 Rev. No. 1
HAZARDS Effect
Main Activity Sub Activity HAZARDS
Likelihood
Likelihood
Risk Level
Risk Level
( If the Hazard is Released )
Severity
Severity
Class
Class
Prevention & Mitigation Recovery Measures
1 Electrical Work Electrical Work Static electricity Fire A 5P 5P H Raise permit to work and implement lock out and tag out system if required. ERP, A 1P A1P L
High Voltage Equipment damage Conduct TBT and discuss about electrical hazards, risks and controls. MEDEVAC,
Slippery surface Electrical burns Confirm that the electricity is isolated by testing the ON switch. Medical
Inadequate hand Personnel injury Double checking of isolation by using fluke multi meter. facilities
tools Fatality Use proper electrical tester (amp meter/volt meter) to confirm that electricity is
Down time off.
Effecting Company Technical training for all electricians.
reputation Proper grounding system and lay out
Electric shock Use special PPE’s for electrical works if required.
Provision of good quality electrical wires
Controlled power supply area.
Inspect all electric cables regularly and ensure all cables are wrapped and in
good condition.
Provision of STOP, HSE induction and PTW trainings.
Training and awareness campaign on electric risks.
Only authorized personnel to isolate and execute repairs.
Rescue rod to be available in main electrical room.
Use quality product and certified items suitable for specified hazardous zones 1
& 2.
Each installation shall have one common earth grid connected to at least two
groups of earth electrodes.
The earth grid shall extend throughout the installation in the form of a ring
circuit with branch connections to the equipment and structures to be earthed.
Use non-conductive hand tools
Provision of preventive maintenance system
Maintain good housekeeping after completing any electrical job.
Refer to the following documentations:
PDO Haz-ID Section # 12.Electrical.
PDO SP-1099 Electrical Safety Rules.
PDO SP-1111 Specification for Temporary Electrical Supplies for Construction &
Maintenance Work.
NDSC PTW Procedure.
Hazard Identification STOP SYSTEM.
RA-R9-01-003-01