Fabrication S Curve STP for Reliance KGD6 RUBY FPSO Project

Plan
Cut off 19-Feb-20 Description Wtg Actual Variance
Progress
Overall Progress 100.00% 26.67% 20.60% -6.07%
Procurement 20.92% 63.67% 51.94% -11.73%
Profab Documentation 6.17% 82.83% 70.77% -12.06%
Prefab Buoy Lower Section 4.37% 90.91% 66.06% -24.85%
Prefab Buoy Middle Section 6.41% 35.95% 19.83% -16.12%
Prefab Buoy Upper Section 5.03% 0.00% 0.00% 0.00%
Assembly Buoy Lower Section 4.42% 36.53% 25.75% -10.78%
Assembly Buoy Middle Section 4.10% 5.16% 0.00% -5.16%
Assembly Buoy Upper Section 3.58% 0.00% 0.00% 0.00%
Final Assembly Buoy 6.36% 0.00% 0.00% 0.00%
Prefabrication Turret Tank 10.94% 1.21% 0.61% -0.61%
Prefabrication Mooring Lugs Cluster 5.59% 0.00% 0.00% 0.00%
Prefabrication Turret Shaft 7.52% 0.00% 0.00% 0.00%
Assembly Turret 13.59% 0.00% 0.00% 0.00%
Assembly Buoy to Turret 0.37% 0.00% 0.00% 0.00%
FAT STP Buoy and Turret 0.40% 0.00% 0.00% 0.00%
Delivery Preparation 0.24% 0.00% 0.00% 0.00%

No Task Name Duration Start Finish % Complete

2 LOA 0 days 9/16/2019 9/16/2019 100%


3 Contract Award (APL P.O.) 0 days 10/18/2019 10/18/2019 100%
4 Kick-off Meeting 0 days 10/16/2019 10/16/2019 100%
5 Pre-Inspection Meeting 0 days 12/3/2019 12/3/2019 100%
6 Procurement 194 days 10/4/2019 5/28/2020 52% 790 20.92% 63.67% 51.94% -11.73%
7 APL MTO 0 days 10/4/2019 10/4/2019 100% 1 0.13% 100 100 0
8 Plate from mill -ABS AH/DH/EH36 18 wks 10/4/2019 1/21/2020 100% 110 13.92% 100 100 0
9 Plate from mill - S460 G2+M 18 wks 10/4/2019 1/21/2020 100% 110 13.92% 100 100 0
10 Plate from Stock (5 sheet) 5.96 wks 11/12/2019 12/16/2019 100% 35 4.43% 100 100 0
11 Turret Lug - Plate 100mm THK& 50mm THK 18 wks 10/4/2019 1/21/2020 100% 110 13.92% 100 100 0
12 Pedestal Flange - Plate 140mm 37 days 10/16/2019 11/27/2019 100% 43 5.44% 100 100 0
13 Riser Guide Pipe (Plate 12& 30mm) 90 days 2/7/2020 5/28/2020 0% 112 14.18% 12 0 -12
14 Round Bar Mooring Lug& Riser Hub Forging 60 days 2/7/2020 4/18/2020 0% 72 9.11% 18 0 -18
15 Material Protection for ROV Ballast System 14 days 2/24/2020 3/10/2020 0% 16 2.03% 0 0 0
16 Pipe Fender& Buoy Protection Structure 14 days 2/24/2020 3/10/2020 0% 16 2.03% 0 0 0
17 Paint Material 60 days 1/18/2020 3/30/2020 0% 73 9.24% 45 0 -45
18 Bolts& Nuts Material 60 days 1/18/2020 3/30/2020 0% 73 9.24% 45 0 -45
19 Material Sturcture (Tranportation Frame / Grillage) 14 days 3/31/2020 4/16/2020 0% 17 2.15% 0 0 0
20 Engage Third Party certification 0 days 11/30/2019 11/30/2019 100% 1 0.13% 100 100 0
21 Engage Machining subcontactor 0 days 12/3/2019 12/3/2019 30% 1 0.13% 100 30 -70
22 APL Engineering 113 days 10/2/2019 2/12/2020 0% 7 0.19% 100.00% 31.43% -68.57%
23 Buoyancy Cone AFC Drawings 0 days 10/2/2019 10/2/2019 100% 1 14.29% 100 100 0
24 Buoyancy Protection Struct' AFC Drawings 0 days 2/7/2020 2/7/2020 0% 1 14.29% 100 0 -100
25 Turret AFC Drawings 0 days 2/7/2020 2/7/2020 20% 1 14.29% 100 20 -80
26 Riser Guide Pipe Drawing 0 days 2/7/2020 2/7/2020 100% 1 14.29% 100 100 0
27 Turret Mooring Lugs Cluster AFC Drawing 0 days 2/8/2020 2/8/2020 0% 1 14.29% 100 0 -100
28 Protection ROV& Ballast Pipe AFC drawing 0 days 2/12/2020 2/12/2020 0% 1 14.29% 100 0 -100
29 Transportation Frame / Grillage Turret Drawing 0 days 2/12/2020 2/12/2020 0% 1 14.29% 100 0 -100
30 APL CPI 209 days 12/16/2019 8/31/2020 0% 19 0.50% 15.79% 21.05% 5.26%
31 Bearing Upper Axial Segment 0 days 8/31/2020 8/31/2020 0% 1 5.26% 0 0 0
32 Bearing Dynamic Seawater Seal 0 days 8/31/2020 8/31/2020 0% 1 5.26% 0 0 0
33 Bearing Lower Radial Segment 0 days 8/31/2020 8/31/2020 0% 1 5.26% 0 0 0
34 Bearing Upper Radial Segment 0 days 8/31/2020 8/31/2020 0% 1 5.26% 0 0 0
35 Bearing Ring 0 days 8/31/2020 8/31/2020 0% 1 5.26% 0 0 0
36 Bearing Locking Ring Segment 0 days 8/31/2020 8/31/2020 0% 1 5.26% 0 0 0
37 Bearing Distance Sleeve 0 days 8/31/2020 8/31/2020 0% 1 5.26% 0 0 0
38 Bearing Static Seal 0 days 8/31/2020 8/31/2020 0% 1 5.26% 0 0 0
39 Bearing PTFE Plug (dia 30x9) 0 days 8/31/2020 8/31/2020 0% 1 5.26% 0 0 0
40 Bearing PTFE Plug (dia 26x9) 0 days 8/31/2020 8/31/2020 0% 1 5.26% 0 0 0
41 Bearing Upper Axial Insert 0 days 8/31/2020 8/31/2020 0% 1 5.26% 0 0 0
42 Bearing Assembly Bolt and Nuts 0 days 8/31/2020 8/31/2020 0% 1 5.26% 0 0 0
43 Bearing Lip Seal 0 days 8/31/2020 8/31/2020 0% 1 5.26% 0 0 0
44 Turret Lower ring 0 days 4/20/2020 4/20/2020 100% 1 5.26% 0 100 100
45 Turret Upper Ring 0 days 12/30/2019 12/30/2019 100% 1 5.26% 100 100 0
46 Ballast System ROV Pannel 0 days 5/18/2020 5/18/2020 0% 1 5.26% 0 0 0
47 Ballast System Ball Valve 0 days 5/18/2020 5/18/2020 0% 1 5.26% 0 0 0
48 Buoy Upper Ring 0 days 2/10/2020 2/10/2020 100% 1 5.26% 100 100 0
49 Buoy lower Ring 0 days 12/16/2019 12/16/2019 100% 1 5.26% 100 100 0
50 Profab Documentation 139 days 9/30/2019 3/11/2020 59% 233 6.17% 82.83% 70.77% -12.06%
51 Buoyancy Cone Shop drawings 21 days 9/30/2019 10/24/2019 100% 25 10.73% 100 100 0
52 Buoyancy Protection Struct' Shop drawings 14 days 2/24/2020 3/10/2020 0% 16 6.87% 0 0 0
53 Turret Shop drawings 14 days 2/7/2020 2/22/2020 0% 16 6.87% 81 0 -81
54 Turret Mooring Lugs Cluster Shop drawings 14 days 2/10/2020 2/25/2020 0% 16 6.87% 63 0 -63
55 Protection ROV& Ballast Pipe Shop drawings 6 days 2/26/2020 3/3/2020 0% 7 3.00% 0 0 0
56 Transportation Frame / Grillage Turret Shop Drawing 7 days 3/4/2020 3/11/2020 0% 8 3.43% 0 0 0
57 QC Docs Preparation 28 days 10/19/2019 11/29/2019 95% 42 18.03% 100 95 -5
58 QC Doc approval 24 days 11/1/2019 12/30/2019 95% 60 25.75% 100 95 -5
59 WPS Approval 14 days 11/27/2019 1/8/2020 100% 43 18.45% 100 100 0
60 Buoyancy Cone Fabrication 302.5 days 10/18/2019 10/20/2020 16% 1294 34.27% 24.08% 15.95% -8.13%
61 Prefabrication 168.5 days 12/17/2019 7/11/2020 26%
62 Bottom Level Web Frames& T Beams 66.5 days 12/17/2019 3/6/2020 64% 165 4.37% 90.91% 66.06% -24.85%
63 Web Frame Part#1 (Material Stock) 14 days 12/17/2019 1/3/2020 100%
64 Mark& Cut 2 days 12/17/2019 12/18/2019 100% 2 1.21% 100 100 0
65 Roll 3 days 12/19/2019 12/21/2019 100% 3 1.82% 100 100 0
66 Fit Flange Plate 4 days 12/23/2019 12/27/2019 100% 5 3.03% 100 100 0
67 Weld Out 5 days 12/28/2019 1/3/2020 100% 7 4.24% 100 100 0
68 T Beam 9 days 1/23/2020 2/4/2020 100%
69 Mark& Cut 2 days 1/23/2020 1/27/2020 100% 5 3.03% 100 100 0
70 Fit& Weld 7 days 1/27/2020 2/4/2020 100% 9 5.45% 100 100 0
71 Web Frame Part#2 16 days 2/1/2020 2/20/2020 63%
72 Mark& Cut 2 days 2/1/2020 2/4/2020 100% 4 2.42% 100 100 0
73 Roll 4 days 2/3/2020 2/7/2020 100% 5 3.03% 100 100 0
Fabrication S Curve STP for Reliance KGD6 RUBY FPSO Project

Plan
Cut off 19-Feb-20 Description Wtg Actual Variance
Progress
Overall Progress 100.00% 26.67% 20.60% -6.07%
Procurement 20.92% 63.67% 51.94% -11.73%
Profab Documentation 6.17% 82.83% 70.77% -12.06%
Prefab Buoy Lower Section 4.37% 90.91% 66.06% -24.85%
Prefab Buoy Middle Section 6.41% 35.95% 19.83% -16.12%
Prefab Buoy Upper Section 5.03% 0.00% 0.00% 0.00%
Assembly Buoy Lower Section 4.42% 36.53% 25.75% -10.78%
Assembly Buoy Middle Section 4.10% 5.16% 0.00% -5.16%
Assembly Buoy Upper Section 3.58% 0.00% 0.00% 0.00%
Final Assembly Buoy 6.36% 0.00% 0.00% 0.00%
Prefabrication Turret Tank 10.94% 1.21% 0.61% -0.61%
Prefabrication Mooring Lugs Cluster 5.59% 0.00% 0.00% 0.00%
Prefabrication Turret Shaft 7.52% 0.00% 0.00% 0.00%
Assembly Turret 13.59% 0.00% 0.00% 0.00%
Assembly Buoy to Turret 0.37% 0.00% 0.00% 0.00%
FAT STP Buoy and Turret 0.40% 0.00% 0.00% 0.00%
Delivery Preparation 0.24% 0.00% 0.00% 0.00%

No Task Name Duration Start Finish % Complete

74 Fit Flange Plate 6 days 2/6/2020 2/13/2020 100% 8 4.85% 100 100 0
75 Weld Out 7 days 2/12/2020 2/20/2020 0% 9 5.45% 89 0 -89
76 Bottom Cone 5 days 1/22/2020 1/29/2020 100%
77 Mark& Cut 3 days 1/22/2020 1/27/2020 100% 6 3.64% 100 100 0
78 Roll 4 days 1/23/2020 1/29/2020 100% 7 4.24% 100 100 0
79 Bottom Centre Tube 11 days 1/24/2020 2/7/2020 100%
80 Mark& Cut 2 days 1/24/2020 1/28/2020 100% 5 3.03% 100 100 0
81 Roll 3 days 1/27/2020 1/30/2020 100% 4 2.42% 100 100 0
82 Fit 3 days 1/30/2020 2/3/2020 100% 5 3.03% 100 100 0
83 Weld Long Seam 4 days 2/3/2020 2/7/2020 100% 5 3.03% 100 100 0
84 Bottom Inner Tube 12 days 2/1/2020 2/15/2020 67%
85 Mark& Cut 2 days 2/1/2020 2/4/2020 100% 4 2.42% 100 100 0
86 Roll 3 days 2/4/2020 2/7/2020 100% 4 2.42% 100 100 0
87 Fit 3 days 2/7/2020 2/11/2020 100% 5 3.03% 100 100 0
88 Weld Long Seam 4 days 2/11/2020 2/15/2020 0% 5 3.03% 100 0 -100
89 Mating Ring Cone 9 days 2/15/2020 2/26/2020 20%
90 Mark& Cut 4 days 2/15/2020 2/20/2020 50% 6 3.64% 83 50 -33
91 Roll 6 days 2/19/2020 2/26/2020 0% 8 4.85% 13 0 -13
92 Bottom Centre Tube Ring 6 days 2/4/2020 2/11/2020 0%
93 Mark& Cut 2 days 2/4/2020 2/6/2020 0% 3 1.82% 100 0 -100
94 Fit& Weld 4 days 2/6/2020 2/11/2020 0% 6 3.64% 100 0 -100
95 Centre Tube Ring 15 days 1/27/2020 2/13/2020 60%
96 Mark& Cut 3 days 1/27/2020 1/30/2020 100% 4 2.42% 100 100 0
97 Roll 3 days 1/30/2020 2/3/2020 100% 5 3.03% 100 100 0
98 Fit 3 days 2/3/2020 2/6/2020 100% 4 2.42% 100 100 0
99 Weld Long Seam 6 days 2/6/2020 2/13/2020 0% 8 4.85% 100 0 -100
100 Connecting Outer Cone 10 days 2/13/2020 2/25/2020 0%
101 Mark& Cut 4 days 2/13/2020 2/18/2020 0% 6 3.64% 100 0 -100
102 Roll 6 days 2/18/2020 2/25/2020 0% 8 4.85% 25 0 -25
103 1st Level Base Deck 9 days 2/25/2020 3/6/2020 0% 242 6.41% 35.95% 19.83% -16.12%
104 Fit Joints 3 days 2/25/2020 2/28/2020 0% 4 1.65% 0 0 0
105 Weld Long Seam 6 days 2/28/2020 3/6/2020 0% 8 3.31% 0 0 0
106 Inner Cone 15 days 1/27/2020 2/13/2020 100%
107 Mark& Cut 3 days 1/27/2020 1/30/2020 100% 4 1.65% 100 100 0
108 Roll 6 days 1/30/2020 2/6/2020 100% 8 3.31% 100 100 0
109 Fit and Weld LS& CS 6 days 2/6/2020 2/13/2020 100% 8 3.31% 100 100 0
110 2nd Level Web Frames, Deck Plate& T Beams 20 days 1/30/2020 2/22/2020 53%
111 Deck Plate 2nd level 7 days 1/30/2020 2/7/2020 100%
112 Mark& Cut 3 days 1/30/2020 2/3/2020 100% 5 2.07% 100 100 0
113 Weld 4 days 2/3/2020 2/7/2020 100% 5 2.07% 100 100 0
114 T Beam 9 days 2/3/2020 2/13/2020 67%
115 Mark& Cut 3 days 2/3/2020 2/6/2020 100% 4 1.65% 100 100 0
116 Fit& Weld 6 days 2/6/2020 2/13/2020 50% 8 3.31% 100 50 -50
117 Web Frame 14 days 2/6/2020 2/22/2020 21%
118 Mark& Cut 3 days 2/6/2020 2/10/2020 100% 5 2.07% 100 100 0
119 Roll 3 days 2/10/2020 2/13/2020 0% 4 1.65% 100 0 -100
120 Fit Flange Plate 4 days 2/13/2020 2/18/2020 0% 6 2.48% 100 0 -100
121 Weld Out 4 days 2/18/2020 2/22/2020 0% 5 2.07% 40 0 -40
122 3rd Level Web Frames& T Beams 26 days 2/6/2020 3/7/2020 10%
123 Deck Plate 3rd level 7 days 2/6/2020 2/14/2020 43%
124 Mark& Cut 3 days 2/6/2020 2/10/2020 100% 5 2.07% 100 100 0
125 Weld 4 days 2/10/2020 2/14/2020 0% 5 2.07% 100 0 -100
126 T Beam #13 - #14 10 days 2/10/2020 2/21/2020 0%
127 Mark& Cut 4 days 2/10/2020 2/14/2020 0% 5 2.07% 100 0 -100
128 Fit& Weld 6 days 2/14/2020 2/21/2020 0% 8 3.31% 75 0 -75
129 Web Frame #09 13 days 2/21/2020 3/7/2020 0%
130 Mark& Cut 3 days 2/21/2020 2/25/2020 0% 5 2.07% 0 0 0
131 Roll 3 days 2/25/2020 2/28/2020 0% 4 1.65% 0 0 0
132 Fit Flange Plate 3 days 2/28/2020 3/3/2020 0% 5 2.07% 0 0 0
133 Weld Out 4 days 3/3/2020 3/7/2020 0% 5 2.07% 0 0 0
134 4th Level Web Frames& T Beams 30 days 2/14/2020 3/20/2020 0%
135 Deck Plate 4th level 7 days 2/14/2020 2/22/2020 0%
136 Mark& Cut 3 days 2/14/2020 2/18/2020 0% 5 2.07% 100 0 -100
137 Weld 4 days 2/18/2020 2/22/2020 0% 5 2.07% 40 0 -40
138 T Beam #15 9 days 2/22/2020 3/4/2020 0%
139 Mark& Cut 3 days 2/22/2020 2/26/2020 0% 5 2.07% 0 0 0
140 Fit& Weld 6 days 2/26/2020 3/4/2020 0% 8 3.31% 0 0 0
141 Web Frame 14 days 3/4/2020 3/20/2020 0%
142 Mark& Cut 2 days 3/4/2020 3/6/2020 0% 3 1.24% 0 0 0
143 Roll 3 days 3/6/2020 3/10/2020 0% 5 2.07% 0 0 0
144 Fit Flange Plate 4 days 3/10/2020 3/14/2020 0% 5 2.07% 0 0 0
145 Weld Out 5 days 3/14/2020 3/20/2020 0% 7 2.89% 0 0 0
Fabrication S Curve STP for Reliance KGD6 RUBY FPSO Project

Plan
Cut off 19-Feb-20 Description Wtg Actual Variance
Progress
Overall Progress 100.00% 26.67% 20.60% -6.07%
Procurement 20.92% 63.67% 51.94% -11.73%
Profab Documentation 6.17% 82.83% 70.77% -12.06%
Prefab Buoy Lower Section 4.37% 90.91% 66.06% -24.85%
Prefab Buoy Middle Section 6.41% 35.95% 19.83% -16.12%
Prefab Buoy Upper Section 5.03% 0.00% 0.00% 0.00%
Assembly Buoy Lower Section 4.42% 36.53% 25.75% -10.78%
Assembly Buoy Middle Section 4.10% 5.16% 0.00% -5.16%
Assembly Buoy Upper Section 3.58% 0.00% 0.00% 0.00%
Final Assembly Buoy 6.36% 0.00% 0.00% 0.00%
Prefabrication Turret Tank 10.94% 1.21% 0.61% -0.61%
Prefabrication Mooring Lugs Cluster 5.59% 0.00% 0.00% 0.00%
Prefabrication Turret Shaft 7.52% 0.00% 0.00% 0.00%
Assembly Turret 13.59% 0.00% 0.00% 0.00%
Assembly Buoy to Turret 0.37% 0.00% 0.00% 0.00%
FAT STP Buoy and Turret 0.40% 0.00% 0.00% 0.00%
Delivery Preparation 0.24% 0.00% 0.00% 0.00%

No Task Name Duration Start Finish % Complete

146 5th Level Web Frames& T Beams 34 days 2/21/2020 4/2/2020 0%


147 Deck Plate 5th level 7 days 2/21/2020 2/29/2020 0%
148 Mark& Cut 3 days 2/21/2020 2/25/2020 0% 5 2.07% 0 0 0
149 Weld 4 days 2/25/2020 2/29/2020 0% 5 2.07% 0 0 0
150 T Beam 10 days 2/29/2020 3/12/2020 0%
151 Mark& Cut 4 days 2/29/2020 3/5/2020 0% 6 2.48% 0 0 0
152 Fit& Weld 6 days 3/5/2020 3/12/2020 0% 8 3.31% 0 0 0
153 Web Frame 17 days 3/12/2020 4/2/2020 0%
154 Mark& Cut 3 days 3/12/2020 3/16/2020 0% 5 2.07% 0 0 0
155 Roll 3 days 3/16/2020 3/19/2020 0% 4 1.65% 0 0 0
156 Fit Flange Plate 6 days 3/19/2020 3/27/2020 0% 9 3.72% 0 0 0
157 Weld Out 5 days 3/27/2020 4/2/2020 0% 7 2.89% 0 0 0
158 Outer Cone 6 days 3/27/2020 4/3/2020 0%
159 Mark& Cut 3 days 3/27/2020 3/31/2020 0% 5 2.07% 0 0 0
160 Roll 3 days 3/31/2020 4/3/2020 0% 4 1.65% 0 0 0
161 Upper Centre Tube 9 days 4/3/2020 4/15/2020 0%
162 Mark& Cut 3 days 4/3/2020 4/7/2020 0% 5 2.07% 0 0 0
163 Roll 3 days 4/7/2020 4/11/2020 0% 5 2.07% 0 0 0
164 Long Seam weld 3 days 4/11/2020 4/15/2020 0% 5 2.07% 0 0 0
165 Upper Centre Tube Stiffener 7 days 4/15/2020 4/23/2020 0%
166 Mark& Cut 3 days 4/15/2020 4/18/2020 0% 4 1.65% 0 0 0
167 Fit Up and weld 4 days 4/18/2020 4/23/2020 0% 6 2.48% 0 0 0
168 6th Level Web Frames 19 days 4/2/2020 4/25/2020 0% 190 5.03% 0.00% 0.00% 0.00%
169 Deck Plate 6th level 7 days 4/2/2020 4/11/2020 0%
170 Mark& Cut 3 days 4/2/2020 4/6/2020 0% 5 2.63% 0 0 0
171 Weld 4 days 4/6/2020 4/11/2020 0% 6 3.16% 0 0 0
172 Web Frame 16 days 4/6/2020 4/25/2020 0%
173 Mark& Cut 3 days 4/6/2020 4/9/2020 0% 4 2.11% 0 0 0
174 Roll 3 days 4/9/2020 4/14/2020 0% 6 3.16% 0 0 0
175 Fit Flange Plate 4 days 4/14/2020 4/18/2020 0% 5 2.63% 0 0 0
176 Weld Out 6 days 4/18/2020 4/25/2020 0% 8 4.21% 0 0 0
177 Outer Cone Upper Section 12 days 4/25/2020 5/12/2020 0%
178 Mark& Cut 3 days 4/25/2020 4/29/2020 0% 5 2.63% 0 0 0
179 Roll 3 days 4/29/2020 5/4/2020 0% 6 3.16% 0 0 0
180 Fit up and weld 6 days 5/4/2020 5/12/2020 0% 9 4.74% 0 0 0
181 Middle Centre Tube 14 days 4/18/2020 5/6/2020 0%
182 Mark& Cut 3 days 4/18/2020 4/22/2020 0% 5 2.63% 0 0 0
183 Roll 4 days 4/22/2020 4/27/2020 0% 6 3.16% 0 0 0
184 Long Seam weld 7 days 4/27/2020 5/6/2020 0% 10 5.26% 0 0 0
185 Middle Centre Tube Stiffener 7 days 4/22/2020 4/30/2020 0%
186 Mark& Cut 3 days 4/22/2020 4/25/2020 0% 4 2.11% 0 0 0
187 Fit and Weld 4 days 4/25/2020 4/30/2020 0% 6 3.16% 0 0 0
188 Buoy Protection Structure Foundation 8 days 4/30/2020 5/12/2020 0%
189 Mark& Cut 4 days 4/30/2020 5/6/2020 0% 7 3.68% 0 0 0
190 Roll 4 days 5/6/2020 5/12/2020 0% 7 3.68% 0 0 0
191 Lifting Lugs 17 days 5/6/2020 5/29/2020 0%
192 Mark& Cut 3 days 5/6/2020 5/11/2020 0% 6 3.16% 0 0 0
193 Fit Cheek Plate 4 days 5/11/2020 5/15/2020 0% 5 2.63% 0 0 0
194 Drill Hole 4 days 5/15/2020 5/20/2020 0% 6 3.16% 0 0 0
195 Weld Out 6 days 5/20/2020 5/29/2020 0% 10 5.26% 0 0 0
196 Buoy Protection Structure 45 days 5/16/2020 7/11/2020 0%
197 Send Pipe for Rolling 6 days 5/16/2020 5/26/2020 0% 11 5.79% 0 0 0
198 Mark& Cut Plates 5 days 5/26/2020 6/2/2020 0% 8 4.21% 0 0 0
199 Roll Cone 3 days 6/2/2020 6/5/2020 0% 4 2.11% 0 0 0
200 Mark& Cut Pipe 3 days 6/5/2020 6/9/2020 0% 5 2.63% 0 0 0
201 Fit Up 7 days 6/9/2020 6/17/2020 0% 9 4.74% 0 0 0
202 Weld Out 7 days 6/17/2020 6/25/2020 0% 9 4.74% 0 0 0
203 Drill Holes on Base Plate 7 days 6/25/2020 7/3/2020 0% 9 4.74% 0 0 0
204 Blast and Paint 7 days 7/3/2020 7/11/2020 0% 9 4.74% 0 0 0
205 Assembly 302.5 days 10/18/2019 10/20/2020 7% 167 4.42% 36.53% 25.75% -10.78%
206 Prepare Fabrication Support 27 days 10/18/2019 11/18/2019 100%
207 Mark& Cut 6 days 10/18/2019 10/24/2019 100% 7 4.19% 100 100 0
208 Fit Up 6 days 10/25/2019 10/31/2019 100% 7 4.19% 100 100 0
209 Weld 8 days 10/31/2019 11/13/2019 100% 14 8.38% 100 100 0
210 Levelling 4 days 11/14/2019 11/18/2019 100% 5 2.99% 100 100 0
211 Assembly Bottom Base 27 days 1/29/2020 2/29/2020 20%
212 Fit Bottom Cone to Lower Ring 5 days 1/29/2020 2/4/2020 100% 7 4.19% 100 100 0
213 Fit Bottom Centre Tube to Lower Ring 4 days 2/7/2020 2/12/2020 50% 6 3.59% 100 50 -50
214 Fit Bottom Centre Tube Ring 3 days 2/12/2020 2/15/2020 0% 4 2.40% 100 0 -100
215 Fit Bottom Inner Tube 2 days 2/15/2020 2/18/2020 0% 4 2.40% 100 0 -100
216 Fit Bottom Web Frames& T Beams 4 days 2/20/2020 2/25/2020 0% 6 3.59% 0 0 0
217 Fit Centre Tube Ring 3 days 2/25/2020 2/28/2020 0% 4 2.40% 0 0 0
Fabrication S Curve STP for Reliance KGD6 RUBY FPSO Project

Plan
Cut off 19-Feb-20 Description Wtg Actual Variance
Progress
Overall Progress 100.00% 26.67% 20.60% -6.07%
Procurement 20.92% 63.67% 51.94% -11.73%
Profab Documentation 6.17% 82.83% 70.77% -12.06%
Prefab Buoy Lower Section 4.37% 90.91% 66.06% -24.85%
Prefab Buoy Middle Section 6.41% 35.95% 19.83% -16.12%
Prefab Buoy Upper Section 5.03% 0.00% 0.00% 0.00%
Assembly Buoy Lower Section 4.42% 36.53% 25.75% -10.78%
Assembly Buoy Middle Section 4.10% 5.16% 0.00% -5.16%
Assembly Buoy Upper Section 3.58% 0.00% 0.00% 0.00%
Final Assembly Buoy 6.36% 0.00% 0.00% 0.00%
Prefabrication Turret Tank 10.94% 1.21% 0.61% -0.61%
Prefabrication Mooring Lugs Cluster 5.59% 0.00% 0.00% 0.00%
Prefabrication Turret Shaft 7.52% 0.00% 0.00% 0.00%
Assembly Turret 13.59% 0.00% 0.00% 0.00%
Assembly Buoy to Turret 0.37% 0.00% 0.00% 0.00%
FAT STP Buoy and Turret 0.40% 0.00% 0.00% 0.00%
Delivery Preparation 0.24% 0.00% 0.00% 0.00%

No Task Name Duration Start Finish % Complete

218 Weld Out 14 days 2/13/2020 2/29/2020 0% 17 10.18% 41 0 -41


219 Assembly Mating Ring 25 days 2/29/2020 3/31/2020 0%
220 Fit Mating Ring Cone 4 days 2/29/2020 3/5/2020 0% 6 3.59% 0 0 0
221 Weld Out 6 days 3/5/2020 3/12/2020 0% 8 4.79% 0 0 0
222 PWHT 3 days 3/12/2020 3/16/2020 0% 5 2.99% 0 0 0
223 DC Check 1 day 3/16/2020 3/17/2020 0% 2 1.20% 0 0 0
224 Cut / Trim 2 days 3/17/2020 3/19/2020 0% 3 1.80% 0 0 0
225 Fit 1st Level Base Deck 3 days 3/19/2020 3/23/2020 0% 5 2.99% 0 0 0
226 Fit Connecting Outer Cone 2 days 3/23/2020 3/26/2020 0% 4 2.40% 0 0 0
227 Weld Out 4 days 3/26/2020 3/31/2020 0% 6 3.59% 0 0 0
228 Leak Test Lower Section 6 days 3/31/2020 4/7/2020 0%
229 Buoy Lower Part, Compt 1A, 1B 3 days 3/31/2020 4/3/2020 0% 4 2.40% 0 0 0
230 Buoy Lower Part, Compt 2A, 2B 3 days 4/3/2020 4/7/2020 0% 5 2.99% 0 0 0
231 Machining Mating Ring Cone 13 days 4/7/2020 4/23/2020 0%
232 Preparation 2 days 4/7/2020 4/9/2020 0% 3 1.80% 0 0 0
233 Machining 10 days 4/9/2020 4/22/2020 0% 14 8.38% 0 0 0
234 DC Check 1 day 4/22/2020 4/23/2020 0% 2 1.20% 0 0 0
235 Surface Protection Lower Buoy 12 days 4/23/2020 5/9/2020 0%
236 Covering 2 days 4/23/2020 4/25/2020 0% 3 1.80% 0 0 0
237 Blast and TSA centre tube area 5 days 4/25/2020 5/2/2020 0% 8 4.79% 0 0 0
238 Blast and Paint Surface area 5 days 5/2/2020 5/9/2020 0% 8 4.79% 0 0 0
239 Sub Assembly Middle Centre Tube 19 days 5/6/2020 6/2/2020 0% 155 4.10% 5.16% 0.00% -5.16%
240 Fit Centre Tube 3 days 5/6/2020 5/11/2020 0% 6 3.87% 0 0 0
241 Weld LS and CS 7 days 5/11/2020 5/19/2020 0% 9 5.81% 0 0 0
242 Fit Centre Tube Stiffeners 3 days 5/19/2020 5/23/2020 0% 5 3.23% 0 0 0
243 Weld Out 6 days 5/23/2020 6/2/2020 0% 11 7.10% 0 0 0
244 Surface Protection Middle Centre Tube 7 days 6/2/2020 6/10/2020 0%
245 Blast 3 days 6/2/2020 6/5/2020 0% 4 2.58% 0 0 0
246 TSA Inside centre Tube 4 days 6/5/2020 6/10/2020 0% 6 3.87% 0 0 0
247 Sub Assembly Inner Cone (Middle Buoy Section) 76 days 2/13/2020 5/16/2020 0%
248 Fit Inner Cone 4 days 2/13/2020 2/18/2020 0% 6 3.87% 100 0 -100
249 Fit 2nd Level Base Deck 3 days 2/18/2020 2/21/2020 0% 4 2.58% 50 0 -50
250 Fit 2nd Level Web Frames& T Beam 4 days 2/22/2020 2/27/2020 0% 6 3.87% 0 0 0
251 Weld Out 8 days 2/25/2020 3/5/2020 0% 10 6.45% 0 0 0
252 Fit 3rd Level Base Deck 3 days 3/7/2020 3/11/2020 0% 5 3.23% 0 0 0
253 Fit 3rd Level Web Frames& T Beam 4 days 3/11/2020 3/16/2020 0% 6 3.87% 0 0 0
254 Weld Out 8 days 3/13/2020 3/23/2020 0% 11 7.10% 0 0 0
255 Fit 4th Level Base Deck 3 days 3/23/2020 3/27/2020 0% 5 3.23% 0 0 0
256 Fit 4th Level Web Frames& T Beam 4 days 3/27/2020 4/1/2020 0% 6 3.87% 0 0 0
257 Weld Out 10 days 3/30/2020 4/11/2020 0% 13 8.39% 0 0 0
258 Fit 5th Level Base Base Deck 3 days 4/11/2020 4/15/2020 0% 5 3.23% 0 0 0
259 Fit 5th Level Web Frames& T Beam 4 days 4/15/2020 4/20/2020 0% 6 3.87% 0 0 0
260 Weld Out 10 days 4/18/2020 4/30/2020 0% 13 8.39% 0 0 0
261 Fit Outer Shell 4 days 4/30/2020 5/6/2020 0% 7 4.52% 0 0 0
262 Weld Out 8 days 5/6/2020 5/16/2020 0% 11 7.10% 0 0 0
263 Sub Assembly Upper Section Buoy 45 days 4/23/2020 6/20/2020 0% 135 3.58% 0.00% 0.00% 0.00%
264 Fit Upper Part Centre Tube to Upper Ring 4 days 4/23/2020 4/28/2020 0% 6 4.44% 0 0 0
265 Fit Web Frames 6th Level 3 days 4/28/2020 5/2/2020 0% 5 3.70% 0 0 0
266 Weld Out 4 days 5/2/2020 5/8/2020 0% 7 5.19% 0 0 0
267 Fit Ring Stiffeners 3 days 5/8/2020 5/12/2020 0% 5 3.70% 0 0 0
268 Fit Top Outer Cone 4 days 5/12/2020 5/16/2020 0% 5 3.70% 0 0 0
269 Weld Out (including NDT) 8 days 5/15/2020 5/27/2020 0% 13 9.63% 0 0 0
270 Flip over upper section 3 days 5/27/2020 5/30/2020 0% 4 2.96% 0 0 0
271 Cut Add. Bracing/Stiffener (on Upper Web Frame) 3 days 5/30/2020 6/4/2020 0% 6 4.44% 0 0 0
272 Fit/weld add bracing/stiffener on upper web frame 7 days 6/4/2020 6/12/2020 0% 9 6.67% 0 0 0
273 Fit& Weld Lifting Lugs 7 days 6/12/2020 6/20/2020 0% 9 6.67% 0 0 0
274 Grouting 24 days 5/16/2020 6/17/2020 0% 33 24.44% 0 0 0
275 Fit/weld support grouting 24 days 5/16/2020 6/17/2020 0% 33 24.44% 0 0 0
276 Move Bottom Section Buoy to Assembly Area 6 days 5/9/2020 5/16/2020 0% 240 6.36% 0.00% 0.00% 0.00%
277 Move out 2 days 5/9/2020 5/12/2020 0% 4 1.67% 0 0 0
278 Jack Up& Levelling 4 days 5/12/2020 5/16/2020 0% 5 2.08% 0 0 0
279 Assembly Inner Cone to Bottom Section Buoy 21 days 5/16/2020 6/13/2020 0%
280 Move Inner Cone to assembly area 2 days 5/16/2020 5/19/2020 0% 4 1.67% 0 0 0
281 Lift& Fit to Deck 2 days 5/19/2020 5/22/2020 0% 4 1.67% 0 0 0
282 Erect Scaffolding 3 days 5/22/2020 5/27/2020 0% 6 2.50% 0 0 0
283 Fit 1st Deck Web Frames& T Beams 4 days 5/27/2020 6/2/2020 0% 7 2.92% 0 0 0
284 Weld Out 10 days 6/2/2020 6/13/2020 0% 12 5.00% 0 0 0
285 Assembly Middle Centre Tube 8 days 6/13/2020 6/23/2020 0%
286 Lift& Fit Centre Tube 4 days 6/13/2020 6/18/2020 0% 6 2.50% 0 0 0
287 Weld Out 4 days 6/18/2020 6/23/2020 0% 6 2.50% 0 0 0
288 Assembly Upper Section to Buoy 11 days 6/23/2020 7/6/2020 0%
289 Lift& Fit Upper Ring 2 days 6/23/2020 6/25/2020 0% 3 1.25% 0 0 0
Fabrication S Curve STP for Reliance KGD6 RUBY FPSO Project

Plan
Cut off 19-Feb-20 Description Wtg Actual Variance
Progress
Overall Progress 100.00% 26.67% 20.60% -6.07%
Procurement 20.92% 63.67% 51.94% -11.73%
Profab Documentation 6.17% 82.83% 70.77% -12.06%
Prefab Buoy Lower Section 4.37% 90.91% 66.06% -24.85%
Prefab Buoy Middle Section 6.41% 35.95% 19.83% -16.12%
Prefab Buoy Upper Section 5.03% 0.00% 0.00% 0.00%
Assembly Buoy Lower Section 4.42% 36.53% 25.75% -10.78%
Assembly Buoy Middle Section 4.10% 5.16% 0.00% -5.16%
Assembly Buoy Upper Section 3.58% 0.00% 0.00% 0.00%
Final Assembly Buoy 6.36% 0.00% 0.00% 0.00%
Prefabrication Turret Tank 10.94% 1.21% 0.61% -0.61%
Prefabrication Mooring Lugs Cluster 5.59% 0.00% 0.00% 0.00%
Prefabrication Turret Shaft 7.52% 0.00% 0.00% 0.00%
Assembly Turret 13.59% 0.00% 0.00% 0.00%
Assembly Buoy to Turret 0.37% 0.00% 0.00% 0.00%
FAT STP Buoy and Turret 0.40% 0.00% 0.00% 0.00%
Delivery Preparation 0.24% 0.00% 0.00% 0.00%

No Task Name Duration Start Finish % Complete

290 Weld Out 5 days 6/25/2020 7/1/2020 0% 7 2.92% 0 0 0


Fit&Weld web frame (between inner cone and centre
6 days 6/29/2020 7/6/2020 0% 8 3.33% 0 0 0
291 tube)
Assembly Outer Cone (Level #5 / Compartment #8) 12 days 7/3/2020 7/17/2020 0%
292
293 Fit Outer Cone 5 days 7/3/2020 7/9/2020 0% 7 2.92% 0 0 0
294 Weld Out 7 days 7/9/2020 7/17/2020 0% 9 3.75% 0 0 0
295 Leak Test Compartment 14 days 7/16/2020 8/3/2020 0%
296 Compartment 6B 2 days 7/16/2020 7/18/2020 0% 3 1.25% 0 0 0
297 Compartment 5A 2 days 7/18/2020 7/21/2020 0% 4 1.67% 0 0 0
298 Compartment 5B 2 days 7/21/2020 7/23/2020 0% 3 1.25% 0 0 0
299 Compartment 3 2 days 7/23/2020 7/25/2020 0% 3 1.25% 0 0 0
300 Compartment 8 2 days 7/25/2020 7/28/2020 0% 4 1.67% 0 0 0
301 Compartment 4A 2 days 7/28/2020 7/30/2020 0% 3 1.25% 0 0 0
302 Compartment 4B 2 days 7/30/2020 8/3/2020 0% 5 2.08% 0 0 0
303 Pipe Fender Assembly 12 days 7/11/2020 7/25/2020 0%
304 Fit Half Pipe to Buoy Outer Cone 4 days 7/11/2020 7/16/2020 0% 6 2.50% 0 0 0
305 Weld Out 8 days 7/16/2020 7/25/2020 0% 10 4.17% 0 0 0
306 Machining Upper Ring 18 days 8/3/2020 8/26/2020 0%
307 Rigging& Set Up 2 days 8/3/2020 8/5/2020 0% 3 1.25% 0 0 0
308 Machining 7 days 8/5/2020 8/13/2020 0% 9 3.75% 0 0 0
309 Drill and Tapping 7 days 8/13/2020 8/24/2020 0% 12 5.00% 0 0 0
310 Remove Support 2 days 8/24/2020 8/26/2020 0% 3 1.25% 0 0 0
311 Machining Lower Ring 16 days 8/26/2020 9/14/2020 0%
312 Support Preparation 2 days 8/26/2020 8/28/2020 0% 3 1.25% 0 0 0
313 Machining 6 days 8/28/2020 9/4/2020 0% 8 3.33% 0 0 0
314 Drill and Tapping 6 days 9/4/2020 9/11/2020 0% 8 3.33% 0 0 0
315 Remove Support 2 days 9/11/2020 9/14/2020 0% 4 1.67% 0 0 0
316 Blast& Paint 25 days 9/14/2020 10/13/2020 0%
317 Outside Area 15 days 9/14/2020 10/1/2020 0%
318 Blast& Prime Coat 3 days 9/14/2020 9/17/2020 0% 4 1.67% 0 0 0
319 2nd Coat 2 days 9/17/2020 9/19/2020 0% 3 1.25% 0 0 0
320 3rd Coat 3 days 9/19/2020 9/23/2020 0% 5 2.08% 0 0 0
321 4th Coat 3 days 9/23/2020 9/26/2020 0% 4 1.67% 0 0 0
322 Final Coat 3 days 9/26/2020 9/30/2020 0% 5 2.08% 0 0 0
323 Marking 1 day 9/30/2020 10/1/2020 0% 2 0.83% 0 0 0
324 Center Tube (TSA / Metalizing) 11 days 9/30/2020 10/13/2020 0%
325 Blasting 4 days 9/30/2020 10/5/2020 0% 6 2.50% 0 0 0
326 Metalizing Centre Tube 6 days 10/5/2020 10/12/2020 0% 8 3.33% 0 0 0
327 2nd Coat / Sealer 1 day 10/12/2020 10/13/2020 0% 2 0.83% 0 0 0
328 Anode Installation 8 days 9/30/2020 10/9/2020 0%
329 Fit& Weld Anodes bottom buoy 4 days 9/30/2020 10/5/2020 0% 6 2.50% 0 0 0
330 Fit& Weld Anodes Outer Shell 4 days 10/5/2020 10/9/2020 0% 5 2.08% 0 0 0
331 Bearing Upper and Lower Installation 3 days 10/13/2020 10/16/2020 0% 4 1.67% 0 0 0
332 Dismantle Scaffolding 2 days 10/16/2020 10/19/2020 0% 4 1.67% 0 0 0
333 Moving to assembly area (by SPMT) 1 day 10/19/2020 10/20/2020 0% 2 0.83% 0 0 0
334 Buoy Fabrication Completed ( ready for integration ) 0 days 10/20/2020 10/20/2020 0% 1 0.42% 0 0 0
335 Turret Fabrication 230 days 2/15/2020 11/24/2020 0% 1421 14.16% 0.30% 0.15% -0.15%
336 Prefabrication Turret Tank 147 days 2/15/2020 8/13/2020 1% 413 10.94% 1.21% 0.61% -0.61%
337 Lower Base Deck ( 30mm plate ) 19 days 2/15/2020 3/7/2020 11%
338 Fit Joints 4 days 2/15/2020 2/19/2020 50% 5 1.21% 100 50 -50
339 Weld Out 12 days 2/20/2020 3/4/2020 0% 14 3.39% 0 0 0
340 Cut Ouside Diameter 3 days 3/5/2020 3/7/2020 0% 3 0.73% 0 0 0
341 Lower Deck T Beams ( 36 units ) 18 days 2/20/2020 3/11/2020 0%
342 Mark& Cut 4 days 2/20/2020 2/24/2020 0% 5 1.21% 0 0 0
343 Fit up Flange Plate 6 days 2/25/2020 3/2/2020 0% 7 1.69% 0 0 0
344 Weld 10 days 2/29/2020 3/11/2020 0% 12 2.91% 0 0 0
345 Pedestal Lower Tube ( 30mm plate ) 16 days 2/25/2020 3/13/2020 0%
346 Mark& Cut 2 days 2/25/2020 2/26/2020 0% 2 0.48% 0 0 0
347 Roll 4 days 2/27/2020 3/2/2020 0% 5 1.21% 0 0 0
348 Fit Up 4 days 3/3/2020 3/6/2020 0% 4 0.97% 0 0 0
349 Weld Out 6 days 3/7/2020 3/13/2020 0% 7 1.69% 0 0 0
350 Inner lower Cone ( 15mm plate ) 10 days 3/14/2020 3/26/2020 0%
351 Mark& Cut 4 days 3/14/2020 3/18/2020 0% 5 1.21% 0 0 0
352 Roll Cone 6 days 3/19/2020 3/26/2020 0% 8 1.94% 0 0 0
353 Lower Web Frames ( 30 unit ) 20 days 3/7/2020 3/31/2020 0%
354 Mark& Cut 2 days 3/7/2020 3/9/2020 0% 3 0.73% 0 0 0
355 Roll Flange Plate 4 days 3/10/2020 3/13/2020 0% 4 0.97% 0 0 0
356 Fit up Flange Plate 4 days 3/14/2020 3/18/2020 0% 5 1.21% 0 0 0
357 Weld 10 days 3/19/2020 3/31/2020 0% 13 3.15% 0 0 0
358 Inner Deck Plate #1 turret tank 10 days 3/19/2020 3/31/2020 0%
359 Mark& Cut 4 days 3/19/2020 3/23/2020 0% 5 1.21% 0 0 0
Fabrication S Curve STP for Reliance KGD6 RUBY FPSO Project

Plan
Cut off 19-Feb-20 Description Wtg Actual Variance
Progress
Overall Progress 100.00% 26.67% 20.60% -6.07%
Procurement 20.92% 63.67% 51.94% -11.73%
Profab Documentation 6.17% 82.83% 70.77% -12.06%
Prefab Buoy Lower Section 4.37% 90.91% 66.06% -24.85%
Prefab Buoy Middle Section 6.41% 35.95% 19.83% -16.12%
Prefab Buoy Upper Section 5.03% 0.00% 0.00% 0.00%
Assembly Buoy Lower Section 4.42% 36.53% 25.75% -10.78%
Assembly Buoy Middle Section 4.10% 5.16% 0.00% -5.16%
Assembly Buoy Upper Section 3.58% 0.00% 0.00% 0.00%
Final Assembly Buoy 6.36% 0.00% 0.00% 0.00%
Prefabrication Turret Tank 10.94% 1.21% 0.61% -0.61%
Prefabrication Mooring Lugs Cluster 5.59% 0.00% 0.00% 0.00%
Prefabrication Turret Shaft 7.52% 0.00% 0.00% 0.00%
Assembly Turret 13.59% 0.00% 0.00% 0.00%
Assembly Buoy to Turret 0.37% 0.00% 0.00% 0.00%
FAT STP Buoy and Turret 0.40% 0.00% 0.00% 0.00%
Delivery Preparation 0.24% 0.00% 0.00% 0.00%

No Task Name Duration Start Finish % Complete

360 Fit and weld 6 days 3/24/2020 3/31/2020 0% 8 1.94% 0 0 0


361 Inner upper Cone ( 30mm plate ) 12 days 3/24/2020 4/7/2020 0%
362 Mark& Cut 4 days 3/24/2020 3/28/2020 0% 5 1.21% 0 0 0
363 Roll Cone 8 days 3/30/2020 4/7/2020 0% 9 2.18% 0 0 0
364 Outer Shell T Beams ( 25 unit ) 20 days 3/30/2020 4/22/2020 0%
365 Mark& Cut 2 days 3/30/2020 3/31/2020 0% 2 0.48% 0 0 0
366 Roll Flange Plate 4 days 4/1/2020 4/4/2020 0% 4 0.97% 0 0 0
367 Fit up Flange Plate 4 days 4/6/2020 4/9/2020 0% 4 0.97% 0 0 0
368 Weld 10 days 4/11/2020 4/22/2020 0% 12 2.91% 0 0 0
369 Outer Deck Plate #1 turret tank 10 days 4/1/2020 4/13/2020 0%
370 Mark& Cut 4 days 4/1/2020 4/4/2020 0% 4 0.97% 0 0 0
371 Fit and weld 6 days 4/6/2020 4/13/2020 0% 8 1.94% 0 0 0
372 Lower Outer Shell ( 25mm plate ) 12 days 4/14/2020 4/27/2020 0%
373 Mark& Cut 4 days 4/14/2020 4/17/2020 0% 4 0.97% 0 0 0
374 Roll 8 days 4/18/2020 4/27/2020 0% 10 2.42% 0 0 0
375 Upper Web Frames ( 30 unit ) 16 days 4/14/2020 5/2/2020 0%
376 Mark& Cut 2 days 4/14/2020 4/15/2020 0% 2 0.48% 0 0 0
377 Roll Flange Plate 2 days 4/16/2020 4/17/2020 0% 2 0.48% 0 0 0
378 Fit up Flange Plate 4 days 4/18/2020 4/22/2020 0% 5 1.21% 0 0 0
379 Weld 8 days 4/23/2020 5/2/2020 0% 10 2.42% 0 0 0
380 Upper Deck T Beams ( 30 units ) 16 days 4/18/2020 5/8/2020 0%
381 Mark& Cut 4 days 4/18/2020 4/22/2020 0% 5 1.21% 0 0 0
382 Fit up Flange Plate 4 days 4/23/2020 4/27/2020 0% 5 1.21% 0 0 0
383 Weld 8 days 4/28/2020 5/8/2020 0% 11 2.66% 0 0 0
384 Upper Cone T Beams ( 16 unit ) 20 days 4/23/2020 5/18/2020 0%
385 Mark& Cut 4 days 4/23/2020 4/27/2020 0% 5 1.21% 0 0 0
386 Fit Up 6 days 4/28/2020 5/5/2020 0% 8 1.94% 0 0 0
387 Weld 10 days 5/6/2020 5/18/2020 0% 13 3.15% 0 0 0
388 Upper Outer Shell ( 25mm plate ) 12 days 5/19/2020 6/4/2020 0%
389 Mark& Cut 4 days 5/19/2020 5/23/2020 0% 5 1.21% 0 0 0
390 Roll 8 days 5/26/2020 6/4/2020 0% 10 2.42% 0 0 0
391 Outer Cone ( 30mm plate ) 12 days 5/19/2020 6/4/2020 0%
392 Mark& Cut 4 days 5/19/2020 5/23/2020 0% 5 1.21% 0 0 0
393 Roll Cone 8 days 5/26/2020 6/4/2020 0% 10 2.42% 0 0 0
394 ROV Panel& Ballast Pipe 30 days 6/5/2020 7/9/2020 0%
395 Mark& Cut Pipe 6 days 6/5/2020 6/11/2020 0% 7 1.69% 0 0 0
396 Bending 10 days 6/12/2020 6/23/2020 0% 12 2.91% 0 0 0
397 Fit Up& Weld Pipe 14 days 6/24/2020 7/9/2020 0% 16 3.87% 0 0 0
398 Turret Pull in Lug Structure 25 days 6/12/2020 7/10/2020 0%
399 Mark& Cut 4 days 6/12/2020 6/16/2020 0% 5 1.21% 0 0 0
400 Fit Up& Weld 14 days 6/17/2020 7/2/2020 0% 16 3.87% 0 0 0
401 Machining 7 days 7/3/2020 7/10/2020 0% 8 1.94% 0 0 0
402 Installation Padeyes 25 days 6/17/2020 7/15/2020 0%
403 Mark& Cut 4 days 6/17/2020 6/20/2020 0% 4 0.97% 0 0 0
404 Fit Up& Weld 14 days 6/22/2020 7/7/2020 0% 16 3.87% 0 0 0
405 Machining 7 days 7/8/2020 7/15/2020 0% 8 1.94% 0 0 0
406 Diving Platform& Transponder Buckets 12 days 7/8/2020 7/21/2020 0%
407 Prefab 12 days 7/8/2020 7/21/2020 0% 14 3.39% 0 0 0
408 Cable Routing Pipe (SS 316) 28 days 7/11/2020 8/13/2020 0%
409 Mark& Cut Pipe 4 days 7/11/2020 7/15/2020 0% 5 1.21% 0 0 0
410 Bending 10 days 7/16/2020 7/27/2020 0% 12 2.91% 0 0 0
411 Fit Up& Weld Pipe 14 days 7/28/2020 8/13/2020 0% 17 4.12% 0 0 0
412 Prefabrication Mooring Lug Cluster 113 days 2/26/2020 7/16/2020 0% 211 5.59% 0.00% 0.00% 0.00%
413 Mark& Cut PL.100mm THK 14 days 2/26/2020 3/12/2020 0% 16 7.58% 0 0 0
414 Mark& Cut PL.50mm THK 6 days 3/13/2020 3/19/2020 0% 7 3.32% 0 0 0
415 Prefab T Beam 14 days 3/13/2020 3/30/2020 0% 18 8.53% 0 0 0
416 Cluster #1 63 days 3/13/2020 6/4/2020 0%
417 Layout PL.100mm THK to Base Plate 4 days 3/13/2020 3/17/2020 0% 5 2.37% 0 0 0
418 Fit Outer shell PL.50mm THK 4 days 3/20/2020 3/24/2020 0% 5 2.37% 0 0 0
419 Fit T Beam 4 days 3/31/2020 4/3/2020 0% 4 1.90% 0 0 0
420 Fit Round Bar 6 days 4/20/2020 4/25/2020 0% 6 2.84% 0 0 0
421 Weld out 16 days 4/27/2020 5/16/2020 0% 20 9.48% 0 0 0
422 NDT 2 days 5/18/2020 5/19/2020 0% 2 0.95% 0 0 0
423 PWHT 2 days 5/20/2020 5/22/2020 0% 3 1.42% 0 0 0
424 Dim Check 1 day 5/23/2020 5/23/2020 0% 1 0.47% 0 0 0
425 Machining 8 days 5/26/2020 6/4/2020 0% 10 4.74% 0 0 0
426 Cluster #2 47 days 4/27/2020 6/25/2020 0%
427 Layout PL.100mm THK to Base Plate 4 days 4/27/2020 4/30/2020 0% 4 1.90% 0 0 0
428 Fit Outer shell PL.50mm THK 4 days 5/2/2020 5/6/2020 0% 5 2.37% 0 0 0
429 Fit T Beam 4 days 5/8/2020 5/12/2020 0% 5 2.37% 0 0 0
430 Fit Round Bar 6 days 5/13/2020 5/19/2020 0% 7 3.32% 0 0 0
431 Weld out 16 days 5/20/2020 6/10/2020 0% 22 10.43% 0 0 0
Fabrication S Curve STP for Reliance KGD6 RUBY FPSO Project

Plan
Cut off 19-Feb-20 Description Wtg Actual Variance
Progress
Overall Progress 100.00% 26.67% 20.60% -6.07%
Procurement 20.92% 63.67% 51.94% -11.73%
Profab Documentation 6.17% 82.83% 70.77% -12.06%
Prefab Buoy Lower Section 4.37% 90.91% 66.06% -24.85%
Prefab Buoy Middle Section 6.41% 35.95% 19.83% -16.12%
Prefab Buoy Upper Section 5.03% 0.00% 0.00% 0.00%
Assembly Buoy Lower Section 4.42% 36.53% 25.75% -10.78%
Assembly Buoy Middle Section 4.10% 5.16% 0.00% -5.16%
Assembly Buoy Upper Section 3.58% 0.00% 0.00% 0.00%
Final Assembly Buoy 6.36% 0.00% 0.00% 0.00%
Prefabrication Turret Tank 10.94% 1.21% 0.61% -0.61%
Prefabrication Mooring Lugs Cluster 5.59% 0.00% 0.00% 0.00%
Prefabrication Turret Shaft 7.52% 0.00% 0.00% 0.00%
Assembly Turret 13.59% 0.00% 0.00% 0.00%
Assembly Buoy to Turret 0.37% 0.00% 0.00% 0.00%
FAT STP Buoy and Turret 0.40% 0.00% 0.00% 0.00%
Delivery Preparation 0.24% 0.00% 0.00% 0.00%

No Task Name Duration Start Finish % Complete

432 NDT 2 days 6/11/2020 6/12/2020 0% 2 0.95% 0 0 0


433 PWHT 2 days 6/13/2020 6/15/2020 0% 3 1.42% 0 0 0
434 Dim Check 1 day 6/16/2020 6/16/2020 0% 1 0.47% 0 0 0
435 Machining 8 days 6/17/2020 6/25/2020 0% 9 4.27% 0 0 0
436 Cluster #3 47 days 5/20/2020 7/16/2020 0%
437 Layout PL.100mm THK to Base Plate 4 days 5/20/2020 5/26/2020 0% 7 3.32% 0 0 0
438 Fit Outer shell PL.50mm THK 4 days 5/27/2020 5/30/2020 0% 4 1.90% 0 0 0
439 Fit T Beam 4 days 6/2/2020 6/5/2020 0% 4 1.90% 0 0 0
440 Fit Round Bar 6 days 6/6/2020 6/12/2020 0% 7 3.32% 0 0 0
441 Weld out 16 days 6/13/2020 7/1/2020 0% 19 9.00% 0 0 0
442 NDT 2 days 7/2/2020 7/3/2020 0% 2 0.95% 0 0 0
443 PWHT 2 days 7/4/2020 7/6/2020 0% 3 1.42% 0 0 0
444 Dim Check 1 day 7/7/2020 7/7/2020 0% 1 0.47% 0 0 0
445 Machining 8 days 7/8/2020 7/16/2020 0% 9 4.27% 0 0 0
446 Prefabrication Turret Shaft 113 days 2/24/2020 7/14/2020 0% 284 7.52% 0.00% 0.00% 0.00%
447 Turret Shaft T Ring 20 days 2/24/2020 3/17/2020 0%
448 Mark& Cut 2 days 2/24/2020 2/25/2020 0% 2 0.70% 0 0 0
449 Roll Flange Plate 4 days 2/26/2020 2/29/2020 0% 4 1.41% 0 0 0
450 Fit up Flange Plate 6 days 3/2/2020 3/7/2020 0% 6 2.11% 0 0 0
451 Weld 8 days 3/9/2020 3/17/2020 0% 9 3.17% 0 0 0
452 Turret Shaft ( 25mm plate ) 22 days 2/26/2020 3/21/2020 0%
453 Mark& Cut 4 days 2/26/2020 2/29/2020 0% 4 1.41% 0 0 0
454 Roll 6 days 3/2/2020 3/7/2020 0% 6 2.11% 0 0 0
455 Fit Up& Weld LS 12 days 3/9/2020 3/21/2020 0% 13 4.58% 0 0 0
456 Turret Shaft Web Frames ( 6 unit ) 6 days 3/23/2020 3/30/2020 0%
457 Mark& Cut 6 days 3/23/2020 3/30/2020 0% 8 2.82% 0 0 0
458 Pedestal Upper Tube ( 30mm plate ) 18 days 3/9/2020 3/30/2020 0%
459 Mark& Cut 2 days 3/9/2020 3/10/2020 0% 2 0.70% 0 0 0
460 Roll 4 days 3/11/2020 3/14/2020 0% 4 1.41% 0 0 0
461 Fit Up 4 days 3/16/2020 3/19/2020 0% 4 1.41% 0 0 0
462 Weld Out 8 days 3/20/2020 3/30/2020 0% 11 3.87% 0 0 0
463 Pedestal Flange (140mm plate) 40 days 3/11/2020 4/28/2020 0%
464 Mark& Cut 4 days 3/11/2020 3/14/2020 0% 4 1.41% 0 0 0
465 Fit& Weld 20 days 3/16/2020 4/8/2020 0% 24 8.45% 0 0 0
466 NDT 2 days 4/9/2020 4/11/2020 0% 3 1.06% 0 0 0
467 PWHT 2 days 4/13/2020 4/14/2020 0% 2 0.70% 0 0 0
468 Machining 12 days 4/15/2020 4/28/2020 0% 14 4.93% 0 0 0
469 Riser Guide Pipe 68 days 4/18/2020 7/14/2020 0%
470 Mark& Cut Cone 4 days 4/18/2020 4/22/2020 0% 5 1.76% 0 0 0
471 Roll Cone 6 days 4/23/2020 4/29/2020 0% 7 2.46% 0 0 0
472 Fit Up& Weld Cone 12 days 4/30/2020 5/15/2020 0% 16 5.63% 0 0 0
473 Vacuum test Guide Pipe 6 days 5/29/2020 6/5/2020 0% 8 2.82% 0 0 0
474 Mark& Cut Guide Pipe 8 days 6/8/2020 6/16/2020 0% 9 3.17% 0 0 0
475 Fit Up& Weld Guide Pipe w/ Riser Hub 12 days 6/17/2020 6/30/2020 0% 14 4.93% 0 0 0
476 Internal Coating Guide Pipe 12 days 7/1/2020 7/14/2020 0% 14 4.93% 0 0 0
477 Turret Top pull-in structure 16 days 4/29/2020 5/19/2020 0%
478 Mark& Cut 4 days 4/29/2020 5/4/2020 0% 6 2.11% 0 0 0
479 Fit& Weld 10 days 5/5/2020 5/16/2020 0% 12 4.23% 0 0 0
480 NDT 2 days 5/18/2020 5/19/2020 0% 2 0.70% 0 0 0
481 Transportation Frame / Grillage Prefabrication 30 days 7/1/2020 8/5/2020 0%
482 Cutting 4 days 7/1/2020 7/4/2020 0% 4 1.41% 0 0 0
483 Prefabrication beam 12 days 7/6/2020 7/18/2020 0% 13 4.58% 0 0 0
484 Welding 14 days 7/20/2020 8/5/2020 0% 17 5.99% 0 0 0
485 Rotation Frame 30 days 8/6/2020 9/11/2020 0%
486 Cutting 4 days 8/6/2020 8/10/2020 0% 5 1.76% 0 0 0
487 Prefabrication beam 12 days 8/11/2020 8/26/2020 0% 16 5.63% 0 0 0
488 Welding 14 days 8/27/2020 9/11/2020 0% 16 5.63% 0 0 0
489 Assembly 226 days 2/20/2020 11/24/2020 0% 513 13.59% 0.00% 0.00% 0.00%
490 Prepare Fabrication Support 12 days 2/20/2020 3/4/2020 0%
491 Mark& Cut 4 days 2/20/2020 2/24/2020 0% 5 0.97% 0 0 0
492 Fit& Weld 6 days 2/25/2020 3/2/2020 0% 7 1.36% 0 0 0
493 Levelling 2 days 3/3/2020 3/4/2020 0% 2 0.39% 0 0 0
494 Assembly Turret Tank 137 days 3/9/2020 8/28/2020 0%
495 Fit Lower Base Plate to Fabrication Support 4 days 3/9/2020 3/12/2020 0% 4 0.78% 0 0 0
496 Fit T Beams 4 days 3/13/2020 3/17/2020 0% 5 0.97% 0 0 0
497 Fit Pedestal Lower Tube 4 days 3/18/2020 3/21/2020 0% 4 0.78% 0 0 0
498 Weld out 8 days 3/21/2020 3/31/2020 0% 11 2.14% 0 0 0
499 Fit Inner lower Cone 4 days 4/1/2020 4/4/2020 0% 4 0.78% 0 0 0
500 Fit Lower Web Frames 4 days 4/6/2020 4/9/2020 0% 4 0.78% 0 0 0
501 Fit Inner Deck Plate #1 turret tank 4 days 4/11/2020 4/15/2020 0% 5 0.97% 0 0 0
502 Fit inner upper Cone 4 days 4/16/2020 4/20/2020 0% 5 0.97% 0 0 0
503 Weld Out 6 days 4/21/2020 4/27/2020 0% 7 1.36% 0 0 0
Fabrication S Curve STP for Reliance KGD6 RUBY FPSO Project

Plan
Cut off 19-Feb-20 Description Wtg Actual Variance
Progress
Overall Progress 100.00% 26.67% 20.60% -6.07%
Procurement 20.92% 63.67% 51.94% -11.73%
Profab Documentation 6.17% 82.83% 70.77% -12.06%
Prefab Buoy Lower Section 4.37% 90.91% 66.06% -24.85%
Prefab Buoy Middle Section 6.41% 35.95% 19.83% -16.12%
Prefab Buoy Upper Section 5.03% 0.00% 0.00% 0.00%
Assembly Buoy Lower Section 4.42% 36.53% 25.75% -10.78%
Assembly Buoy Middle Section 4.10% 5.16% 0.00% -5.16%
Assembly Buoy Upper Section 3.58% 0.00% 0.00% 0.00%
Final Assembly Buoy 6.36% 0.00% 0.00% 0.00%
Prefabrication Turret Tank 10.94% 1.21% 0.61% -0.61%
Prefabrication Mooring Lugs Cluster 5.59% 0.00% 0.00% 0.00%
Prefabrication Turret Shaft 7.52% 0.00% 0.00% 0.00%
Assembly Turret 13.59% 0.00% 0.00% 0.00%
Assembly Buoy to Turret 0.37% 0.00% 0.00% 0.00%
FAT STP Buoy and Turret 0.40% 0.00% 0.00% 0.00%
Delivery Preparation 0.24% 0.00% 0.00% 0.00%

No Task Name Duration Start Finish % Complete

504 Fit Outer Shell T Beams 4 days 4/28/2020 5/2/2020 0% 5 0.97% 0 0 0


505 Fit 1st outer deck plate turret Tank 4 days 5/4/2020 5/8/2020 0% 5 0.97% 0 0 0
506 Weld Out 10 days 5/6/2020 5/18/2020 0% 13 2.53% 0 0 0
507 Fit Lower Outer Shell 4 days 5/19/2020 5/23/2020 0% 5 0.97% 0 0 0
508 Fit Upper Web Frame Turret Tank 4 days 5/26/2020 5/29/2020 0% 4 0.78% 0 0 0
509 Fit Upper Deck T Beams 2 days 5/30/2020 6/2/2020 0% 4 0.78% 0 0 0
510 Fit Outer Shell T Beams 4 days 6/3/2020 6/6/2020 0% 4 0.78% 0 0 0
511 Fit Upper Cone T Beams 4 days 6/8/2020 6/11/2020 0% 4 0.78% 0 0 0
512 Weld Out 8 days 6/10/2020 6/18/2020 0% 9 1.75% 0 0 0
513 Fit Upper Outer Shell 4 days 6/19/2020 6/23/2020 0% 5 0.97% 0 0 0
514 Weld Out 6 days 6/24/2020 6/30/2020 0% 7 1.36% 0 0 0
515 Fit Mooring Lugs Cluster (#1) 3 days 7/1/2020 7/3/2020 0% 3 0.58% 0 0 0
516 Fit Mooring Lugs Cluster (#2) 3 days 7/4/2020 7/7/2020 0% 4 0.78% 0 0 0
517 Fit Mooring Lugs Cluster (#3) 3 days 7/17/2020 7/20/2020 0% 4 0.78% 0 0 0
518 Fit Outer Cone ( Mooring Lugs Section ) 4 days 7/21/2020 7/24/2020 0% 4 0.78% 0 0 0
519 Weld Out 8 days 7/24/2020 8/3/2020 0% 11 2.14% 0 0 0
520 Fit Turret Lower Ring 2 days 8/4/2020 8/5/2020 0% 2 0.39% 0 0 0
521 Fit Outer Cone 3 days 8/6/2020 8/8/2020 0% 3 0.58% 0 0 0
522 Fit Ballast Pipe 3 days 8/10/2020 8/12/2020 0% 3 0.58% 0 0 0
523 Weld Out 4 days 8/12/2020 8/15/2020 0% 4 0.78% 0 0 0
524 Fit / Weld ROV Panel 6 days 8/8/2020 8/14/2020 0% 7 1.36% 0 0 0
525 Fit / Weld Installation Padeyes 16 days 7/25/2020 8/13/2020 0% 20 3.90% 0 0 0
526 Blasting Painting 10 days 8/15/2020 8/28/2020 0% 14 2.73% 0 0 0
527 Assembly Turret Shaft 58 days 3/23/2020 6/5/2020 0%
528 Fit Turret Shaft 4 days 3/23/2020 3/27/2020 0% 5 0.97% 0 0 0
529 Fit Turret Shaft Stiffeners 4 days 3/28/2020 4/1/2020 0% 5 0.97% 0 0 0
530 Weld Out 12 days 4/2/2020 4/16/2020 0% 15 2.92% 0 0 0
531 Fit& Weld TS. Web Frames to Turret Outer Shaft 8 days 4/17/2020 4/25/2020 0% 9 1.75% 0 0 0
532 Fit Turret Upper Ring 4 days 4/27/2020 4/30/2020 0% 4 0.78% 0 0 0
533 Weld Out 8 days 5/2/2020 5/12/2020 0% 11 2.14% 0 0 0
534 Fit& Weld Pedestal Upper Tube (PL.50mm THK) 4 days 5/13/2020 5/16/2020 0% 4 0.78% 0 0 0
535 Fit Pedestal Flange 6 days 5/18/2020 5/26/2020 0% 9 1.75% 0 0 0
536 Weld Out incl. Inner Web Frames 8 days 5/27/2020 6/5/2020 0% 10 1.95% 0 0 0
537 Turret Pull In Assembly 8 days 5/20/2020 5/30/2020 0%
538 Assembly turret top pull in 2 days 5/20/2020 5/22/2020 0% 3 0.58% 0 0 0
539 Assembly position indicator 2 days 5/23/2020 5/26/2020 0% 4 0.78% 0 0 0
540 Routing tubing turret top pull in 2 days 5/27/2020 5/28/2020 0% 2 0.39% 0 0 0
541 Pressure Test& Flushing 2 days 5/29/2020 5/30/2020 0% 2 0.39% 0 0 0
542 Paint Turret Shaft 16 days 6/2/2020 6/19/2020 0%
543 Blasting& Metalizing Turret Shaft 12 days 6/2/2020 6/15/2020 0% 14 2.73% 0 0 0
544 Blasting& Painting Turret Upper Ring (Primer) 4 days 6/16/2020 6/19/2020 0% 4 0.78% 0 0 0
545 Fit& Weld Risers /Umbilicals - Turret Shaft 48 days 7/15/2020 9/11/2020 0%
546 Fit Umbilical Guide Pipes - 2ea (Incl. DC) 4 days 7/15/2020 7/18/2020 0% 4 0.78% 0 0 0
547 Weld Out 8 days 7/20/2020 7/28/2020 0% 9 1.75% 0 0 0
548 Fit 8"Riser Guide Pipes - 4ea (Incl. DC) 6 days 7/29/2020 8/5/2020 0% 8 1.56% 0 0 0
549 Weld Out 12 days 8/6/2020 8/21/2020 0% 16 3.12% 0 0 0
550 Fit 10"Riser Guide Pipes - 3ea (Incl. DC) 8 days 8/22/2020 8/31/2020 0% 10 1.95% 0 0 0
551 Weld Out 10 days 9/1/2020 9/11/2020 0% 11 2.14% 0 0 0
552 Final Turret Assembly 74 days 8/29/2020 11/24/2020 0%
553 Move Turret Tank to final assembly area 8 days 8/29/2020 9/7/2020 0%
554 Moving out& Lifting onto Transport frame 2 days 8/29/2020 8/31/2020 0% 3 0.58% 0 0 0
555 Jack Up& levelling 2 days 9/1/2020 9/2/2020 0% 2 0.39% 0 0 0
556 Scaffolding works 4 days 9/3/2020 9/7/2020 0% 5 0.97% 0 0 0
557 Guide Pipe Assembly on Turret Tank 8 days 9/8/2020 9/16/2020 0%
558 Mark& Cut Deck Plates 2 days 9/8/2020 9/9/2020 0% 2 0.39% 0 0 0
559 Lift& Fit Guide Pipe - 9set 4 days 9/12/2020 9/16/2020 0% 5 0.97% 0 0 0
560 Lift& Fit Turret Shaft to Turret Tank ( at Quay Side ) 2 days 9/17/2020 9/18/2020 0% 2 0.39% 0 0 0
561 Weld out CS Turret Shaft incl. NDT 6 days 9/19/2020 9/25/2020 0% 7 1.36% 0 0 0
562 Fit Riser Hub Pipe - 9 Circum 4 days 9/26/2020 9/30/2020 0% 5 0.97% 0 0 0
563 Weld Out Riser hub Pipe - 9 Circum incl. NDT 8 days 10/1/2020 10/9/2020 0% 9 1.75% 0 0 0
564 Fit Bend Pipe to Guide Pipe - 9 Circum 4 days 10/10/2020 10/14/2020 0% 5 0.97% 0 0 0
Weld Out Bend pipe to guide pipe - 9 Circum incl. NDT 8 days 10/15/2020 10/23/2020 0% 9 1.75% 0 0 0
565
566 Fit Insert Plate - 18 Circum 6 days 10/23/2020 10/30/2020 0% 8 1.56% 0 0 0
567 Weld Out insert plate - 18 Circum incl. NDT 8 days 10/26/2020 11/4/2020 0% 10 1.95% 0 0 0
568 Fit Bottom Flange - 9 Circum 4 days 10/24/2020 10/28/2020 0% 5 0.97% 0 0 0
569 Weld Out Bottom Flange - 9 Circum incl. NDT 8 days 10/30/2020 11/7/2020 0% 9 1.75% 0 0 0
570 Dimensional check incl. potential adjustment 2 days 11/9/2020 11/10/2020 0% 2 0.39% 0 0 0
571 Ballast Pipe Assembly - Fit and Weld 8 days 10/1/2020 10/9/2020 0% 9 1.75% 0 0 0
572 Leak Test for remaining comparments 4 days 10/10/2020 10/14/2020 0% 5 0.97% 0 0 0
573 Anode Installation 6 days 10/10/2020 10/16/2020 0% 7 1.36% 0 0 0
574 Fit / Weld Cables Pipe (Inclinometer) 12 days 10/17/2020 10/31/2020 0% 15 2.92% 0 0 0
Fabrication S Curve STP for Reliance KGD6 RUBY FPSO Project

Plan
Cut off 19-Feb-20 Description Wtg Actual Variance
Progress
Overall Progress 100.00% 26.67% 20.60% -6.07%
Procurement 20.92% 63.67% 51.94% -11.73%
Profab Documentation 6.17% 82.83% 70.77% -12.06%
Prefab Buoy Lower Section 4.37% 90.91% 66.06% -24.85%
Prefab Buoy Middle Section 6.41% 35.95% 19.83% -16.12%
Prefab Buoy Upper Section 5.03% 0.00% 0.00% 0.00%
Assembly Buoy Lower Section 4.42% 36.53% 25.75% -10.78%
Assembly Buoy Middle Section 4.10% 5.16% 0.00% -5.16%
Assembly Buoy Upper Section 3.58% 0.00% 0.00% 0.00%
Final Assembly Buoy 6.36% 0.00% 0.00% 0.00%
Prefabrication Turret Tank 10.94% 1.21% 0.61% -0.61%
Prefabrication Mooring Lugs Cluster 5.59% 0.00% 0.00% 0.00%
Prefabrication Turret Shaft 7.52% 0.00% 0.00% 0.00%
Assembly Turret 13.59% 0.00% 0.00% 0.00%
Assembly Buoy to Turret 0.37% 0.00% 0.00% 0.00%
FAT STP Buoy and Turret 0.40% 0.00% 0.00% 0.00%
Delivery Preparation 0.24% 0.00% 0.00% 0.00%

No Task Name Duration Start Finish % Complete

575 Position indicator for Pull-in pin assembly 4 days 11/2/2020 11/5/2020 0% 4 0.78% 0 0 0
576 Pull-in cable (inclinometer) 4 days 11/6/2020 11/10/2020 0% 5 0.97% 0 0 0
577 Remaining Blasting and Painting Turret Tank 6 days 11/11/2020 11/17/2020 0% 7 1.36% 0 0 0
578 Mooring Connectors Installation 6 days 11/18/2020 11/24/2020 0% 7 1.36% 0 0 0
579 Assembly Buoy to Turret 6 days 11/11/2020 11/17/2020 0% 14 0.37% 0.00% 0.00% 0.00%
580 Lift Buoy to Turret 1 day 11/11/2020 11/11/2020 0% 1 7.14% 0 0 0
581 Bearing Assembly 2 days 11/12/2020 11/13/2020 0% 2 14.29% 0 0 0
582 Install Pull-in/Hang-off for Riser& Umb 3 days 11/14/2020 11/17/2020 0% 4 28.57% 0 0 0
583 Install BSC Female and J Tube covers 6 days 11/11/2020 11/17/2020 0% 7 50.00% 0 0 0
584 FAT STP Buoy and Turret 11 days 11/18/2020 11/30/2020 0% 15 0.40% 0.00% 0.00% 0.00%
585 Dummy pull-in for all guide tubes 2 days 11/18/2020 11/19/2020 0% 2 13.33% 0 0 0
586 Functional Test (Mooring Connector) 3 days 11/20/2020 11/23/2020 0% 4 26.67% 0 0 0
587 Functional Test (Turret Pull In System) 2 days 11/18/2020 11/19/2020 0% 2 13.33% 0 0 0
588 Rotation Test 3 days 11/20/2020 11/23/2020 0% 4 26.67% 0 0 0
589 Weighing 2 days 11/28/2020 11/30/2020 0% 3 20.00% 0 0 0
590 Delivery Preparation 10 days 11/24/2020 12/4/2020 0% 9 0.24% 0.00% 0.00% 0.00%
591 Dismantle Rotation Test frame 1 day 11/24/2020 11/24/2020 0% 1 11.11% 0 0 0
592 Assembly Protection Frame& Torquing 3 days 11/25/2020 11/27/2020 0% 3 33.33% 0 0 0
593 Touch up painting 4 days 12/1/2020 12/4/2020 0% 4 44.44% 0 0 0
594 Ready for Delivery 0 days 12/4/2020 12/4/2020 0% 1 11.11% 0 0 0
PROGRESS %

Variance
Actual Overall
Original Overall

Actual Progress
Planned Progress

Revise Plan Rev.01

0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
30-Sep-19

Actual Progress Table


7-Oct-19

14-Oct-19 0% 0.00% 30-Sep-19 0.00% 0.00% 0.00% 0.00% 30-Sep-19

21-Oct-19 0% 0.57% 7-Oct-19 0.56% 0.56% 0.25% 0.25% 7-Oct-19

30-Oct-19 0% 1.00% 14-Oct-19 0.74% 1.30% 0.55% 0.79% 14-Oct-19

6-Nov-19 0% 2.01% 21-Oct-19 1.09% 2.38% 0.90% 1.70% 21-Oct-19

13-Nov-19
1% 3.35% 30-Oct-19 1.51% 3.89% 1.08% 2.78% 30-Oct-19

Original Overall
Actual Progress
20-Nov-19
1% 4.75% 6-Nov-19 1.30% 5.19% 1.36% 4.13% 6-Nov-19

Revise Plan Rev.01


27-Nov-19
0% 5.64% 13-Nov-19 1.35% 6.54% 1.37% 5.50% 13-Nov-19

-1% 6.53% 20-Nov-19 1.43% 7.97% 1.86% 7.36% 20-Nov-19


4-Dec-19

-1% 7.94% 27-Nov-19 1.32% 9.30% 1.94% 9.31% 27-Nov-19


11-Dec-19

-3% 8.23% 4-Dec-19 1.22% 10.51% 1.81% 11.11% 4-Dec-19


18-Dec-19

-4% 8.71% 11-Dec-19 1.11% 11.63% 1.59% 12.70% 11-Dec-19


25-Dec-19

-5% 9.30% 18-Dec-19 1.11% 12.74% 1.48% 14.18% 18-Dec-19


1-Jan-20

-6% 9.63% 25-Dec-19 1.09% 13.82% 1.20% 15.38% 25-Dec-19


8-Jan-20

-6% 10.68% 1-Jan-20 1.06% 14.88% 1.15% 16.53% 1-Jan-20


15-Jan-20

-7% 10.84% 8-Jan-20 0.79% 15.68% 0.99% 17.52% 8-Jan-20


22-Jan-20

-8% 11.89% 15-Jan-20 0.56% 16.23% 2.35% 19.87% 15-Jan-20


29-Jan-20

-10% 13.54% 22-Jan-20 0.77% 17.00% 3.59% 23.46% 22-Jan-20


5-Feb-20

-12% 15.19% 29-Jan-20 1.30% 18.30% 3.81% 27.27% 29-Jan-20


8-Feb-20

-15% 16.39% 5-Feb-20 2.07% 20.37% 3.97% 31.23% 5-Feb-20


15-Feb-20

-15% 17.57% 8-Feb-20 1.30% 21.66% 1.56% 32.79% 8-Feb-20


22-Feb-20

-19% 18.37% 15-Feb-20 3.20% 24.87% 4.13% 36.93% 15-Feb-20

29-Feb-20

22-Feb-20 3.31% 28.18% 3.86% 40.79% 22-Feb-20

7-Mar-20

29-Feb-20 4.18% 32.36% 3.48% 44.26% 29-Feb-20

14-Mar-20

7-Mar-20 3.92% 36.28% 3.61% 47.88% 7-Mar-20

21-Mar-20

14-Mar-20 3.52% 39.80% 3.26% 51.14% 14-Mar-20

28-Mar-20
21-Mar-20 3.34% 43.14% 3.09% 54.23% 21-Mar-20

4-Apr-20
28-Mar-20 3.26% 46.40% 2.90% 57.13% 28-Mar-20

11-Apr-20
4-Apr-20 2.97% 49.36% 2.60% 59.73% 4-Apr-20

18-Apr-20
11-Apr-20 2.52% 51.88% 2.79% 62.52% 11-Apr-20

25-Apr-20
18-Apr-20 2.52% 54.40% 2.96% 65.48% 18-Apr-20

2-May-20
25-Apr-20 3.10% 57.49% 2.66% 68.14% 25-Apr-20

9-May-20 2-May-20 3.07% 60.57% 2.66% 70.79% 2-May-20


Fabrication Progress S Curves

Weekly Cut Off

16-May-20 9-May-20 3.05% 63.61% 2.82% 73.61% 9-May-20

23-May-20 16-May-20 2.83% 66.45% 2.87% 76.49% 16-May-20


JN1350 - STP Buoy for Reliance KGD6 RUBY FPSO

30-May-20 23-May-20 2.89% 69.33% 2.38% 78.87% 23-May-20

6-Jun-20
30-May-20 2.83% 72.17% 2.33% 81.19% 30-May-20

13-Jun-20
6-Jun-20 2.67% 74.84% 2.03% 83.22% 6-Jun-20

13-Jun-20 2.28% 77.12% 1.67% 84.89% 13-Jun-20


20-Jun-20

20-Jun-20 2.20% 79.32% 1.64% 86.53% 20-Jun-20


27-J un-20

27-Jun-20 1.67% 80.99% 1.72% 88.26% 27-Jun-20


4-Jul-20

4-Jul-20 1.75% 82.73% 1.20% 89.46% 4-Jul-20


11-Jul-20

11-Jul-20 1.69% 84.43% 1.01% 90.47% 11-Jul-20


18-Jul-20

18-Jul-20 1.51% 85.94% 0.90% 91.38% 18-Jul-20


25-Jul-20

25-Jul-20 1.27% 87.21% 0.60% 91.98% 25-Jul-20


1-Aug-20

1-Aug-20 1.17% 88.37% 0.57% 92.55% 1-Aug-20


8-Aug-20

8-Aug-20 1.19% 89.57% 0.68% 93.24% 8-Aug-20


15-Aug-20

15-Aug-20 1.22% 90.78% 0.68% 93.92% 15-Aug-20


22-Aug-20

22-Aug-20 0.74% 91.53% 0.60% 94.53% 22-Aug-20


29-Aug-20

29-Aug-20 0.82% 92.35% 0.60% 95.13% 29-Aug-20


5-Sep-20

5-Sep-20 0.77% 93.11% 0.63% 95.76% 5-Sep-20


12-Sep-20

12-Sep-20 0.66% 93.78% 0.63% 96.39% 12-Sep-20

19-Sep-20

19-Sep-20 0.45% 94.23% 0.77% 97.15% 19-Sep-20

26-Sep-20

26-Sep-20 0.42% 94.65% 0.82% 97.97% 26-Sep-20

3-Oct-20

3-Oct-20 0.64% 95.29% 0.66% 98.63% 3-Oct-20

10-Oct-20

10-Oct-20 0.79% 96.08% 0.49% 99.12% 10-Oct-20

17-Oct-20
17-Oct-20 0.74% 96.82% 0.27% 99.40% 17-Oct-20

24-Oct-20
24-Oct-20 0.56% 97.38% 0.19% 99.59% 24-Oct-20

31-Oct-20
31-Oct-20 0.66% 98.04% 0.22% 99.81% 31-Oct-20

7-Nov-20
7-Nov-20 0.45% 98.49% 0.19% 100.00% 7-Nov-20

14-Nov-20
14-Nov-20 0.45% 98.94% 0.00% 100.00% 14-Nov-20

22-Nov-20
22-Nov-20 0.64% 99.58% 0.00% 100.00% 22-Nov-20

30-Nov-20 30-Nov-20 0.29% 99.87% 0.00% 100.00% 30-Nov-20

8-Dec-20 8-Dec-20 0.13% 100.00% 0.00% 100.00% 8-Dec-20


PREFAB ASSEMBLY PREFAB ASSEMBLY
DESCRIPTION QTY TARGET ACTUAL DESCRIPTION QTY TARGET ACTUAL
TARGET ACTUAL TARGET ACTUAL
FIT—UP WELD FIT—UP WELD FIT—UP WELD FIT—UP WELD
Deck Plate Deck Plate
12 PCS 03-Feb-20 07-Feb-20 05-Mar-20 12 PCS 28-Feb-20 06-Mar-20 31-Mar-20
2nd Level 1st Level

PREFAB ASSEMBLY PREFAB ASSEMBLY


DESCRIPTION QTY TARGET ACTUAL DESCRIPTION QTY TARGET ACTUAL
TARGET ACTUAL TARGET ACTUAL
FIT—UP WELD FIT—UP WELD FIT—UP WELD FIT—UP WELD
Deck Plate Deck Plate
12 PCS 18-Feb-20 22-Feb-20 11-Apr-20 12 PCS 10-Feb-20 14-Feb-20 23-Mar-20
4th Level 3rd Level

PREFAB ASSEMBLY PREFAB ASSEMBLY


DESCRIPTION QTY TARGET ACTUAL DESCRIPTION QTY TARGET ACTUAL
TARGET ACTUAL TARGET ACTUAL
FIT—UP WELD FIT—UP WELD FIT—UP WELD FIT—UP WELD
Deck Plate 25-Feb-20 29-Feb-20 30-Apr-20 WEB FRAME 27-Mar-20 02-Apr-20 30-Apr-20
12 PCS 36 PCS
5th Level LEVEL 05

PREFAB ASSEMBLY PREFAB ASSEMBLY


DESCRIPTION QTY TARGET ACTUAL DESCRIPTION QTY TARGET ACTUAL
TARGET ACTUAL TARGET ACTUAL
FIT—UP WELD FIT—UP WELD FIT—UP WELD FIT—UP WELD
WEB FRAME WEB FRAME
36 PCS 14-Mar-20 20-Mar-20 11-Apr-20 36 PCS 03-Mar-20 07-Mar-20 23-Mar-20
LEVEL 04 LEVEL 03

PREFAB ASSEMBLY PREFAB ASSEMBLY


DESCRIPTION QTY TARGET ACTUAL DESCRIPTION QTY TARGET ACTUAL
TARGET ACTUAL TARGET ACTUAL
FIT—UP WELD FIT—UP WELD FIT—UP WELD FIT—UP WELD
WEB FRAME WEB FRAME
36 PCS 18-Feb-20 22-Feb-20 05-Mar-20 36 PCS 17-Dec-19 03-Jan-20 29-Feb-20
LEVEL 02 LEVEL 01

PREFAB ASSEMBLY
DESCRIPTION QTY TARGET ACTUAL
TARGET ACTUAL
ROLL/FIT WELD FIT—UP WELD
INNER CONE 3 SEC 28-Feb-20 06-Mar-20 18-Feb-20

PREFAB ASSEMBLY
DESCRIPTION QTY TARGET ACTUAL
TARGET ACTUAL
FIT—UP WELD FIT—UP WELD
MIDDLE CENTRE TUBE 7 SET 25-Apr-20 30-Apr-20 02-Jun-20
STIFFENER
PREFAB ASSEMBLY
DESCRIPTION QTY TARGET ACTUAL
TARGET ACTUAL
FIT—UP WELD FIT—UP WELD
OUTER SHELL 6 PCS 25-Apr-20 12-May-20 20-Jun-20

PREFAB ASSEMBLY
DESCRIPTION QTY TARGET ACTUAL
TARGET ACTUAL
FIT—UP WELD FIT—UP WELD
UPPER SHELL 1 PCS 03-Apr-20 23-Apr-20 06-Jul-20

PREFAB ASSEMBLY
DESCRIPTION QTY TARGET ACTUAL
TARGET ACTUAL
FIT—UP WELD FIT—UP WELD
UPPER RING 1 PCS

PREFAB ASSEMBLY
DESCRIPTION QTY TARGET ACTUAL
TARGET ACTUAL
FIT—UP WELD FIT—UP WELD
Deck Plate
6th Level 18 SET 11-Apr-20 25-Apr-20 23-Apr-20 09-Oct-20