Name Duration

<Project Name>
Phase 1 : Technical Upgrade & Unicode conversion
Detailed Project Plan
Upgrade Preparation;Finalize the ABAP Object List for Modification Scope
Copy  Upgrade Media and EHP 4 Stack to local disc
Check  min required Support packages , SPAM and Kernel Level  if required update
Full Offline Database Backup
System Health Check before Upgrade
Pre-requisite checks before PREPARE
Preparations for UC (consistency checks for cluster tables)
PREPARE Phase (INITIALIZATION, EXTRACTION, CONFIGURATION and CHECKS)
Initial SPUM4 / SPUMG SCAN
MDMP Pre-conversion (Additional scans for MDMP system)
Creation of vocabulary
Maintaining the vocabulary
Reprocessing SCANS
Backup (optional)
UPGRADE - Preprocessing Phase 
SPDD confirmation during Upgrade
Continue Pre-Processing Phase after SPDD
Perform Offline Backup before Downtime phase
Continue with Upgrade  Downtime 
Post UPGRADE steps 
Perform Offline Backup before Export
Pre-requisite Steps before Export and Distribution Monitor Configuration
Export steps (Unicode Conversion)
Backup
Cleanup system
Oracle 11g and patch  Installation on Target
Import steps (Unicode Conversion)
Post Import steps
Update of latest kernel
Post Unicode steps  (Related basis)
SPUMG steps (for MDMP systems)
Full Offline Database Backup
Dialog instance configuration for SAP System
Create and save the Transport Requests from POC 

Phase 2 : ABAP remediation & Business testing


ABAP : SPAU and custom objects remediation
Unit Testing
User Acceptance Testing & Resolve issues
Prepare Upgrade Documentation
Phase 3 : Sign-off
Resolve UAT issues and Handover
Start_Date Finish_Date Predecessors Resource_Names
Version Description Date Author
KI 4-0 T140688: KI transformation changes 11/29/2018 Global B&PS Automation Team