SITE SAFETY INSPECTION REPORT - SSIR

SSIR Number NHC-KAC-AH-JFR-SSIR-037 Date: Sunday, July 26, 2020


Program Title Developmental Housing Project of Saudi Arabia
Project Title Developmental Housing For Al-Ahsa
Client National Housing Company
Engineer EHAF CONSULTING ENGINEER
Contractor: Kabbani Architectural concepts
CONTRACT No. LOCATION MAIN CONTRACTOR INSPECTION BY (Print Name) POSITION
C1900175 Al Hasa Jafer Kabbani Architectural concepts Farrukh Ijaz HSE Manager

ITEM
DESCRIPTION CHECK ITEM
DESCRIPTION CHECK ITEM
DESCRIPTION CHECK
1 Accident reporting system / forms þ 11 Personal protective equipment þ 21 Openings ×
2 First aid equipment / first aider x 12 Barriers × 22 Overhead and underground services N/A
3 Fire procedures / extinguishers x 13 Scaffold / working platforms × 23 Electricity - general ×
4 Safe method of work procedure docs. þ 14 Ladders × 24 Electrical equipment / hand tools ×
5 Hazards to the public N/A 15 Bridges N/A 25 Air driven equipment / hand tools x
6 Safety sign board x 16 Cranes / hoists x 26 Welding equipment N/A
7 Site fencing / security x 17 Lifting equipment x 27 Gas / air cylinders - storage / use ×
8 Welfare facilities × 18 Excavation access N/A 28 Substances hazardous to health þ
9 Site tidiness þ 19 Dewatering / excavation support N/A 29 Supervision / safety officer þ
10 Stores / storage x 20 Conf. spaces method of work / equipment N/A 30 Other hazards N/A

KEY : þ- ACCEPTABLE û- FOR ACTION N/A - NOT APPLICABLE

ITEM *CONTRACTOR - COMMENTS / RECOMMENDATIONS ITEM *ENGINEER's - COMMENTS / RECOMMENDATIONS ITEM PM's - COMMENTS / RECOMMENDATIONS

1 Remove unwanted material and waste near Generator area. 1 1 Contractor should follow project HSE Plan

2 2 2 Contractor should ensure PPE compliance

Contractor should incorporate consultant engineer's


3 3 3
comment
Daily body temperature should be done for all operatives
4 5 4
including visitors

5 6 5 Contractor should follow all instruction from Govt.


authorities related to COVID 19
6 6
7
7 8 7

Manpower ( Staff -7+ workers -15) 22 Manpower (Staff - 3) SAPL -1 Grand Total -89
Sub Contractor - 59 Total - 81
For Contractor : Farrukh Ijaz ( HSE Manager) Date : 26-07-2020

For PM's. : Engr. Renjith Janardhanan (HSE Engineer) Date : 26-07-2020

Form Ref:.....................
Form Rev: (...........) Page 1 of 2
Form Issue Date:...........
SAPL HSE OBSERVATION PHOTOS

Operator cabin covered using cloth obstructing


visibility

Form Ref:.....................
Form Rev: (...........) Page 2 of 2
Form Issue Date:...........