DESCRIPTION LOW AVERAGE HIGH
Qty Unit Qty Unit Qty Unit
A. FORM WORKS INSTALLATION
1.1 Wall in Ground 4.00 MH/SM 2.00 MH/SM 1.60 MH/SM
1.2 Wall above ground 4.70 MH/SM 2.35 MH/SM 1.88 MH/SM
1.3 Beams 6.16 MH/SM 3.08 MH/SM 2.46 MH/SM
1.4 Columns 4.70 MH/SM 2.35 MH/SM 1.88 MH/SM
1.5 Suspended slab
0 - 18" 3.34 MH/SM 1.67 MH/SM 1.34 MH/SM
18 - 36" 6.66 MH/SM 3.33 MH/SM 2.66 MH/SM
1.6 Elevated and shored slab forming
Forming only 17.20 MH/SM 8.60 MH/SM 6.88 MH/SM
Forming and shoring 22.00 MH/SM 11.00 MH/SM 8.80 MH/SM
1.7 Wood wall and partition 1.00 MH/SM 0.50 MH/SM 0.40 MH/SM

B. FORM WORKS FABRICATION 2.15 MH/SM 1.08 MH/SM 0.86 MH/SM

C. STRIPPING OF FORM WORKS

1.1 Wall in Ground 0.50 MH/SM 0.25 MH/SM 0.20 MH/SM


1.2 Wall above ground 2.58 MH/SM 1.29 MH/SM 1.03 MH/SM
1.3 Beams 2.06 MH/SM 1.03 MH/SM 0.82 MH/SM
1.4 Columns 1.70 MH/SM 0.85 MH/SM 0.68 MH/SM
1.5 Suspended slab
0 - 18" 1.67 MH/SM 0.83 MH/SM 0.67 MH/SM
18 - 36" 2.16 MH/SM 1.08 MH/SM 0.86 MH/SM
1.6 Elevated and shored slab forming
1.7 strip of forms 7.00 MH/SM 3.50 MH/SM 2.80 MH/SM

Floor Slab at grade strip of forms 5.60 MH/SM 2.80 MH/SM 2.24 MH/SM

D. INSTALLATION OF CARPENTRY WORKS

1.1 Plywood partition 2.00 MH/PC 1.00 MH/PC 0.80 MH/PC


1.2 T & G Flooring and Siding 0.29 MH/BF 0.14 MH/BF 0.11 MH/BF
1.3 Ceiling Framework 0.73 MH/BF 0.36 MH/BF 0.29 MH/BF
1.4 Siding Framework 0.53 MH/BF 0.27 MH/BF 0.21 MH/BF
1.5 Flooring framing 1.94 MH/BF 0.97 MH/BF 0.77 MH/BF
1.6 Wooden Post Erection 0.85 MH/BF 0.43 MH/BF 0.34 MH/BF
1.7 Truss Fabrication 0.70 MH/BF 0.35 MH/BF 0.28 MH/BF
1.8 Truss Installation 1.60 MH/BF 0.80 MH/BF 0.64 MH/BF
1.9 Girt Installation 0.43 MH/BF 0.21 MH/BF 0.17 MH/BF
2 Plates Installation 0.27 MH/BF 0.13 MH/BF 0.11 MH/BF
2.1 Purlins Installation 0.53 MH/BF 0.27 MH/BF 0.21 MH/BF
2.2 Facia Board Installation 0.91 MH/BF 0.46 MH/BF 0.36 MH/BF
2.3 1/4" or 3/4" thck plywood
cutting by manual 2.00 MH/PC 1.00 MH/PC 0.80 MH/PC
assembly 0.83 MH/SH 0.42 MH/SH 0.33 MH/SH
2.4 Ceiling Framework
Frame Installation 2.66 MH/SM 1.33 MH/SM 1.06 MH/SM
Plywood Installation 2.00 MH/SM 1.00 MH/SM 0.80 MH/SM
2.5 Cabinet Boarding 0.26 MH/BF 0.13 MH/BF 0.10 MH/BF
2.6 Cabinet Framing 0.36 MH/BF 0.18 MH/BF 0.14 MH/BF

Carpentry Works Pages 1 of 2


CARPENTRY WORKS
Man-hour per quantity
DESCRIPTION LOW AVERAGE HIGH
Qty Unit Qty Unit Qty Unit
2.7 Wood Wall Partitions 1.00 MH/SM 0.50 MH/SM 0.40 MH/SM
2.8 Panel Wall 14.00 MH/SM 7.00 MH/SM 5.60 MH/SM
2.9 Forming Weight Anchor Bolts 9.00 MH/SM 4.50 MH/SM 3.60 MH/SM
3.0 Net Forming 7.00 MH/SM 3.50 MH/SM 2.80 MH/SM

E. DOORS AND WINDOWS

1.1 W-Panel Installation 0.8 MH/PC 0.40 MH/PC 0.32 MH/PC


1.2 Steel Windows Installation 4.00 MH/PC 2.00 MH/PC 1.60 MH/PC
1.3 Louver Windows Installation
Fixed Asbestos 9.26 MH/SM 4.63 MH/SM 3.70 MH/SM
Fixed Metal Louver 6.24 MH/SM 3.12 MH/SM 2.50 MH/SM
Fixed G.I. Sheet 9.26 MH/SM 4.63 MH/SM 3.70 MH/SM
Fixed Glass 6.24 MH/SM 3.12 MH/SM 2.50 MH/SM
Fixed Wooden 6.76 MH/SM 3.38 MH/SM 2.70 MH/SM
1.4 Aluminum Framed Windows 20.00 MH/EA 10.00 MH/EA 8.00 MH/EA
1.5 Sliding Glass Door 24.00 MH/EA 12.00 MH/EA 9.60 MH/EA
1.6 Hollow Metal Door 20.00 MH/EA 10.00 MH/EA 8.00 MH/EA
1.7 Rolling Doors 50.00 MH/EA 25.00 MH/EA 20.00 MH/EA
1.8 Fixed Window 0.63 MH/SF 0.31 MH/SF 0.25 MH/SF
1.9 Door Lockset 3.20 MH/SET 1.60 MH/SET 1.28 MH/SET
2.0 Door Jamb: Fabrication 0.44 MH/BF 0.22 MH/BF 0.18 MH/BF
Installation 0.66 MH/BF 0.33 MH/BF 0.26 MH/BF
2.1 Cyclone wire Installation 6.24 MH/SM 3.12 MH/SM 2.50 MH/SM