Schedule - GMI Halol GA Shop Expansion Project

ID WBS Task Name Start Finish Baseline % 2011


Duration 10 Nov '10 Dec '10 Jan '11 Feb '11 Mar '11 Apr '11 May '11 Jun '11 Jul '11
18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25
1 1 Overall Activities Mon Oct 18, '10 Tue Dec 20, '11 334days? 6%

2 1.1 Project milestones Mon Oct 18, '10 Tue Dec 20, '11 334days? 20%

15 1.2 Project Data Gathering Mon Nov 1, '10 Mon Nov 15, '10 11days? 70%

17 1.3 Scope Items Thu Nov 4, '10 Fri Jun 10, '11 161days? 2%

18 1.3.1 New platform Fri Dec 10, '10 Mon Apr 18, '11 108days? 2%

23 1.3.2 Gripper Modification Front Strut Assist Sun Jan 16, '11 Mon Apr 11, '11 74days? 0%

28 1.3.3 Radiator Lifting & drop facility - Tackle Fri Dec 10, '10 Tue Apr 19, '11 109days? 2%

33 1.3.4 New Fuel Tank Loader Sun Feb 20, '11 Fri Jun 10, '11 97days? 0%

39 1.3.5 Rear Axle tackle Fri Dec 10, '10 Tue Apr 12, '11 103days? 2%

44 1.3.6 New Engine tackle Fri Dec 10, '10 Tue Apr 12, '11 103days? 2%

49 1.3.7 Engine S/A pallet modification. Fri Dec 10, '10 Tue Apr 12, '11 103days? 2%

54 1.3.8 Front Cross Member Loading Assist Mon Feb 7, '11 Fri Jun 10, '11 107days? 0%

60 1.3.9 Spare Wheel AD Mon Feb 7, '11 Fri Jun 10, '11 107days? 0%

66 1.3.10 Relocate & Install Front seat assist device. Fri Dec 10, '10 Mon Mar 7, '11 72days? 13%

70 1.3.11 Gripper Modification Front Seat: Thu Jan 20, '11 Mon Apr 11, '11 67.5days? 0%

75 1.3.12 Structure of New assist for middle & rear seat. Fri Dec 10, '10 Mon May 23, '11 138days? 33%

79 1.3.13 New assist for middle & rear seat. Thu Jan 20, '11 Mon Jun 6, '11 116.5days? 0%

85 1.3.14 Jigs for badges & Decals. Fri Dec 10, '10 Thu Jun 2, '11 147days? 1%

90 1.3.15 Brake line sub assembly fixture Fri Dec 10, '10 Mon May 16, '11 132days? 2%

95 1.3.16 Brake Pedal sub assembly Jig Fri Dec 10, '10 Mon May 16, '11 132days? 2%

100 1.3.17 Steering column sub assembly Jig Fri Dec 10, '10 Mon May 16, '11 132days? 2%

105 1.3.18 Non ABS sub assembly Jig Fri Dec 10, '10 Mon May 16, '11 132days? 2%

110 1.3.19 Radiator sub assembly Jig Fri Dec 10, '10 Mon May 16, '11 132days? 2%

115 1.3.20 Rear Bumper sub assembly Jig Fri Dec 10, '10 Mon May 16, '11 132days? 2%

120 1.3.21 Striker locator Jig. Fri Dec 10, '10 Mon May 16, '11 132days? 2%

125 1.3.22 Clutch pedal sub assembly Jig. Fri Dec 10, '10 Mon May 16, '11 132days? 2%

130 1.3.23 Happy tools Trim / Chassis / Final. Fri Dec 10, '10 Mon May 16, '11 132days? 2%

135 1.3.24 Seat front / Middle / Rear transfer & storage facility. Fri Dec 10, '10 Mon May 16, '11 132days? 2%

140 1.3.25 Front Bumper sub assembly Jig Fri Dec 10, '10 Mon May 16, '11 132days? 2%

145 1.3.26 Transmission lifting / alignment device.-Tackle Fri Dec 10, '10 Mon Apr 11, '11 102days? 2%

150 1.3.27 Door handle sub assembly jig. Fri Dec 10, '10 Mon Apr 11, '11 102days? 2%

155 1.3.28 Front Cross member loading hanger. Fri Dec 10, '10 Mon Apr 11, '11 102days? 2%

Z1100_002B_Schedule_MS_Project_GMI_VG_110107 1 /3
Schedule - GMI Halol GA Shop Expansion Project
ID WBS Task Name Start Finish Baseline % 2011
Duration 10 Nov '10 Dec '10 Jan '11 Feb '11 Mar '11 Apr '11 May '11 Jun '11 Jul '11
18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25
160 1.3.29 Engine & Transmission loading hanger. Fri Dec 10, '10 Mon Apr 11, '11 102days? 2%

165 1.3.30 Brake disc locking tool for hub nut tightening. Fri Dec 10, '10 Mon Apr 11, '11 102days? 2%

170 1.3.31 Clutch pedal height setting tool. Fri Dec 10, '10 Mon Apr 11, '11 102days? 2%

175 1.3.32 Door outside mirror sub assembly jig. Fri Dec 10, '10 Mon Apr 11, '11 102days? 2%

180 1.3.33 Diesel & petrol filling jig. Fri Dec 10, '10 Mon Apr 11, '11 102days? 0%

185 1.3.34 Battery Assist Gripper Thu Jan 20, '11 Mon Jun 6, '11 116.5days? 0%

191 1.3.35 Transmission mounter ( for repairs)-Modification Fri Dec 10, '10 Mon Apr 11, '11 102days? 2%

196 1.3.36 Engine mounter ( for repairs) - Modification Fri Dec 10, '10 Mon Apr 11, '11 102days? 2%

201 1.3.37 Rear Axle Dismantling Jig for Repairs Mon Jan 31, '11 Mon Apr 11, '11 60days? 0%

206 1.3.38 VIN Plate jig & prog. Mon Feb 14, '11 Thu Jun 2, '11 94days? 0%

211 1.3.39 Engine dress up tool & fixtures. Fri Dec 10, '10 Mon Apr 11, '11 102days? 2%

216 1.3.40 Door on line assembly fixture & tools. Fri Dec 10, '10 Mon Apr 11, '11 102days? 2%

221 1.3.41 Cockpit on line assembly fixture & tools.(Two new tables withFri
bp)Dec 10, '10 Mon Apr 11, '11 102days? 2%

226 1.3.42 Cockpit on line assembly fixture & tools.(Rotary Type) Mon Jan 31, '11 Mon Apr 11, '11 60days? 0%

231 1.3.43 Hood Stay Rod Special Tool Fri Dec 10, '10 Mon Apr 11, '11 102days? 2%

236 1.3.44 Skin sub assembly fixture Fri Dec 10, '10 Mon Apr 11, '11 102days? 2%

241 1.3.45 MBU S/A Fixture Fri Dec 10, '10 Mon Apr 11, '11 102days? 2%

246 1.3.46 Special tool for parking brake cable adjustment. Fri Dec 10, '10 Mon Apr 11, '11 102days? 2%

251 1.3.47 Filling adaptors. Fri Dec 10, '10 Mon Apr 11, '11 102days? 2%

256 1.3.48 Rear bumper reflector assembly (LH & RH) table for drilling operation
Fri Dec 10,
+ locating
'10 jig.
Mon Apr 11, '11 102days? 2%

261 1.3.49 Belt insertion fixture. Fri Dec 10, '10 Mon Apr 11, '11 102days? 2%

266 1.3.50 Line side racks main line. Mon Feb 14, '11 Thu Jun 2, '11 94days? 0%

271 1.3.51 'New tool Rail on the extended trim line & final line. Mon Jan 24, '11 Mon Apr 11, '11 66days? 0%

276 1.3.52 New static station 4 stations creation (2 trim, 1 chassis, 1 AC area,
Fri Dec
1 on
10,SIP
'10line). Sat Apr 9, '11 100days? 2%

281 1.3.53 Shifting Of Pillar Fri Dec 10, '10 Tue Feb 8, '11 50days? 4%

286 1.3.54 Station arrangements for Final line along with jig fixtures & special
Fri Dec
tooling
10, '10pneumatic
Tue lines
Mar 8,
& '11
electrical 73days?
connections
13%relocations after pitch modification from 5.4 to 5.7.

290 1.3.55 Station Widening Fri Dec 10, '10 Sun Feb 20, '11 42.79days? 55%

291 1.3.55.1 Ordering Fri Dec 10, '10 Fri Dec 10, '10 1day? 100%

292 1.3.55.2 Installation & Commissioning Sun Dec 26, '10 Sun Feb 20, '11 32.29days? 52%

293 1.3.55.2.1 Widening Stn Tr-2 Sun Feb 20, '11 Sun Feb 20, '11 11days? 0%

294 1.3.55.2.2 Widening Stn Tr-3 Sun Dec 26, '10 Sun Jan 2, '11 8days 100%

295 1.3.55.2.3 Widening Stn Tr-4 Sun Jan 9, '11 Sun Jan 9, '11 1day 100% 1/9

296 1.3.55.2.4 Widening Stn Tr-5 Sat Jan 15, '11 Sat Jan 15, '11 1day 100%

Z1100_002B_Schedule_MS_Project_GMI_VG_110107 2 /3
Schedule - GMI Halol GA Shop Expansion Project
ID WBS Task Name Start Finish Baseline % 2011
Duration 10 Nov '10 Dec '10 Jan '11 Feb '11 Mar '11 Apr '11 May '11 Jun '11 Jul '11
18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25
297 1.3.55.2.5 Widening Stn Tr-6 Sun Jan 16, '11 Sun Jan 16, '11 1day 0%

298 1.3.55.2.6 Widening Stn Tr-7 Sun Jan 23, '11 Sun Jan 23, '11 1day 0%

299 1.3.55.2.7 Widening Stn Tr-8 Wed Jan 26, '11 Wed Jan 26, '11 1day 0%

300 1.3.55.2.8 Widening Stn Tr-9 Sun Jan 30, '11 Sun Jan 30, '11 1day 0%

301 1.3.55.2.9 Widening Stn Tr-10 Sun Feb 6, '11 Sun Feb 6, '11 1day 0%

302 1.3.55.2.10 Widening Stn Tr-11 Sun Feb 13, '11 Sun Feb 13, '11 1day 0%

303 1.3.56 Procurement & Installation of Fan Fri Dec 10, '10 Tue Mar 8, '11 73days? 7%

307 1.3.57 Engine Loading hoist 500 Kgs. With 06 mtr. y axis rail. (Demag)
Mon Feb 14, '11 Thu Jun 2, '11 94days? 0%

312 1.3.58 2-Post lifter modification for resting. Fri Dec 10, '10 Mon Apr 11, '11 102days? 2%

317 1.3.59 Rear Axle Marriage Van Thu Nov 4, '10 Fri Mar 11, '11 82days? 25%

Z1100_002B_Schedule_MS_Project_GMI_VG_110107 3 /3