Task Name Duration Start Date

Project at Bansbari, Footsal 101 days 5/15/2019 8:00


Finishing of Block A 101 days 5/15/2019 8:00
Plumbing Pipe line Remaining first Phase 15 days 5/15/2019 8:00
Master Bathroom 2 days 5/15/2019 8:00
Powder Room 2 days 5/17/2019 8:00
Water profing of head room terrace 4 days 5/15/2019 8:00
pipe connection 1 day 5/19/2019 8:00
Protection layer 2 days 5/21/2019 8:00
Floor Tile 3 days 5/23/2019 8:00
Tank Connection 2 days 5/28/2019 8:00
Electrical First Phase 8 days 5/15/2019 8:00
GF 3 days 5/15/2019 8:00
FF 3 days 5/18/2019 8:00
Terrace 2 days 5/21/2019 8:00
Plaster Repair 6 days 5/18/2019 8:00
GF 1 day 5/18/2019 8:00
FF 1 day 5/21/2019 8:00
Terrace 1 day 5/23/2019 8:00
Water Proofing 22 days 5/19/2019 8:00
Terrace and floor 10 days 5/19/2019 8:00
Floors of GF 2 days 5/19/2019 8:00
FF Terrace 4 days 5/21/2019 8:00
SF Tarrace 4 days 5/25/2019 8:00
Bathrooms 12 days 5/29/2019 8:00
Master Bathroom 3 days 5/29/2019 8:00
Powder room 3 days 6/1/2019 8:00
Bathroom1 3 days 6/4/2019 8:00
Bathroom2 3 days 6/7/2019 8:00
Flooring 31 days 5/18/2019 8:00
Screeding and Punning 6 days 5/23/2019 8:00
GF 3 days 5/23/2019 8:00
FF 3 days 5/26/2019 8:00
Tiling 31 days 5/18/2019 8:00
GF Kitchen 2 days 5/18/2019 8:00
GF Lounge 2 days 5/20/2019 8:00
FF Balcoly, Store 2 days 5/22/2019 8:00
East Terrace 2 days 5/24/2019 8:00
South Terrace 2 days 5/26/2019 8:00
SF Terrace 2 days 5/28/2019 8:00
Master Bathroom 3 days 6/3/2019 8:00
Powder room 3 days 6/6/2019 8:00
Bathroom1 3 days 6/9/2019 8:00
Bathroom2 3 days 6/12/2019 8:00
External Tile 3 days 6/15/2019 8:00
Granite works 6 days 5/15/2019 8:00
Windows sill 3 days 5/15/2019 8:00
Parapets 3 days 5/18/2019 8:00
Door Frame fixing 22 days 5/15/2019 8:00
Available at site 3 days 5/15/2019 8:00
New required 3 days 5/18/2019 8:00
Door Shutter 7 days 5/30/2019 8:00
Wall Putty 10 days 5/29/2019 8:00
GF 4 days 5/29/2019 8:00
FF 4 days 6/2/2019 8:00
Headroom 2 days 6/6/2019 8:00
Windows 12 days 5/18/2019 8:00
GF 5 days 5/18/2019 8:00
FF 5 days 5/23/2019 8:00
SF 2 days 5/28/2019 8:00
Painting first coat 30 days 6/8/2019 8:00
Inside 15 days 6/8/2019 8:00
Outside 15 days 6/23/2019 8:00
Metal works 7 days 5/15/2019 8:00
Edge of Cantilevers 7 days 5/15/2019 8:00
Fixtures 15 days 6/23/2019 8:00
Electrical 15 days 6/23/2019 8:00
Sanitary 15 days 6/23/2019 8:00
Initial Handover for Other Activities 0 days 7/7/2019 17:00
Finalizing Block A 17 days 8/7/2019 8:00
Paint Final Touchup 10 days 8/7/2019 8:00
Cleaning 7 days 8/18/2019 8:00
Handover 0 days 8/24/2019 17:00
Finish Date Predesessor Succeessor %Complete
8/24/2019 17:00 0%
8/24/2019 17:00 0%
5/29/2019 17:00 0%
5/16/2019 17:00 5,6SS,12SS,25,46SS,49SS,64SS 0%
5/18/2019 17:00 4 26,25FS+2 days 0%
5/18/2019 17:00 4SS 8FS+2 days,21,7 0%
5/19/2019 17:00 6 8 0%
5/22/2019 17:00 6FS+2 days,7 9 0%
5/25/2019 17:00 8 10FS+2 days 0%
5/29/2019 17:00 9FS+2 days 68 0%
5/22/2019 17:00 0%
5/17/2019 17:00 4SS 13,16,34 0%
5/20/2019 17:00 12 14,17 0%
5/22/2019 17:00 13 18 0%
5/23/2019 17:00 0%
5/18/2019 17:00 12 17 0%
5/21/2019 17:00 13,16 18 0%
5/23/2019 17:00 14,17 53 0%
6/9/2019 17:00 0%
5/28/2019 17:00 0%
5/20/2019 17:00 6 22,31FS+2 days 0%
5/24/2019 17:00 21 23 0%
5/28/2019 17:00 22 25 0%
6/9/2019 17:00 0%
5/31/2019 17:00 5FS+2 days,4,23 26,40FS+2 days 0%
6/3/2019 17:00 5,25 27,41FS+1 day 0%
6/6/2019 17:00 26 28,42FS+1 day 0%
6/9/2019 17:00 27 43FS+1 day 0%
6/17/2019 17:00 0%
5/28/2019 17:00 0%
5/25/2019 17:00 21FS+2 days 32 0%
5/28/2019 17:00 31 51,53 0%
6/17/2019 17:00 0%
5/19/2019 17:00 12 35 0%
5/21/2019 17:00 34 36 0%
5/23/2019 17:00 35 37 0%
5/25/2019 17:00 36 38 0%
5/27/2019 17:00 37 39 0%
5/29/2019 17:00 38 51,40 0%
6/5/2019 17:00 39,25FS+2 days 41 0%
6/8/2019 17:00 40,26FS+1 day 42 0%
6/11/2019 17:00 41,27FS+1 day 43 0%
6/14/2019 17:00 42,28FS+1 day 67,44 0%
6/17/2019 17:00 43 62 0%
5/20/2019 17:00 0%
5/17/2019 17:00 4SS 47,57 0%
5/20/2019 17:00 46 61 0%
6/5/2019 17:00 0%
5/17/2019 17:00 4SS 50 0%
5/20/2019 17:00 49 51 0%
6/5/2019 17:00 50,32,39 66,67 0%
6/7/2019 17:00 0%
6/1/2019 17:00 32,57,18 54 0%
6/5/2019 17:00 53,58 55 0%
6/7/2019 17:00 54 61 0%
5/29/2019 17:00 0%
5/22/2019 17:00 46 58,53 0%
5/27/2019 17:00 57 59,54 0%
5/29/2019 17:00 58 67,66 0%
7/7/2019 17:00 0%
6/22/2019 17:00 55,47 62,66,67 0%
7/7/2019 17:00 61,44 68 0%
5/21/2019 17:00 0%
5/21/2019 17:00 4SS 68 0%
7/7/2019 17:00 0%
7/7/2019 17:00 61,51,59 68 0%
7/7/2019 17:00 61,51,59,43 68 0%
7/7/2019 17:00 67,10,62,64,66 70FS+30 days 0%
8/24/2019 17:00 0%
8/17/2019 17:00 68FS+30 days 71 0%
8/24/2019 17:00 70 72 0%
8/24/2019 17:00 71 0%